Home / Financial Firm (Unknown - Credit) / Determination 309912
Determination 309912
Incorrect fees/ costs
Summary
A company (through its director) disputed default interest, legal fees and a $407.19 debit charged after its business bill facilities expired and went into default. AFCA found the FSP entitled to charge default interest from 28 June 2012, the legal fees reasonable and the debit not a fee, so no compensation is payable.
The applicant was in default under the facility contracts after it did not accept the offered terms, so default interest and reasonable enforcement costs were payable under those contracts.
Issues
- Incorrect fees or charges primary · not upheld
“The Applicant has not shown that the FSP charged default interest unfairly or unreasonably.”
- Instructions not followed secondary · not upheld
“The $407.19 debit on 30 August 2012 was not a fee.”
- Misleading conduct secondary · not upheld
“There is no evidence to show that the FSP recommended that the refinance of the applicant Company, Company 2, and Company 3 should be linked.”
Subjects and remedies
no remedy
Text of the determination
Determination
Credit - Business Finance - Business Loans - Charges - Incorrect fees/ costs
Credit - Business Finance - Business Loans - Instructions - Failure to follow
instructions/agreement
Determination
Case No: 309912 Determination Page 1 of 4
Case number : 309912 31 October 2014
1 Overview
1.1 Dispute
Mr S is a director of the Applicant company. He is also the director of Company W
and Company R.
The Applicant had two Commercial Bill Line facilities with the FSP. The facilities
expired on 2 March 2012. The Applicant says the FSP wrongly charged it default
interest and charges, and legal fees.
The Case Manager provided the parties with a Recommendation on the issues in
dispute. The Recommendation was in favour of the FSP. A copy of the
Recommendation is attached to this Determination. The FSP accepted the
Recommendation but the Applicant rejected it.
1.2 Issues and Key findings
Were the findings of the Recommendation correct?
The Applicant disputed the findings in the Recommendation that there was no
evidence to show that the FSP recommended that the refinance of the Applicant,
Company W, and Company R should be “linked”. The Applicant says that the FSP
misled and coerced it and Company R into staying with the FSP by requiring it to
support Company W’s facilities and saying it would obtain better pricing as a
group. It subsequently released the Applicant and company R from the
requirement to support Company W.
However the Appl icant’s position is that it has suffered loss because:
it was precluded from refinancing earlier and
it ended up being charged default interest for being in default and before it
could arrange refinance.
The findings contained in the Recommendation were correct and are adopted in
this Determination .
Was the FSP entitled to charge default interest and fees to the Applicant?
The Applicant was in default and the FSP was entitled to charge default interest
and fees.
1.3 Determination
This Determination is in favour of the FSP.
Case No: 309912 Determination Page 2 of 4
2 Reasons for Determination
2.1 Were the findings in the Recommendation correct?
Case No: 309912 Determination Page 3 of 4
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
Recommendation. I am satisfied that the documentation I have relied on has been
provided to both parties.
I am satisfied that the case manager’s Recommendation contains an accurate
summary of the dispute, the issues to be determined, any applicable paragraphs
of the Terms of Reference and any relevant law.
Th e Applicant is correct in saying that up until 28 June 2012, the FSP’s indicative
terms sheets for continued lending to Company W were conditional on the
Applicant and Company R signing letters of offer for renewal of their facilities.
However this does not change the outcome of the Recommendation.
I agree with the case manager’s reasons for the Recommendation and the
recommended outcome.
2.2 Was the FSP entitled to charge default interest and fees to the
Applicant?
The conditions in company W’s indicative t erms sheet were not unfair to the
Applicant
The Applicant said it intended to stay with the FSP. Therefore even if the FSP had
made the Applicant aware earlier that Company W was no longer required to
have the Applicant and Company R support its borrowings by signing their own
letters of offer, it is reasonable to assume that the Applicant would have stayed
with the FSP.
The FSP released the Applicant from the requirement to support Company W’s
borrowings after the Applicant was notified that it was in default. The Applicant
intended to keep its facilities with the FSP. It was only after being notified that it
was in default and having to pay default interest from that point, that the Applicant
sought refinance from another FSP, as it was entitled to do at any time.
In any event I note that:
There were extensive negotiations taking place between the Applicant,
Company W and Company R, and the FSP
There were numerous handwritten amendments made to the letters of offer
and the indicative terms sheet and any issue about the Applicant being
required to support Company W could have been raised then as well
The Applicant made no objection at the time to the inclusion of the letters of
offer condition in Company W’s indicative term sheet
The Applicant did not sign either of the letters of offer put to it dated 10 May
2012 and 6 June 2012, or the extension letter dated 14 May 2012, which
extended facilities to 28 May 2012.
Therefore I do not accept the Applicant’s argument that the condition in Company
W’s indi cative term sheet was unfair or coercive to the Applicant or prejudiced it in
any way. The terms on which the FSP was prepared to provide continued
Case No: 309912 Determination Page 4 of 4
support were the subject of a commercial negotiation. The Applicant had a choice
to accept or reject the F SP’s terms. It chose not to accept. As it had a choice,
there can be no basis for a claim of duress or coercion.
The Applicant was in default
The bill facility matured on 2 March 2012 and had not been repaid by 27 June
2012. Despite negotiations over the preceding months in relation to the Applicant
and Company R and W’s facilities, no resolution had been reached. The FSP
sent a default letter to the Applicant on 27 June 2012. It noted that the revised
letter of offer dated 6 June 2012 containing the terms on which it was prepared to
continue to lend to the Applicant had not been accepted by the expiry date of 11
June 2012.
The FSP was entitled to commence charging the Applicant default interest
Once the FSP notified the Applicant of the event of default, it was entitled to
commence charging the Applicant default interest.
No compensation is payable.
Recommendation
Credit - Business Finance - Business Loans - Charges - Incorrect fees/ costs
Credit - Business Finance - Business Loans - Instructions - Failure to follow
instructions/agreement
Recommendation
Case No: 309912 Recommendation Page 1 of 4
Case number : 309912 25 July 2014
1 Overview
1.1 Dispute
The Applicant is a director of A (the Applicant company). There are two other
companies relevant to the dispute. In this Recommendation, I will refer to them as
Company 2 and Company 3.
The Applicant company had two Commercial Bill Line facilities with the FSP. On 2
March 2012, the facilities expired.
After the facilities expired, the Applicant says the FSP inappropriately charged the
following amounts:
$61,876 of default interest incurred from 28 June 2012, until the refinance of
the facilities on 30 August 2012;
$2,388 in legal fees, and
An extra charge of $407.19, which the Applicant says was charged without his
authority.
1.2 Issues and key findings
Did the FSP make an error by charging default interest?
The Applicant has not shown that the FSP charged default interest unfairly or
unreasonably. The FSP was entitled to charge default interest from 28 June 2012
until t he refinance of the Applicant company’s facilities.
Did the FSP incorrectly charge any other fees?
The $407.19 debit on 30 August 2012 was not a fee.
1.3 Recommendation
This Recommendation is in favour of the FSP. The FSP did not make the errors
claimed by the Applicant. The FSP is not required to compensate the Applicant
company for the amounts claimed.
Case No: 309912 Recommendation Page 2 of 4
2 Reasons for Recommendation
2.1 Did the FSP make an error by charging default interest?
The Applicant does not dispute that the FSP was contractually entitled to
apply default interest
The Applicant acknowledges that the FSP’s letter of 27 June 2012 meant that a
default rate would apply from that date to the Applicant company’s facilities in
accordance with the facility contracts. As outlined in the App licant’s letter of 26
October 2012, however, the Applicant says the default rate was applied unfairly
and unreasonably taking into account the FSP’s actions from the date of the
expiry of the facilities (2 March 2012) onwards.
The FSP did not advise or mislead the Applicant about refinancing
There is no evidence to show that the FSP provided advice to the Applicant about
the best way to submit the refinance application. Communications between the
Applicant and the FSP about the refinance application took the form of
commercial negotiations about refinance conditions, not advice. This type of
negotiation is an ordinary part of commercial dealings on this scale.
There is no evidence to show that the FSP recommended that the refinance of the
applicant Company, Company 2, and Company 3 should be linked. In any case, it
was reasonable for the FSP to arrange the refinance of the three companies
together, given the facilities for each company had expired or gone into default at
around the same time.
There is also no evidence to show that the Applicant raised concerns at any time
about the fact the indicative loan offer for Company 3 was linked to the offers for
the Applicant company and Company 2. The Applicant was more concerned with
terms in the offers relating to fees and review conditions, terms which were the
subject of negotiations between the FSP and the Applicant. If the Applicant felt
the FSP’s requirement for the Company 3 refinance to be linked was
unreasonable or unfair, it is expected he would have raised that concern earlier
than 26 October 2012.
The FSP acted fairly and reasonably before deciding to apply to the default
rate
The Applicant says that because the FSP did not “express any concern” that the
facilities had expired in March 2012, it acted unreasonably by waiting until 27
June 2012 to notify the Applicant that the facilities were expired and in default.
The facilities expired on 2 March 2012. The process of refinancing the facilities
was underway by 15 March 2012, when the Applicant sent information to the FSP
about the financial status of the Applicant company. The first Letter of Offer to
refinance was sent to the Applicant company on 10 May 2012. On 14 May 2012,
the FSP wrote to the Applicant company to say that the facilities had expired but
that the FSP was extending the expiry date of the facilities to 28 May 2012 to
Case No: 309912 Recommendation Page 3 of 4
“allow an opportunity to finalise the formal credit approval and documentation to
amend these facilities”. The FSP did express concern to the Applicant prior to 27
June 2012 that the facilities had expired but that it was willing to allow a
reasonable amount of time to ensure the facilities were refinanced.
The FSP allowed refinance negotiations to continue until 27 June 2012 without
applying a default rate of interest. It was not unreasonable for the FSP to begin
charging a default rate from 28 June 2012 onwards given fair and reasonable
efforts to find a commercial compromise had stalled.
The FSP did not cause delays during refinancing
The Applicant says that the FSP caused unreasonable delays in the Company 3
refinance that meant Letters of Offer for the Applicant company and Company 2
could not be signed before 28 June 2012.
The Applicant raised a number of concerns with the FSP about the terms of the
Indicative Term Sheet sent to Company 3 on 10 May 2012 and 14 May 2012. The
FSP replied to these concerns on 14 May 2012. The FSP sent another Indicative
Term Sheet in relation to Company 3 on 6 June 2012. It was not signed. Instead,
the Applicant emailed the FSP on 13 June 2012 explaining that they did not agree
with a condition in the 6 June 2012 Term Sheet.
Up until 28 June 2012, discussions continued about the conditions of the
Indicative Term Sheet to Company 3. The delays until this date were caused by
the Applicant and, in any case, did not prevent the Applicant from signing the
Letters of Offer to the Applicant company. The FSP told the Applicant on 28 June
2012 that it was still open to the Applicant to sign the Letter of Offer to the
Applicant company dated 6 June 2012 “independant of any other loan offer you
are negotiating with the Bank” (sic).
The Applicant could have avoided being charged default interest
The Applicant could have signed any of the Letters of Offer sent to the Applicant
company. Accepting these offers was not dependent on the execution of any
other contracts. If the offers were accepted, new agreements could have been
executed and default interest avoided. The Applicant chose not to sign the
contracts and to wait until the Company 3 refinance was finalised. The Applicant
cannot reasonably claim for losses that could have been avoided.
2.2 Did the FSP incorrectly charge a discharge fee?
The $400.19 debit amount on 30 August 2012 was not a fee
The debit balance of $400.19 that is shown on the Applicant comp any’s Business
Cash Reserve account xxx1055 on 31 August 2012 was not a fee. The debit
balance resulted when the Applicant transferred $24,002,121 from account
xxx1055 to the Applicant company’s Business One account xxx1001 on 30
August 2012. The debit balance on xxx1055 was cleared by a transfer from the
Applicant company’s Business One account xxx1001 on 26 September 2012.
Case No: 309912 Recommendation Page 4 of 4
3 Supporting information
3.1 Legal fees incurred by the FSP
The Applicant did not argue that the FSP’s legal fees were incurred in error, but
did include the fees as part of the Applicant company’s monetary claim against
the FSP. Please find below my review of whether the fees incurred were
reasonable.
The legal fees in dispute were reasonably charged
The FSP’s right to charge reasonable enforcement costs and expenses to the
Applicant company is set out at section B1 of the Memorandum of Common
Provisions relevant to the Applicant company’s facilities. The provisions state that
the Applicant company promises to pay “all reasonable amounts which the Lender
reasonably pays or incurs...in relation to the actual or contemplated enforcement
of, or exercise of rights under, the Document or any security for the Document”.
The legal fees of $1,200.50 charged between 20 June 2012 and 28 June 2012
were reasonably charged because:
They were for a reasona ble amount given the size of the Applicant company’s
facilities, and
They were charged in relation to the “contemplated enforcement” of the FSP’s
rights, specifically, the drafting of the 27 June 2012 default letter which said
that attempts to refinance had stalled, that the facilities were in default, and
that the FSP reserved its rights.
The legal fees of $1,187.50 charged between 12 July 2012 and 25 July 2012
were reasonably charged because:
They were for a reasonable amount given the size of the Applic ant company’s
facilities, and
They were charged in relation to the “contemplated enforcement” of the FSP’s
rights, specifically, the drafting of the 25 July 2012 letter which explained that
the facilities were still in default and that the FSP reserved its rights in the
event that the refinance to the new FSP did not occur by 31 August 2012.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.