Determination 311676

Extent of insurer's liability for accidental damage to boundary fence and retaining wall

FirmFinancial Firm (Unknown - Insurer)
Decided2013-12-23
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed$14,454
SourceAFCA PDF

Summary

The applicant's accidental damage claim for a boundary fence damaged by a neighbour's bobcat was disputed over scope and a 50% Fences Act limit. AFCA decided the FSP must pay for the damaged section of fence and a new retaining wall in full, less the excess, with interest if cash settled, and that it could not consider the neighbour's conduct.

Under the policy the insured is entitled to full indemnity for accidental damage, the Fences Act does not reduce the insurer's policy liability, and the exclusions for earth movement and faulty design were not established on the balance of probabilities.

Issues

Subjects and remedies

home or building damagepay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 311676 Determination Page 1 of 12 Case number: 311676 General Insurance - Domestic Insurance - Home Building - FSP Decision – Extent of the FSP’s Liability - Clause 8.2 of FOS’s Terms of Reference. 29 November 2013 Summary Description: This dispute concerns a claim by the Applicant under a home building insurance policy for accidental damage to a boundary fence. Basis for Determination: The causes of the damage to the fence were such that the accidental damage policy did respond to the claim. The policy provision regarding reinstatement applied. The policy exclusions of erosion and wrong design did not apply. The FSP was not entitled to pay only half the claim pursuant to the Fences Act. Determination: The FSP is to indemnify the Applicant. Background 1. The Financial Service Provider is legally represented. For the sake of simplicity, both parties will be referred to as the (“FSP”) herein. 2. The Applicant insured his home and contents for accidental damage under a home insurance policy issued by the FSP. 3. On 20 O ctober 2008, the Applicant‟s neighbour (“Mr G”) engaged a tree lopping contractor to remove a tree root. In doing so, the contractor impacted the dividing fence with a bobcat. 4. After becoming aware that Mr G had no intention of getting the fence repaired, the Applicant lodged a claim for the damage with the FSP on 30 July 2009. 5. The FSP‟s assessor (“CL”) attended the property to inspect the damage. CL obtained two quotes for repairing the damage, one of which was obtained from Mr G‟s business. 6. Upon receipt of CL‟s reports, the FSP offered to pay the Applicant $2,159.50. This amount represents 50% of the costs of repairing the fence by Mr G‟s business. Determination Case No: 311676 Determination Page 2 of 12 7. The claim was closed because the Applicant did not respond to the FSP‟s offer. However, it was re-opened in November 2010 as requested by the Applicant. 8. The FSP engaged a new assessor (“MYI”) to investigate the claim. MYI considered a more specialist analysis of the damage was required, so it ins tructed a building consultant (“ADC”) and an engineer (“MP”) to report on the damage. 9. Both experts shared common views regarding the causes leading to the current deteriorated condition of the fence. They reported that the fence structure failed due to a combination of stormwater run-off from the neighbour and the impact from the bobcat. 10. MYI appointed a builder (JL) to provide a quote for repairing the damage, based on MP‟s specifications. 11. Following receipt of the experts‟ reports and JL‟s quote, the FS P accepted the impact damage and offered to pay the Applicant $3,446.35 (being 50% of JL‟s quote, less $100 policy excess). However, it advised the Applicant that it would not cover the costs associated with installing a retaining wall. 12. The Applicant rejected the offer, as he believes the entire fence required replacement due to the severity of the impact. He seeks reinstatement of the entire fence structure, including a retaining wall. 13. The Applicant has provided a quote from his own builder for reinstatement of the fence and a new retaining wall for the cost of $14,454. Summary of Applicant’s p osition 14. The fence structure sustained severe damage following the impact by the bobcat. The current condition of the entire structure poses a significant danger to his family and Mr G‟s tenants. 15. Although the FSP elected to limit the damage to a 7 metre section, the severity of the impact also damaged 20 metres of the front and middle sections of the fence and footings (including pillars which were embedded into the ground) and pushed some 1.5 tonne of solid concrete, dirt and fence into his yard. 16. He did not accept the FSP‟s offer because he purchased the insurance policy to cover the cost of fixing the damage and not just parts of it. 17. Under the FSP‟s direction , Mr G provided a quote for repairing the damage from his own business. However, while he acknowledged the severity of the impact to the fence structure, Mr G‟s quote was confined to only a small part of the fence that was pushed over. Case No: 311676 Determination Page 3 of 12 18. It was inappropriate for the FSP to obtain a quote from Mr G because he caused damage to the fence. There is also conflict of interest as he is also insured by the FSP. 19. The fence structure is an integral structure built on the boundary of both properties. Therefore, it should be replaced as one structure and not as two independent items. The most cost effective replacement is a concrete sleeper wall. 20. He also considers the cost of installing the new retaining wall should be covered by the policy because there was previously no require ment for him to build one when the house was constructed. At that time, he could walk along the side of the fence on a path that was about 1 metre wide, but the neighbour ‟s storm water run-off washed this away. He refers to the following policy provisions: “ Reinstatement or replacement value We will also pay the reasonable cost to rebuild or repair any damaged part of your building to the same condition as when it was new. We will pay the additional costs required to comply with any statutory or by- laws associated with repair or removal of property, provided you were not required to comply with any by- laws before the loss or damage occurred” . 21. Earth movement, faulty material or workmanship has not contributed to the damage, as the fence structure did not exhibit any structural defects or faults prior to being impacted by the bobcat. 22. Regardless how well the concrete border was constructed, the impact from the bobcat was so severe that it would have damaged whatever was in its way. In his view, the damage was ca used by Mr G‟s contractor‟s negligence. 23. He should not be out of pocket due to something that he had no control over and it is unfair for the FSP to back away from its obligation under the policy terms and conditions. 24. He does not wish to receive any cash payment; he simply wants the fence returned to its pre-loss condition, which would now include the costs associated with the installation of a new retaining wall. Summary of FSP’ s position 25. Expert evidence clearly established that at the time of the construction of the insured‟s property, a retaining wall should have been erected to support the fence structure. 26. The original construction does not include a retaining wall and therefore, it should not be required to install one now. 27. The Applicant‟s policy does n ot extend to provide cover for the installation of items that were not present before the loss. Case No: 311676 Determination Page 4 of 12 28. It offered to pay 50% of the cost involved to replace the dividing fence as fences are regarded as a joint asset between neighbours. 29. A fence on the boundary is legally considered to be part of the land on each side. Courts will assume that each will get equal benefit from the fence and therefore should contribute equally to the cost of repairing, maintaining or erecting a fence. 30. Under section 12(7) of the Fences Act 1975 (SA) it states: “If fencing work consist in the erection of an adequate fence or a fence of better quality than an adequate fence, or the conversion of an existing fence into an adequate fence or a fence of better quality than an adequate fence, then, in the absence of agreement between the adjoining owners, the contribution for which an adjoining owner is liable shall be one-half of the minimum cost of erecting an adequate fence, or converting the existing fence into an adequate fence.” 31. In accordance with section 12(7) of the Fences Act 1975 (SA), the property owners must share the cost of building and maintaining boundary fences. The costs to build or mend an “adequate” fence – one that meets council laws – are normally split 50:50. 32. Therefore, the payment issued to the Applicant of $3,546.35, being 50% of the cost involved in replacing the dividing fence is fair and reasonable. 33. The FSP relies on the following policy provisions: “ What you are insured for We will pay for loss or damage caused by the Occurences listed under Defined Events Cover or Accidental Damage Cover to your Buildings or Contents, depending on the cover you have selected. ... SECTION A – HOME COVER Subsections 1 & 2 – Building & Contents Cover Method of settlement Building Reinstatement or replacement value We will also pay the reasonable costs to rebuild or repair any damaged part of your Building to the same condition as when it was new. We will pay the additional costs required to comply with any statutory authority or by-laws associated with repair or removal of property, provided you were not required to comply with any of the by-laws before the loss or damage occurred. ... What you are not insured for Under Section A – Home Cover will not pay for: 2. Loss of or damage to your property caused by: Case No: 311676 Determination Page 5 of 12 b. earth movement, vibration, erosion, landslide or subsidence (except when caused by earthquake); ... e. faulty materials, faulty workmanship, wrong or incorrect design, plan or specification or failure of design. ” Issue 34. The extent of the FSP‟s obligation under the terms and conditions of the policy. Reasons for Decision 35. Due to the nature of this dispute, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. The parties have been previously advised that a Determination will be issued in this case. 36. I am satisfied a full exchange of informa tion has taken place between the parties and each party has had the opportunity to address any issues raised. 37. Each FOS case is decided on its merits, taking into account the facts of the case. I have carefully reviewed all the material submitted by the parties in order to reach my decision. I will only refer to the relevant submissions and materials raised. 38. It is not disputed the Applicant suffered a loss from a risk insured against, when the bobcat impacted the fence in 2008. What is in dispute is the extent of that damage and the extent of the Applicant‟s entitlement , in view of the exclusions relied on by the FSP. 39. It is an accepted principle of general insurance law that an insured bears the onus to establish, on the balance or probabilities, that the insured has suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. 40. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies, if it wishes to deny or limit its liability for the loss. 41. In this matter, the Applicant must prove that he has suffered a loss to which the policy responds. The Applicant‟s policy provides cover for accidental loss or damage. The Applicant must show that the bobcat caused all the damage to the entire fence and that a new retaining wall must be built because of the damage done by the bobcat and other events. Case No: 311676 Determination Page 6 of 12 42. If established, the onus shifts to the FSP to prove that the loss or damage to the fence and the necessity to build the new retaining wall is excluded from cover as it was caused by earth movement, erosion or subsidence or by incorrect design. 43. The Applicant has raised a number of issues regarding his neighbour‟s conduct. However, these issues do not fall within the Service‟s jurisdiction and as such, I am unable to consider them. I will only address the issues that I consider pertinent to the outcome of the Applicant‟s dispute with the FSP. The evidence and contentions of the parties 44. The Applicant‟s case is summarised above. He has provided no expert reports. He has provided a quote from AP dated 29 October 2012 to repair the damage for $14,454. I do not know whether AP has considered the drawings provided by the FSP‟s experts and has quoted on those scope of works. 45. The FSP‟s case is also summarised above. The FSP has provided a number of expert reports prepared by ADC (a licenced builder) and MP (an engineer). ADC inspected the damage on 9 February 2011 and MP‟s inspection was on 4 May 2011. I have read those reports carefully and examined the photographs provided by both parties. 46. ADC discussed the structural requirements. He says any retaining wall structure must incorporate stormwater management. He also said poorly designed retaining walls are notorious for failure and proposed three methods to construct the retaining wall. He said whatever method is selected that:  The wall will need to have its structural base at the level of the ground adjacent to the Applicant‟s house not on top of the remaining mould against the boundary.  Any option will require Council approval. 47. MP also noted at the time of writing the report in 2011:  The insured home was built about 9 to 10 years ago (about 2001).  Before construction, the property was benched and the general front of the block of land was lowered with some of the soil graded towards the rear of the property.  No specific work was done to the southern boundary fence and one could walk along the embankment and talk face to face with the neighbour which is no longer the case.  About 18 months - 2 years ago (about 2008/2009) the size of the embankment diminished. Case No: 311676 Determination Page 7 of 12  At about that time, the southern neighbour changed. The house was reroofed and the gutters and downpipes redirected. Water discharged under the fence on to the Applicant‟s property al though some of the water was reported to discharge generally into the rear fence south-western corner before this. (I note a letter to the Council from the Applicant dated 23 May 2011 says this happened “almost three years ago”).  MP reviewed the report from ADC and agreed that the stability of the fence where the embankment has been reduced has been compromised not only by the removal of the part of the embankment when building the Applicant‟s house , but also the stormwater run-off from the neighbour has contributed to the fence footing beams structural incompetence.  He also agrees with ADC‟s recommendations regarding rectification and that the quotes provided from the two builders are inadequate.  He provided a scope of works which included a separate 5 to 6 metre length of impact damaged fence and footing beam and an appropriate 17 meter length of new retaining wall to stabilise the existing fence footing beam. He says the existing fence beam footing is not structurally suitable to act as a retaining wall.  T he assessor also asked MP whether the “retaining wall” was properly constructed in the first place. The assessor notes in his report of 12 August 2011 that MP replied that the benching of the site “has not helped matters” and that “it was always going to erode”. 48. The following are relevant extracts from the reports: ADC’s report dated 11 February 2011: “it is evident that the residence at #8, the fence and concrete edge were constructed many years before the residence at #4-6 was constructed... the concrete wall is only a fairly sturdy unreinforced „concrete border‟, not a retaining wall. Equally evident …is the fact that the #4 -6 site was excavated to conduct a level “bench” in order to accommodate the house. ... The degree of soil shoulder left to support the boundary in the area behind the side fence is uncertain, as there has been some subsidence and washing away since the recent incidents. It does seem reasonable to assume that the profile would have been similar to that shown...as the side fence was obviously constructed accordingly. It is certain that the soil shoulder was inadequate to support the fence structure indefinitely and that failure would have occurred eventually in any case. The site at #8 has a fall to the rear and RH side and there is no storm water management other than the concrete edge in question. The down pipes on that side are damaged ... and discharging alongside the fence. This situation would certainly result in saturation of the soils along the boundary in a sustained rain period and expedite the abovementioned failure. Case No: 311676 Determination Page 8 of 12 It would be normal practice, when constructing the house #4-6, to either leave an adequate soil shoulder with a protective covering or to construct a retaining wall at the outset. The claim that damage to the concrete edge was caused by earthmoving machinery cannot be substantiated by the current evidence but is consistent and not disputed. (It is a strong possibility that the damage would not have been anywhere near as severe if the structure had been adequately supported on the low side.) It is clear that the fence is being undermined upstream of the damaged section and is perilously close to falling over. It is evident that ongoing water discharge from #8 is worsening the problem and will result in failure of up to 15m of the structure (plus probable subsidence of the house at #8) over a relatively short time span. The fence is/was... slightly dilapidated but structurally sound 1.5m high galvanised iron construction and was, before the incident in question, in serv iceable order. This type of fencing is considered adequate in this area….. ... CONCLUSIONS:  The fence and concrete border were structurally sound and constituted adequate storm water control at #8 prior to excavation at #4-6.  The excavation of #4-6 has resulted in insufficient support for the fence and border.  The poor storm water management at #8 has acerbated undermining of the structure.  The alleged „Bobcat‟ damage has directly exacerbated the damage, probably in one area only.  The structure currently presents a significant danger and should be demolished or shored immediately, to prevent toppling.  An engineered or certified proprietary retaining wall is required to provide a sound solution”. MP’s report dated 20 June 2011: “ SUMMARY In the writer‟s opinion, based on the available evidence, there had been a number of contributing factors which had led to the condition of the insured‟s southern boundary fence. The impact from the southern neighbour‟s tree removal is not in question. However, over the years since the alignment and level of the natural ground was altered due to the preparation of the insured‟s dwelling foundation platform, it is likely the embankment depth and width had allowed the fence footing to become slowly undermined, but the reported relatively rapid disappearance of the embankment in the last 2 or so years is consistent with the impact that the neighbour‟s reconfigured discharging surface and roof stormwater has likely washed the embankment‟s soil away from and underneath the concrete fence footing beam. The essence of the [building consultant] report dated 11 February 2011 is consistent with the writer‟s observations from our 4 May 2011 site inspection. We agree with the extent of repair required and believe the most economical Case No: 311676 Determination Page 9 of 12 replacement wall is a steel upright, concrete pier footing and concrete horizontal sleeper retaining wall designed to retain a depth of soil measured from the insured‟s flat ground level and a fence height to match the existing. An appropriate surcharge live load should be applied on the neighbour‟s ground line”. 49. JL provided a quote dated 2 November 2011 to the FSP to repair the damaged part of the dividing fence and concrete plinth in the amount of $7,092.70. The retaining wall was quoted at $16,714.85. Analysis 50. The FSP does not deny that the bobcat‟s impact has caused damage to the fence and its supporting structure, but the FSP says it will not pay for the retaining wall costs, as that loss is excluded from cover as the excavation of the ground at the time of the original building construction has contributed to fence‟s collapse as a retaining wall should have been built then. It also seeks to limit liability to only 50% costs of reinstating the impact-damaged section of the fence because of the Fences Act. 51. T he FSP‟s experts‟ site inspections occurred a few years after the impact incident and after the soil and site conditions had already changed and deteriorated significantly. Therefore, I do not accept that they knew of the conditions at the time of the impact damage so as to conclusively determine the cause and extent of contribution to the fence‟s collapse. 52. I do not accept that the expert evidence is conclusive that the excavation at the Applicant‟s property upon construction of the house had actually undermined the structure in the sense that it could be regarded as a dominant cause of the damage. Whilst it may have contributed, I do not accept that the level of its contribution was so significant that it can be regarded as a dominant cause, particularly because the fence structure was still functional prior to the bobcat‟s impact. 53. I note, ADC says in his report that “ the degree of soil shoulder left to support the boundary …is uncertain as there has been …washing away since the recent incidents ” and “it is a strong possibility that the damage would not have been anywhere near as severe if the structure had been adequately supported on the low side”, but I do not accept this amounts to the standard necessary – that this is established on the balance of probabilities that the lack of support caused the damage. 54. ADC is certain however, that “ the soil shoulder was inadequate to support the fence indefinitely and that failure would have occurred eventually in any case.” He is also certain that the stormwater from the neighbour ‟s property has expedited the failure and that the bobcat has made the damage worse in one area. 55. I also noted the following comments from MP:  The impact from the neighbour‟s bobcat is not in question.  The benching of the site has not helped matters. Case No: 311676 Determination Page 10 of 12  Excavation was “likely” to have “slowly undermined” the fence footing .  The relatively rapid disappearance of the embankment in the last two or so years is consistent with the impact that the neighbour‟s reconfigured discharging surface and roof stormwater has likely washed the embankment‟s soil away. 56. When read together, I accept that the experts say with the requisite degree of certainty, that the bobcat‟s impact coupled with the poor stormwater drainage at the neighbour‟s property were the caus es of the damage to the fence and the footing. I do not accept that the experts can say that on the balance of probabilities, that the Applicant‟s excavation works were a cause of the damage at the time of the bobcat impact. I do accept that the fence would have failed eventually but not necessarily at the time of the bobcat impact in 2008. 57. The experts inspected the property in 2011. It is evident that the neighbour‟s property had poor drainage and the area was left to deteriorate further (post impact) because the neighbour failed to rectify this problem. 58. In my view, the evidence points to a conclusion that the impact damage coupled with the poor stormwater drainage at the neighbour‟s property had made the structure deteriorate more quickly than it would have had over time without these two events. 59. It is also critical to note that whilst the FSP ‟s experts considered that the Applicant should have left adequate soil shoulder or constructed a retaining wall when the house was constructed, Council‟s approved pl ans did not require him to do this. I accept that the Applicant is entitled to rely on the Council‟s approved plans. I do not accept that on the balance of probabilities that exclusion 2 e. in the policy applies to exclude or limit this claim. 60. Having regarded all the above, I am satisfied that the main cause of the collapse of the fence and the concrete edge was the impact by the bobcat in one area and the poor stormwater management by the neighbour which has undermined the fence structure. 61. The damage caused by the impact of the bobcat is covered under the policy. I do not accept that on the balance of probabilities that exclusion 2 b in the policy applies to exclude or limit this claim. The loss or damage to the fence was not caused by earth movement or erosion but by the poor stormwater management by the neighbour. This is an event that the Applicant neither expected nor intended to happen and which resulted in damage to the fence structure and is covered under the policy. T he FSP’s Settlement Offer 62. The Ap plicant‟s home insurance policy provides that the FSP will pay reasonable costs to rebuild or repair any damaged part of the building to the same condition as when it was new. It also pays the additional costs required to comply with any statutory authority or by-laws associated with Case No: 311676 Determination Page 11 of 12 repair or removal of property, provided the Applicant were not required to comply with any of the by-laws before the loss or damage occurred. 63. The policy also provides that the FSP can, at its option, cash settle the claim or repair or replace the damaged part of the building. 64. The FSP did not dispute that the fence support structure was not repairable following the impact by the bobcat and its replacement of the damaged section, including a retaining wall, is required to meet current Australian Building Standards and requires Council approval. 65. However, it relies on section 12(7) of the Fences Act to argue that it is entitled to limit its liability to 50% of the costs of repairing the impact damage section only. 66. I accept that the FSP is not liable to replace the whole fence but only that part actually damaged by the bobcat. I am not satisfied that the whole of the fence has to be replaced. Rather, the expert evidence is that the bobcat damaged only part of the fence. In the absence of objective independent evidence from the Applicant, I accept that is the extent of the damage. 67. However, I am not satisfied that the FSP is entitled to limit its liability to 50% of the costs of repairing the impact damage. The claim on the FSP is governed by the policy and in that regard, the policy provides that the Applicant is entitled to full indemnity for his loss. 68. I do not accept that section 12(7) of the Fences Act is relevant to the claim made by the Applicant against the FSP for indemnity. I do not accept that it allows the FSP to reduce its liability under the policy for a neighbour‟s acts both causing the impact damage and allowing poor stormwater drainage on to his neighbour‟s property. 69. In this circumstance, I find that the Applicant is entitled to full indemnity for the loss caused by the bobcat to the fence. However, the FSP is not liable to repair that part of the fence not damaged by the bobcat. The FSP may have recovery rights against the neighbour rather than reduce the Applicant‟s claim by 50%. 70. As for the retaining wall, although I accept it was not there before but rather a concrete edge was constructed, the policy does provide that the FSP is to pay any additional cost required to comply with any statutory authority or by laws associated with the repair. In my view, it is fair in all the circumstances that the fence and its retaining structure complies with the scope of works and all relevant building standards and local council approval that apply now but may not have been in force at the time the fence was constructed. I am of this view, particularly in circumstances where the FSP‟s own expert, MP, said the existing fence beam footing is not structurally suitable to act as a retaining wall and that any option will require Council approval. 71. The FSP has a quote to repair part of the dividing fence and build the retaining wall for $23,807.55. The Applicant has submitted a quote for Case No: 311676 Determination Page 12 of 12 $14,454 to remove the existing fence and build a new one and construct the retainer wall. The FSP should consider the quotes and adjust the claim accordingly at all times ensuring that the quotes are for work to be done that is structurally suitable to act as a retaining wall. Determination 72. On the basis of the available information and for the reasons stated, I determine that the FSP is liable to pay for the installation of a new retaining wall and is liable to pay all the cost of replacing that part of the dividing fence damaged by the bobcat less the policy excess. 73. The FSP is entitled to exercise its right under the terms of the policy to decide the method of settlement. 74. Should the FSP decide to cash settle the claim, the amount payable should also include interest at a statutory rate from 12 January 2012 (being the date of its IDR decision) until payment is made.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.