Home / Financial Firm (Unknown - Credit) / Determination 309913

Determination 309913

Default interest and legal fees on expired facilities

FirmFinancial Firm (Unknown - Credit)
Decided2014-10-31
ProductCredit · Business lending
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$7,519
SourceAFCA PDF

Summary

A company whose commercial bill facilities expired in February 2012 disputed default interest, legal fees and a $400.19 debit after refinancing stalled. AFCA found the FSP was entitled to charge default interest from the notice of default, the legal fees were reasonable and the debit was not a fee, and ordered no compensation.

Once the FSP gave notice of default, the contract entitled it to default interest and reasonable enforcement costs, and the applicant could have avoided default interest by signing the offers it was sent.

Issues

Subjects and remedies

small businessno remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Credit - Business Finance - Business Loans - Charges - Incorrect fees/ costs Credit - Business Finance - Business Loans - Instructions - Failure to follow instructions/agreement Determiantion Case No: 309913 Determination Page 1 of 3 Case number : 309913 2 9 October 2014 1 Overview 1.1 Dispute Mr S is a director of the Applicant company. He is also the director of Company W and Company A. The Applicant had two Commercial Bill Line facilities with the FSP. The facilities expired on 16 February 2012. The Applicant says the FSP wrongly charged it default interest and charges, and legal fees. The Case Manager provided the parties with a Recommendation on the issues in dispute. The Recommendation was in favour of the FSP. A copy of the Recommendation is attached to this Determination. The FSP accepted the Recommendation but the Applicant rejected it. 1.2 Issues and Key findings Were the findings of the Recommendation correct? The Applicant disputed the findings in the Recommendation that there was no evidence to show that the FSP recommended that the refinance of the Applicant, Company W, an d Company A should be “linked”. The Applicant says that the FSP misled and coerced it and Company A into staying with the FSP by requiring it to support Company W’s facilities and saying it would obtain better pricing as a group. It subsequently released the Applicant and Company A from the requirement to support Company W. However the Applicant’s position is that it has suffered loss because:  it was precluded from refinancing earlier and  it ended up being charged default interest for being in default and before it could arrange refinance. The findings contained in the Recommendation were correct and are adopted in this Determination . Was the FSP entitled to charge default interest and fees to the Applicant? The Applicant was in default and the FSP was entitled to charge default interest and fees. 1.3 Determination This Determination is in favour of the FSP. Case No: 309913 Determination Page 2 of 3 2 Reasons for Determination 2.1 Were the findings in the Recommendation correct? I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the Recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied that the case manager’s Recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. Th e Applicant is correct in saying that up until 28 June 2012, the FSP’s indicative terms sheets for continued lending to Company W were conditional on the Applicant and Company A signing letters of offer for renewal of their facilities. However this does not change the outcome of the Recommendation. I agree with the case manager’s reasons for the Recommendation and the recommended outcome. 2.2 Was the FSP entitled to charge default interest and fees to the Applicant? The conditions in Company W’s indicative t erms sheet were not unfair to the Applicant The Applicant said it intended to stay with the FSP. Therefore even if the FSP had made the Applicant aware earlier that Company W was no longer required to have the Applicant and Company A support its borrowings by signing their own letters of offer, it is reasonable to assume that the Applicant would have stayed with the FSP. The FSP released the Applicant from the requirement to support Company W’s borrowings after the Applicant was notified that it was in default. The Applicant intended to keep its facilities with the FSP. It was only after being notified that it was in default and having to pay default interest from that point, that the Applicant sought refinance from another FSP, as it was entitled to do at any time. In any event I note that:  There were extensive negotiations taking place between the Applicant, Company W and Company A, and the FSP  There were numerous handwritten amendments made to the letters of offer and the indicative terms sheet and any issue about the Applicant being required to support Company W could have been raised then as well  The Applicant made no objection at the time to the inclusion of the letters of offer condition in Company W’s indicative term sheet Case No: 309913 Determination Page 3 of 3  The Applicant did not sign either of the letters of offer put to it dated 10 May 2012 and 6 June 2012, or the extension letter dated 14 May 2012, which extended facilities to 28 May 2012 Therefore I do not accept the Applicant’s argument that the condition in Company W’s indicative term sheet was unfair or coercive to the Applicant or prejudiced it in any way. The terms on which the FSP was prepared to provide continued support were the subject of a commercial negotiation. The Applicant had a choice to accept or reject t he FSP’s terms. It chose not to accept. As it had a choice, there can be no basis for a claim of duress or coercion. The Applicant was in default The bill facility matured on 16 February 2012 and had not been repaid by 27 June 2012. Despite negotiations over the preceding months in relation to the Applicant and Company A and Company W’s facilities, no resolution had been reached. The FSP sent a default letter to the Applicant on 27 June 2012. It noted that the revised letter of offer dated 6 June 2012 containing the terms on which it was prepared to continue to lend to the Applicant had not been accepted by the expiry date of 11 June 2012. The FSP was entitled to commence charging the Applicant default interest Once the FSP notified the Applicant of the event of default, it was entitled to commence charging the Applicant default interest. No compensation is payable. Recommendation Credit - Business Finance - Business Loans - Charges - Incorrect fees/ costs Credit - Business Finance - Business Loans - Instructions - Failure to follow instructions/agreement Recommendation Case No: 309913 Recommendation Page 1 of 4 Case number : 309913 25 July 2014 1 Overview 1.1 Dispute The Applicant is a director of R (the Applicant company). There are two other companies relevant to the dispute. In this Recommendation, I will refer to them as Company 2 and Company 3. The Applicant company had three Commercial Bill Line facilities with the FSP. On 16 February 2012, the facilities expired. After the facilities expired, the Applicant says the FSP made errors and acted unreasonably and unfairly. As a result of these errors, the Applicant company claims the following:  $4,683 of default interest incurred from 28 June 2012 until the refinance of the facilities on 30 August 2012;  $2,436 in legal fees, and  An extra charge of $400.19, which the Applicant says was charged without his authority. 1.2 Issues and key findings Did the FSP make an error by charging default interest? The Applicant has not shown that the FSP charged default interest unfairly or unreasonably. The FSP was entitled to charge default interest from 28 June 2012 until the refinance of the Applicant company’s facilities. Did the FSP incorrectly charge any other fees? The $400.19 debit on 30 August 2012 was not a fee. 1.3 Recommendation This Recommendation is in favour of the FSP. The FSP did not make the errors claimed by the Applicant. The FSP is not required to compensate the Applicant company for the amounts claimed. Case No: 309913 Recommendation Page 2 of 4 2 Reasons for Recommendation 2.1 Did the FSP make an error by charging default interest? The Applicant does not dispute that the FSP was contractually entitled to apply default interest The Applicant acknowledges that the FSP’s letter of 27 June 2012 meant that a default rate would apply from that date to th e Applicant company’s facilities in accordance with the facility contracts. As outlined in the Applicant’s letter of 26 October 2012, however, the Applicant says the default rate was applied unfairly and unreasonably taking into account the FSP’s actions f rom the date of the expiry of the facilities (16 February 2012) onwards. The FSP did not advise or mislead the Applicant about refinancing There is no evidence to show that the FSP provided advice to the Applicant about the best way to submit the refinance application. Communications between the Applicant and the FSP about the refinance application took the form of commercial negotiations about refinance conditions, not advice. This type of negotiation is an ordinary part of commercial dealings on this scale. There is no evidence to show that the FSP recommended that the refinance of the applicant Company, Company 2, and Company 3 should be linked. In any case, it was reasonable for the FSP to arrange the refinance of the three companies together, given the facilities for each company had expired or gone into default at around the same time. There is also no evidence to show that the Applicant raised concerns at any time about the fact the indicative loan offer for Company 3 was linked to the offers for the Applicant company and Company 2. The Applicant was more concerned with terms in the offers relating to fees and review conditions, terms which were the subject of negotiations between the FSP and the Applicant. If the Applicant felt the FSP’s requirement for the Company 3 refinance to be linked was unreasonable or unfair, it is expected he would have raised that concern earlier than 26 October 2012. The FSP acted fairly and reasonably before deciding to apply to the default rate The Applicant says that bec ause the FSP did not “express any concern” that the facilities had expired in February 2012, it acted unreasonably by waiting until 27 June 2012 to notify the Applicant that the facilities were expired and in default. The facilities expired on 16 February 2012. The process of refinancing the facilities started in February 2012, when the Applicant sent information to the FSP about the financial status of the Applicant company. The first Letter of Offer to refinance was sent to the Applicant company on 10 Ma y 2012. On 14 May 2012, the FSP wrote to the Applicant to say that the facilities had expired but that the FSP was extending the expiry date of the facilities to 28 May 2012 to “allow an Case No: 309913 Recommendation Page 3 of 4 opportunity to finalise the formal credit approval and documentation to amend these facilities”. The FSP did express concern to the Applicant prior to 27 June 2012 that the facilities had expired but that it was willing to allow a reasonable amount of time to ensure the facilities were refinanced. The FSP allowed refinance negotiations to continue until 27 June 2012 without applying a default rate of interest. It was not unreasonable for the FSP to begin charging a default rate from 28 June 2012 onwards given fair and reasonable efforts to find a commercial compromise had stalled. The FSP did not cause delays during refinancing The Applicant says that the FSP caused unreasonable delays in the Company 3 refinance that meant Letters of Offer for the Applicant company and Company 2 could not be signed before 28 June 2012. The Applicant raised a number of concerns with the FSP about the terms of the Indicative Term Sheet sent to Company 3 on 10 May 2012 and 14 May 2012. The FSP replied to these concerns on 14 May 2012. The FSP sent another Indicative Term Sheet in relation to Company 3 on 6 June 2012. It was not signed. Instead, the Applicant emailed the FSP on 13 June 2012 explaining that they did not agree with a condition in the 6 June 2012 Term Sheet. Up until 28 June 2012, discussions continued about the conditions of the Indicative Term Sheet to Company 3. The delays until this date were caused by the Applicant and, in any case, did not prevent the Applicant from signing the Letters of Offer to the Applicant company. The FSP told the Applicant on 28 June 2012 that it was still open to the Applicant to sign the Letter of Offer to the Applicant company dated 6 June 2012 “independant of any other loan offer you are negotiating with the Bank” (sic). The Applicant could have avoided being charged default interest The Applicant could have signed any of the Letters of Offer sent to the Applicant company. Accepting these offers was not dependent on the execution of any other contracts. If the offers were accepted, new agreements could have been executed and default interest avoided. The Applicant chose not to sign the contracts and to wait until the Company 3 refinance was finalised. The Applicant cannot reasonably claim for losses that could have been avoided. 2.2 Did the FSP incorrectly charge a discharge fee? The $400.19 debit amount on 30 August 2012 was not a fee The debit balance of $400.19 that is shown on the Applicant company’s Business Cash Reserve account on 30 August 2012 was not a fee. The debit balance resulted when the Applicant transferred $11,711,223 from the Applicant co mpany’s Business Cash Reserve account to the Applicant company’s Business Cheque Plus account. The debit balance was cleared by a transfer from the Applicant company’s Business Cheque Plus account on 26 September 2012. Case No: 309913 Recommendation Page 4 of 4 3 Supporting information 3.1 Legal fees incurred by the FSP The Applicant did not argue that the FSP’s legal fees were incurred in error, but did include the fees as part of their monetary claim against the FSP. Please find below my review of whether the fees incurred were reasonable. The legal fees in dispute were reasonably charged The FSP’s right to charge reasonable enforcement costs and expenses to the Applicant company is set out at section B1 of the Memorandum of Common Provisions relevant to the Applicant company’s facilities. The provision s state that the Applicant company promises to pay “all reasonable amounts which the Lender reasonably pays or incurs...in relation to the actual or contemplated enforcement of, or exercise of rights under, the Document or any security for the Document”. The legal fees of $1,249 charged between 20 June 2012 and 28 June 2012 were reasonably charged because:  They were for a reasonable amount given the size of the Applicant company’s facilities, and  They were charged in relation to the “contemplated enforcement” of the FSP’s rights, specifically, the drafting of the 27 June 2012 default letter which said that attempts to refinance had stalled, that the facilities were in default, and that the FSP reserved its rights. The legal fees of $1,187 charged between 12 July 2012 and 25 July 2012 were reasonably charged because:  They were for a reasonable amount given the size of the Applicant company’s facilities, and  They were charged in relation to the “contemplated enforcement” of the FSP’s rights, specifically, the drafting of the 25 July 2012 letter which explained that the facilities were still in default and that the FSP reserved its rights in the event that the refinance to the new FSP did not occur by 31 August 2012.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.