Cash settlement of home and contents claim; total loss and temporary accommodation claims
Text of the determination
Case No: 313203 Determination Page 1 of 17
Case number: 313203
General Insurance - Domestic Insurance - Home Building - Instructions -
Failure to follow instructions/agreement – Failure
8 November 2013
Background
1. The Applicants’ home and contents were insured with the Financial Services
Provider (FSP) under a home and contents policy for $300,000 and $50,000
respectively.
2. They claimed for damage caused to their property as a result of water
inundating their home on/about 28 September 2011.
3. The FSP accepted liability for the claim.
4. During the course of the claim it was discovered that the home had been
contaminated by mould, which it was concluded arose from the water
inundation, so arrangements were made to:
Decontaminate the home;
Decontaminate and restore contents items that could be salvaged and
dispose of those that could not be salvaged; and
Place the Applicants in temporary accommodation.
5. A dispute arose between the parties as to the adequacy of the FSP’s
proposed remedial works, resulting in the Applicants refusing works to be
carried out or completed on a number of occasions.
6. In light of the Applicants continued refusal to allow remedial works to be
completed, the FSP sought to settle the remainder of the claim with a cash
payment of $87,400, comprising:
$49,000 for the contents (being the sum insured of $50,000 less $1,000
it previously paid as emergency payment); and
$38,400 being its assessed cost to complete the remaining remedial
works to the home and some 3 months worth of alternative
accommodation.
7. The Applicants believe that the FSP and its contractors have negligently
managed their claim and are attempting to avoid its policy obligations. They
believe the FSP should:
Determination
Case No: 313203 Determination Page 2 of 17
Declare the home to be a total loss and settle the claim on this basis;
Indemnify them for a sum in excess of $50,000 for the loss of their
contents;
Indemnify them for the cost of temporary accommodation until their
home is rebuilt; and
Pay them compensation for stress.
Summary of Applicants ’ position
8. The Applicants have presented a large number of submissions detailing their
complaints with respect to the claim and the manner in which it had been
handled. For the sake of brevity, the Panel does not propose to list down
every complaint made and will summarise them generally.
9. Essentially, their submissions and complaints may be summarised as
follows:
Their home had been contaminated by mould as a result of water
inundating it on 28 September 2011.
The home’s concrete slab has been cracked by water inundating the
heating ducts during the 28 September 2011 weather event.
The FSP and its contractors poorly handled their claim, causing them
stress and causing their home to deteriorate further.
The FSP’s proposed remedial actions were inadequate and
unsatisfactory.
They have not hindered the FSP’s contractors in carrying out remedial
works to the home.
The FSP had disposed of their contents without authority and their
contents were worth in excess of $50,000.
The FSP is attempting to avoid its obligations under the policy.
The FSP should be required to continue paying the cost of the ongoing
temporary accommodation until such time as it has met all of its
obligations.
Summary of FSP’s position
10. The Applicants’ claim is complicated as it involved managing a health risk
posed by the presence of mould in the home. There were numerous
discussions and consultations involving a number of parties to determine the
scope of works required to safely decontaminate and restore the home to a
safe and liveable condition.
Case No: 313203 Determination Page 3 of 17
11. When the scope of works was finalised, the Applicants refused to allow
access to their home for decontamination and restoration works to be
completed.
12. It ultimately made the decision to cash settle the outstanding aspects of the
Applicants’ claim in view of their continued refusal to allow decontamin ation
and restorations works to commence.
13. There is no evidence to support a view that the home has to be demolished
and rebuilt.
14. It had attempted to decontaminate and restore contents items which were
salvageable, particularly those that were of sentimental value to the
Applicants. Some items could be saved while some could not. It then made a
decision to treat the Applicants’ contents as a total loss.
15. Having settled the Applicants’ contents claim as a total loss, it is entitled to
retain the contents and deal with them as it sees fit.
16. The Applicants are not entitled to further temporary accommodation benefits.
17. It has not managed the claim in a manner inconsistent with the General
Insurance Code of Practice.
18. The FSP relies on the following policy provisions:
“ We do not cover:
…
Extra costs following an insured incident
Consequential losses or extra costs following an insured incident including:
loss of income or wages
cost of your time to prove your loss or to help us assess your claim
cost of hiring appliances after yours are lost, damaged or stolen
professional, expert, legal, consulting or valuation costs unless you
obtained our prior written authority to incur these costs
cost of replacing or reapplying pest control chemicals and baits in or
around your home
loss of water from a bursting or leaking pipe or water container
unless this is covered by an additional feature or option under this policy.
…
Home claims
How we settle home claims
If we agree to pay a claim for loss, theft or damage to your home, we will
decide if we will:
repair the damage new for old or
rebuild your home new for old or
Case No: 313203 Determination Page 4 of 17
pay you what it would cost us to repair or rebuild your home new for
old.
…
Contents claims
How contents claims are settled
If we agree to pay a claim for loss, theft or damage to your contents, we will
decide if we will:
repair damage new for old or
replace your contents or
pay you what it would cost us to repair or replace your contents new
for old.
…
What we will do after a claim is paid
Salvaged home contents
We can take and keep any recovered or salvaged item and sell it and keep
the proceeds after we have replaced the item or paid you for it.
…
Terms explained
…
sum insured
The most you can claim for any one incident. The amount is shown on the
certificate of insurance or in this PDS. The sum insured includes GST. The
sum insured on your home and contents includes any adjustment to which
you are entitled under additional feature 4 (automatic adjustments to the sum
insured). ”
Issues
19. Whether the FSP has met its obligations under the policy.
20. Whether the FSP was entitled to cash settle the Applicants’ home claim and
if so, is a payment of $87,400 fair and reasonable and sufficient to discharge
its policy obligation in that regard.
21. Whether the Applicants are entitled to a sum in excess of $50,000 for the
loss of their contents.
22. Whether the Applicants are entitled to further temporary accommodation
benefits.
23. Whether the Applicants are entitled to reimbursement of miscellaneous
costs, such as, electricity and expert reports commissioned by them.
Case No: 313203 Determination Page 5 of 17
24. Whether the Applicants are entitled to compensation for the manner in which
their claim had been handled.
Reasons for decision
25. Due to the nature and complexity of the dispute, it has been directly referred
to the Panel for Determination in accordance with the Operational Guidelines
to the Financial Ombudsman Service’s (FOS) Terms of Reference.
26. The Panel consists of an Ombudsman and two Panel members with
extensive experience in the insurance industry and consumer claims.
27. The Panel is satisfied that there has been an extensive exchange of material
between the parties and the parties have had the opportunity to respond to
the issues raised.
28. As this dispute gives rise to a number of issues for consideration, the Panel
will attempt to address each issue separately, insofar as it is reasonably
possible and practicable to do so.
Home building
29. The Applicants believe that their home is a total loss because their local
Council (“the Council”) had declared it to be a public health r isk as a result of
significant contamination by mould and bacteria. They allege that the
contamination was caused by the 28 September 2011 weather event and
had become worse due to the FSP’s alleged lack of diligence in the claim
handling.
30. For these reasons, they believe the home should be demolished and that
this aspect of their claim should be settled on the basis of a total loss.
31. They further allege that in addition to the contamination, the inundation has
caused cracks to appear in the concrete slab.
32. Th e FSP’s position is that:
The Applicants have continually frustrated its attempts to have remedial
works carried out leaving it with no choice but cash settle this aspect of
their claim.
The cracks in the home’s concrete slab were superficial and in any
case, did not arise from the 28 September 2011 weather event.
Summary of the evidence
33. Summary:
There is no dispute that the Applicants’ home was inundated by water
on 28 September 2011 and that some of this water had flooded the
heating ducts.
Case No: 313203 Determination Page 6 of 17
The FSP engaged contractor “S” to attend to make safe repairs
immediately. This entailed removal of the carpets in the home and
employing a number of measures to dry the home.
The Applicants expressed concern of possible bacterial contamination
at the outset of the claim, citing the fact that the heating ducts were
flooded with mud and water. At that time, their concern appeared to be
confined to bacteria capable of causing legionnaires disease.
This concern was initially dismissed by the FSP, relying on advice from
its initial contractor “CC” to the effect that it did not observe signs of the
relevant bacteria in the home. In any case, CC indicated that the ducts
would be cleaned and sanitised.
The Applicants continued to maintain their concern, so S carried out
microbial tests at the home on/about 17 November 2011. S’s report
was issued on 25 November 2011, confirming the presence of mould at
various locations in the home, with mould in the living room being some
3 times greater than outside the home.
The FSP engaged an assessor to inspect the home. Contractor CC
also provided recommendations that:
i. The heating ducts should be sealed off completely.
ii. Further testing be carried out to determine the actual extent of
mould contamination in the home.
These actions occurred in December 2011.
S took further samples from the home on/about 9 January 2012. These
were sent to a laboratory (“ML”) for verification. In an undated report, S
essentially confirms that the home was still contaminated by mould with
some areas showing less/more and unchanged concentrations than
when the first test was undertaken.
A general action plan to deal with the contamination was formulated
between January and February 2012.
The Applicants were dissatisfied with the proposed action, citing a host
of issues including a suggestion that the home should be demolished
because it had a “deadly” type of mould. This suggestion appeared to
have been made on/about 21 February 2012.
The FSP engag ed consultants “NA” to conduct further tests. NA
conducted site tests on 6 and 7 March 2012 and reported that the air
quality in the home was not particularly severe. It reported as follows:
i. The level of “respirable dust” in the home was within the
recommended American Society of Heating, Refrigeration and Air-
Conditioning Engineers (ASHRAE) guideline.
ii. There were low concentrations of acetone in the kitchen/living
room sample with concentrations of dicholoromethane being
“marginally above” adopted indoor ai r quality guideline values.
Case No: 313203 Determination Page 7 of 17
iii. “Trace amounts” of formaldehyde was detected at concentrations
below 1/10 th of the exposure standard.
iv. Airborne fungi (yeast and mould) and bacteria were “within
acceptable magnitude” when compared with average external
reference samples.
v. There were small, isolated pockets of visible mould on the cement
sheet wall and timber ceiling in the main bathroom and above the
window in the kitchen.
Based on NA’s findings and previous reports, the FSP determined that
the home was liveable and that temporary accommodation was no
longer required.
The Applicants engaged consulting firm “A” to undertake a mould
assessment of the home. A’s report was provided to the FSP on 24
May 2012.
According to the report, tests carried out by Dr. MC and her team on 17
April 2012 revealed a fairly significant presence of a number of species
of mould in the home, including some that were hazardous to humans.
In addition, consultant firm A also reported:
i. All members of the team which conducted the 17 April 2012 site
visit experienced “smarting/itching eyes”, with one team member
experiencing “itchy skin and flushed face”.
Be that as it may, A was unable to conclude if this was due to the
mould that was in the home or some other cause. It appears that
the cause or causes of these symptoms were never persuasively
established. In particular, it has never been persuasively
demonstrated that these symptoms were caused by the mould or
bacteria which were found to exist in the home.
ii. The difference between its findings and that of NA may be due to
differing climate conditions.
Consultant A’s report also included a number of recommendations to
rid the home of its contaminants.
Subsequent to consultant A’s report, the FSP appointed a restoration
company “R” to undertake restoration of the Applicants’ home as well
as contents (insofar as it was possible to do so).
At around the same time:
i. Dr. MC wrote to a number of health authorities (including the
Applicants’ local Council), reporting that the Applicants’ home was
a “public health risk”.
ii. A copy of consultant A’s report was provided to the local Council.
iii. Associate Professor NDH (Dr. NDH) wrote to the FSP, agreeing
with Dr. MC’s opinion.
Case No: 313203 Determination Page 8 of 17
The Panel notes that Dr. NDH was also acting as landlord of the
Applicants’ rental proper ty which they were utilising whilst unable to live
in their home.
Subsequent to Dr. MC’s letter and the provision of consultant A’s
report:
i. The local Council contacted the FSP to say that the Applicants
showed up at the Council office on 22 June 2012, asking for the
home to be issued with a condemnation notice.
ii. The local Council issued a building notice (on 22 June 2012)
asking the Applicants to show cause why occupation of their
home should not be prohibited and why works should not be
carried out to the home to return it to a safe and habitable
condition.
The Applicants refused R access to their home on 3 July 2012 to
commence the remedial work, citing the lack of a scope of works as
their reason for refusing the commencement of the remedial works.
R issued its scope of works on 5 July 2012 (5 July 2012 scope of
works) and a copy was sent to the Applicants’ solicitors at that time as
well as the local Council on/about 12 July 2012. The FSP also wrote to
the Council on the same day, outlining the progress of the claim and
the steps that were being taken to address it.
Building consultant JLG attended the home on 13 July 2012 to prepare
a scope of works and estimate to seal the in-slab heating ducts. This
was issued on the same day.
On 17 July 2012, the Council wrote to the parties asking them to come
to an agreement to restore the home to a safe and liveable condition.
R contacted the FSP on 7 August 2012, reporting that it had attempted
to make arrangements for remedial works to be carried out, but that the
A pplicants had refused access to the home until they had seen R’s
scope of works.
The FSP wrote to the Applicants’ solicitors on 7 August 2012, attaching
JLG’s 13 July 2012 quote and seeking clarification as to the Applicants’
refusal of access. It should b e noted that R’s 5 July 2012 scope of
works had also already been provided to the Applicants’ solicitors on 12
July 2012.
The Council issued a building order on 15 August 2012, directing the
female Applicant (“MT”) to restore the home to a safe and liveab le
condition within 90 days. The building order also specified that:
i. MT and the FSP should come to an agreed scope of works; and
ii. The parties’ experts (i.e. consultant A and NA) should certify that
the home is safe for occupation subsequent to remedial works
being completed.
The Council wrote to the FSP on 17 August 2012, attaching a list of the
Applicants’ concerns (as outlined in their 10 August 2012 email).
Case No: 313203 Determination Page 9 of 17
On 5 September 2012, the Applicants’ solicitors informed the FSP that
the Applicants were now agreeable to proceed with remedial works.
On/about the same time however:
i. The Applicants also contacted the FSP directly to say that the
Council’s approval should be sought to gain access to the home.
ii. R also contacted the FSP to say that the Applicants had again
refused it access to the home. According to R, the Applicants
reportedly advised that they had disagreed with their solicitors’
advice for remedial works to be commenced and that the scope of
works needed to be agreed upon.
The Applicants wrote to the Council and the FSP on 18 September
2012 saying that their solicitors no longer represented them in the
matter.
NA provided its feedback on R’s 5 July 2012 scope of works on 24
September 2012. R then issued a scope of works dated 9 October
2012, taking into account NA’s feedback (9 October 2012 scope of
works).
A copy of R’s 9 October 2012 scope of works was then sent to NA and
Dr. NDH (in Dr. MC’s absence) for further comment. It appears that NA
had no further issues with the amended scope of works but Dr. NDH
was critical of it.
Following the 9 October 2012 scope of works and the comments of NA
and Dr. NDH, the Council wrote to the Applicants on 15 November
2012, essentially suggesting that R should proceed with the remedial
works taking into account the matters raised by Dr. NDH.
The Applicants were not prepared to allow works to commence,
suggesting that a further test should be carried out to determine the
latest extent of contamination in the home before works commenced.
MT issued an email on 24 November 2012, again denying access to
the home on the basis several items of a “procedural matter” were
unclear and these items were also allegedly in “breach of previous
discussions”.
The FSP wrote to the Applicants (via solicitors) on 5 December 2012,
asking them to confirm if they would allow its contractors access to their
home (to conduct remedial works) by 4.00pm on 14 December 2012
failing which, the FSP would proceed to cash settle their claim.
It appears that company “TVH” was able to gain access int o the home
on 3 January 2013 to clean the heating ducts. However, after cleaning
of the ducts, – MT intervened in the matter causing TVH to leave the
home without completing some other work.
The Council issued an amended building order on 27 February 2013,
this time including optional directions that the Applicants either took the
necessary steps to de-contaminate the home and reinstate it to a safe
and liveable condition, or demolish same.
Case No: 313203 Determination Page 10 of 17
On 14 March 2013 the Applicants’ Legal Aid Solicitor confirmed the
FSP had access to the property.
34. A s the FSP had not arranged an engineer’s report, the Applicants engaged
JGA to do an onsite inspection to determine the cause of the cracking of the
slab. JGA determined the cracking was related to the 28 September 2011
even t. FMG Engineering attended the Applicants’ property on 29 April 2013
at the request of the FSP. In a report dated 8 May 2013, FMG concluded
that no structural damage was observed to the property, the damage was
considered cosmetic only.
35. Cracking to the concrete slab was consistent with typical long term concrete
shrinkage movement and not due to short term water inundation.
36. No abnormal moisture level was identified within the timber beams and no
structural distress identified.
37. Proximate cause of the external distress to the house was ongoing, long
term, foundation soil movements resulting from normal variations in the
moisture content to the reactive soils.
38. The stormwater flood event has not caused nor contributed to the observed
building distress.
Was the contamination due to the insured event?
39. Although recent statements from the Applicants’ experts MC and NDH now
cast some doubt over the cause of the contamination, the FSP has accepted
the contamination is related to the storm damage to the Applicants’ pro perty.
40. Whilst the Applicants claim the FSP should meet the cost of demolishing the
house, there is no evidence to support that demolition of the house is
necessary. The Council, while serving notice on the Applicants, does not
require the demolition of the house. It requires rectification of certified issues
and gives the option of demolition.
Cracks in concrete slab do not render home a total loss
41. Whilst the Applicants’ engineer JGA has commented that it would be fair to
assume that the stormwater inundation of the home on 28 September 2011
had contributed to the occurrence of the cracks in the slab, the FSP’s
engineer, FGM, has concluded that they observed that the cracking to the
concrete slab was consistent with typical long term concrete shrinkage
movement and not caused by the short term water inundation of the site and
house during the September 2011 event. FGM concluded that the distress to
the house was cosmetic only.
42. The Panel notes that the Applicants have only recently included the cracking
of the slab in their claim, whilst there is some evidence, given the comments
of JGA of the relationship to the cracking to the inundation of the home the
Panel prefers the eviden ce of FGM. In the Panel’s view, the evidence of JGA
Case No: 313203 Determination Page 11 of 17
when considered against the evidence of FGM is not sufficient for the
Applicants to establish on the balance of probabilities, that the inundation on
28 September 2011 stormwater event was the proximate cause of the
cracking in the slab. In the Panel’s view, most likely the cracking in the slab
was consistent with long term concrete shrinkage.
43. Having considered the evidence as a whole, the Panel is satisfied that the
damage sustained to the property is largely cosmetic and whilst there may
be some structural damage, such structural damage is most likely due to
ongoing, long term foundation soil movements. The Panel prefers the latest
engineering report of FGM, that the damage identified is largely cosmetic.
Have the Applicants frustrated the FSP’s attempts to carry out remedial work ?
44. The evidence establishes that there was some delay in accurately
assessing the extent of the damage to the home. The delay has been in part
contributed to by the Applicants’ re fusal to allow access to the premise on at
least three occasions, namely 7 August 2012, 5 September 2012 and in late
November 2012. There is also an indication that the Applicants refused to
allow the FSP’s contractor access to the home to commence remedia l work
on or about 3 July 2012.
45. Some of the delay can be attributed to the Applicants’ concern that they had
not been provided with an adequate scope of works. The Panel accepts that
it was not unreasonable for the Applicants to be concerned whether the FSP
is able to restore a contaminated home to a safe and liveable condition,
however, by refusing the FSP access to the property, the Panel accepts that
the Applicants have frustrated the FSP’s efforts to carry out the remedial
work.
46. It must be borne in mind that the situation confronting the parties was unique
and complicated, so it is reasonable to accept that the scope of works would
be a work in progress, including (as shown) the FSP’s preparedness to
refine the scope to incorporate the Applicants’ feedba ck wherever justifiable.
47. Ultimately, the FSP and its nominated contractors have planned for testing to
be done after the relevant remedial works have been carried out to
determine if they have been successful in properly decontaminating the
Applicants’ ho me. This was in fact already planned for fairly early into the
claims process although the scope of works prepared then may have been
fairly general.
48. In addition:
The experts NA and consultant A were also required to certify that the
home has been restored to a safe and liveable condition in order for the
Council’s building order to be lifted.
The FSP provides a lifetime guarantee on the quality of repairs it
carries out to the home.
Case No: 313203 Determination Page 12 of 17
49. Given that the FSP had elected to undertake the repair of the Applicants’
home, it was under an obligation to restore it to a safe and liveable condition
prior to allowing them access to return to their home. The information
exchanged indicates that the FSP was prepared to do this, throughout the
course of the claim. In this regard, whether the FSP had/had not provided a
complete scope of works does not in the Panel’s view justify the Applicants’
conduct.
50. Having had careful regard to the events that have transpired since
lodgement of the claim, the Panel finds the conduct of the Applicants
(throughout the course of the claim) to be somewhat inconsistent with a view
that they were willing to have their home restored to a safe and liveable
condition.
Decision to cash settle
51. The evidence establishes that the FSP’s decision to cash s ettle the home
claim was predominantly due to its inability to carry out the required remedial
works, following the Applicants’ continuous interference with the FSP’s
remedial plans and hindrance of access.
52. Having regard to the Applicants’ conduct, the Pa nel does not consider the
FSP’s decision unreasonable or inconsistent with the policy terms, good
insurance practice and an obligation to act with utmost good faith. The
Applicants created a situation which essentially left the FSP with little choice
but to cash settle the home claim.
Adequacy of cash settlement
53. The evidence establishes that the FSP had provided an allowance of
$27,000 to complete the relevant remedial works at the home. This sum
comprises:
An allowance of $12,000 to complete cleaning and sanitising works in
the home; which was derived from R’s cost estimate of $9,000
(excluding GST) plus a further 33% allowance.
The Panel notes that R’s cost estimation only relates to carrying out the
following tasks:
i. Contact cleaning of all surfaces within the household using HEPA
filtered extraction equipment.
ii. Surface cleaning of all internal surfaces using liquid based
cleaning solutions.
iii. Assessment of building materials in order to determine whether
any are contaminated and if removal is required.
An allowance of $15,000 to fill and seal the ducts in the home; which
was rounded up from JLG’s $14,833.58 quote to carry out such work
inclusive of GST.
Case No: 313203 Determination Page 13 of 17
54. The Panel is mindful that the costing prepared by the FSP’s experts does not
appear to specifically include:
The cost of inspection and testing of the home (subsequent to remedial
works) to determine the success or otherwise of the decontamination
works; and
The cost of replacing building materials that may require removal
following the assessment work identified by R.
55. The Panel presumes that the FSP’s allowance of an additional 33% over and
above R’s $9,000 estimation is meant to cater for such contingencies.
56. Whilst the Applicants have objected to many things, they have not provided
an alternative quote or for that matter, any persuasive evidence to
demonstrate that the FSP’s cost estimation was inherently inadequate to
carry out the remaining works to the home.
57. In the absence of persuasive evidence to the contrary, the Panel accepts
that the FSP’s allow ance of $27,000 to complete the remaining works to the
home is fair and reasonable and sufficient to discharge its obligation to the
Applicants for the home claim.
Contents
58. The Panel is unsure if payment of the total contents sum insured alone
discharges t he FSP’s obligation for the contents. The FSP does not appear
to have undertaken a full valuation of the Applicants’ contents prior to its
decision to declare their contents a total loss.
59. Had a full valuation been carried out, and subject to certain policy conditions,
the Applicants may have been entitled to a pro rata adjustment for the
amount payable.
60. However, although the FSP may not have fully explored this aspect, the
Applicants themselves have not provided any evidence to support a view
that their contents were worth in excess of $50,000. As they claim that their
contents were worth more than $50,000, they bear the burden of proof in this
regard and this has not been discharged.
61. The Applicants’ position is essentially as follows:
R had assured them that it would be providing an inventory list of their
contents before anything is removed from the home or disposed of.
They were never provided with the inventory list.
They believe the contents taken from their home or disposed of were
worth more than $50,000 (they believe their contents were worth
double the sum insured).
As the FSP has not properly handled this aspect of their claim, they are
entitled to full restitution of all contents.
Case No: 313203 Determination Page 14 of 17
62. It is the Applicants’ contention that their contents were worth doubl e the sum
insured. In such circumstances, the terms of the policy provide that the only
sum insured (in this instance $50,000) would be payable.
63. As the Applicants have provided no evidence to establish their contents were
worth in excess of the sum insured, the Panel is not satisfied that the FSP
has breached its obligations under the policy. The FSP has agreed to pay
the Applicants for the total loss of contents for the total sum insured of
$50,000. This in the Panel’s view meets the FSP’s obligations unde r the
terms of the policy. However, it does not mean that the FSP is entitled to
remove or destroy items that were not damaged; to the extent that the FSP’s
contractor’s computer records in this regard indicate that some items were
salvageable, the Applicants are either entitled to their repatriation or further
compensation, in respect of those items.
Temporary accommodation
64. Insofar as temporary accommodation is concerned, the policy provides that
the Applicants are entitled to temporary accommodation cover when an
insured event damages:
Their home to the extent it cannot be lived in; and/or
Their contents to the extent they cannot live in their home.
65. The benefit provides for a maximum of 52 weeks ’ worth of accommodation
subject to a maximum 10% of the sums insured for the home or contents, as
the case may be.
66. In other words, the Applicants are entitled to a maximum of:
$30,000 in situations where temporary accommodation is required
when their home is damaged by an insured event.
$5,000 in situations where temporary accommodation is required when
their contents have been damaged to an extent they cannot live in their
home.
67. The evidence establishes that the Applicants have already exhausted their
policy’s entitlement to temporary accommodation.
68. In this respect, the evidence demonstrates that the FSP:
Had paid for the Applicants’ temporary accommodation for the period
between 23 November 2011 and 12 April 2013, incurring a total cost of
$94,010 in the process.
Had allowed for a further 3 months worth of temporary accommodation
(at $3,800 a month) in its cash settlement to enable the Applicants to
complete the relevant remedial works, paying $11,400 for this purpose.
69. In short, the Applicants were provided with some $105,410 worth of
temporary accommodation benefits, some 3 times their maximum
entitlement.
Case No: 313203 Determination Page 15 of 17
70. It is plain that the amounts paid by the FSP were significantly in excess of
the Applicants’ maximum entitlement f or temporary accommodation and
much of the delay which gave rise to a need for extended temporary
accommodation was of the Applicants’ creation.
71. In the circumstances, the Panel is satisfied that the FSP has met its liability
to meet the costs of the Applic ants’ temporary accommodation.
Miscellaneous costs
72. The Applicants have submitted claims for a number of miscellaneous
matters, including claims for electricity usage and the cost of their experts’
reports.
73. The FSP has reimbursed the Applicants for electricity usage and has met the
cost of 2 reports issued by their experts.
74. The Panel is satisfied that the FSP has met its liability with respect to any
miscellaneous costs incurred.
Legal liability
75. The material indicates:
The landlord of the Applicants’ tempora ry accommodation has provided
evidence to the effect that the temporary accommodation has since
been contaminated by substantially the same contaminants found in
the Applicants’ home.
Dr. NDH holds the Applicants responsible for the contamination and
seeks compensation for the cost to restore the accommodation to a
safe and liveable condition.
The Applicants deny responsibility for the contamination and have
provided a number of assertions calculated to discredit Dr. NDH as well
as the findings of A (one of the Applicants’ nominated experts); which
essentially suggests that the temporary accommodation has been
contaminated by substantially the same contaminants as found in the
Applicants’ home.
76. The FSP has not addressed the claim by Dr. NDH in its submissions. Its file
notes appear to suggest that it had formed the view it has nothing to do with
the matter which is plainly incorrect.
77. There is no dispute that the Applicants have both home and contents cover
and according to the PDS, they are entitled to legal liability cover under each
category of cover.
78. The Panel notes that the nature of the legal liability cover for the contents
aspect of the Applicants’ policy appears to be virtually unrestricted. The
Applicants are covered for any:
Case No: 313203 Determination Page 16 of 17
“legal liability to pay compensation for an incident causing… loss or damage
to [other people’s] property which happens anywhere in Australia…”
79. Based on these wordings, the Panel is satisfied that the FSP is under an
obligation to indemnify the Applicants against Dr. NDH’s claim s hould they
be found to be legally responsible for the contamination of their temporary
accommodation.
80. In the circumstances, the Panel is of the view that the FSP is required to
attend to the claim by Dr. NDH pursuant to its legal liability provisions and
decide whether or not it wishes to accept liability for this claim and thereafter,
take the appropriate or necessary actions based on its decision on the
matter.
Compensation for stress/delay
81. Turning to the Applicants’ claim for compensation (based on the FSP’s
alleged poor handling of their claim), the Panel does not consider it
appropriate or fair in all the circumstances to require the FSP to pay
compensation for the following reasons:
The Panel finds no evidence to support a view that the FSP had
conducted itself poorly, such as to justify the payment of compensation.
Whilst the Panel accepts there have been significant delays, this was
significantly due to the Applicants’ conduct.
The FSP had provided the Applicants with temporary accommodation
benefits significantly in excess of their maximum entitlement.
Determination
82. In light of the above analysis, the Panel determines as follows:
a. The FSP is not required to settle the Applicants’ home claim on the
basis of a total loss.
b. The FSP is entitled to cash settle the remainder of the Applicants’
home claim based on the amount it would have incurred had it been
allowed to complete the necessary remedial works.
c. The FSP’s payment of $27,000 for the remainder of the home claim is
fair and reasonable, and sufficient to discharge its obligation for this
aspect of their claim. The FSP was only entitled to settle the Applicants’
contents claim as a total loss and pay the full sum insured for that
aspect, to the extent that items were not otherwise salvageable. The
FSP is to return to the Applicants any items that remain in storage and
were deemed restorable by its contractor at the time; if these items
have since been disposed of, the FSP is required to further cash settle
the Applicants in that regard.
d. The FSP is not required to provide or pay the cost of providing the
Applicants with further temporary accommodation.
Case No: 313203 Determination Page 17 of 17
e. Insofar as the Applicants may have a claim under the legal liability
provisions of the policy for contamination of a third party’s premise,
such claim is to be determined on its merits, pursuant to the policy
terms.
f. The FSP is not required to pay any compensation pursuant to clause
9.3 of the Terms of Reference.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.