Determination 311122

Claim amount - cash settlement adequacy and delay

FirmFinancial Firm (Unknown - Insurer)
Decided2013-07-23
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$5,000
Non-financial loss—
Amount claimed$150,000
SourceAFCA PDF

Summary

A homeowner claimed a $150,000 cash settlement for flood damage after the insurer offered $21,975.14 because preferred builders would not guarantee the repairs. AFCA ordered an additional $5,000 for concealed and consequential damage, plus interest, and rejected the larger claim.

The insurer was entitled to cash settle, but a cash settlement based on a quote that makes no allowance for likely concealed damage is not fair in all the circumstances.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 311122 Determination Page 1 of 12 Case number: 311122 General Insurance - Domestic Insurance – Home Building - FSP Decision – Claim Amount 21 June 2013 Background 1. The Applicant holds a home insurance policy underwritten by the Financial Services Provider (FSP). The policy commenced on 5 February 1990 and was current during the period 5 February 2012 to 5 February 2013. It provided cover against defined events, including storm and flood. The Applicant‟s home building was insured for a sum of $200,000 and the contents insured for $20,000 during this period. 2. On 5 March 2012, the Applicant‟s spouse lodged a claim for damage to carpets resulting from rainwater runoff and/or flood. Repair work and replacement was undertaken to carpets and linoleum tiles by “S” pursuant to its quote dated 21 March 2012. The claim for damage to contents was accepted and is not in dispute. 3. On 13 and 23 April 2012, the Applicant contacted the FSP and advised that there was further damage, which included the sinking of some parts of the floor. The FSP arranged for an internal loss assessor to inspect the property. 4. Following the assessor‟s inspection on 4 May 2012, the FSP arranged for an engineer to inspect the property to discern what damage was caused by the recent inundation of water. The engineer (engineer 1) submitted a report dated 24 May 2012. 5. On 18 July 2012 the Applicant complained to the FSP about the delay in dealing with his claim an d that complaint was escalated to the FSP‟s IDR service for review. 6. On 10 August 2012 the FSP appointed a second engineer to provide them with another opinion. The second engineer (engineer 2) submitted a report dated 24 August 2012. 7. The FSP sought and obtained quotes from two of its preferred builders. On 8 October 2012, builder 1 was appointed to complete the work. However, on 4 January 2013, builder 1 advised that it was unable to guarantee the repairs after re-inspecting the property following a further report from engineer 2 on the method of repair. Determination Case No: 311122 Determination Page 2 of 12 8. On 8 January 2013, the FSP spoke with the Applicant and said they would cash settle the claim or see if builder 2 would do the work. The Applicant preferred that the FSP did the work so the FSP contacted builder 2, who had also provided a quotation for repairs but on 18 January 2013, builder 2 advised the FSP that it also could not guarantee the repairs. 9. On 18 January 2013 the FSP advised the Applicant that, due to the inability of the preferred repairers to guarantee the proposed works, it would be cash settling the claim for $21,975.14 being the figure quoted by builder 1. The Applicant was also advised on 8 January that if there was more damage once the floor was ripped up, the Applicant would need to send in another quote. Summary of Applicant’s position 10. The Applicant says that his home is a total loss and that a cash settlement of $150,000 would be sufficient for him to rebuild. 11. The Applicant says that the FSP has taken too long to deal with his claim and the delays have been likely to have resulted in further damage being caused to the building. 12. The Applicant is suffering from illness and says that he does not want to undertake the responsibility of managing the repairs. His preferred option is for the FSP to find a builder who will undertake the repairs and for them to reinstate or replace his house. Summary of FSP’s position 13. The FSP says that there was a significant amount of pre-existing damage which does not relate to the event for which the Applicant is claiming. It refers to comments to that effect made by engineer 1 in his report dated 24 May 2012. 14. The FSP says that it does not dispute that it has an obligation to meet the Applicant‟s claim for damage to the home and contents subsequent to the claimed event. However, it submits that there is no causal link between the claimed event and any damage beyond that for which a cash settlement has already been made. 15. The FSP refers to the scope of work recommended by engineer 1: “Therefore, we would recommend that the following Scope of Works could be used to reinstate the damage to the house due to the recent flooding. - The floor covering including carpet and vinyl floor would need to be removed. - Sections of the timber floor should be cut out to gain access to the sub floor area. Case No: 311122 Determination Page 3 of 12 - Re-levelling could be carried out of the floors to the lounge room, bedroom three and the kitchen area. This re-levelling would not be to level the floor back to zero datum but would be to feather into adjoining areas, - The sections of the floor would need to be reinstated. - Floor finishes would need to be reinstated. Our office is concerned regarding the rotting of the sub floor framing and we would recommend that the following works would need to be carried out by the owner to reinstate the sub floor framing. - All of the rotted timber stumps and sub floor framing should be replaced with new concrete stumps and new timber framing - All of the brick cladding should be removed from the external walls. It should be noted that if the cladding contains asbestos then this cladding would need to be removed using current health and safety Worksafe procedures. - The timber weather boards can be rei nstated or new cladding provided.” 16. The FSP says that engineer 1 identified the poor condition of the home building as including wear and tear, rot and pre-existing movement. He says in an email dated 22 June 2012 “in our opinion, the majority of damage is due to long term rotting of the subfloor framing.” The FSP says that any damage arising from or involving these causes is excluded from cover and it relies upon the following exclusions contained in the policy: “ What is not covered under any part of your policy This section details what is not covered under any part of your policy We do not cover: Wear, tear, rust or mould Loss or damage caused by wear, tear, rust, fading, gradual deterioration, mould, rising damp, mildew, action of light, atmospheric or climatic conditions or rot unless this is covered under: - Insured event 1 ( storm and flood) - Insured event 2 (burst pipes, leaks and overflow)” 17. The FSP says that the report from engineer 2 confirms the opinion provided by engineer 1 that rectification was required to part of the lounge room, the kitchen and part of bedroom 3. It says that no other parts of the home building required repairs and reinstatement as a result of the flood event. 18. The FSP says that neither of its preferred builders is prepared to undertake the work due to the age and condition of the existing structure and that it has no choice but to cash settle. It relies on its rights under the policy to do so. The policy states: “ How we settle your claim We choose how your claim is settled If we agree to pay a claim for loss, theft or damage to your home, contents or landlord‟s fixtures and fittings, we will decide if we will: Case No: 311122 Determination Page 4 of 12 - Repair damage new for old or - Replace home or contents new for old or - Pay you what it would cost us to repair or replace your home or contents new for old. The meaning of new for old is defined below. We will not: - Pay extra to replace your home, contents or landlord‟s fixtures and fittings to a better standard, specification or quality than it was before the loss or damage oc curred except as stated in „new for old‟ below - Fix a fault that existed before the loss or damage occurred” 19. Relying on the expert opinion, the FSP also relies on the following policy condition: “ Dealing with defects If undamaged defective parts of your home will not support repairs If undamaged defective parts of your home will not support repairing damage by an insured incident, we will only pay what it would have cost us to repair the damage had your home not been defective.” 20. The FSP says that the Applicant has provided no evidence: a. That indicates that the builder‟s quotation, upon which it has based the cash settlement figure, is in any way unreliable; b. That supports the view that there is further claimable damage over and above that which has been scoped and quoted; c. That the amount of the cash settlement is unreasonable; d. That the cash settlement does not comply with the terms and conditions of the policy. 21. The FSP also addresses section 46 of the Insurance Contracts Act and says it has no application to the claim. Issues 22. Whether the FSP is entitled to cash settle. 23. Whether the scope of works identified by the FSP is reasonable. 24. Whether the cash settlement is reasonable under the circumstances. 25. Whether delays in settling the Applicant‟s claim warrant further recompense by the FSP. Case No: 311122 Determination Page 5 of 12 Reasons for decision 26. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with clause 8.6 of the FOS Terms of Reference. This is due to the quantum and complexity of the dispute. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 27. I am satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issues raised. 28. The FSP has decided to cash settle this claim and relies on the policy condition titled “How we settle your claim”. This condition is quoted at paragraph 18 above. 29. In addition, both builders have indicated an unwillingness to complete the work due to the age and condition of the building and the potential for the work itself to create or exacerbate other problems with the building. The policy also includes a condition (refer paragraph 19 above) that says that the FSP may cash settle if the condition of a building is such that it will not support the repairs. 30. The Applicant says he is suffering from illness and says that he does not want to undertake the responsibility of managing the repairs. He says his preferred option is for the FSP to find a builder who will undertake the repairs and for them to reinstate or replace his house. 31. I can sympathise with that position but the evidence before me is that, neither builder engaged by the FSP is prepared to undertake the repairs. 32. In all the circumstances and ha ving considered carefully the FSP‟s policy, its notes, the expert engineer reports and plans and photographs, I am satisfied that the FSP is entitled to offer cash in settlement of this claim and that, in doing so, it is not acting unfairly or unreasonably. 33. In his report dated 24 May 2012 engineer 1 determined that part of the damage to the Applicant‟s house was not caused by the flood event of March 2012. The following are extracts from his report: “Access was not available to the sub -floor area however several of the timber stumps around the perimeter of the house were inspected and this showed that a considerable amount of rotting was evident of the timber stumps inspected. Floor levels were taken on the house and this showed that a considerable amount o f falls were evident in the house….” “CONCLUSIONS The cracking and movement of the house is typical of problems that occur due to long term rotting of the timber stumps and sub-floor framing. Long term rotting can occur of timber stumps and sub-floor framing particularly if poor clearance has been provided between the ground and the timber framing as Case No: 311122 Determination Page 6 of 12 well as poor ventilation. Rotting occurs of timber stumps over a long period of time and, in our opinion, is not related to a single flood event.” “Therefore , in our opinion, the cracking and movement of the house has resulted due to long term rotting of the timber stumps and subfloor framing and it would appear that the recent flooding has highlighted a pre-existing problem that occurred with the sub floor fr aming.” 34. The full extent of damage to the sub floor area could not be determined as access was not available to it so as detailed at paragraph 15 above, engineer 1 determined a scope of works. Engineer 1 also described the work the owner needed to do to reinstate the sub floor framing. 35. Engineer 1 was asked to clarify some matters and he wrote an email to the FSP dated 22 June 2012 in which he also stated: “This claim is not straight forward as we are dealing with a very old building that has been flooded and repaired previously. a. Our office has not carried out a previous inspection of the house however it would appear that a lot of movement has been occurring in the house for some time. We would estimate that possibly 10-20% additional movement has occurred following the recent flood. b. The owner repaired the house himself following the previous flood as insurance did not cover this work. With the amount of previous movement in the house I would assume the owner would be aware of problems with the subfloor as a house does not move this much without some reason. c. The subfloor area could not be seen at all as the brick cladding goes all the way to the ground. The subfloor area needs to be inspected for the extent of rotting of timber not moisture levels. In our opinion the majority of the damage is due to long term rotting of the subfloor framing. ” 36. Engineer 2 proposed a similar but slightly wider scope of works which included replacement of those house stumps which were obviously affected by flood water although, he subsequently amended that scope in a report dated 20 October 2012, by saying that it might be possible to jack and pack over some of the existing stumps. In his report dated 24 August 2012 he said: “The water levels were over the lower floor levels and hav e resulted in damage to the sub floor framing and supports, with the three areas shown on the floor plan now springy due to loss of support. The original flooring in Bedroom 3 has been replaced with chipboard sheet flooring, possibly due to a previous similar failure or damaged flooring. The lack of entry space prevented close inspection of the sub floor framing however it is obvious that supports have sunk or collapsed in the 3 locations as a result of saturation related to the inundation. The two other bedrooms and hallway floors remain sound. Case No: 311122 Determination Page 7 of 12 Conclusion All damages are related to the effects of saturation from inundation of ground under floor causing floor support stumps to sink or collapse away from floor framing resulting in very springy, sunken parts of the floors in kitchen, bedroom 3 and the lounge rooms. The recommended treatment is to remove several lengths of timber flooring in the kitchen and lounge rooms adjacent to the room walls to allow access to the 3 locations and to install new concrete stumps or brick piers, including ant caps under bearers, to make the floor level and sound under foot, and then replace the flooring and make good the floor coverings.” 37. The FSP appears to have adopted the recommendations of engineer 2 as the FSP then drew up quote requests dated 5 September 2012, which reflects engineer 2‟s report. I accept, even given the extent of pre-existing damage to the property, that this is a reasonable approach. It is improbable that the extent of all the rotting observed by the engineers could have occurred between March and May 2012 and I note that the Applicant has not disputed the fact there was pre-existing damage. 38. This scope of works is reflected in the quotes of builder 2 (his quote was $22,496.64) and the quote dated 24 September as prepared by builder 1: “Carpenter $ 2,480.00 Carpet $ 800.00 Insurance $ 600.00 Plans & Permits $ 1,800.00 Vinyl $ 1,200.00 Restumper $ 9,450.00 Remove Debris $ 600.00 Subtotal $16,930.00 Margin 18% $ 3,047.40 Total ex GST $19,977.40 GST $ 1,997.74 Total inc GST $21,975.14” 39. Engineer 2 provided a further report dated 20 October 2012 about the methodology of the floor repairs. He stated: “ Repairs of soft floor areas . The attached marked up plan shows the areas where the flooring will require removal to allow for access to the under floor framing and stumps/piers. Note the primary areas are within the kitchen and lounge, and these may be adequate to access all soft areas and allow for repairs. Case No: 311122 Determination Page 8 of 12 The repair will involve identification of the soft stumps/piers and if these have now hardened up, it may be possible to make the floor good, by jacking and packing over sound stumps/piers. Otherwise, install new concrete stumps/brick piers under floor bearers with ant caps and pack to make floor solid. As a proviso, allow to augment bearers and joists if timbers are damaged due to the loss of support. That is, split or broken. The flooring removed, should be suitable for reuse if adequate care is taken during removal, but may require replacement with similar materials if damaged during lifting. Similarly, with the floor coverings removed for access, it may require replacement if damaged, particularly the kitchen lino.” 40. The FSP‟s file notes show many entries about builde r 1 providing a variation to the quote and on 21 November, there is a file note indicating builder 1 was instructed to “start repairs and submit variation once they have accessed the sub floor which can only be done after repairs begin.” 41. However, delay sti ll occurs as it is noted builder 1 says “they are still awaiting the trades person to submit the variation to them to forward to the (FSP).” 42. I note a further file note dated 18 December 2012, which sets out some of the reasons for the delay. The file notes say: “(Builder 1) advised that he is unable to provide a variation at this stage – (builder 1) advised that he has sent several re-stumpers to site and they have not returned his calls about the job. (Builder 1) is not certain they will be able to guarantee repairs due to the condition of the property. He advised that they can begin repairs and then submit variation/s but he believes it could really escalate. He advised the original estimator that quoted no longer works for the company but he could attend property and complete more exploratory works by pulling up some of the floorboards to determine more the extent of the damage to the subfloor/stumps. (Builder 1) advised to proceed with this. He advised he will be able to get to property to do this in the New Year.” 43. Further file notes dated 4 January 2013 amplify Builder 1‟s concerns; “(Builder 1) advised that the engineer‟s report is not very clear. He advised original estimator is no longer with them, he met the carpenter trades yesterday at the property. He advised that they will not be able to guarantee repairs due to the condition of the property, old weatherboard house. (Builder 1) advised he does not feel comfortable to start the repairs as this may blow out and the cost will escalate. He does not want to pull up the floor. He had booked the trades for February.” 44. Builder 2 was approached and the file notes of 18 January 2013 indicate Builder 2 could not guarantee the works either, due to the age and structure of the home. 45. Builder 2 set out concerns regarding the scope of the works in a memo to the FSP dated 17 January 2013. It said: Case No: 311122 Determination Page 9 of 12 “(Builder 2‟s) quotation dated 25 September 2012 and recent telephone conversations refer to: Scope of works has been referred to inspecting estimator for further comment. Job notes indicate property is around 100 years old, so it is possible unforeseen concealed damage exists below the flooring that is to be removed and replaced. Commonly, joists or bearers may be affected, so if damage is found to be present additional repairs or replacement of affected elements would be necessary. Related to this, once the building has settled after restumping, external or internal cracking to building components such walls may develop. In addition, if items such as door alignments have been adjusted in the past to accommodate gradual wear or depreciation they may also become misaligned as flooring levels are adjusted. All issues are at this stage unforeseen and unpredictable, but if all become evident, repair cost could be expected to substantially increase. As initially unscoped, this type of work is not included in the quotation on issue. (Builder 2) repairs attract normal Builder‟s warranty, however, this would exclude future building movement, which might affect structure. The partial repair of flooring at property would not, nor could it be expected to return the entire building to new condition.” 46. In all these circumstances, the FSP decided then to cash settle this aspect of the claim with the excess deducted. I presume the excess has been deducted in settlement of the contents claim. 47. Both engineer 1 and engineer 2 stated that a full inspection of the sub floor area was not possible. Both builder 1 and builder 2 indicated that they could not be certain that additional damage would not be found once the floor is lifted and that neither had made allowance in their quotes for additional damage and the cost of repairing it. 48. I am satisfied that the scope of works identified by the FSP, and reflected in the quotes provided by builder 1 and builder 2, is reasonable in relation to the damage that was visible or foreseeable from an external inspection. In any event, it is the only evidence before me about the cost of repairs. 49. However, I am also of the view that it is also likely that the re will be additional concealed damage or that once the house is aligned, other cracks or adjustments may occur. That would not be an issue if the FSP had agreed to reinstate or repair, but it is an issue if the FSP chooses to cash settle based on a quote that makes no allowance for such additional repairs and damage particularly when the builders have expressed concerns about this. 50. In my view, a cash settlement that is based on a quote, which only deals with the known damage and from a builder who will not complete the work, is not acceptable and not fair in all the circumstances. The evidence before me suggests there is a likelihood of further concealed damage and consequential damage once the house is aligned. The file notes of the FSP Case No: 311122 Determination Page 10 of 12 indicate it contemp lated builder 1 may “submit a variation once he accessed the sub floor”. The conversation with the Applicant on 8 January also indicates an acknowledgment by the FSP that there may be more damage once the floor is ripped up. In my view, a cash settlement in these circumstances should have more thoroughly investigated these possible variations and should have made a further reasonable allowance for the cost of concealed damage over and above the quote for visible and foreseeable damage. 51. Neither party has adduced evidence of what that further amount might be. 52. The Applicant has requested a cash settlement of $150,000 but has provided no evidence to support that figure. The figure suggested by the Applicant is in my view disproportionate to the damage caused by the flood event. It seems clear from the engineers‟ reports that the property is old, that there is pre existing damage and that the house has suffered prior flood damage. Also Engineer 2 says; “The two other bedrooms and hallway floors remain sound.” 53. I am satisfied that the figure of $150,000 sought by the Applicant exceeds the amount that would indemnify him for the loss suffered solely from the flood event. 54. However, I also note the Builder 1 thinks the “repairs may blow out and the cost will really esca late”. 55. Builder 2 says while “unforseen and unpredictable”, “repair costs could be expected to substantially increase”. 56. I also note the view that the rotting is not related to a single flood event. Engineer 1 said; “we would estimate that possibly 10 -20% additional movement has occurred following the recent flood” and that “the majority of the damage is due to long term rotting of the subfloor framing.” 57. The quoted repair costs are about $20,000 plus GST. I confirm the FSP is not obliged to pay for pre-existing damage. It only has to pay for the damage caused by the flood. However, I am not satisfied that it has satisfied itself completely that the amount offered will cover all the concealed damage and damage consequential upon the repairs necessary because of the flood damage and accordingly, I am not satisfied that the amount offered as a cash settlement is fair in all the circumstances. 58. Therefore, on the basis of the available information and what I consider to be fair in all the circumstances, I determine that the FSP should make an additional payment to the Applicant in the sum of $5,000 for the damage, which cannot be seen and for the damage consequential upon repairs. This amount is calculated taking into account a fair percentage of the quoted amounts for the carpenter, re-stumper and removal of debris, to which has been added the builder‟s margin and goods and services tax. I have also taken into account the words used by the builders when they expressed their Case No: 311122 Determination Page 11 of 12 concerns. They were worried about costs, which could “really escalate” and costs which could be expected to “substantially increase.” 59. In determining this further sum, I have also take into account the concerns about the resultant further damage and adjustments which may be required and which may occur as noted by builder 2 in its memo to the FSP. I have also considered the repairs are being done to an old house which has pre- existing damage, but in my view, this remedy is fair in all the circumstances as I am of the view once the FSP decided to cash settle in all the circumstances of this claim the FSP should have attempted an estimate of and better consideration of the unseen damage and taken into account the concerns of two builders who will not guarantee the job and who are concerned about other unknown flood damage. 60. The Applicant has complained about the length of time that it has taken to settle his claim. His complaint appears to have merit when one considers the assessor had seen the property and an engineer‟s report was handed in by late May 2012. Indeed, this was acknowledged by the FSP who wrote an IDR letter on 30 July 2012 apologising for the delay and promising to expedite the claim. Despite that, the FSP was still arranging quotations as late as September 2012. 61. Having read the FSP‟s fi le notes carefully, I acknowledge though that the claim is not without complications and that although the claim was not handled as quickly as it could have been, the actions of the FSP were not unreasonable in all the circumstances. A repairer assessment was required for more information about how to do the repairs and this necessitated another opinion after the IDR letter even though the IDR letter indicated a decision would be made on the material to hand. 62. Further, the Applicant has not requested any specific remedy nor provided any evidence to the effect that the delay has resulted in more damage or that he has been adversely affected financially or that he has suffered any non- financial loss because of the delay. 63. As to the application of section 46 of the Act to the claim, I note that the insurance contract was entered into 5 January 1990 and the storm, the subject of this claim occurred on 29 February 2012. There is insufficient evidence before me to deal with the applicability of this section to the claim. The Applicant has not raised it, nor is there any evidence adduced as to the state of the property at the time the contract was entered into some 22 years before the storm event nor is there any evidence of the Applicant‟s knowledge of the defect at that time. My determination is not based on any applicability or not of section 46 of the Act to the claim and the dispute. 64. In summary: a. I am satisfied that the FSP is entitled to cash settle this claim. b. I am satisfied that the scope of works addresses visible and foreseeable damage, but does not address all possible concealed damage and damage consequential upon the repairs. Case No: 311122 Determination Page 12 of 12 c. I am not satisfied that the amount of the cash settlement is reasonable. Since there is a reasonable probability of concealed damage and damage consequential upon the repairs, the cash settlement should have made some allowance for the cost of rectifying that damage. I have fixed that amount at $5,000. d. I am satisfied that the FSP has not handled this claim as efficiently as the Applicant wished but the claim was not without complication and so in all the circumstances, I will restrict any compensation to the payment of interest prescribed by the Insurance Contracts Act 1984. Determination 65. On the information provided and for the reasons stated, I determine the FSP is to pay the Applicant a further $5,000 for the possible concealed flood damage to the property and for further damage that may occur once the property is aligned. I presume the excess of $300 has been deducted already but if that is not correct, then the excess of $300 is to be deducted from this sum. 66. Further, I determine that interest should be payable at the rates prescribed under section 57 of the Insurance Contracts Act on the amount of $5,000, once the Appliance indicates whether he accepts this Determination or not, from 5 February 2013 (the date of the final IDR decision) until the date that the payment is actually made.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.