Storm water damage claim denied as faulty workmanship; damage from make-safe works
Text of the determination
Case No: 311154 Determination Page 1 of 12
Case number: 311154
General Insurance - Domestic Insurance - Home Building - Service - Service
quality
19 February 2014
Summary
Description
This dispute concerns a claim by the Applicants for storm damage to their
property. The Financial Services Provider denied liability for the claim on
the basis that the damage to the roof of the property was not caused by a
storm, but by factors which were excluded under the policy. The
Applicants dispute the FSP’s denial of their claim and ar e also dissatisfied
with the make safe repairs arranged by the FSP, which they say have
caused further damage.
Basis of Determination
The available information establishes that the cause of the water damage
to the Applicants’ property was faulty workmansh ip in the construction of
their roof and/or balcony, which is excluded under the policy.
The Applicants have established that, on the balance of probabilities, the
FSP’s contractor did not follow an appropriate procedure to obtain their
authority prior to undertaking the make safe works.
The Applicants have failed to establish that the actions of the FSP’s
contractor caused them any financial loss, as the available information
establishes that the section of the ceiling removed by the FSP ’s contractor
would have needed to be replaced in any event. However, the Applicants
have suffered non-financial loss.
Determination
The FSP is entitled to deny the Applicants’ claim.
The FSP is to pay the Applicants’ the amount of $750 as compensation for
non-financial loss resulting from the actions of its contractor.
Determination
Case No: 311154 Determination Page 2 of 12
Background
1. This Determination follows the review of a Recommendation issued on
behalf of the Financial Ombudsman Service (FOS) on 2 December 2013.
The Recommendation was rejected by the FSP.
2. The Applicants held a home building and contents insurance policy with the
FSP which was current at the time of the loss.
3. On 12 October 2012, the Applicants lodged a claim with the FSP for water
damage to their property following a storm. The Applicants advised that
heavy rain had entered the tin roof and leaked into the ceiling, causing it to
bow in one area of the living room.
4. The FSP arranged for its contractor (“PP”) to carry out “make safe” repairs to
the property, which included removing a section of damaged plaster from the
living room ceiling.
5. The FSP subsequently denied the Applicants’ claim on the basis that the
damage was not caused by the storm, but was due to faulty workmanship.
6. The Applicants do not accept the FSP’s denial of liability. They also say that
t he make safe repairs undertaken by the FSP’s contractor caused further
damage to their property.
Summary of Applicants ’ position
7. The Applicants say that the water damage to their living room ceiling was
caused by a leak in the roof and therefore the FSP should indemnify them.
They deny that they have failed to maintain their home, on the basis that the
leak was located in a concealed area of the roof and could only be found by
lifting up tin roofing sheets above the living room.
8. The Applicants say that PP ’s removal of part of the living room ceiling in the
course of the make safe repairs was unnecessary, as the male Applicant
had already made a drill hole in the ceiling which allowed any remaining
water in the ceiling cavity to escape.
9. The Applicants say that they would not have authorised the make safe
works, had they had known that the FSP would not cover the cost of
repairing the resulting damage. They say that:
they were advised by the FSP that the make safe works would be
limited to placing a tarpaulin over the leaking area;
PP assured the female Applicant that the FSP would repair any
damage resulting from the make safe repairs; and
PP intimidated the female Applicant and refused to leave the property
unless she signed the make safe form.
Case No: 311154 Determination Page 3 of 12
10. Accordingly, the Applicants say that, even if the FSP is entitled to deny
liability for their claim, it should be required to reimburse them for the
difference between the cost of repairing the additional damage to the living
room ceiling caused by the make safe repairs and the cost of repairing the
original damage (estimated to be $2,150).
Summary of FSP’s position
11. The FSP says that:
PP considered that it was necessary to remove the relevant section of
the ceiling to avoid any additional damage to the property and potential
injury to the Applicants and their family, if the sagging plaster were to
fall; and
the Applicants have not been prejudiced by the make safe repairs as
the section of the ceiling which was removed was already so damaged
that the Applicants would have had to replace it in the course of
carrying out the necessary repairs.
12. The FSP says that PP denies that its employee intimidated the female
Applicant or acted in a threatening manner. Further, the FSP says that as
the claimed damage was not subject to cover under the policy, the dispute is
a private matter between PP and the Applicants.
13. The FSP notes that, as the Applicants’ claim was denied, it is entitled to
recover the cost of the make safe repairs from them. However, it has agreed
to bear these costs as a gesture of goodwill.
Issues
14. Whether the FSP is entitled to deny liability for the Applicants’ claim.
15. Whether the FSP is required to reimburse the Applicants for the damage to
their property caused by the make safe repairs.
Reasons for decision
16. I am satisfied that there has been an exchange of material information
between the parties and that each party has had an opportunity to address
any issues raised therein.
Cause of damage
17. While the Applicants’ submissions to FOS have primarily focussed on th e
FSP’s liability for damage to their property caused by the make safe repairs,
in the course of their submissions, the Applicants have also confirmed that
they do not accept the FSP’s denial of liability for their original claim.
Case No: 311154 Determination Page 4 of 12
Accordingly, it is necessary for me to determine the cause of the damage to
the Applicants’ property and, therefore, whether the FSP is entitled to deny
the Applicants’ claim.
Available information
18. After the Applicants lodged their claim, the FSP arranged for its builder (PP)
to attend the property to assess the damage and carry out make safe
repairs. P attended the property on 16 October 2012 and reported that:
there was damage to the living room ceiling and window arch caused
by water leaking in heavy rain;
the damage was consistent with water leaking from the roof/balcony
above the living room;
his inspection of the area above the leak showed no signs of storm
damage and no storm created openings were visible;
he suspected that the water was entering through gaps in the tiles of
the balcony above the living room as a result of the failure of the
waterproofing membrane applied to the balcony system, due to poor
workmanship at the time of construction. There was evidence of
previous attempts to repair the leaks, which indicated tha t this was a
long term issue unrelated to the recent storm; and
he had placed a tarpaulin over the balcony to prevent further leaks.
However, as he could not confirm that the balcony was the source of
the leaks, he had also arranged for a leak detection specialist to attend
the property.
19. The FSP’s leak detection specialist (“IL”) attended the property on
22 October 2010 and reported that:
his inspection of the property revealed several other areas of water
damage, all of which had occurred in areas directly underneath the
balcony;
the balcony was poorly maintained and the grout had deteriorated
throughout the entire tiled area. There was evidence of attempted
repairs using new grout and silicone had been applied to prevent water
entering the house; and
based on his observations, all of the water damage to the property was
a direct result of the failure of the waterproofing membrane applied to
the balcony. This was due to poor workmanship at the time of
construction and was in no way related to the storm.
20. Aft er reviewing PP and IL’s reports, the FSP denied the Applicants’ claim on
the basis that the water damage to their property was not caused by a storm
or any other insured event. The FSP noted that the damage was caused by
the poor construction of the balcony and therefore, also fell within the policy
exclusion for damage arising from faulty design or workmanship.
Case No: 311154 Determination Page 5 of 12
21. The Applicants subsequently advised the FSP that they were dissatisfied
with IL’s failure to carry out a spray test on the balcony and that, as re sult of
carrying out their own spray tests, they believed that the source of the leaks
was the roof, not the balcony. To address the Applicants’ concerns, the FSP
arranged for IL to carry out a further leak test, following which he reported
that:
when the roof was spray tested, the valley gutter timber supports
became wet, which showed that water was entering through the roof;
when he removed the roof sheets and ridge capping flashings from the
relevant area, he identified broken down silicon joints at the junction of
the soaker flashing system and the valley guttering system; and
it was apparent that, during the construction of the roof, the roof
plumber had cut the valley gutters weathering fold so that the soaker
flashing would sit flat. This had created a hole in the flashing system
which allowed water to enter the ceiling cavity of the lounge room.
22. After reviewing IL’s revised report, the FSP advised the Applicants that it
was willing to offer them an amount equal to 50% of the cost of the repairs
(less the applicable policy excess), on the basis that some of the water
damage may have been caused by the leak in the roof. The FSP says that
this offer was made on an ex gratia basis.
23. The FSP’s offer was rejected by the Applicants and the FSP now says that it
is entitled to deny liability for the Applicants’ claim , on the basis that the
Applicants have not established that the damage was caused by an insured
event and/or the damage falls within the policy exclusion for faulty
workmanship (as regards both the roof and the balcony).
Analysis
24. I have carefully reviewed the reports provided by the FSP’s contractors in
relation to the cause of the water damage to the Applicants’ property. After
conducting further tests, the leak detection specialist (IL) concluded that,
while the majority of the water damage was likely to have been caused by
the failure of the waterproofing membrane on the balcony, part of the
damage could also be attributable to the manner in which the roof had been
constructed.
25. The Applicants have maintained all along that the water damage to the living
room ceiling was caused by the roof, although they have acknowledged that
issues with the balcony may have been responsible for water damage to
other areas of the house. They say that there have been no further leaks
since they repaired the roof flashing.
26. However, the Applicants have not provided any information which
contradicts IL’s findings that the leak in the roof was caused by the manner
in which the roof plumber cut the valley gutters weathering fold during the
construction of the roof. In the absence of any conflicting information, I
Case No: 311154 Determination Page 6 of 12
accept IL’s findings that this was the cause of the leak in the roof (and
therefore the resulting water damage).
27. The Applicants say that the FSP should be liable for this damage because
the problem with the roof was located in a concealed area and could only be
found by lifting tin sheets from the roof above the living room.
28. The Applicants’ policy provides that the FSP is not liable for any damage
arising from faulty design or workmanship. The application of this exclusion
is unqualified and does not depend on whether or not the Applicants were
aware (or could reasonably have been aware) of the problem with the roof.
Accordingly, as it had been established that the leak was caused by faulty
workmanship (for the reasons set out above), it follows that the FSP is
entitled to rely on this policy exclusion to deny the Applicants’ claim.
29. Accordingly, even I were to accept the Applicants’ position that the leak in
the roof (and not the balcony) was the sole cause of the damage to their
ceiling, the FSP would still be entitled to deny liability for their claim, on the
basis that the underlyi ng cause of the damage was the faulty workmanship
by the roof plumber during the construction of the roof.
Make safe repairs
30. As a preliminary issue, I note that I do not accept the FSP’s argument that
the Applicants’ concerns about the behaviour of PP are a private matter
between PP and the Applicants. The FSP appointed PP to attend the
Applicants’ property for the purpose of undertaking make safe repairs and as
such, is responsible for the actions of PP as its contractor.
Available information
31. The Applicants have provided the following description of the events
surrounding PP’s attendance at their home to carry out the make safe
repairs. The Applicants say that:
the FSP arranged for PP to attend for the purpose of erecting a
tarpaulin to prevent further water entering the house, as more bad
weather was expected. The FSP expressly advised them that this
would be done at no cost to them;
the Applicants explained to the FSP that they had drilled a hole in the
ceiling to drain the water and would continue with this approach if there
were any further leaks. However, when the FSP offered to send PP to
their house, they accepted on the basis that no harm could be done by
erecting a tarpaulin to prevent further damage;
while PP was erecting the tarpaulin, he advised the female Applicant
that he would take out a section of the ceiling. PP said that he was
doing this in order to determine the source of the leak, not as a make
safe;
Case No: 311154 Determination Page 7 of 12
when the female Applicant asked PP about costs, he said that the FSP
would pay for the costs of any repairs to the ceiling as part of the claim.
On the basis of this statement, the female Applicant allowed PP to
proceed to remove the ceiling. This caused further damage;
before leaving the property, PP asked the female Applicant to sign an
“Authority to Safe and Makesafe”, she refused to sign this in the form in
which it was provided (which stated that the Applicants may be liable
for the costs of the make safe) because she had been advised that the
costs would be met by the FSP. When PP insisted that the document
be signed so that he could invoice the FSP for his work, the female
Applicant signed an amended form of the document; and
on 29 October 2012, the female Applicant contacted the FSP to find out
what was happening in relation to the dam age caused by PP’s work.
She was told by the FSP on 30 October 2012 that the FSP was not
liable for repairing this damage, as PP had advised that it was
necessary to remove the ceiling to make the property safe.
32. The FSP has provided copies of its claim records which reflect that the
female Applicant contacted the FSP on 22 October 2012 (some six days
after PP attended the property) to advise that she was not happy with how
the claim was progressing. During this conversation:
the female Applicant said that PP had made a big hole in the ceiling as
part of the make safe repairs and had asked her to sign a contract
stating that she was liable for the costs if the claim was not accepted;
the FSP confirmed that, if the claim was not accepted, it would not
cover the cost of replacing the section of the ceiling which had been
removed as part of the make safe repairs; and
the female Applicant expressed her view that it was unnecessary for
PP to remove such a large part of the ceiling.
33. The FSP subsequently contacted PP to ask why he had removed part of the
ceiling. PP advised that:
the holes drilled in the ceiling were not sufficient to mitigate further
damage given the amount the ceiling had started to drop;
the plaster in the relevant section of the ceiling had suffered significant
and ongoing water damage and had become spongy and mouldy as a
result. The plaster was sagging and there was wet insulation above it
which was putting weight on the plaster and had already started pulling
it away from the battens. The ceiling was very likely to have collapsed,
had this section of plaster not been removed;
this section of the ceiling would have required replacement in any event
as it had been damaged beyond repair. This would also have
necessitated repainting of the adjoining walls, given the way in which
the ceiling was designed;
Case No: 311154 Determination Page 8 of 12
in order to completely repair the water damage to the ceiling, it would
be necessary to remove a section of the ceiling three times as large as
the section which he removed; and
during the make safe repairs, he advised the female Applicant of each
step he was taking and obtained her approval.
34. The FSP has provided copies of:
a photograph taken by PP showing the damage to the relevant section
of the ceiling before it was removed. This shows the plaster bubbling
and areas of what appear to be mould; and
a photograph taken by IL showing the ceiling after the make safe
repairs were completed. This shows that PP removed a section of the
ceiling approximately 30 centimetres by 60 centimetres in area and
secured timber battens to the plaster around the area where this
section had been removed.
35. The FSP has also provided a copy of the “Authority to Safe and Makesafe
Form” signed by the female Applicant. As noted above, the female Applicant
refused to sign the form as printed. Instead, she inserted handwritten words
confirming that she accepted that PP had made the site safe and she was
happy and satisfied with the work carried out. She also amended the form
by:
deleting words acknowledging that she may later be required to pay
PP’s invoice;
inserting the words “Refused to sign” in the signature box provided
under the printed words which authorised PP to carry out the make
safe repairs; and
adding words stating that she accepted that the work was carried at no
cost to her and that the FSP had advised her that it would pay for the
costs of the make safe works.
36. The Applicants say that PP should have sought authority to carry out the
make safe works prior to commencing them, instead of presenting the form
for signing after the make safe works had already been completed.
37. The Applicants also say that it was not necessary for PP to remove the
relevant section of the ceiling because:
the water pressure on the ceiling had been removed due to the holes
drilled in the ceiling and therefore there was no possibility of the ceiling
collapsing; and
the ceiling was on a slope of around 20 degrees and therefore there
was no risk of further water pooling in the damaged area.
38. Finally, the Applicants say that, even if this part of the ceiling did ultimately
need to be removed, the fact that this was done by PP as part of the make
safe works means that they have been denied an opportunity to arrange for
it to be done by their own contractors at their convenience.
Case No: 311154 Determination Page 9 of 12
39. In support of their position, the Applicants have provided a copy of a report
from their builder / waterproofer (“AS”) dated 31 July 2013 which states that:
he has been advised by the Applicants that the original damaged area
of the ceiling was approximately 30 centimetres by 60 centimetres and
the damage was to the ceiling only;
in his opinion, the original damage as described by the Applicants was
significantly less than the damage currently present and could have
been repaired by a simple patch and repainting of part of the ceiling, at
a cost of approximately $700; and
the current damage will require a much larger patch for the ceiling, as
well as the repair and painting of two walls, at an estimated cost of
$2,850.
40. The FSP says that, based on PP’s advice, the make safe works were
necessary. The FSP has agreed to bear the costs of the make safe works
(for which it says the Applicants would ordinarily be liable), but says that it is
not liable for the costs of repairing the damage to the ceiling, as the repairs
would have been required in any event due to the extent of the water
damage. Accordingly, the FSP believes that the Applicants have not been
prejudiced by the fact that PP carried out the make safe repairs.
Analysis
41. The versions of events provided by the parties in relation to the make safe
repairs differ in significant respects. In particular:
the Applicants say that they were not aware that the removal of the
ceiling was part of the make safe repairs and understood that this was
being done in order to investigate the source of the leak. However, the
FSP says that the Applicants were fully informed about and approved,
each step of the make safe repairs;
the Applicants say that PP intimidated the female Applicant into signing
the make safe form, while the FSP strongly denies this; and
the Applicants say that they were expressly advised by the FSP that it
would fund the cost of the make safe repairs, and by PP that the FSP
would pay for any resultant damage. However, the FSP says that the
Applicants were made aware (by being provided with the make safe
form) that they would be liable if the FSP did not accept liability for their
claim.
42. In circumstances where the parties have provided differing versions of
events, it is appropriate to have regard to any available contemporaneous
documentation to determine, on the balance of probabilities, what is more
likely to have occurred.
43. Having reviewed all of the available information, I consider that:
the FSP claim notes do not provide any details as to what the
Applicants were told about the scope of the make safe repairs at the
Case No: 311154 Determination Page 10 of 12
time the FSP arranged for PP to attend their property. Having said this,
the removal of the ceiling appears to have been done solely at PP’s
suggestion. I accept that the Applicants genuinely believed that this
was unnecessary, given the measures which the male Applicant had
taken to prevent additional water pooling in the ceiling cavity;
the FSP’s claim notes of its discussions with the female Applicant on
22 October 2012, indicate that she was aware that the section of the
ceiling was removed as part of the make safe works (rather than to
investigate the source of the leak). Having said that, it does not
necessarily follow that the female Applicant fully understood this at the
time the relevant works were carried out;
the Applicants’ key concern in relation to the make safe repairs was to
ensure that they would not be liable for the costs. Even though the
make safe form made it clear that the Applicants may be liable for the
costs if their claim was denied, it is equally clear that the Applicants
expressly rejected this position, as evidenced by the handwritten
amendments to the form made by the female Applicant; and
in my view, the available information is not sufficient to establish that
PP intimidated the female Applicant into signing the form. I note that
the female Applicant’s actions in amending the form and inserting the
words “Refused to sign” suggest that she was at pains to ensure that
she only signed a version of the form which she was comfortable with.
44. It is possible that there was a genuine misunderstanding between the female
Applicant and PP as to whether or not she had authorised the removal of
part of the ceiling (and if so, for what purpose). PP has stated that he
understood that the female Applicant had verbally consented to the make
safe works. However, given that the make safe form is in two parts ( the first
part authorising the works and the second part confirming satisfaction with
them), it would have been appropriate for PP to have the female Applicant
sign the first section before commencing the works. The Applicants ’ version
of events (and the language she used to amend this section of the form)
suggests that this did not occur.
45. Having regard to the above, I consider that PP acted inappropriately in not
obtaining the Applicants’ written authorisation prior to commencing the make
safe works. Had he done so, it is possible that the Applicants would have
had an opportunity to gain a better understanding of what the works involved
and would have been able to make an informed decision as to whether or
not they wished PP to proceed with them.
46. However, based on the available information, I am not satisfied that PP ’s
failure to follow the appropriate process has resulted in any prejudice to the
Applicants. I consider that, on the balance of probabilities, the relevant
section of the ceiling would have required removal in any event. In this
respect, I note that:
PP has confirmed his view that this section of the ceiling was sagging
as a result of water damage and was subject to further weight from the
Case No: 311154 Determination Page 11 of 12
wet insulation above it. Accordingly, he considered it to be so damaged
that it required replacement and constituted a potential danger to the
Applicants and their family. I accept that, as a builder, PP is
appropriately qualified to express a view as to the extent of the damage
to the ceiling;
the FSP’s claim notes reflect that when they lodged their claim, the
Applicant s reported that the ceiling had “bowed” in one section of the
living room. In my view, this confirms that the water damage to at least
part of the ceiling was such that it had caused the plaster to sag;
I do not accept the Applicants’ position that, had this section of the
ceiling been allowed to dry out, it could have been sanded and
repainted. In my view, while this may be an appropriate approach in
some cases, where plaster has already started to sag, it is highly
unlikely that simply allowing it to dry will result in it returning to its
original position. Further, where the plaster in part of a ceiling has
started to sag, there is a real risk that the weight of this section will
result in further sections of the ceiling detaching; and
while the Applicants have provided a report from their builder /
waterproofer (“AS”) in support of their position, in reaching his view , AS
necessarily relied on the description of the damage provided by the
Applicants. Further, it is not apparent that AS was provided with any
photographs of the damage prior to the make safe repairs, for the
purpose of preparing his report.
47. For the reasons outlined above, I consider that the Applicants would have
been required to remove the relevant section of the ceiling in any event and
therefore they have not suffered any financial loss as the result of the make
safe repairs carried out by PP. Accordingly, they would have had to meet the
costs of repairing this damage.
48. However, the Applicants say that the fact that the make safe repairs were
carried out by PP has inconvenienced them, as they have not been able to
arrange for the repairs to be carried out by their own co ntractor at their
convenience. Further, it is apparent that PP’s failure to take appropriate
steps to ob tain the Applicants’ authorisation for the make safe repairs has
caused them some distress.
49. Under paragraph 9.3(b) of FOS’s Terms of Reference, compensation for
non-financial loss (capped at $3,000) may be awarded where there has been
an unusual degree or extent of physical inconvenience, time taken to resolve
the situation or interference with an insured’s expectation of enjoyment or
peace of mind.
50. FOS generally takes a conservative approach to the award of compensation
for non-financial loss. FOS considers that compensation should not be
awarded where an insured merely suffers inconvenience that is a normal
part of doing business and expects an insured to be moderately robust and
bear the normal degree of inconvenience experienced when a problem
occurs.
Case No: 311154 Determination Page 12 of 12
51. I note that the Applicants’ policy expressly provides that the FSP does not
cover compensation for distress, inconvenience or other non-financial loss.
While I consider that this provision operates to exclude compensation for
such matters arising from an event insured under the policy, in my view, it
does not prevent the award of compensation for non-financial loss, where
the relevant loss is caused by the FSP’s claim handling process (rather than
the insured event itself).
52. I accept that the Applicants have suffered stress and inconvenience as a
result of the manner in which the make safe repairs were carried out by PP
(and in particular, PP’s failure to obtain the Applicants’ prior written authority
to carry out the make safe works). In the circumstances, I consider that an
award of compensation in the amount of $750 is appropriate.
Determination
53. On the basis of the available information I determine that:
the FSP is entitled to deny liability for the Applicants’ claim;
the FSP is not liable to reimburse the Applicants for the cost of
undertaking the repairs to the property required as a result of the make
safe works; and
the FSP is to pay the Applicants the amount of $750 as compensation
for non-financial loss suffered as a result of the manner in which it has
handled their claim.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.