Text of the determination
Case No: 312292 Determination Page 1 of 12
Case number: 312292
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
14 March 2014
Summary
Description
A claim under a Home and Contents Insurance Policy following a fire in
October 2010. The parties are unable to agree as to the settlement
amount.
Basis of Determination
The property was substantially destroyed by fire in October 2010.
A Scope of Works to repair the property was arranged and not
disputed.
The FSP have cash settled the Applicant s‟ claim for the sum of
$559,569.70 pursuant to a quotation obtained having determined that
the property needs to be demolished.
The Applicants have now commenced rebuilding the property but it is
unclear whether they are building in accordance with the Scope of
Works.
Three detailed quotations have been exchanged. Given the time since
the original incident, the Panel accepts it is appropriate to finalise this
dispute by way of cash settlement based on a compromise of the
quotation.
Determination
The FSP is to cash settle the Applicants‟ claim for the total sum of
$650,000 with respect to the loss of the home building.
The FSP is to pay temporary accommodation at the rate previously
paid until 30 November 2012.
Background
1. The Applicants held a home insurance policy with the Financial Services
Provider (FSP) for their residential home. During the relevant period of
insurance, the building was covered for complete replacement and contents
for a sum up to $75,000. Claims were subject to a $100 excess.
Determination
Case No: 312292 Determination Page 2 of 12
2. On 6 October 2010, the Applicants lodged a claim for damage sustained by
fire. The FSP accepted liability for the claim. The contents were ultimately
settled by way of payment of the full sum insured.
3. The claim became protracted with respect to the building damage. The FSP
initially decided the damage was repairable although substantial aspects of
the home would be required to be rebuilt. However, the FSP ultimately
accepted the property needed to be demolished and decided to cash settle
the Applicants‟ claim by way of payment in the sum of $559,569.70
comprised of the following:
$547,169.70 for the cost to demolish and rebuild.
$12,400 for temporary accommodation (40 weeks @ $320 per week).
4. The Applicants have disputed the FSP‟s d ecision and believe they are
entitled to a further $500,000.
Summary of Applicants ’ position
5. They are dissatisfied with the FSP‟s handling of the claim, particularly with
respect to the following:
The delays experienced before the FSP decided to cash settle the
claim;
The arrangement of temporary accommodation; and
The fact the FSP stopped paying storage costs for their contents
without notifying them.
6. The cash settlement offered would not be sufficient to restore the house to
the condition it was in prior to the fire. For instance, it did not include all
bigger hardwood beams and silky oak windows and features. To this end,
they obtained two quotes and the cheapest available was $751,926.
However, obtaining these quotes was very difficult as many builders were
too busy or found the process too time consuming.
7. In addition, they seek compensation for the fact they were not placed in
temporary accommodation comparable to their home, have had to underg o
an owners builders course to arrange the rebuild of their home, paid for
storage costs of new contents and incurred professional fees when engaging
lawyers, architects, designers and certifiers. In particular, with respect to the
amounts allowed in the F SP‟s cash settlement for architects, designers and
certifiers, all of these professionals sought higher amounts than budgeted
for .
8. Based on the above, the Applicants submit they are entitled to a payment of
a further $500,000.
Case No: 312292 Determination Page 3 of 12
Summary of FSP’s position
9. In regards to the settlement for the building damage, the FSP submits the
following:
The Applicants have not disputed the Scope of Works set out.
Accordingly, the dispute in this regard is limited to quantum.
Although both parties have provided quotations, the FSP has relied on
a contractor who has both supplied a more complete quote and was
prepared to do the work privately for the Applicants.
The basis for deciding to cash settle the claim was due to the
numerous instances of the Applicants stating they wanted to alter the
design and layout of the insured building.
There is no basis to state the Applicants could not rebuild their home
for $547,169.70.
10. With respect to temporary accommodation, the FSP denies the Applicants‟
submission that they were compelled to stay in a location unacceptable to
them. The FSP undertook reasonable attempts to locate an appropriate
property but there were no equivalent places available, as acknowledged by
the Applicants. Further, the FSP has paid 24 months of temporary
accommodation, which is double the maximum allowable under the policy.
11. The FSP acknowledges there were delays experienced in the claim.
However, these delays were due to the FSP awaiting builders, architects,
engineers, certifiers and the council to assist it in determining its liability.
Despite this, the FSP has paid amounts beyond the Applicants‟ entitlements
such as an additional 10% towards building costs, 12 months temporary
accommodation and in excess of $5,000 for storage costs of new contents
purchased by the Applicants. Accordingly, the FSP disputes the award of
any compensation for either consequential financial loss or non-financial
loss.
12. The FSP therefore relies on the above and the following policy provisions to
substantiate its position:
“ What we will pay – new for old
Repairing or rebuilding your building
If your home building is damaged during the period of cover by an insured
event, we will decide if the damage:
can be properly repaired, or
is so severe that we reasonably believe your building will need to be
rebuilt.
Rebuilding your building
When we establish that your home building will need to be rebuilt, we will
decide to:
rebuild it to the same size and standard as your current building, or
Case No: 312292 Determination Page 4 of 12
pay the cost of rebuilding it to the same size and standard as your
current building.
When we rebuild your building, we will use new materials.
…
What we cover – additional benefits
We help with…
The cost of temporary accommodation
When an insured event has caused damage or loss to your building, we will
help with the cost of temporary accommodation for you and, where
necessary, for your domestic pets, provided:
we are satisfied your building is no longer habitable, and
you were living permanently in it at the time, and
you have claimed on this policy and we are satisfied everything is in
order.
We will pay the reasonable cost incurred by you for comparable
accommodation for up to 12 months while your building is being rebuilt or
repaired.
…
What happens when you claim on your [FSP] policy …
Changes to your building
You can have changes made to the design and structure of your building
before repair or rebuilding. Any extra cost of such changes will be your
responsibility.
We may decide to pay you the cost of repairing or rebuilding your building
without the changes you require.”
Home Contents Policy
“ Other costs …
When your contents are removed for storage or repair
If your building is damaged or destroyed by an insured event, we will pay:
the reasonable cost and, at our option, make the necessary
arrangements for any necessary removal and storage of your
contents during the reasonable period for up to 12 months while
your building is being rebuilt or repaired,
Issues
13. Whether the FSP‟s settlement offer for the building is fair and in accordance
with its policy obligations.
14. Whether the Applicants are entitled to additional compensation for temporary
accommodation and storage of new contents.
15. Whether the Applicants are entitled to compensation for the additional costs
incurred in the claim (such as legal costs, owners builders course, etc).
Case No: 312292 Determination Page 5 of 12
Reasons for decision
16. As advised to the parties, due to the nature of the dispute, the matter has
been referred to the Panel for Determination in line with the Operational
Guidelines to the Service‟s Terms of Ref erence. This dispute has not been
the subject of a FOS Recommendation and has proceeded directly to
Determination.
17. The Panel consists of an Ombudsman and two Panel members with
extensive experience in the insurance industry and consumer claims.
Building Settlement
18. There is a significant disparity between the quotations provided by the
parties. The FSP‟s contractor, CQ, in its job number 10509 quoted an
amount of $497,427. The FSP added 10% to this amount to arrive at the
total of $547,169.70. In contrast, the Applicants obtained two quotations from
different builders, WQ and GH, for amounts $769,231.89 and $751,926
respectively. This is an additional 50% loading of the amount quoted by CQ.
19. Upon reviewing these quotations in more detail, both of the Applica nts‟
builders provided a fairly substantial builders margin. WQ allowed for
$116,550.28 and GH allowed $128,000. This is approximately 20% of the
amount quoted, a fairly substantial margin which has not been explained.
20. Even if the builders‟ margin is excl uded from the two quotations, the
difference in amounts quoted is approximately $150,000, a substantial sum.
21. Other differences in the quotations include:
WQ‟s quote allowed $78,527.27 for demoli tion as compared to $23,650
for CQ. The Applicants stated buil ders laughed at CQ‟s amount but
provided no evidence to support this. On the face of it, $78,000 for
demoli tion appears excessive .
GH‟s quote allowed $12,099 for BSA insurance whereas CQ allowed
$4,070. It is unclear why there is such a significant disparity.
22. The FSP has advised that CQ is prepared to do the work directly for the
Applicants for the amount quoted. This does not of course allow for
variations that may arise in the building process and builders‟ margins that
may be applied by CQ. The Panel not es that CQ has not included a builders‟
margin in the quotation.
23. One of the principal complaints by the Applicants raised has been the delays
experienced. The delays were substantially due to the FSP attempting to
certify the draft plans with Council for the proposed repairs to the property.
Issues arose with the Council and the zoning of the area. Given this, the
Applicants‟ concerns regarding the certified fees and the potential for CQ‟s
costing to be inaccurate are justified as it is difficult to anticipate what further
delays and issues may arise.
Case No: 312292 Determination Page 6 of 12
24. The Panel would normally accept a quotation provided the builder is
prepared to commit to the repairs for the sum quoted. In this dispute
however, the Panel is concerned that the Applicants would not in fact be
able to have the repairs completed for the cash settlement amount. The
Panel is concerned as to the accuracy of CQ‟s quotation even though the
FSP has allowed an additional 10% margin on the quote in the settlement
amount.
25. As the FSP elected to cash sett le the dispute based on CQ‟s quote , no
allowance has been provided for possible variations or the likelihood CQ
would impose a builder‟s margin over and above the 10% allowed by the
FSP. The Panel accepts the difficulty for all parties when determining an
appropriate cash settlement in circumstances such as this in particular
where there is no evidence to dispute any of the actual building estimates
provided by either the Applicants or the FSP.
26. One view is that it would be fair to allow the FSP‟s cash settl ement to stand
whilst the Applicants proceeded to rebuild the property. The Applicants could
then claim from the FSP, subject to providing proof of the actual costs
incurred, the amount that exceeds the cash settlement offer. As indicated
earlier, the Panel understands the Applicants have commenced rebuilding,
but it is unclear whether the Applicants are rebuilding based on the Scope of
Works agreed between the parties or not. Such a resolution may see a
further protracted dispute between the parties.
27. The Panel is also mindful that the fire occurred in October 2010 and this
dispute has been ongoing for some time. To leave it unresolved until the
building had been completed would in the Panel‟s view not be in the best
interests of either party. Given the time that has elapsed since the original
claim, in the Panel‟s view it is only fair that this matter be finalised as early
as possible.
28. With this in mind, the Panel believes it is more appropriate that rather than
rely purely on the quotation provided by CQ, that there be a compromise of
the quotations provided by both parties. The Panel as indicated whilst having
concerns with the quotation of CQ also has concerns as to the accuracy of
the quotations provided by the Applicants from WQ and GH. The variation in
the quotations is considerable.
29. Whilst CQ did not include a builders ‟ margin, the Panel notes the builders‟
margins provided for by GH and WQ are significant although the Panel
accepts it is not unusual to see a builders‟ margin of between 10 and 20%
applied. The Panel considers a builders ‟ margin of 15% to be a fair
compromise.
30. The quotation from GH of $751,926 includes a builders‟ margin of $128,000
but does not allow for GST. Not only is the builders ‟ margin at the top end of
the range, the failure to include GST raises concern as to the accuracy of the
quotation.
Case No: 312292 Determination Page 7 of 12
31. The quotation from WQ of $769,231.89 includes GST and a builders‟ margin
of $116,550.28. Although the quotation is relatively brief, it appears to
consider the Scope of Works and in the Panel‟s view, the quotation is the
more reliable of the quotations provided by the Applicants.
32. In the circumstances the Panel considers it fair in the circumstances that
settlement be reached based on a compromise between the quotations of
WQ and CQ. In reaching a compromise between these quotations, the Panel
considers it appropriate to apply a builders‟ margin of 15%.
33. If a builders‟ margin of 15% is applied to the quotation from WQ based on
the building repair tender of $582,751.44, then the builders‟ margin is
reduced to $87,412.65 and after allowing for GST, reduces the quotation to
$737,180.70.If the same process is applied to the quotation of CQ, based on
the quotation for the rebuilding at $452,206.34, then a 15% builders‟ margin
would equal $67,830.95 and after allowing for GST, would bring the total
quotation to $572,041.02.If you were to average these two quotes, you will
come out with a figure of approximately $654,000 which averaged down
gives a figure of $650,000.
36. The Panel accepts that the foregoing assessment is arguably a crude way of
dealing with this dispute. However as this claim arose from a 2010 incident
and a cash settlement is the preferred settlement option of both parties, it is
a fair and appropriate compromise. To leave the final cash settlement of the
dispute until such time as the house is rebuilt is likely to simply prolong the
dispute and create uncertainty for both parties. In the Panel‟s view an
appropriate figure to cash settle the claim in these circumstances is
$650,000. As the FSP has already paid the Applicants the sum of
$547, 169.70 then the FSP would be liable, subject to the Applicants‟
acceptance of this Determination, to pay an additional $102,830.30 by way
of settlement for the cost to rebuild the Applicants‟ property.
Additional Compensation for Temporary Accommodation
37. The Applicants maintain the accommodation they ultimately stayed in for a
large portion of the claim was not comparable to their home. In particular,
their home had four bedrooms, was particularly large, had air-conditioning
and was fenced. In contrast, the home they have predominantly stayed in
only had two bedrooms, no air-conditioning, no fencing (for their two dogs)
and a toilet outside.
38. Given this, they are seeking the difference in rent between the amount paid
by the FSP versus the rent the FSP would have incurred had comparable
accommodation been found.
39. The policy provision notes the following regarding this benefit:
“ The cost of temporary accommodation
When an insured event has caused damage or loss to your building, we will
help with the cost of temporary accommodation for you and, where
necessary, for your domestic pets, provided:
Case No: 312292 Determination Page 8 of 12
we are satisfied your building is no longer habitable, and
you were living permanently in it at the time, and
you have claimed on this policy and we are satisfied everything is in
order.
We will pay the reasonable cost incurred by you for comparable
accommodation for up to 12 months while your building is being rebuilt or
repaired.”
40. The Panel accepts the FSP‟s obligation is to pay the actual cost incurred by
the Applicants, provided the costs were reasonable and associated with
comparable accommodation. It does not extend to the costs that would have
been payable had comparable accommodation been found.
41. With respect to the Applicants‟ allegation that the FSP compelled them to
move into non-comparable accommodation, the Panel is not satisfied this
has been established as:
Both parties appear to agree that at the relevant time, there were no
properties available in the area the Applicants‟ property was located
which were comparable to their insured property.
For more than a month, the Applicants remained at a motel in two
rooms whilst attempting to find alternative accommodation. The only
one that appeared suitable was the two bedroom home offered by their
friends.
There is no evidence that during the claim process, more suitable
accommodation was available or that if it was, the FSP would not have
allowed the Applicants to utilise same.
42. The Applicants have claimed for their temporary accommodation to be
covered until their home is rebuilt. The FSP has limited the payment for
approximately 24 months in total which takes into account the following:
The time it spent assessing the claim and attempting to finalise plans
with the council before deciding to cash settle.
Allowing a period of approximately 40 weeks for the estimated time of
repair, which is 8 weeks more than allowed by the contractor they
based their settlement on.
43. The Panel notes th at the actual funds for the rebuilding costs were not made
available to the Applicants until 24 February 2012. Prior to this, the FSP did
attempt to cash settle the claim but it appeared their offer was contingent on
the Applicants accepting it in full and final settlement .
44. It was only when the matter was reviewed through the FSP‟s Internal
Dispute Resolution (IDR) process that the FSP paid the Applicants the actual
funds that would enable them to begin the rebuild. This was by way of two
payments issued on 14 February and 24 February 2012.
Case No: 312292 Determination Page 9 of 12
45. In the Panel‟s view, it is fair in all the circumstances that the temporary
accommodation allowance should have been calculated from the time the
FSP made the funds available. This is based on the following.
46. Although the Applicants disputed the amount offered, there is no dispute
between either party that, at a minimum, the FSP was liable to pay the
amount offered. What was in dispute was whether this amount was sufficient
to discharge its obligations under the policy.
47. Secondly, the FSP does not dispute that the period of time to complete the
repair, based on its contractor‟s quote, is 40 weeks. However, it would be
unfair in all the circumstances that in settling the claim, it would include the
period of time it retained the funds which the Applicants would have required
access to, in order to start the repair process.
48. The Panel notes the FSP did not pay any amount to the Applicants for
almost four months after attempting to cash settle the claim. It appears that
the period allowed for temporary accommodation included this portion of
time when it is clear that even if the Applicants wanted to, they could not
begin the repair process as they did not have the funds necessary to do so.
49. The Panel acknowledges the FSP‟s counter position is that its offer was
reasonable and it was the Applicants‟ disputation of same that led to the
delay. However, the Panel would have regard to the terms of the policy and
the FSP was obliged to make these funds unconditionally available once it
decided to cash settle the claim and had determined the extent of its liability.
50. In regards to the actual period allowed, the Panel notes the FSP nominated
40 weeks based on their contractor‟s estimate of 32 weeks with an additional
allowance of 8 weeks. T he Applicants‟ contractors allowed 48 weeks.
51. The Panel considers the 40 weeks allowed by the FSP was reasonable
given there is no dispute that CQ‟s period was achievable if th at company
was engaged to conduct the rebuild. Accordingly, the Panel considers that
the temporary accommodation allowable should be extended until 30
November 2012. This is based on 40 weeks being calculated from 24
February 2012 being the date when all of the funds were made available to
the Applicants.
52. It is unclear up to what date the FSP has paid temporary accommodation.
According to the FSP, it states it has paid for 2 years of temporary
accommodation, which would mean that this was paid until 7 October 2012.
Given this, it is clear the FSP has not paid for temporary accommodation
until 30 November 2012.
53. As a result, the Panel accepts that it is fair in all the circumstances that the
FSP pay for temporary accommodation, at the rates it was previously
paying, until 30 November 2012. In addition, the FSP should pay interest on
the amount owing with the rate of interest to begin from 30 November 2012
until the date of payment, in accordance with Section 57 of the Insurance
Contracts Act 1984 ("the Act").
Case No: 312292 Determination Page 10 of 12
Storage of New Contents
54. There is no dispute the Applicants were paid out the full contents sum
insured. In such circumstances, the policy states the following:
“If we decide to pay the cost of repairing or replacing your contents:
our payment will not exceed any limits detailed in this policy and it will
not exceed the contents amount covered, except as provided for under
„What we cover – additional benefits‟ …”
55. The relevant provision that addresses contents removed for storage or repair
is not found under “What we cover – additional benefits”. Instead, it is an
amount payable subject to there being available funds under the sum
insured.
56. Given this, it is clear that the FSP was not liable to pay for these costs under
the policy.
57. However, in recognition of the substantive delays experienced, the FSP
decided to pay storage costs for the new contents up to a period of 32 weeks
on an ex gratia basis. The period of time allowed was to reflect the period of
time the FSP initially accounted for with respect to the building repairs.
58. According to the FSP‟s claim notes, this period was expanded t o 40 weeks
with the period of time to cease on 7 June 2012.
59. The initial decision to pay for these storage costs was set out in the FSP‟s
claim notes dated 5 September 2011 and 20 October 2011. In regards to the
initial period of time allowed, this was apparently communicated to the
Applicants‟ solicitors via email dated 20 October 2011.
60. The Panel acknowledges that the FSP was not liable under the terms of the
contents policy to pay for the storage costs. In the Panel‟s view, the FSP in
agreeing to make payment to the Applicants has acted fairly. Whilst the
Applicants may argue that they were not informed by the FSP that they
intended ceasing such payments and whilst there is no evidence of the FSP
actually informing the Applicants that it intended to cease such payment,
there is no evidence that the Applicants were actually prejudiced as a result
of this. There is no evidence that the Applicants incurred any additional
expenditure by the failure of the FSP to notify the Applicants of its intention
to cease payment of the storage costs.
61. There is no evidence that the contents were removed or stored in a manner
that resulted in the Applicants reducing their expenses. The evidence
establishes that the storage facility notified the Applicants that payment of
the storage costs was to cease. In the absence of any information to suggest
that the Applicants were subsequently prejudiced, the Panel is not of the
mind to award payment in respect of this aspect of the dispute.
Case No: 312292 Determination Page 11 of 12
Whether the Applicants are entitled to compensation for the additional costs
incurred in the claim (such as legal costs, owners builders course, etc)
62. The Applicants have sought a range of additional costs associated with the
claim. This is particularly set out in their email dated 15 July 2013.
63. It is clear however that there is no provision in the policy that would entitle
them to these costs. For instance, these costs being sought are not covered
in any way under the policy:
Daily car trips to the insured property.
Installation of a watering system to maintain the property and poultry.
Items they purchased for the temporary accommodation, such as little
air-conditioning units, heaters and small cupboards for storage.
64. The Panel is not satisfied that these costs can be directly linked to the FSP‟s
mishandling of the claim. For instance, the Applicants have not explained the
purpose of the daily car trips to the insured property or the reasons why
these costs would have been avoidable had the FSP handled the claim
differently. This similarly extends to the installation of the watering system.
65. In regards to the purchasing items for the temporary accommodation, this
appears to be attributable to the fact there was no other place available for
the Applicants to stay in, that was comparable to their insured property. As
stated previously, the Panel does not accept that the limited accommodation
available can be attributable to the FSP‟s conduct.
66. In so far as compensation is concerned, the Panel accepts that the
Applicants have suffered a substantial degree of i nconvenience as a result of
the circumstances in which they have found themselves and delay due
initially to the FSP efforts in dealing with the Council and its subsequent
decision to cash settle the claim. Under paragraph 9.3(b)(i) of the Terms of
Reference, FOS may award up to $3,000 for non-financial loss in the
following circumstances:
“an unusual degree or extent of physical inconvenience, time taken to resolve
the situation or interference with the Applicant‟s expectation of enjoyment or
peace of mind has occurred” .
67. The Panel notes the Applicants have received remuneration and
compensation beyond their entitlements under the policy. The amounts
exceed the compensation allowed under the Terms of Reference.
68. For instance, the FSP had no liability to pay for storage costs of their new
contents but already paid more than $5,000 in this regard on an ex gratia
basis.
69. The Panel accepts that the FSP has already paid a substantial sum to the
Applicants by way of a cash settlement. The proposed further cash
settlement determined by the Panel is designed to take into account the
various contingencies that could occur in rebuilding a property.
Case No: 312292 Determination Page 12 of 12
70. The accommodation costs arguably exceed the amount payable under the
terms of the policy.
71. Given all of this, the Panel does not consider an award under paragraph
9.3(b)(i) of the Terms of Reference is appropriate.
72. In regards to legal costs sought by the Applicants, FOS may award an
amount in this regard pursuant to paragraph 9.4 of the Terms of Reference.
This paragraph states the following:
“FOS may decide that the Financial Services Provider contribute to the legal
or other professional costs or travel costs incurred by the Applicant in the
course of the Dispute.”
73. The Panel does not accept an award in this regard is appropriate. Legal
costs are normally awarded when legal issues arise that require the
assistance of a lawyer, particularly in advocating the dispute before FOS to
properly articulate the Applicants‟ legal position. The Panel notes the
Applicants were able to clearly enunciate their concerns and the legal issues
involved were neither complex nor controversial.
Determination
74. On the basis of the available information the Panel determines that:
a. The FSP is to cash settle the Applicants‟ claim for the total sum of
$650,000; as the FSP has already paid the Applicants the sum of
$547,169.70, then the FSP is to pay the Applicants the sum of
$102,830.30 in satisfaction of this award with respect to the cost of
rebuilding the property.
b. The FSP is liable to pay for temporary accommodation, at the rates it
was previously paying, until 30 November 2012.
c. In regards to the shortfall owing with respect to temporary
accommodation at the time of this Determination being made, the FSP
is to pay interest on that amount owing in accordance with Section 57
of the Act. The relevant period that interest is to be calculated on is
from 30 November 2012 until payment is made.
d. The FSP is not liable to pay any additional amount to the Applicants.