Home / Financial Firm (Unknown - Insurer) / Determination 312632

Determination 312632

Claim amount for fire damage (cash settlement)

FirmFinancial Firm (Unknown - Insurer)
Decided2014-03-31
ProductGeneral Insurance · Landlord
OutcomeFor the complainant in part
Amount awarded$235,000
Non-financial loss—
Amount claimed$278,764
SourceAFCA PDF

Summary

The landlord claimed a fire-damaged rental home was beyond repair and sought $278,764, while the insurer offered $139,310.14 cash settlement based on a consultant's scope of works. AFCA found the home repairable but that the insurer's scope was incomplete, and ordered a cash settlement of $235,000 plus interest from 14 October 2013.

The insurer must meet the claim under the policy, and where experts' estimates differed and the insurer's scope omitted asbestos and structural works, a compromise cash settlement was fixed with interest under section 57 of the Insurance Contracts Act.

Issues

Subjects and remedies

home or building damagepay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 312632 Determination Page 1 of 10 Case number: 312632 General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim amount 26 March 2014 Summary Description  Claim under a Landlord Insurance Policy following the property sustaining significant fire damage on 17 October 2012. Whilst the FSP has accepted liability for the claim, a dispute has arisen as to the quantum. Basis of Determination  There is no dispute the property suffered significant damage in the fire on 17 October 2012.  There have been different estimates provided with respect to the Scope of Works and cost of repairs with the FSP’s offer to cash settle $139,310.14 being based on the lowest possible estimate whilst the Applicant seeks an amount of $278,764 based on the highest estimate provided.  It is apparent that the Scope of Works provided needs to be revised as it does not include all relevant works including external asbestos cladding removal and replacement.  It is the desire of the parties to try and cash settle this dispute and the Applicants have requested that the matter be cash settled. Determination  Based on the information exchanged, the Panel determines it fair and reasonable in the circumstances that the FSP cash settle the Applicant’s claim for the total sum of $235,000. Background 1. The Applicant held a Landlord Insurance Policy (the policy) with the Financial Services Provider (FSP) for a tenanted property (insured property). Determination Case No: 312632 Determination Page 2 of 10 2. The insured property suffered significant fire damage on 17 October 2012 for which a claim was lodged under the policy later the same day. 3. The FSP accepted the claim and after having assessed the damage offered to authorise repairs and/or cash settle the claim in an amount of $139,310.14. 4. The Applicant remains dissatisfied with the FSP’s assessment of its liability under the claim and its final settlement offer. She is seeking a higher cash settlement amount in line with her preferred consultants’ assessment and calculation of the cost of repairs. Summary of Applicant’s position 5. The Applicant has sought the assistance of “JK” in submitting her dispute to the Service. In the interest of brevity both the Applicant as well as JK will be referred to as “the Applicant” for the purpose of this Determination. 6. The Applicant acknowledges the FSP has accepted her claim however maintains the following:  The total cash settlement offered by the FSP was $139,310.14 and not $138,729.34 as noted throughout the FSP’s submission to the Service.  The FSP asserts the quote from “BE” in the amount of $193,246.22 included additiona l damage not allowed for by engineers “M” appointed by the FSP. However, having considered the quote from BE the Applicant couldn’t see any additional damage included.  The scope of works (SOW) prepared by “S” and based upon which “C” has submitted a quote, which is the basis of the FSP’s settlement offer, is flawed.  The insured dwelling is beyond repair and cannot be properly restored to its pre-event condition.  It is consistently acknowledged in the information submitted by all consultants including C that damage has occurred to all rooms of the insured property.  In the documentation sent to the Applicant as part of its cash settlement offer the FSP’s consultant accepts the building needs to be demolished. Therefore the Applicant questions why she is being offered a settlement amount based on repairs when the building needs to be demolished.  Also, it was clear on reviewing the SOW/quotes relied upon by the FSP that the consultants were conscious of the fact there were likely to be further costs, in addition to the quoted amounts relied upon by the FSP.  The FSP obtained two quotes to rebuild the insured dwelling to a similar design however it has ignored requests from the Applicant to make these available to her for review. Case No: 312632 Determination Page 3 of 10  The FSP has failed to acknowledge the significance of the asbestos issue. All toxic asbestos material needs to be removed and disposed.  Asbestos fibres will have dispersed all throughout the building and the Applicant remains concerned about her safety if expected to live in the home post repairs having regard to the airborne asbestos fibres.  Since the fire event vandals had entered the property and removed windows from three rooms and floor boards from all other rooms. The sunroom has been completely demolished. 7. The Applicant is seeking one of the following outcomes under the claim:  Another SOW be arranged which is to include ALL the work required to repair the building and subsequently a quote prepared on the basis of the new SOW;  The FSP pay the amount of $278,764 in line with the quote s ubmitted by P; or  An engineer/architect is appointed by the FSP to draw up a set of plans and SOW to use to prepare a quote to rebuild the dwelling. Summary of FSP’s position 8. The Applicant contacted the FSP on 17 October 2012 to lodge a claim following a fire event which damaged the insured dwelling earlier that day. 9. The FSP accepted the claim and arranged an assessment of the resultant damage as well as estimates for the cost to restore the insured dwelling to its pre-event condition. This assessment was carried out by M. on 26 October 2012 and produced a report dated 2 November 2012. 10. BE provided the FSP an initial quote of $102,649.64 dated 09/01/2012 (sic); however, on 29.11.12 BE provided a Revised Building Repair Quotation, in the amount of $193,246.22. 11. The FSP acknowledges an offer was made by email dated 4 February 2013 to the Applicant based on BE’s Revised quote in the amount of $193,246.22. However, it maintains that this was made in error as this quote included additional damage not allowed for by M. 12. The Applicant responded to the offer in the negative and advised the FSP she would accept $300,000 by way of a cash settlement under the claim. 13. The FSP does not accept this to be reasonable and notes that it has offered to authorise and manage the required repairs and/or cash settle the claim. However, its obligations of indemnity are limited to what it would cost it to complete the repairs and therefore any cash settlement would be calculated on this basis. Case No: 312632 Determination Page 4 of 10 14. The Applicant has not made available substantiating evidence to establish the quote sourced by the FSP would not adequately repair and restore the insured building. Accordingly, the FSP was entitled to rely upon the opinions and quotes provided by its commissioned consultants. 15. The FSP acknowledges its submission to the Service incorrectly included reference to the offer of settlement as $138,729.34 with the actual final offer amount being $139,310.14. 16. The FSP arranged for S to review the information submitted by the Applicant’s commissioned consultant “NH”. S maintains that even if it were to accept NH’s consideration of the extent of unrepairable fire damage (this being 40%), the insured dwelling would still be deemed repairable. 17. S has however acknowledged that its proposed SOW will need to be amended to include removal of all external cladding. The FSP will arrange for an amended quote to reflect this should FOS decide the insured building is repairable. 18. The FSP maintains the policy does not include a sum insured amount rather is a complete replacement policy. Even if the additional costs referred to are to be included in the final cost of repairs, the insured building still remains repairable. The only way the building would be deemed uneconomical to repair would be in the instance the cost of repairs exceeds the cost of total replacement of the building. 19. Accordingly, on the basis of the available information the FSP maintains it is entitled to declare the insured building as repairable and it is not obliged to authorise complete replacement. Issues 20. Whether the Applicant has established, on the balance of probabilities, that the insured property is not capable of repair and requires complete replacement. 21. Whether the FSP’s offer of settlement is in line with its obligations under the policy. Reasons for decision 22. Due to the nature and complexity of the dispute, it has been directly referred to the Panel for Determination in accordance with the Operational Guidelines to the Financial Ombudsman Service’s (FOS) Terms of Reference. 23. The Panel consists of an Ombudsman and two Panel members with extensive experience in the insurance industry and consumer claims. Case No: 312632 Determination Page 5 of 10 24. The Panel is satisfied there has been a full exchange of the material relied upon and the parties have had the opportunity to respond to the issues raised. 25. Having considered the available evidence, the Panel is satisfied the parties do not dispute the following:  The Applicant held an active landlord insurance policy with the FSP at the time of the loss.  The FSP provided and the Applicant received the relevant policy documentation including the Product Disclosure Statement (PDS).  The insured building suffered significant damage due to a fire event and for which a claim was lodged with and accepted by the FSP.  The FSP having commissioned the services of various consultants has offered to settle the claim by way of authorising and managing the repairs to the insured building and/or by way of a cash settlement equal to what it claims it would cost it to complete the repairs.  The Applicant remains dissatisfie d with the FSP’s calculation of its liability under the claim and has proposed a few different options with respect to resolving the dispute between the parties under the claim. 26. The Panel has been provided with numerous reports prepared by the consultants commissioned to the claim by the parties and which have been exchanged between them. In the interests of brevity the Panel does not intend to restate these reports in full and information from the various reports relied on will only be reiterated, where considered relevant. M’s Report on Fire Damage to the dwelling dated 2 November 2012  The dwelling is a small cottage style building constructed in around the 1960’s. It is built on a stump and bearer sub -floor with timber wall frames cladded with asbestos wall sheets externally and fibre plaster sheeting internally.  The front bedroom (bedroom 1) was the ignition site for the fire and where the most significant damage occurred (completely destroyed).  The dwelling had undergone an extreme fire event and should be approached with care as the remaining structure was quite unstable.  The property was in a reasonable to poor condition and at first seemed to be relatively unaffected by fire other than the front bedroom area.  There was black smoke and water staining everywhere inside on the walls. The tenant’s belongings were still present and the fierce heat from the fire was evident as quite a lot of the belongings were blackened and melted.  The hallway had also suffered major damage as well as bedroom 2. The remaining rooms had all suffered some degree of damage mainly from smoke, soot and water. Case No: 312632 Determination Page 6 of 10  The entire roof structure has been affected and M considered it to be unstable in some sections.  M was able to ascertain why so much damage had been caused as any item within 400mm below the ceiling line damaged/melted due to the heat generated.  The bulk of the main living areas had been affected, apart from the two back rooms (laundry and sunroom) which were in sound condition. However, these rooms had also been affected by smoke, soot and water damage.  The condition of the wall frame top plates was difficult to ascertain due to the amount of ash and debris sitting on the ceilings. However, arising from the obvious heat that had been generated M was of the view that some damage would have occurred.  M concluded:  Estimated cost of reconstruction was in the range of $185,000 to $280,000.  Complete roof including members were to be replaced.  Many project home builders could produce a similar size dwelling for possibly less outlay.  M would need to re-attend the site once the roof structure was removed and sub-floor exposed. 27. On the basis of M’s assessment a nd Scope of Works the FSP requested builders BE to provide a quote for repairs which BE submitted (after first submitting a quote for $102,649.64) in the amount of $193,246.22 and dated 29 November 2012. P’s Report and Scope of Works March 2013 28. P was appointed by the Applicant and after undertaking an assessment of the damaged dwelling it submitted a detailed report and itemised SOW for consideration. It noted all the damage considered by M as well as other damage. Further, a greater degree of concern was shown to the issue of asbestos being present and P noted that:  The building is clad with asbestos sheeting that has been contaminated with smoke.  Asbestos can’t be worked with so the cleaning and sealing of the sheeting would not be possible without disturbing the fibres.  All asbestos materials including the eaves linings should be removed by licensed contractors and disposed in accordance with the relevant legislation.  All internal ceilings and insulation need to be removed due to contamination and water damage including all internal wall linings. Case No: 312632 Determination Page 7 of 10 29. On the basis of P’s assessment a Scope of Works and quote was offered. This was in the amount of $278,764. S Inspection Report dated 21 May 2013  An inspection was completed on 5 May 2013 in the presence of the Applicant’s representative JK.  Most severe fire damage was located in bedroom 1.  There was significant fire damage to the roof s tructure and internal areas of the dwelling.  There was a significant presence of material containing asbestos throughout the dwelling.  As a consequence of the broken asbestos sheets it was likely that airborne asbestos fibres had been carried throughout the dwelling in a smoke plume from the fire.  In view of the damage and spread of asbestos fibres S recommended that local authorities and Safe Work SA representatives be consulted regarding the method of removal/disposal.  The estimated cost to rebuild the dwelling to its former condition was provided by S as between $170,000 and $210,000. 30. The FSP arranged for builders C to provide a quote for the cost of repairs/rebuild having regard to the SOW prepared by S. C submitted a quote for repairs dated 5 June 2013 in the amount of $139,310.14. This being the quote the FSP sought to base its offer of full and final settlement of the claim. Comments from NH (Applicant appointed consultants in the field of ‘Structural and Civil Engineering – Residential and Commer cial’) dated 23 July 2013  NH examined photographic evidence provided to it in relation to the fire damage to the insured dwelling.  It asserts that it is apparent around 40% of the dwelling had been structurally damaged beyond repair with the remainder significantly smoke affected.  Given the extent of smoke damage under the eaves to the entire perimeter of the dwelling the fire smell can only be removed by replacing all linings (roof timbers, ceiling and wall linings).  NH was not able to determine whether or not the roof and wall timbers away from the main fire had been fire affected. However, given the building was still intact in these areas it was assumed they were structurally sound.  Once the fire damaged section is removed along with the entire wall, floor, ceiling lining, door and windows, only a small amount of framing will remain, on the assumption it is structurally sufficient. Case No: 312632 Determination Page 8 of 10  The complete removal of all external linings is essential given that it is asbestos based.  On the basis of the above NH formed the opinion that the dollar value of what can be salvaged would be only a small percentage of the total replacement cost of what is a basic dwelling. S’s Supplementary Report dated 25 September 2013  During S’s physical inspection of the property on 5 Ma y 2013 he observed extensive damage to the front bedroom (1).  The fire spread into the roof cavity and above bedroom 1 as well as adjacent rooms.  The bedroom structure was affected to approximately 20% of the area.  Based on the damage observed, even if NH’ s proposed percentage of irreparable structural damage (40%) was accepted, S maintains the dwelling still remains repairable.  S’s previous SOW allowed for the removal and replacement of only 85.5m 2 of external cladding however S now accepts that all external cladding (151m 2 ) must be removed under the claim.  The SOW of works submitted by P includes entire replacement of the residence and elevates the work required such as extensive replacement of windows, carpentry works and associated materials and the demolition of the entire insured building. 31. The Panel has carefully considered all of the available evidence and notes the photographic material was found to be of great assistance in forming an opinion with respect to the degree and extent of fire damage to the insured building. The Panel is satisfied, having regard to the various reports from the commissioned consultants, that for the most part there is a consensus on the extent of damage to the insured dwelling. 32. In saying that, there have been different estimates provided with respect to the Scope of Works and cost of repairs, the Panel notes the following estimations by the various consultants:  M = $185,000 - $280,000  BE = $193,246.22  P = $278,764  S = $170,000 - $210,000  C = $139,310.14 33. Further, S in its last report, having considered NH’s comments does not dispute that consultant’s estimation (40%) of the building structural damage as well as the fact that all external asbestos cladding will need to be removed and replaced. This essentially will increase the SOW and therefore cost of repairs impacting on its estimate as well as that of C. Case No: 312632 Determination Page 9 of 10 34. It is clear that the consultants were of the opinion the SOW and repairs required to repair/rebuild the insured dwelling were much higher than what C has proposed and which is being relied upon by the FSP to calculate its liability under the claim. The Panel is also satisfied that there has been an acknowledgement by the FSP of the existence of additional structural damage as well as asbestos related works. It would therefore not be unreasonable to form the opinion that the cost of repairs is going to be higher than C’s quote. 35. In saying that, the Panel is not satisfied the Applicant has been able to establish, on the balance of probabilities, that the insured dwelling is beyond repair and needs complete demolition and reconstruction. 36. On the basis of the available expert material the Panel is satisfied it has been established that, although there exists significant structural damage, the dwelling is repairable. Therefore, the Panel determines the FSP is not obliged to authorise the complete replacement of the dwelling and/or cash settle the Applicant under the claim on the basis of total reconstruction. 37. The Panel notes the Applicant is seeking settlement under the claim in line with P’s quote which is at $278,764 whilst the FSP is seeking to cash settle the claim on the basis of a quote submitted by C at $139,310.14. There is a significant difference between these two quoted amounts with C’s quote almost 50% lower than P’s estimation. This presents a clear indication that each of the parties is seeking to claim/settle the matter on the basis of opposing extremes available to them which the Panel does accept to be reasonable. 38. In the Panel’s view, the quotations submitted by C are significantly under the amounts quoted by the other builders. Whilst the Panel acknowledges that in view of the additional works referred to in NH’s assessment that the quotation from C would need to be increased, the Panel considers that this would also be the case with respect to the quotations from S. 39. In the Panel’s view, one option open to the parties wo uld be: to have a further independent consultant undertake a fresh assessment of all of the damage based on a revised Scope of Works and then obtain an independent builder to submit a quote for the cost of repairs including an appropriate builder’s allowan ce. The Applicant however has expressed a very clear view to the Service, through the Case Manager in discussions with the Applicant’s representative of 24 March 2013 that the only option they are now seeking is in the form of a settlement figure, as they wish to resolve this matter. 40. With this in mind and acknowledging the Applicant’s concern with respect to the possibility that additional works/repairs may become apparent once the repairs to the insured dwelling are under way and are likely to add to the total cost of repairs, the Panel considers it would be appropriate to cash settle the dispute based on a compromise between the various assessments save for the assessment of C which in the Panels view is inconsistent with the other assessments. Allowance also needs to be made for the comments by NH in any assessment. Case No: 312632 Determination Page 10 of 10 41. An average of the assessments between the quotes of M, B, P and S amounts to $223,627. If there is a 5% allowance for the variations suggested by NH, then you would reach a figure round about $235,000. 42. The Panel is satisfied that given the delays and frustration expressed by the Applicants, that it is appropriate in these circumstances that the matter be cash settled and is satisfied that the above figure represents a fair figure to cash settle this dispute in all the circumstances. 43. The Panel has also considered the question of interest payable on any cash settlement amount. The quotations provided, which form the basis of the Panel’s Determination, were calculated during 2013. The most recent quotation provided by the Applicant to the Service from P is undated but accompanies correspondence of 26 July 2013 from the Applicant’s representative. 44. Given the extensive efforts by the parties to try and reach agreement based on the quotations provided, the Panel is satisfied that it is reasonable that interest does not apply until the FSP had had an opportunity of considering the various quotations in 2013 and responding to them in a timely fashion. 45. In the Panel’s view, in particular given the FSP had of fered to either repair the property or cash settle the same, it was reasonable for the FSP to withhold such cash settlement until the Applicant had provided a response. In the Panel’s view, this was reasonable until 14 October 2013 when it is clear from the information provided to the Service that the parties were no longer in a position to reach a compromise. Accordingly, the Panel determines that the FSP should pay interest on the settlement amount from 14 October 2013 (that being the date from which it was unreasonable for the FSP not to have settled the matter) to date of payment of the claim. Determination 46. That the FSP is liable to meet the Applicant’s claim to the damage sustained in the fire on 17 October 2012 and the FSP is to cash settle the claim for the sum of $235,000 plus interest in accordance with Section 57 of the Insurance Contracts Act from 14 October 2013 to date of payment of the claim.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.