Strata property damage claim declined on exclusions; FSP's engineering evidence did not establish the exclusions

FirmFinancial Firm (Unknown - Insurer)
Decided2014-07-11
ProductGeneral Insurance · Strata
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant's strata insurer declined a claim for underpinning and property damage after a tree-root blockage in a common drain. AFCA found the FSP had not established any exclusion and determined the FSP must meet the claim under the policy terms, without stating a figure.

The FSP bore the onus to prove an exclusion on the balance of probabilities and its engineering evidence did not establish that the damage fell within one, while the leaking drain was an excepted water-leak event.

Issues

Subjects and remedies

home or building damagepay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 308389 Determination Page 1 of 10 Case number: 308389 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of Claim - Exclusion 4 July 2014 Background 1. This is a claim by the Applicant under a Residential Strata Insurance Plan underwritten by the FSP for damage to the Applicant‟s property. 2. The Applicant lodged a claim through her broker on 27 June 2012 for damage sustained due to a cracked/broken pipe on the common property. Prior to lodgement of the claim, the damage to the property had been repaired. 3. The FSP through its loss adjustors notified the Applicant‟s broker on 9 November 2012 that the claim was rejected as the loss was not a result of or associated with an insured event. 4. It appears that the FSP in fact was relying upon exclusions contained within the policy. As a result of ongoing delays in receiving a final decision from the FSP, the Applicant has lodged the dispute with the Financial Ombudsman Service. Issues 5. Whether the FSP was entitled to decline the claim pursuant to the terms of the policy. 6. Whether the FSP has been prejudiced by the repairs being completed prior to the lodgement of the claim. Reasons for Determination 7. As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a Recommendation and has p roceeded directly to Determination. Determin ation Case No: 308389 Determination Page 2 of 10 8. There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues as they arise in the material exchanged. Applicant has established a prima facie claim 9. The policy is a broad form accidental loss and damage policy that provides insurance against accidental loss or damage sustained to the Applicant‟s property during the period of insurance. 10. Accidental loss or damage is commonly described as damage that is unintended and unexpected. 11. There is no doubt given the information exchanged that the damage to the Applicant‟s property was unintended and unexpected. 12. The report obtained from ALD confirms that there was blockage in the pipe works caused by tree roots. As a result of the damage underpinning was required to the north facade of the building. 13. In the circumstances, I am satisfied that the Applicant has established a prima facie claim under the terms of the policy. FSP must prove application of the relevant exclusion(s) under the policy 14. Insofar as the FSP seeks to deny liability for the claim the FSP bears the onus to establish the application of one or more of the relevant exclusions on the balance of probabilities. 15. The Applicant has provided the following information in support of the claim. a) AL‟s report of 21 June 2012 provides the following relevant information:  CCTV inspection of the stormwater line failed. A blockage caused by tree roots was located in the common line that units 4, 5, 6 and 7 all run into.  Unit 7‟s stormwater line enters the common line at the lowest point being closest to the easement.  In heavy rain the water would be backing up the pipe work overflowing from the lowest point which are the downpipes of unit 7 and the box drain at the front of u nit 6 and 7‟s garage.  A plumber is to repair the pipe work; the blockage is marked with a stake in the ground. b) Plumbing firm “W”s quotation of 26 June 2012 provides the following relevant information:  They will replace a 1.5mt section of PVC pipe that is broken/blocked downstream of unit 7 at a cost of $2093.30. Case No: 308389 Determination Page 3 of 10  The scope of works included to locate the exact position and depth of the blockage, excavate and expose drain, cut and remove 1.5mt section of drain, install new section of drain in crushed rock and backfill, flow test new drain and test drain downstream. c) The original stormwater drainage specifications as prepared by geotechnical engineering firm “T” dated July 1997 were supplied. The plan provides the following relevant information:  The closest stor mwater pit to unit 7 is „pit 3‟ on the north side of the property, on common grassed property close to the boundary line.  The system was to be adequate for a 1 in 100 year storm.  All 100 and 150mm pipes were to be PVC and all 225mm pipes were to be class 2 reinforced concrete with rubber ring joints.  All landscaping and paving to be graded away from dwellings and adjoining properties to grated pits. d) AR‟s quotation of 17 May 2012 and invoice of 20 July 2013 provide, respectively:  All works to be carried out by AR as per specifications supplied “AC” engineers.  Three underpinning pads estimated.  One extra underpin was required.  An extra man was required for two days due to trench flooding. e) A „certificate of compliance‟ (CC) for the underpinning design prepared by AC issued on 7 June 2012 (supplied to AR on the same date) has been provided. A building permit for the works was issued on 12 June 2012. The CC provides the following relevant information:  All works were to be carried out as per design and layout.  Any construction difficulties to be reported immediately to the engineer in order to make necessary changes.  During construction, the underpin holes need to be monitored and protection measures installed if necessary. Size and depth may be varied if solid rock encountered, in founding material wet or soft, or fill found; engineer to be notified.  All underpins shall be involved in two stage construction, first pour new concrete, concrete to remain without load until solid, jack existing footings and back into position, then pour next underpin.  In the event that existing concrete footings less than 300mm thickness, underpin spacing may have to be reduced and engineer notified. Case No: 308389 Determination Page 4 of 10  Contractor responsible to inform owner to repair or replace any broken pipes, tree roots etc if found.  Owner will be responsible to maintain stable moisture conditions near the building.  The plan called for six underpins to be installed, with pins 5 and 6 optional. 16. The Applicant has also supplied a number of extracts of technical papers addressing extreme brick growth and its effects as well as contour surveys of the property, showing the fall of the land at the residence. 17. A report on the drainage provisions at the site was provided by engineering firm “B”. B‟s report of September 2013 provides the following relevant information:  B‟s commission was to investigate and report on the drainage system at the site, as instructed by the Owners‟ Corporation.  B was required to evaluate the original stormwater design for the site and verify the existing pipe work operated successfully.  B spoke with W who confirmed they had repaired the break, replaced terracotta pipes in the section leading to the outlet to the council drain and had repaired the bases of four pits which had been attacked by tree roots.  B then met with the Applicant and W on site on 28 August 2013 to inspect the property.  W ran a CCTV camera along all main pipe runs which showed all lines were clear of debris and tree roots.  The section of drain between pit 5 and unit 4 appeared to hold water to half height. A hose was inserted into the grate at unit 3 to allow water to flow toward pit 5; the water flowed smoothly to the outlet drain at pit 2.  B took levels at all available pits and noted obvious movement of brickworks in units 3, 4, 5, 6, 7 and 8. Access was not available to the rear of the units.  The construction of the stormwater system was generally 300-700mm below the design levels as set out by T but with consistent falls.  T‟s original design was adequate to drain the site. Analysis of the design showed it was adequate for a one in five year storm event although B recommends 150mm pipes under pavements where grated pits allow leaves to enter the system, as the 100mm pipes clog more easily.  Inspection of the pits and drains showed that all were clean and water drained quite freely. The only deficiency noted was the box drain to unit 3 garage was not aligned correctly with the outlet pipe. Case No: 308389 Determination Page 5 of 10  A number of the box drains were filled with leaves and debris and a number of the roof gutters had sufficient soil in them to have plant growth. B recommended all drains he cleared of debris and kept clean.  A preliminary observation of brickwork movement in unit walls showed several areas of concern.  Analysis of the system shows the capacities of the system and of each pipe run exceed the flow estimated for the site. The system is satisfactory. 18. The FSP in denying the claim has essentially relied upon the findings of its experts, loss adjustor P and the engineer JM. 19. P‟s report of 30 July 2012 provides the following relevant information:  A building permit was issued on 12 June 2012 for the re-blocking works to builder “AR”.  A CCTV leak detection test conducted by leak detection firm “AL” on 21 June 2012 reveals a blockage of tree roots was located in the common line for units 4, 5, 6 & 7. Al‟s report set out that unit 7‟s stormwater line enters the common line at the lowest point closest to the easement and during heavy rain water would be backing up the pipe work and overflowing from the lowest point, which are the downpipes and box drain in front of units 6 and 7.  Generally, when foundations/footings have been compromised by stormwater damage, the result is typically swelling o r heaving. In this instance the property has subsided.  A geotechnical investigation would therefore be required. 20. J‟s initial report of 30 October 2012 provides the following relevant information:  The property was inspected on 3 September 2012 in the company of the tenant.  AL‟s report makes no mention of the very inadequate drainage provisions around the higher sides of the property, particularly the front/eastern side, as contributing factors to the excessively moist ground conditions.  The footing foundations were still very moist at the time of inspection despite the fact the drain blockage had been repaired months earlier. The ensuing timeframe should have provided ample time for excessive groundwater to have abated had it been caused by a blocked or leaking drain.  A blocked or leaking drain usually only causes a localised effect closest to the downpipe which is at the lowest point of the spouting.  The subject drain is downhill on lower ground and could not cause any soil saturation which would affect the foundations directly. Occasional spillage from spouting would be unlikely to cause even saturation of the surface soil let alone foundation saturation. Case No: 308389 Determination Page 6 of 10  No soil report as required for the underpinning design was made available for review. J considered underpinning was not necessary as the foundations were adequately supported by the soil conditions at the site. This is supported by the lack of any significant plaster distress in the home. No footing failure or settlement had occurred.  A large tree whose roots had most likely blocked the subject drain had been recently removed. There were other large trees in the vicinity which could have been a factor in causing some slight foundation rotation although this would not have required underpinning to remedy.  The driveway and grassed area outside the property collects rainwater runoff directly toward the property and under the foundations. Both surface and sub-surface drainage provisions at the front of the property were inadequate.  The underpinning took place in saturated soil conditions ignoring the drainage issues evident which will likely impact the stability and effectiveness of the underpinning. Proper soil testing should have identified the saturated ground conditions and addressed these shortfalls first before any attempt at underpinning was made. Underpinning should only be done once the soil had dried sufficiently.  The underpin design called for six underpins however only four were installed. The spacings of the underpins are inconsistent with accepted practice as the substantial spacings between the pins would make it impossible to jack and correctly align the foundations without breaking the footings.  Inspection of the foundations showed the footings are roughly 300mm deep although 450mm would have been recommended for a dwelling of this size. Inspection of the soils showed that although moist, the footings had been founded on adequately stiff clay soils and was being provided with adequate support.  As the underpinning was most likely not required, it is possible AR installed less pins that called for as no significant jacking to re-level the property was necessary.  There are gaps visible in the brick works, J considered these to be caused by extreme brick growth due to the absence of appropriate movement joint provision, aggravated by saturated lower brick courses in contact with damp soil for a sustained period of time. The fact that these gaps still existed after the underpinning was completed confirms underpinning was not necessary.  There are no stepped cracks in the brickwork which would indicate a localised footing failure. It appears the reason for the gaps in the brickwork has been missed by the Applicant‟s engineer and AR.  The correct procedure for underpinning is to carry out footing/foundation investigations first for any potential drainage issues, remedy those found and then allow sufficient time to elapse for the soil moisture content to stabilise. The Applicant‟s engineer should have done this before drafting the underpinning concept, including conducting soil tests himself. Case No: 308389 Determination Page 7 of 10  As the underpinning has been carried out in saturated soil conditions, it could move as the soil moisture stabilises.  Despite the considerable expense of the underpinning, the problem of the brick growth has not been remedied.  J concluded the blocked drain has not been an issue with respect to any of the damage sustained to the premises. 21. J‟s second report of 23 May 2013 provides the following relevant information:  AR quoted for three underpins in contr avention of the engineer‟s design for six underpins. AR‟s invoice shows four underpins were eventually installed; no explanation has been provided for the discrepancies.  Photographs show the underpinning was carried out in saturated conditions. Work should have been ceased and the source of water corrected, giving the soil sufficient time to dry out before works continued.  The engineer was required to inspect the works at the completion of the underpinning and issue a certificate of occupancy (the certificate) confirming the works were carried out in accordance with the plans.  J had not been provided with a copy of the certificate for review however he queries how it would have been issued when the completed work did not comply with the design.  It would appear the original engineer was not involved with the execution of the underpinning.  J suspects AR and the surveyor reached the conclusion the underpinning design was in error midway through the repairs hence the alteration.  As only the north eastern corner had some slight settlement, J would not have recommended underpinning but would have recommended drainage improvement to increase stability.  AL‟s report on the leaking pipe is deficient as it did not have a plan of the pipes surveyed nor does it pinpoint the source of the leak. J interpreted the report as the leak lying in the common drain on the lower side of the property, which was confirmed by the tenant as correct.  Further, AL‟s report makes no mention of the impact of the leak on the foundations.  J had since been advised the leak was actually just outside the fenced area of Unit 7, however had not been provided with supporting information.  J noted from his own photographs taken that the fenced area is considerably distanced from the house and also has a substantial fall to the west away from the house, meaning any water leaking from this drain would be unlikely to affect the foundations.  The problem with the saturated foundations is due to the absence of both surface and subsurface drainage around the high sides of the house, in particular on the eastern side. Case No: 308389 Determination Page 8 of 10  J inspected the property three months after the leaking drain had been rectified and the north wall foundations were still saturated. This would not be the case if the leaking pipe were the cause.  The house is still being adequately supported by the stable soil foundings as evidenced by the fact there are no cracks in the brickwork and minimal internal distress with only one crack on the north wall (lounge room).  The gaps in the brickwork were still evident which confirms the underpinning did not remedy the problem. Therefore, the problem was never footing movement or settlement in the first instance. Relevant exclusions under the policy 22. It is difficult to understand exactly what exclusion the FSP is relying upon to deny the claim. 23. The FSP did not complete its IDR process but in the Notice of Response has argued that there has been no accidental loss or damage. The FSP has submitted that on the balance of probabilities the damage was a result of saturated foundation due to the absence of both surface and sub surface drainage around the property and not caused by any ground saturation as a result of a leaking pipe. The FSP maintains that this does not come within the accidental damage insuring clause but does not explain how this is not both unintended and unexpected damage. 24. The FSP has referred to a number of exclusions when reciting the exclusions contained within the policy in the Notice of Response but has not identified which exclusion applies. 25. I note there are exclusions relating to the lack of maintenance, wear and tear or gradual deterioration, although the FSP has not argued that this was a cause of the damage to the Applicant‟s property and there is no evidence to say that it was. 26. There are exclusions relating to damage caused by vibration, erosion or earth movement but there is an exception if the damage is due to bursting, leaking or overflowing of water tanks, pipes, drains, gutters or other water or liquid carrying apparatus. 27. Whilst damage caused by underground (hydrostatic) water is excluded, the policy confirms it will pay if the loss is due to the bursting, leaking or overflow of water tanks, pipes or drains. 28. The policy does not indicate whether the leaking is required to be sudden. T he FSP‟s engineer suggests that as the foundations were still saturated that the damage was due to inadequate drainage provisions which resulted in long term water seepage and gradual deterioration. There is no evidence to say that the cause of the long term water seepage was an excluded event. 29. The FSP in its Notice of Response seems to have misunderstood that it has the onus to prove the application of the exclusion not the Applicant. In my Case No: 308389 Determination Page 9 of 10 view, the Applicant has established on the balance of probabilities that accidental damage has been sustained to the property. The evidence presented by the Applicant in my view establishes on the balance of probabilities that damage would have been sustained as a result of the identified leaking pipes. 30. Whilst the FSP has relied heavily on the evidence of an engineer, I am concerned that the engineer‟s report has not adequately addressed the cause of the damage or saturation of the soil. The initial report failed to properly identify the relevant damaged pipe. In his second report whilst the engineer addresses some of the issues, he does not identify why during the underpinning process, water saturation would have still been observed. 31. I note the engineer comments in a report on 4 February 2014 that the underpinning should not have been done on saturated foundation and further that the excessively moist foundations should have dictated further investigation into the cause of the saturation so that appropriate corrective action could occur. It is apparent from this that the cause of the excessively moist foundations has not been determined. 32. In my view, the evidence as presented by the FSP whilst offering criticism of the Applicant‟s material does not establish on the balance of probabilities the application of the general exclusions referred to by the FSP in the Notice of Response. Has the FSP been prejudiced by the Applicant’s completion of the repairs? 33. I am not satisfied that the FSP has presented evidence to establish any prejudice as a result of the Appl icant‟s failure to lodge the claim until the repairs had been completed. 34. The policy provides that the Applicant has an obligation to take all reasonable steps to reduce the loss or damage and to prevent any further loss or damage. According to the policy: “as soon as you discover that an event likely to result in a claim has occurred you must: a) Take all reasonable steps to reduce the loss or damage and to prevent any further loss or damage.” 35. The Applicant, by arranging for the underpinning works upon detecting the damage to the property and then subsequently arranging for a leak detection test was acting in accordance with the policy terms . 36. The FSP‟s engineer having incorrectly identified the broken/damaged pipe did not re attend the property to inspect the property. Comments in his report of 23 May 2013 whilst critical of the information provided by the Applicant, do not, in my view explain why he failed to correctly identify the area of damage or whether his initial inspection was an adequate inspection. Case No: 308389 Determination Page 10 of 10 37. In the engineer‟s report of 4 February 2014 he has referred to the fact that the claim was lodged retrospectively after the underpinning works had been completed denied the FSP any opportunity to engage an expert to investigate the alleged leaking drain an associated alleged damage. I do not accept that this is the case. Determination 38. Accordingly I determine the FSP is liable to meet the Applicant‟s claim in accordance with the terms of the policy.