Bridging loan approved to fund speculative subdivision without proper evaluation of project risks
Text of the determination
Determination
Case No: 309638 Determination Page 1 of 7
Case number : 309638 6 August 2014
1 Overview
1.1 Dispute
This is a dispute about whether the FSP lent responsibly.
The FSP approved a full-documentation bridging loan of $580,000 in August 2008
for the Applicants to purchase and subdivide a block of land. Instead of being
completed and sold within 12 months, the subdivision was still unfinished after
three years, during which time the FSP had approved two increases to an existing
line of credit facility and the Applicants sold other properties to reduce their
indebtedness.
The FSP admits that approving both increases to the line of credit facility was not
responsible lending, but says that approving the bridging loan was.
1.2 Issues and key findings
Should the FSP have provided the bridging loan?
Approving the bridging loan to fund a speculative property development without
undertaking a proper evaluation of the proposed subdivision was not the act of a
diligent and prudent banker, and was irresponsible lending by the FSP.
What compensation should the FSP pay the Applicants?
If the Applicants accept this Determination within 30 days of its date of issue,
within a further 14 days of that acceptance, the FSP must:
Reconstruct the bridging loan account by crediting it with:
o $6,716.18 as at the initial funding date
o $153,840 as at 1 February 2012, being the reconstructed line of
credit facility’s surplus as at that date
o 50% of the interest charged up to 30 September 2013.
From 30 September 2013, charge interest on 50% of the adjusted balance of
the bridging loan account until the loan is repaid in full.
Provide the Applicants with a statement of their liability under the loan after
the above adjustments have been made.
1.3 Determination
This Determination is substantially in favour of the Applicants. The FSP did not
lend responsibly when it made the bridging loan to the Applicants, but the
Applicants bear responsibility for part of their losses.
Case No: 309638 Determination Page 2 of 7
After the above adjustments to the loan balance have been made, the Applicants
remain liable to repay the adjusted balance of the bridging loan account until it is
repaid in full. In accordance with part 3.2 of this Determination, they should work
with the FSP to agree upon a repayment plan that will see the bridging loan
repaid over a reasonable period.
Case No: 309638 Determination Page 3 of 7
2 Reasons for Determination
2.1 Should the FSP have provided the bridging loan?
Law and Code of Banking Practice set the standard
At law and under the Code of Banking Practice, an FSP has an obligation to
exercise the care and skill of a diligent and prudent banker.
As part of the bridging loan assessment process, an FSP should:
Request documentation to support the application
Make further enquiries where there are obvious inconsistencies or gaps in the
information
Ensure there is sufficient information and supporting documentation provided
to demonstrate capacity to service the bridging loan
Bridging loan was assessed on the value of assets, not repayment capacity
Bridging loans are not assessed upon a borrower ’ s debt servicing and repayment
capacity at the time of the application, unless it is likely that a residual debt will
remain after the relevant security assets have been sold.
Instead, bridging loans are assessed by FSPs according to the value of the
assets offered to secure the loan, an assessment of the likely future value of
those assets (that are intended for sale to repay the bridging loans), and the likely
state of the market at the time of the intended sale.
Bridging loans commonly permit the interest payable to be capitalised (within the
bridging loan ’s approved limit). The industry standard for bridging loans is a
maximum loan to security value ratio of 80%.
Bridging loan inappropriate for inexperienced property developers
A bridging loan may be appropriate where both the lender and borrower accept
that the sale of an asset or assets to clear the whole or a part of the bridging loan
debt must and will take place at an agreed point in the future (having first
undertaken a detailed evaluation of those asset(s) and any proposal to develop
them).
However, it is not appropriate or good practice to offer bridging loans to fund
highly speculative developments, particularly if the proposed borrower has no
established track record or prior experience in property development.
Applicants had no track record or experience in subdivision
After signing an unconditional contract to purchase the block of land in June 2008,
the Applicants approached the FSP without:
Having carried out any previous subdivision of land
A change of use assessment of the block of land
A feasibility study of the future subdivision
Any prepared plans for the future subdivision
Case No: 309638 Determination Page 4 of 7
Knowing the approximate costs of the future subdivision
FSP should have made further enquiries to verify project risks
The FSP’s lending policy requires that loan applications for “development
projects, where the end sale of the development is the only wa y out” be submitted
to its risk assessment team. This particular application was recommended to the
FSP’s risk assessment team by the Applicants’ local manager on 31 July 2008.
The manager gave his recommendation after the Applicants told him they had
spoken with the local council and a land surveyor about their p lans to subdivide
the block of land. He says they told him that the land had an existing electrical
supply and an existing road, the subdivision process was straightforward, costs
were around $35,000, plumbing works would be done by the male Applicant who
was a qualified plumber, and that this sort of subdivision was usually completed
within two to three months.
However, the local manager took no steps to verify this. Expert advice about how
to apply to change the land’s use was first provided to the Applicants on 12
August 2008, one day after the FSP approved the bridging loan application and
three days before it funded the bridging loan. It is not clear whether the FSP saw
this report.
It is clear, though, that there were no presales or enforceable offers received from
any parties interested in purchasing subdivided blocks. A contract of sale for the
portion of land proposed for the landscape supplies centre that the Applicants
provided to the FSP’s lending manager to bolster the applicatio n’s attractiveness
was so highly conditional as to be incapable of being successfully enforced for
specific performance.
In essence, the recommendation the local manager gave to the FSP’s risk
assessment team on 31 July 2008 was based on hope, not a fact-based
evaluation of the foreseeable risks associated with the proposed development.
Project ran into foreseeable problems
The Applicants initially planned to develop a portion of the land adjoining a local
council depot as a landscape supplies centre. This was the subject of the August
advice. However, a subsequent report prepared in November 2008 by an expert
hydrologist assessed that a portion of the land was likely to become inundated
during a one in fifty year storm event.
The Applicants adjusted their plans but the local council’s subsequent approval ,
given in January 2009, was made subject to 19 different conditions.
To intensify an already very difficult challenge, the male Applicants injured his
back in early 2009, forcing him to use his income protection insurance, which paid
only 75% of his salary. The injury also meant that he could not carry out the
plumbing works on the subdivision as he had planned.
The Applicants’ debt obligations evolved and increased over time due to:
prot racted delays in the local council’s approval process,
Case No: 309638 Determination Page 5 of 7
a dramatic collapse in the local real estate market (leading to much lower than
expected selling prices for other property assets that the Applicants sold to
reduce their indebtedness) and
a downturn in the local economy caused by natural disaster in the form of two
severe tropical cyclones.
Prudent lender would not have approved bridging loan
Although neither the FSP nor the Applicants could have foreseen all of these
factors occurring at the same time, the fact remains that if the FSP had carried out
a proper evaluation of the proposed development, contingencies to deal with
unexpected eventualities would either have either been built into the project plan
or the bridging loan application would have been assessed as too risky.
Approving a bridging loan to fund a highly speculative property development
without undertaking a proper evaluation of the proposed subdivision was not the
act of a diligent and prudent banker, and was irresponsible lending.
2.2 What compensation should the FSP pay the Applicants?
Where we find that an FSP should not have lent money, we will determine what
has to be done to put the applicant in the position they would have been in had
the loan application not been approved, to the extent that is possible while being
fair to all the parties.
When FOS finds that a lender has engaged in maladministration in lending when
providing a loan to enable the borrower to buy an investment property, we
generally calculate the borrower’s costs a s follows:
The costs of the borrowing, including application fees, interest on the sum
borrowed, and fees payable, plus
The costs of buying the property, such as legal fees and stamp duty;
The costs of owning the property, such as insurance, rates and repairs and
maintenance; and
The costs of selling the property, such as legal and agents’ fees.
Interest and borrowing costs
The costs incurred by the Applicants as a result of entering into the contract for
the bridging loan, up to 30 September 2013, are as follows:
Fee Name Amount
Application fee $4,350.00
Valuation fee $880.00
Company search fee $12.10
Land title search fee $80.88
Case No: 309638 Determination Page 6 of 7
Company charge registration fee $135.00
Mortgage lodgement fee $120.50
Transfer lodgement fee $1,067.70
Bank cheque fee s $ 7 0.00
Total $6, 71 6.18
Interest to 30 September 2013 $ 345,227.13
No compensation for purchase, maintenance or sale costs
In this dispute, the Applicants bought the block of land before they applied for the
bridging loan. They therefore incurred the costs of acquiring, maintaining and
selling the block of land before the FSP approved the bridging loan.
Accordingly, there is no causative link between the bridging loan and the costs the
Applicants incurred in respect of the block of land. The only costs incurred as a
consequence of the FSP’s approving the bridging loan are interest and fees.
The Applicants’ loss to 30 September 2013 is therefore the total of the borrowing
costs of $6,716.18 and interest of $345,227.13, namely $351.943.31.
The Applicants should bear part of the loss
If a borrower does not consider how they are going to repay a loan, or signs a
blank, incomplete or incorrect loan application and then signs the credit contract,
we may decide that the borrower should take some responsibility for their decision
to enter into the credit contract. In those circumstances, we may conclude that
the borrower should be liable for some of their loss.
At the time they applied for the bridging loan, the Applicants had:
Signed an unconditional contract to purchase the block of land and were, in
their own words, “desperate to obtain funding”
Sought and received their solicitor’ s advice about how best to obtain finance
Two investment properties as well as primary residence , and could be
reasonably characterized as financially literate
Based on the available information, it also appears that the Applicants applied for
the bridging loan knowing they may have to use the line of credit to make interest
payments and that, if their capacity to service debt changed for the worse, they
would have to sell other assets to reduce their indebtedness.
In the circumstances, it is appropriate that they bear some responsibility for the
losses they incurred as a result of applying for the bridging loan, a fair proportion
being 50%.
In addition, after reconstructing the line of credit facility at its original $200,000
limit, the FOS banking specialist calculated that, after paying out the facility’s
interest-bearing liability, the Applicants would have had a surplus of $153,840 to
contribute to other debt on the date the facility was closed, 1 February 2012.
Case No: 309638 Determination Page 7 of 7
Accordingly, the FSP must adjust the bridging loan account by crediting it with:
$6,716.18 as at its initial funding date
$153,840 as at 1 February 2012, being the reconstructed line of credit facility’s
surplus as at that date
50% of the interest charged up to 30 September 2013
The FSP must charge interest on 50% of the adjusted balance 1 of the bridging
loan account as at 30 September 2013 until the loan is repaid in full.
3 Other matters
3.1 Arguments raised but not detailed in this Determination
The Applicants raised the following arguments but it is not necessary to deal with
them in detail. They would not change the outcome, even if they were accepted.
First, that the FSP misrepresented the male Applicant’s earning capacity.
Secondly, that the FSP misrepresented the value of the Applicants’ vehicles.
3.2 Liability for the adjusted balance of the bridging loan account
The Applicants remain liable for the adjusted balance of the loan as well as
interest charged on it by the FSP from time to time in accor dance with this
Determination until the loan is repaid.
If the Applicants decide to accept this Determination within 30 days of its date of
issue, within a further 14 days of that acceptance they should provide a
reasonable payment proposal to the FSP (together with up to date information
about their current financial position).
If the Applicants do so, the FSP should work with them to agree upon a
repayment arrangement that will see the bridging loan repaid over a reasonable
period. If the parties are not able to agree on a repayment arrangement within 14
days after the date the Applicants provide a repayment proposal (or if they do not
provide a repayment proposal within the specified timeframe), then the FSP will
be entitled to take action to recover the remaining outstanding debt (as amended
by this Determination).
1 The FOS banking specialist calculated the adjusted balance of the bridging loan’s account to be
$523,715.64 as at 30 September 2013.