Extent of insurer's liability for accidental damage to boundary fence and retaining wall
Text of the determination
Case No: 311676 Determination Page 1 of 12
Case number: 311676
General Insurance - Domestic Insurance - Home Building - FSP Decision –
Extent of the FSP’s Liability - Clause 8.2 of FOS’s Terms of Reference.
29 November 2013
Summary
Description: This dispute concerns a claim by the Applicant under a home building
insurance policy for accidental damage to a boundary fence.
Basis for Determination: The causes of the damage to the fence were such that
the accidental damage policy did respond to the claim. The policy provision
regarding reinstatement applied. The policy exclusions of erosion and wrong design
did not apply. The FSP was not entitled to pay only half the claim pursuant to the
Fences Act.
Determination: The FSP is to indemnify the Applicant.
Background
1. The Financial Service Provider is legally represented. For the sake of
simplicity, both parties will be referred to as the (“FSP”) herein.
2. The Applicant insured his home and contents for accidental damage under a
home insurance policy issued by the FSP.
3. On 20 O ctober 2008, the Applicant‟s neighbour (“Mr G”) engaged a tree
lopping contractor to remove a tree root. In doing so, the contractor impacted
the dividing fence with a bobcat.
4. After becoming aware that Mr G had no intention of getting the fence
repaired, the Applicant lodged a claim for the damage with the FSP on 30
July 2009.
5. The FSP‟s assessor (“CL”) attended the property to inspect the damage. CL
obtained two quotes for repairing the damage, one of which was obtained
from Mr G‟s business.
6. Upon receipt of CL‟s reports, the FSP offered to pay the Applicant
$2,159.50. This amount represents 50% of the costs of repairing the fence
by Mr G‟s business.
Determination
Case No: 311676 Determination Page 2 of 12
7. The claim was closed because the Applicant did not respond to the FSP‟s
offer. However, it was re-opened in November 2010 as requested by the
Applicant.
8. The FSP engaged a new assessor (“MYI”) to investigate the claim. MYI
considered a more specialist analysis of the damage was required, so it
ins tructed a building consultant (“ADC”) and an engineer (“MP”) to report on
the damage.
9. Both experts shared common views regarding the causes leading to the
current deteriorated condition of the fence. They reported that the fence
structure failed due to a combination of stormwater run-off from the
neighbour and the impact from the bobcat.
10. MYI appointed a builder (JL) to provide a quote for repairing the damage,
based on MP‟s specifications.
11. Following receipt of the experts‟ reports and JL‟s quote, the FS P accepted
the impact damage and offered to pay the Applicant $3,446.35 (being 50%
of JL‟s quote, less $100 policy excess). However, it advised the Applicant
that it would not cover the costs associated with installing a retaining wall.
12. The Applicant rejected the offer, as he believes the entire fence required
replacement due to the severity of the impact. He seeks reinstatement of the
entire fence structure, including a retaining wall.
13. The Applicant has provided a quote from his own builder for reinstatement of
the fence and a new retaining wall for the cost of $14,454.
Summary of Applicant’s p osition
14. The fence structure sustained severe damage following the impact by the
bobcat. The current condition of the entire structure poses a significant
danger to his family and Mr G‟s tenants.
15. Although the FSP elected to limit the damage to a 7 metre section, the
severity of the impact also damaged 20 metres of the front and middle
sections of the fence and footings (including pillars which were embedded
into the ground) and pushed some 1.5 tonne of solid concrete, dirt and fence
into his yard.
16. He did not accept the FSP‟s offer because he purchased the insurance
policy to cover the cost of fixing the damage and not just parts of it.
17. Under the FSP‟s direction , Mr G provided a quote for repairing the damage
from his own business. However, while he acknowledged the severity of the
impact to the fence structure, Mr G‟s quote was confined to only a small part
of the fence that was pushed over.
Case No: 311676 Determination Page 3 of 12
18. It was inappropriate for the FSP to obtain a quote from Mr G because he
caused damage to the fence. There is also conflict of interest as he is also
insured by the FSP.
19. The fence structure is an integral structure built on the boundary of both
properties. Therefore, it should be replaced as one structure and not as two
independent items. The most cost effective replacement is a concrete
sleeper wall.
20. He also considers the cost of installing the new retaining wall should be
covered by the policy because there was previously no require ment for him
to build one when the house was constructed. At that time, he could walk
along the side of the fence on a path that was about 1 metre wide, but the
neighbour ‟s storm water run-off washed this away. He refers to the following
policy provisions:
“ Reinstatement or replacement value
We will also pay the reasonable cost to rebuild or repair any damaged part of
your building to the same condition as when it was new.
We will pay the additional costs required to comply with any statutory or by-
laws associated with repair or removal of property, provided you were not
required to comply with any by- laws before the loss or damage occurred” .
21. Earth movement, faulty material or workmanship has not contributed to the
damage, as the fence structure did not exhibit any structural defects or faults
prior to being impacted by the bobcat.
22. Regardless how well the concrete border was constructed, the impact from
the bobcat was so severe that it would have damaged whatever was in its
way. In his view, the damage was ca used by Mr G‟s contractor‟s negligence.
23. He should not be out of pocket due to something that he had no control over
and it is unfair for the FSP to back away from its obligation under the policy
terms and conditions.
24. He does not wish to receive any cash payment; he simply wants the fence
returned to its pre-loss condition, which would now include the costs
associated with the installation of a new retaining wall.
Summary of FSP’ s position
25. Expert evidence clearly established that at the time of the construction of the
insured‟s property, a retaining wall should have been erected to support the
fence structure.
26. The original construction does not include a retaining wall and therefore, it
should not be required to install one now.
27. The Applicant‟s policy does n ot extend to provide cover for the installation of
items that were not present before the loss.
Case No: 311676 Determination Page 4 of 12
28. It offered to pay 50% of the cost involved to replace the dividing fence as
fences are regarded as a joint asset between neighbours.
29. A fence on the boundary is legally considered to be part of the land on each
side. Courts will assume that each will get equal benefit from the fence and
therefore should contribute equally to the cost of repairing, maintaining or
erecting a fence.
30. Under section 12(7) of the Fences Act 1975 (SA) it states:
“If fencing work consist in the erection of an adequate fence or a fence of
better quality than an adequate fence, or the conversion of an existing fence
into an adequate fence or a fence of better quality than an adequate fence,
then, in the absence of agreement between the adjoining owners, the
contribution for which an adjoining owner is liable shall be one-half of the
minimum cost of erecting an adequate fence, or converting the existing fence
into an adequate fence.”
31. In accordance with section 12(7) of the Fences Act 1975 (SA), the property
owners must share the cost of building and maintaining boundary fences.
The costs to build or mend an “adequate” fence – one that meets council
laws – are normally split 50:50.
32. Therefore, the payment issued to the Applicant of $3,546.35, being 50% of
the cost involved in replacing the dividing fence is fair and reasonable.
33. The FSP relies on the following policy provisions:
“ What you are insured for
We will pay for loss or damage caused by the Occurences listed under
Defined Events Cover or Accidental Damage Cover to your Buildings or
Contents, depending on the cover you have selected.
...
SECTION A – HOME COVER
Subsections 1 & 2 – Building & Contents Cover
Method of settlement
Building
Reinstatement or replacement value
We will also pay the reasonable costs to rebuild or repair any damaged part of
your Building to the same condition as when it was new.
We will pay the additional costs required to comply with any statutory authority
or by-laws associated with repair or removal of property, provided you were
not required to comply with any of the by-laws before the loss or damage
occurred.
...
What you are not insured for
Under Section A – Home Cover will not pay for:
2. Loss of or damage to your property caused by:
Case No: 311676 Determination Page 5 of 12
b. earth movement, vibration, erosion, landslide or subsidence (except when
caused by earthquake);
...
e. faulty materials, faulty workmanship, wrong or incorrect design, plan or
specification or failure of design. ”
Issue
34. The extent of the FSP‟s obligation under the terms and conditions of the
policy.
Reasons for Decision
35. Due to the nature of this dispute, FOS has considered it appropriate to
expedite the dispute in accordance with the Operational Guidelines to the
FOS Terms of Reference. This dispute has not been the subject of a FOS
Recommendation and has proceeded directly to Determination. The parties
have been previously advised that a Determination will be issued in this
case.
36. I am satisfied a full exchange of informa tion has taken place between the
parties and each party has had the opportunity to address any issues raised.
37. Each FOS case is decided on its merits, taking into account the facts of the
case. I have carefully reviewed all the material submitted by the parties in
order to reach my decision. I will only refer to the relevant submissions and
materials raised.
38. It is not disputed the Applicant suffered a loss from a risk insured against,
when the bobcat impacted the fence in 2008. What is in dispute is the extent
of that damage and the extent of the Applicant‟s entitlement , in view of the
exclusions relied on by the FSP.
39. It is an accepted principle of general insurance law that an insured bears the
onus to establish, on the balance or probabilities, that the insured has
suffered a loss caused by an event to which the policy responds. This is
known as a prima facie claim.
40. Once so established, the onus shifts to the insurer to prove on the balance of
probabilities that an exclusion applies, if it wishes to deny or limit its liability
for the loss.
41. In this matter, the Applicant must prove that he has suffered a loss to which
the policy responds. The Applicant‟s policy provides cover for accidental loss
or damage. The Applicant must show that the bobcat caused all the damage
to the entire fence and that a new retaining wall must be built because of the
damage done by the bobcat and other events.
Case No: 311676 Determination Page 6 of 12
42. If established, the onus shifts to the FSP to prove that the loss or damage to
the fence and the necessity to build the new retaining wall is excluded from
cover as it was caused by earth movement, erosion or subsidence or by
incorrect design.
43. The Applicant has raised a number of issues regarding his neighbour‟s
conduct. However, these issues do not fall within the Service‟s jurisdiction
and as such, I am unable to consider them. I will only address the issues that
I consider pertinent to the outcome of the Applicant‟s dispute with the FSP.
The evidence and contentions of the parties
44. The Applicant‟s case is summarised above. He has provided no expert
reports. He has provided a quote from AP dated 29 October 2012 to repair
the damage for $14,454. I do not know whether AP has considered the
drawings provided by the FSP‟s experts and has quoted on those scope of
works.
45. The FSP‟s case is also summarised above. The FSP has provided a number
of expert reports prepared by ADC (a licenced builder) and MP (an
engineer). ADC inspected the damage on 9 February 2011 and MP‟s
inspection was on 4 May 2011. I have read those reports carefully and
examined the photographs provided by both parties.
46. ADC discussed the structural requirements. He says any retaining wall
structure must incorporate stormwater management. He also said poorly
designed retaining walls are notorious for failure and proposed three
methods to construct the retaining wall. He said whatever method is selected
that:
The wall will need to have its structural base at the level of the ground
adjacent to the Applicant‟s house not on top of the remaining mould
against the boundary.
Any option will require Council approval.
47. MP also noted at the time of writing the report in 2011:
The insured home was built about 9 to 10 years ago (about 2001).
Before construction, the property was benched and the general front of
the block of land was lowered with some of the soil graded towards the
rear of the property.
No specific work was done to the southern boundary fence and one could
walk along the embankment and talk face to face with the neighbour
which is no longer the case.
About 18 months - 2 years ago (about 2008/2009) the size of the
embankment diminished.
Case No: 311676 Determination Page 7 of 12
At about that time, the southern neighbour changed. The house was
reroofed and the gutters and downpipes redirected. Water discharged
under the fence on to the Applicant‟s property al though some of the water
was reported to discharge generally into the rear fence south-western
corner before this. (I note a letter to the Council from the Applicant dated
23 May 2011 says this happened “almost three years ago”).
MP reviewed the report from ADC and agreed that the stability of the
fence where the embankment has been reduced has been compromised
not only by the removal of the part of the embankment when building the
Applicant‟s house , but also the stormwater run-off from the neighbour has
contributed to the fence footing beams structural incompetence.
He also agrees with ADC‟s recommendations regarding rectification and
that the quotes provided from the two builders are inadequate.
He provided a scope of works which included a separate 5 to 6 metre
length of impact damaged fence and footing beam and an appropriate 17
meter length of new retaining wall to stabilise the existing fence footing
beam. He says the existing fence beam footing is not structurally suitable
to act as a retaining wall.
T he assessor also asked MP whether the “retaining wall” was properly
constructed in the first place. The assessor notes in his report of 12
August 2011 that MP replied that the benching of the site “has not helped
matters” and that “it was always going to erode”.
48. The following are relevant extracts from the reports:
ADC’s report dated 11 February 2011:
“it is evident that the residence at #8, the fence and concrete edge were
constructed many years before the residence at #4-6 was constructed... the
concrete wall is only a fairly sturdy unreinforced „concrete border‟, not a
retaining wall.
Equally evident …is the fact that the #4 -6 site was excavated to conduct a
level “bench” in order to accommodate the house.
...
The degree of soil shoulder left to support the boundary in the area behind the
side fence is uncertain, as there has been some subsidence and washing
away since the recent incidents. It does seem reasonable to assume that the
profile would have been similar to that shown...as the side fence was
obviously constructed accordingly.
It is certain that the soil shoulder was inadequate to support the fence
structure indefinitely and that failure would have occurred eventually in any
case.
The site at #8 has a fall to the rear and RH side and there is no storm water
management other than the concrete edge in question. The down pipes on
that side are damaged ... and discharging alongside the fence. This situation
would certainly result in saturation of the soils along the boundary in a
sustained rain period and expedite the abovementioned failure.
Case No: 311676 Determination Page 8 of 12
It would be normal practice, when constructing the house #4-6, to either leave
an adequate soil shoulder with a protective covering or to construct a retaining
wall at the outset.
The claim that damage to the concrete edge was caused by earthmoving
machinery cannot be substantiated by the current evidence but is consistent
and not disputed. (It is a strong possibility that the damage would not have
been anywhere near as severe if the structure had been adequately
supported on the low side.)
It is clear that the fence is being undermined upstream of the damaged
section and is perilously close to falling over.
It is evident that ongoing water discharge from #8 is worsening the problem
and will result in failure of up to 15m of the structure (plus probable
subsidence of the house at #8) over a relatively short time span.
The fence is/was... slightly dilapidated but structurally sound 1.5m high
galvanised iron construction and was, before the incident in question, in
serv iceable order. This type of fencing is considered adequate in this area…..
...
CONCLUSIONS:
The fence and concrete border were structurally sound and constituted
adequate storm water control at #8 prior to excavation at #4-6.
The excavation of #4-6 has resulted in insufficient support for the
fence and border.
The poor storm water management at #8 has acerbated undermining
of the structure.
The alleged „Bobcat‟ damage has directly exacerbated the damage,
probably in one area only.
The structure currently presents a significant danger and should be
demolished or shored immediately, to prevent toppling.
An engineered or certified proprietary retaining wall is required to
provide a sound solution”.
MP’s report dated 20 June 2011:
“ SUMMARY
In the writer‟s opinion, based on the available evidence, there had been a
number of contributing factors which had led to the condition of the insured‟s
southern boundary fence. The impact from the southern neighbour‟s tree
removal is not in question. However, over the years since the alignment and
level of the natural ground was altered due to the preparation of the insured‟s
dwelling foundation platform, it is likely the embankment depth and width had
allowed the fence footing to become slowly undermined, but the reported
relatively rapid disappearance of the embankment in the last 2 or so years is
consistent with the impact that the neighbour‟s reconfigured discharging
surface and roof stormwater has likely washed the embankment‟s soil away
from and underneath the concrete fence footing beam.
The essence of the [building consultant] report dated 11 February 2011 is
consistent with the writer‟s observations from our 4 May 2011 site inspection.
We agree with the extent of repair required and believe the most economical
Case No: 311676 Determination Page 9 of 12
replacement wall is a steel upright, concrete pier footing and concrete
horizontal sleeper retaining wall designed to retain a depth of soil measured
from the insured‟s flat ground level and a fence height to match the existing.
An appropriate surcharge live load should be applied on the neighbour‟s
ground line”.
49. JL provided a quote dated 2 November 2011 to the FSP to repair the
damaged part of the dividing fence and concrete plinth in the amount of
$7,092.70. The retaining wall was quoted at $16,714.85.
Analysis
50. The FSP does not deny that the bobcat‟s impact has caused damage to the
fence and its supporting structure, but the FSP says it will not pay for the
retaining wall costs, as that loss is excluded from cover as the excavation of
the ground at the time of the original building construction has contributed to
fence‟s collapse as a retaining wall should have been built then. It also seeks
to limit liability to only 50% costs of reinstating the impact-damaged section
of the fence because of the Fences Act.
51. T he FSP‟s experts‟ site inspections occurred a few years after the impact
incident and after the soil and site conditions had already changed and
deteriorated significantly. Therefore, I do not accept that they knew of the
conditions at the time of the impact damage so as to conclusively determine
the cause and extent of contribution to the fence‟s collapse.
52. I do not accept that the expert evidence is conclusive that the excavation at
the Applicant‟s property upon construction of the house had actually
undermined the structure in the sense that it could be regarded as a
dominant cause of the damage. Whilst it may have contributed, I do not
accept that the level of its contribution was so significant that it can be
regarded as a dominant cause, particularly because the fence structure was
still functional prior to the bobcat‟s impact.
53. I note, ADC says in his report that “ the degree of soil shoulder left to support
the boundary …is uncertain as there has been …washing away since the
recent incidents ” and “it is a strong possibility that the damage would not
have been anywhere near as severe if the structure had been adequately
supported on the low side”, but I do not accept this amounts to the standard
necessary – that this is established on the balance of probabilities that the
lack of support caused the damage.
54. ADC is certain however, that “ the soil shoulder was inadequate to support
the fence indefinitely and that failure would have occurred eventually in any
case.” He is also certain that the stormwater from the neighbour ‟s property
has expedited the failure and that the bobcat has made the damage worse in
one area.
55. I also noted the following comments from MP:
The impact from the neighbour‟s bobcat is not in question.
The benching of the site has not helped matters.
Case No: 311676 Determination Page 10 of 12
Excavation was “likely” to have “slowly undermined” the fence footing .
The relatively rapid disappearance of the embankment in the last two or
so years is consistent with the impact that the neighbour‟s reconfigured
discharging surface and roof stormwater has likely washed the
embankment‟s soil away.
56. When read together, I accept that the experts say with the requisite degree
of certainty, that the bobcat‟s impact coupled with the poor stormwater
drainage at the neighbour‟s property were the caus es of the damage to the
fence and the footing. I do not accept that the experts can say that on the
balance of probabilities, that the Applicant‟s excavation works were a cause
of the damage at the time of the bobcat impact. I do accept that the fence
would have failed eventually but not necessarily at the time of the bobcat
impact in 2008.
57. The experts inspected the property in 2011. It is evident that the neighbour‟s
property had poor drainage and the area was left to deteriorate further (post
impact) because the neighbour failed to rectify this problem.
58. In my view, the evidence points to a conclusion that the impact damage
coupled with the poor stormwater drainage at the neighbour‟s property had
made the structure deteriorate more quickly than it would have had over time
without these two events.
59. It is also critical to note that whilst the FSP ‟s experts considered that the
Applicant should have left adequate soil shoulder or constructed a retaining
wall when the house was constructed, Council‟s approved pl ans did not
require him to do this. I accept that the Applicant is entitled to rely on the
Council‟s approved plans. I do not accept that on the balance of probabilities
that exclusion 2 e. in the policy applies to exclude or limit this claim.
60. Having regarded all the above, I am satisfied that the main cause of the
collapse of the fence and the concrete edge was the impact by the bobcat in
one area and the poor stormwater management by the neighbour which has
undermined the fence structure.
61. The damage caused by the impact of the bobcat is covered under the policy.
I do not accept that on the balance of probabilities that exclusion 2 b in the
policy applies to exclude or limit this claim. The loss or damage to the fence
was not caused by earth movement or erosion but by the poor stormwater
management by the neighbour. This is an event that the Applicant neither
expected nor intended to happen and which resulted in damage to the fence
structure and is covered under the policy.
T he FSP’s Settlement Offer
62. The Ap plicant‟s home insurance policy provides that the FSP will pay
reasonable costs to rebuild or repair any damaged part of the building to the
same condition as when it was new. It also pays the additional costs
required to comply with any statutory authority or by-laws associated with
Case No: 311676 Determination Page 11 of 12
repair or removal of property, provided the Applicant were not required to
comply with any of the by-laws before the loss or damage occurred.
63. The policy also provides that the FSP can, at its option, cash settle the claim
or repair or replace the damaged part of the building.
64. The FSP did not dispute that the fence support structure was not repairable
following the impact by the bobcat and its replacement of the damaged
section, including a retaining wall, is required to meet current Australian
Building Standards and requires Council approval.
65. However, it relies on section 12(7) of the Fences Act to argue that it is
entitled to limit its liability to 50% of the costs of repairing the impact damage
section only.
66. I accept that the FSP is not liable to replace the whole fence but only that
part actually damaged by the bobcat. I am not satisfied that the whole of the
fence has to be replaced. Rather, the expert evidence is that the bobcat
damaged only part of the fence. In the absence of objective independent
evidence from the Applicant, I accept that is the extent of the damage.
67. However, I am not satisfied that the FSP is entitled to limit its liability to 50%
of the costs of repairing the impact damage. The claim on the FSP is
governed by the policy and in that regard, the policy provides that the
Applicant is entitled to full indemnity for his loss.
68. I do not accept that section 12(7) of the Fences Act is relevant to the claim
made by the Applicant against the FSP for indemnity. I do not accept that it
allows the FSP to reduce its liability under the policy for a neighbour‟s acts
both causing the impact damage and allowing poor stormwater drainage on
to his neighbour‟s property.
69. In this circumstance, I find that the Applicant is entitled to full indemnity for
the loss caused by the bobcat to the fence. However, the FSP is not liable to
repair that part of the fence not damaged by the bobcat. The FSP may have
recovery rights against the neighbour rather than reduce the Applicant‟s
claim by 50%.
70. As for the retaining wall, although I accept it was not there before but rather
a concrete edge was constructed, the policy does provide that the FSP is to
pay any additional cost required to comply with any statutory authority or by
laws associated with the repair. In my view, it is fair in all the circumstances
that the fence and its retaining structure complies with the scope of works
and all relevant building standards and local council approval that apply now
but may not have been in force at the time the fence was constructed. I am
of this view, particularly in circumstances where the FSP‟s own expert, MP,
said the existing fence beam footing is not structurally suitable to act as a
retaining wall and that any option will require Council approval.
71. The FSP has a quote to repair part of the dividing fence and build the
retaining wall for $23,807.55. The Applicant has submitted a quote for
Case No: 311676 Determination Page 12 of 12
$14,454 to remove the existing fence and build a new one and construct the
retainer wall. The FSP should consider the quotes and adjust the claim
accordingly at all times ensuring that the quotes are for work to be done that
is structurally suitable to act as a retaining wall.
Determination
72. On the basis of the available information and for the reasons stated, I
determine that the FSP is liable to pay for the installation of a new retaining
wall and is liable to pay all the cost of replacing that part of the dividing fence
damaged by the bobcat less the policy excess.
73. The FSP is entitled to exercise its right under the terms of the policy to
decide the method of settlement.
74. Should the FSP decide to cash settle the claim, the amount payable should
also include interest at a statutory rate from 12 January 2012 (being the date
of its IDR decision) until payment is made.