Text of the determination
Case No: 312883 Determination Page 1 of 10
Case number: 312883
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
17 October 2013
Background
1. This Determination follow the review of a Recommendation issued on behalf
of the Financial Ombudsman Service (FOS) on 16 September 2013. The
Recommendation was rejected by the Applicant.
2. The Applicant held a landlord insurance policy underwritten by the Financial
Services Provider (FSP) which provided cover for his rental property.
3. On 28 September 2012, the Applicant lodged a claim under the policy for
damage to the property from a leaking hot water pipe in the bathroom.
4. Based on the reports of its contractors, the FSP denied the Applicant’s claim
on the basis that the leaking water pipe had not caused any damage to the
property. However, as the make safe work carried out by the FSP’s
contractors had caused damage to the bath and shower recess, the FSP
cash settled the Applicant for $2,498.24, being the amount quoted by the
FSP’s builder to repair this damage (less an excess of $250).
5. The Applicant disputes the FSP’s denial of his claim . He also says that the
cash settlement amount paid by the FSP is not sufficient to meet the costs of
repairing the damage to the bath and shower recess caused by the FSP’s
contractors.
Summary of Applicant’s position
6. The Applicant says that the FSP has incorrectly denied his claim, on the
basis that:
it is not correct to say that no loss occurred as a result of the burst pipe.
The loss included mould growth on the floor frame, the costs of excess
water used due to uncontrolled water flows and the loss of amenity to
the tenant. Further, the invasive works and resultant damage were a
direct result of the burst pipe;
it has relied on a policy exclusion relating to “ wear and tear ” , which is
not relevant to his claim, as the failure of the water pipe did not result
from its usage; and
Determination
Case No: 312883 Determination Page 2 of 10
the report of the FSP’s building consultant does not take into account a
second leak in the water pipe, which cannot have been caused by the
factors identified in the consultant’s report.
7. In relation to the damage caused by the make safe work carried out by the
FSP’s contractor s, the Applicant says that:
the FSP’s contractors demolished the bath and shower recess without
his authorisation. Accordingly, the FSP is responsible for restoring the
bath and shower recess to the condition it was in prior to the works;
and
the cash settlement provided was based on an inadequate scope of
works and is not sufficient to repair the damaged area to the standard
required by the Australian Building Code, Australian Standards and
other applicable regulations.
Summary of FSP’s position
8. The FSP relies on reports by its contractors in support of its position that:
the failure of the pipe under the bath did not cause any damage to the
property; and
the damage observed was due to wear and tear and/or gradual
deterioration which had been sustained over an extensive period of
time.
9. Accordingly, the FSP says that it is not liable for the claimed damage, as this
was not caused by the burst water pipe or any other event insured under the
policy. Further, the claimed damage falls within relevant exclusions under
the policy.
10. The FSP acknowledges that the make safe work carried out by its
contractors caused damage to the bathroom. However, it says that the
Applicant consented to the repair of the pipe, which necessitated the make
safe works.
11. The FSP says that the cash settlement of $2,498.24 represents appropriate
compensation for the damage caused by the make safe works and it is not
required to restore the bathroom to a better condition than it was in prior to
the damage. In particular, the FSP says it is not required to waterproof
undamaged areas of the bathroom.
Issues
12. Whether the FSP is entitled to deny the Applicant’s claim for damage from
the burst water pipe.
Case No: 312883 Determination Page 3 of 10
13. Whether the cash settlement of $2,498.24 is sufficient to reimburse the
Applicant for the damage caused by the FSP’s contractors in carrying out the
make safe works.
Reasons for decision
14. I am satisfied that there has been a full exchange of relevant information
between the parties and that each party has had an opportunity to respond
to the issues raised therein.
Available evidence
15. On 28 September 2012, the Applicant lodged a claim for damage to the
bathroom from a burst water pipe under the bathtub.
16. Following lodgement of the Applicant’s claim, the FSP engaged a plumber to
carry out make safe works. In order to identify the source of the leak and
repair the pipe, the plumber had to undertake invasive work, which created
an opening in the shower wall.
17. After the leak had been repaired, the FSP’s builder (“PC”) attended the
property to inspect the damage. PC reported that:
the invasive make safe works carried out by the plumber had resulted
in damage to the bottom of the wall of the shower recess at the end of
the bath, where the ceramic tiles, brick work and concrete flooring had
been removed so that the leak could be rectified; and
approximately one square metre of tiles at the base of the shower
recess had also been damaged and would need to be replaced. Prior to
replacing the tiles, the pipe would need to be lagged (insulated), new
concrete flooring laid and new brickwork installed to support the bath.
18. The photographs included with PC’s report reflect that the damag e to the
shower wall and floor was confined to a relatively limited area.
19. PC also prepared a scope of works necessary to repair the damage, at an
estimated cost of $2,748.24.
20. The FSP subsequently engaged a building consultant (“SBC”) to determine
the cause of the burst pipe and report on the condition of the bathroom. SBC
attended the property on 1 November 2012 and reported that:
the plumber had successfully repaired a portion of the copper hot water
pipe under the bathtub by replacing it with a section of new pipe;
the bathroom had a concrete infill slab which did not extend under the
bathtub, consistent with common industry practice at the time the
house was built. The bath tub was supported by masonry brick
perimeter walls and the soil sub-base;
Case No: 312883 Determination Page 4 of 10
the water pipes servicing the shower had been laid directly on the
ground the length of the bath and under the concrete slab in the shower
recess. The pipes were unlagged and laid directly on the sub-soil base
containing building rubble, consistent with common industry practice
when the house was built;
unlagged copper water pipes laid directly on the ground will move and
rub against the surrounding soil and building rubble, and over time will
erode and eventually burst; and
this was the cause of the damage to the water pipe under the bath tub,
which had reached the end of its serviceable life due to wear and tear
associated with the way it had been installed. This was considered to
be a maintenance related issue.
21. SBC identified water damage to the walls common to the shower recess and
mould growth on the timber hardwood joists of the sub -floor abutting the
shower recess and the bathroom walls. Based on the results of moisture
readings and leak testing, together with evidence of prior patching, SBC
concluded that this damage had occurred o ver time and was the result of a
failed waterproofing system, which was considered to be a maintenance
related issue.
22. SBC recommended that the concrete floor slab be replaced in its entirety
and the shower feed pipes be rerouted by way of the masonry wall. SBC
prepared a scope of works which included this work, as well as the repair of
the damage caused by the invasive make safe and the installation of a new
waterproofing system.
Claim for damage caused by burst water pipe
23. It is an accepted principle of general insurance that the onus rests with the
insured to prove, upon the balance of probabilities, that they have sustained
a loss caused by an event insured under the policy. This is known as a prima
facie claim. Once the insured satisfies this onus, the burden then shifts to the
insurer to establish that it is entitled to reduce or deny liability for the claim.
24. The Applicant’s policy provides cover for damage to the insured property
“ caused by water or liquid ” , as well as accidental damage (defined to include
damage caused by an unforeseen and uncontrollable incident).
25. Given the broad scope of cover under the policy, and the fact that SBC
observed water damage to the property, I am satisfied that the Applicant has
established a prima facie claim under the policy.
26. However, the FSP says it is entitled to deny the Applicant’s claim based on
general exclusions under the policy for loss or damage as a result of or
caused by:
erosion, rust, corrosion, gradual deterioration, depreciation, wear and
tear; or
a defect in an item, structural defects, or faulty workmanship or design
Case No: 312883 Determination Page 5 of 10
27. The report prepared by the FSP’s building consultant (SBC) states that the
water damage evident to the walls and floor of the property was caused by
the failure of the waterproofing system.
28. I accept that, as a registered builder, SBC is appropriately qualified to
determine the cause of the water damage to the property. Further, I consider
that SBC’s report provides a consistent and logical explanation of the c ause
of the damage which is supported by the attached photographic evidence. In
particular, I note that the nature of the damage shown in the photographs is
consistent with it having occurred over an extended period of time. The
location of the damaged walls also appears to be more consistent with the
damage having been caused by the failure of the waterproofing system,
rather than by the burst water pipe under the bathtub.
29. I consider that the failure of the waterproofing system in a bathroom such as
the Ap plicant’s (which is approximately 35 years old) is properly
characterised as wear and tear and/or gradual deterioration. Accordingly, the
damage resulting from the failure of the waterproofing system is excluded
under the policy.
30. If it is accepted that the water damage to the property was caused by the
failure of the water proofing system, then it follows that the Applicant has
failed to establish that the burst water pipe caused any damage. While the
Applicant has referred to losses incurred as a result of increased water bills,
these are consequential financial losses which are not covered by the policy.
31. In any event, I consider that the failure of the water pipe as a result of
rubbing against the surrounding soil and building rubble (as outlined in
SBC’s report) constitutes “wear and tear” or “gradual deterioration” within the
meaning of the policy. Even if I were to accept the Applicant’s argument that
“wear and tear” necessarily requires a direct relationship between usage of
the relevant item and the extent of the deterioration (which I do not), the
alternative exclusion for “gradual deterioration” would apply in circumstances
where the damage to the pipe occurred as a result of abrading against its
surroundings over an extended period of time.
32. The phot ographs of the repaired section of copper pipe included in SBC’s
report clearly show that it has been laid amongst soil and building rubble. I
am therefore satisfied that the pipe failed for the reasons outlined by SBC.
33. The Applicant has raised a number of issues with SBC’s report. Most
relevantly, he says that the report ignores the fact that there were two
separate leaks, one where the copper pipe entered the concrete slab of the
shower and the other further underneath the bath tub. The Applicant says
that the damaged section of pipe adjacent to the concrete slab was
embedded in the slab and therefore could not move or abrade against rubble
as suggested by SBC.
34. In support of his position, the Applicant has provided a copy of an invoice
from the plumber (“BPG”) engaged by his property manager to identify the
Case No: 312883 Determination Page 6 of 10
leak, and a photograph ta ken by the FSP’s builder (PC) when he attended
the property.
35. However, I am not satisfied that the Applicant has established that there was
a second leak, for the following reasons:
both the invoice issued by the plumber (BPG) and the report of the
FSP’s builder (PC) appear to refer to a single leak;
the reference in BPG’s invoice to “a leak located inside bath hob under
floor” is not inconsistent with the leak in the pipe bein g under the bath
tub;
PC inspected the property within days of the leak being repaired and
therefore could reasonably be expected to have noticed and
commented on two separate repairs to the copper pipe; and
in my view, the photograph provided by the Applicant does not clearly
establish that a second section of the pipe was repaired.
36. Accordingly, to the extent that any damage to the Applicant’s property was
caused by the burst water pipe, I consider that this would also be excluded
under the policy.
Adequacy of cash settlement
37. The Applicant’s policy provides cover for the cost of finding the source of
escaped water, including the cost of repairing any damage that occurs while
looking for the cause. However, the policy expressly excludes cover for the
cost of finding leaks that have not caused loss or damage to the insured
building or contents.
38. For the reasons outlined above, I have found that the Applicant has failed to
establish that the burst water pipe caused damage to his property.
Accordingly, the Applicant is not able to recover the costs of repairing the
make safe damage under the policy.
39. In the present case, the FSP has repaired the leaking pipe at no cost to the
Applicant and has also agreed to reimburse him for the cost of repairing the
make safe damage, as this was caused by the FSP’s contractors. However,
the issue in dispute between the parties is the extent of works which the FSP
is required to fund in order to repair the make safe damage.
40. As the repair of the make safe damage is not the subject of indemnity under
the policy, the terms of the policy governing the FSP’s obligations in relation
to the conduct of repairs are not directly applicable. Rather, the FSP is
required to do what is reasonable in the circumstances.
41. Although the Applicant disputes that he expressly authorised the
investigations which gave rise to the make safe damage, he has not
disputed that the make safe damage was necessary to enable the repair of
the leaking pipe. Given the location of the leak, it can reasonably be
assumed that the make safe damage would have occurred regardless of
Case No: 312883 Determination Page 7 of 10
whether the leaking pipe was repaired by the FSP’s repairer or by an
alternative contractor engaged by the Applicant.
42. In the circumstances, I consider that it is reasonable to require the FSP to
fund the cost of the repairs which are necessary to return the bathroom to its
condition prior to the make safe damage. However, the FSP should not be
liable for any costs which would result i n improvements to the bathroom.
43. The cash settlement paid by the FSP was based on the scope of works
prepared by its builder (PC). This scope of works covers the repair of the
make safe damage (only) at an estimated cost of $2,748.24, and includes
the following items:
lag pipe;
install brickwork;
reinstate new waste pipe;
reinstate concrete flooring;
remove existing damaged tiles;
apply water proofing membrane;
lay new tiles to wall and floor; regrout new tiles; and
remove rubbish and clear site.
44. The Applicant is a licensed builder. He says that the scope of works
prepared by PC is not sufficiently detailed to form the basis for a contract for
building works, and the works specified are not compliant with the Building
Code of Australia and the relevant Australian Standards. Further, the
Applicant says that PC’s scope of works is inadequate because:
it was prepared on the basis that the damage to the concrete shower
base could be repaired. However, as old concrete will not bond with
new concrete, unless the entire shower base is replaced, the excavated
area of the shower base will continue to be a depression where water
will collect and run under the bath area;
as the bath wall and hob rest on the concrete shower base, removing
the slab requires the removal of the bath, surrounding tiles, s hower
screen and tap fittings;
further, as there is a single slab for the bathroom, it is more practical to
remove and replace the entire concreted area. This would also require
the galvanised waste to be replaced and the removal and retiling of the
entire floor area and vanity;
the scope of works does not provide for waterproofing of the entire
area. The Building Code of Australia (the Code) requires that wet areas
must be prevented from penetrating behind fittings and linings or into
concealed spaces and therefore it is not possible to waterproof only
part of a wall and floor, and still comply with the Code;
Case No: 312883 Determination Page 8 of 10
the requirements of the Code can only be satisfied by completely
replacing the shower base and waterproofing the area to a height of
25mm above the bath hob, which necessarily requires the replacement
of the perimeter wall tiles;
the proposed repairs to the bath wall are inadequate as the bath wall is
directly opposite the shower rose and therefore must be fully
waterproofed. Water proofing part of this area only will result in water
running behind the membrane where it will be trapped or will create
hydraulic pressure that could separate the membrane from the
substrate and/or dislodge the tiles; and
the proposed repairs would result in four different types of tiles being
used in the bathroom which is not reasonable, as well as unevenness
in the height of the old and new tiles.
45. Given that PC’s scope of works is inadequate, the Applicant says that the
amount of the cash settlement is not sufficient to enable him to have the
repairs completed by an alternative contractor.
46. The scope of works prepared by SBC is considerably broader than that
prepared by PC, and includes repairs to the damage to the bathroom,
hallway, second bedroom and sub-floor identifi ed in the course of SBC’s
inspection. Accordingly, as the Applicant has acknowledged, SBC’s scope of
works is considerably broader than the repair of the make safe damage
caused by the FSP’s consultants. To date, no quote has been prepared in
relation to the scope of works prepared by SBC.
47. While SBC’s scope of works is admirably thorough, given its breadth it does
not greatly assist in determining an appropriate outcome in relation to the
repair of the make safe damage.
48. It is not the role of FOS to prepare a detailed scope of works for the conduct
of repairs, which is a task more appropriately carried out by professional
tradespeople who have the appropriate qualifications and experience.
However, it is important to ensure that the risks associated with repairs being
completed to a satisfactory standard are appropriately shared as between
the parties.
49. The FSP has advised (and the Applicant has not disputed) that its builder
(PC) is a reputable builder who is a member of the Master Builders
Association and the Housing Industry Association. PC attended the
Applicant’s property shortly after the leaking pipe was repaired and prepared
a scope of works for the repair of the make safe damage only. Accordingly, I
consider that, in the absence of evidence to the contrary, it is appropriate to
rely on the scope of works and quotation prepared by PC.
50. The Applicant has raised a number of concerns with the scope of works
prepared by PC and has suggested that extensive additional works beyond
those proposed are necessary to ensure that the make safe damage is
repaired effectively and in a manner which complies with the requirements of
Case No: 312883 Determination Page 9 of 10
the Building Code of Australia, Standards Australia and relevant local
building regulations.
51. I do not consider it reasonable in the circumstances for the FSP be held
responsible for all of the repairs proposed by the Applicant, which clearly go
beyond the repair of the localised area of damage resulting from the make
safe activities and would result in a material improvement in the condition o f
the bathroom.
52. Having said that, I consider that it is reasonable for the Applicant to expect
that any repairs carried out will comply with applicable legal requirements
(including in relation to waterproofing), and will otherwise be completed to a
reasonable professional standard. Accordingly, this risk should be borne by
the FSP.
53. In relation to the tiling (which raises aesthetic issues), I consider that the
FSP should be required to replace the damaged tiles only. However, if tiles
matching the originals cannot be obtained, then the FSP should be required
to replace the tiles on the entire floor of the shower and the tiles on the
whole of the damaged wall (only), with the replacement tiles to be matched
as closely as possible to the originals. However, the FSP should not be
required to replace the tiles in any other areas of the bathroom.
54. I am also conscious of the Applicant’s concerns that the amount of the cash
settlement is not sufficient to fund the completion of the repairs by another
builder.
55. In circumstances where the FSP has accepted responsibility for the repair of
the make safe damage, I consider that it is appropriate that the FSP also
bear the risk of the quoted amount being insufficient to adequately repair the
damage to the required standard.
56. The FSP has advised that it has deducted an excess of $250 from the
quoted amount of $2,748.24 resulting in a payment of $2,498.24 to the
Applicant. In circumstances where the FSP denied the Applicant’s claim, I
consider that it should be obliged to refund the excess.
57. Accordingly, I consider that it is fair in all the circumstances for the Applicant
to be given the option of electing:
that PC (or an alternative contractor selected by the FSP) repair the
make safe damage at the FSP’s cost, in accordanc e with (at a
minimum) the scope of works prepared by PC; or
to be cash settled for the amount of $2,748.24 (including the refund of
the excess).
58. If the Applicant chooses to have the make safe damage repaired by PC (or
another contractor engaged by the FSP) and the repairs are not carried out
to an appropriate standard, the FSP will be obliged to rectify the repairs.
Case No: 312883 Determination Page 10 of 10
Determination
59. On the basis of the available information I determine that:
within 14 days after the date the Applicant accepts this Determination,
he must notify the FSP of his election to :
o have PC (or an alternative contractor selected by the FSP) repair
the make safe damage at the FSP’s cost, in accordance with (at a
minimum) the scope of works prepared by PC, subject to the
Applicant providing the necessary authorisation; or
o accept the cash settlement for the quoted cost of the repairs; and
if the Applicant elects to have the repairs completed by PC or an
alternative contractor selected by the FSP, then in order to give effect
to that election:
o the Applicant must refund the amount of $2,498.24 to the FSP
prior to the repairs commencing; and
o the FSP must take all reasonable steps to ensure that the repairs
are carried out in accordance with applicable legal requirements
and to a reasonable professional standard; or
if the Applicant elects to be cash settled, then the FSP must pay him
the amount of $250 (being the excess payment previously deducted)
within 7 days of being notified of this election.