Settlement method and scope of repairs for ground-movement building claim, with delays and poor handling
Text of the determination
Case No: 307550 Determination Page 1 of 11
Case number: 307550
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount & Service
11 October 2013
Background
1. The Applicant holds a home insurance policy with the Financial Services
Provider (FSP) for his residential property. The policy was incepted on 31
December 2009, which was shortly after its construction.
2. The policy was subsequently renewed for a further 12 months. During this
period, the building was insured for a sum up to $276,000 and the contents
for $158,000. Claims were subject to a $300 excess.
3. The Applicant lodged a claim with the FSP on 25 February 2011 for
damage sustained to the building. The following description was noted by
the FSP on its system:
“ OI advised of House Movement due to Recent Heavy Rains - Cracking to
Front External Brick Wall - Movement of Door Frames in living room & Master
Bedroom - Cracking of Plaster Wall above Door Frames .”
4. Following an initial assessment and reliance on a report issued by builder
“WW”, on 26 April 2011, the FSP denied liability on 23 August 2011.
5. On reviewing the decision, the FSP obtained an engineer’s report
accompanied by a geotechnical report. Based on the reports, the FSP
reversed its decision and accepted liability for the claim. The FSP proposed
to undertake repairs once the foundation soil is dry and no further
movement has occurred . The Applicant disputes the FSP’s decision and
requests that all rep airs be commenced to return the building to its original
condition or the FSP cash settle the claim.
6. In addition, the Applicant claims compensation for significant distress and
inconvenience as a result of the delays experienced in the FSP’s handling
of the claim.
Summary of Applicant ’s position
7. The Applicant has disputed the FSP’s decision on the following bases:
Determination
Case No: 307550 Determination Page 2 of 11
He believes it is futile awaiting the soil to dry as it has been more than
two years since the event occurred with no repairs being undertaken. In
particular, an inspection by the first engineer “A” established the slab to
be out of alignment by 40mm. At the next inspection by another
engineer “S” a year later, the slab was out of alignment by 45mm.
This shows the slab is not stabilising and is unlikely to ever do so.
The engineers’ reference to tolerance of the slab should be considered
in context of the absence of damage. As damage is clearly evident and
continues to occur, then the unevenness of the slab is unacceptable.
The FSP has continually sought to minimise expenses as evident by
the fact that one of the scope of works provided for expansion joints
above most doors. If this was allowed, it would reduce the value of the
property.
8. Further movement has been observed in the store room pantry area in July
2013, suggesting that the slab is not restabilising, contrary to the FSP’s
engineers ’ reports.
9. Based on the above, the Applicant submits the property cannot be repaired
but instead a replacement option is more appropriate. In this regard, he
submits that he should either be paid out the insured value or be allowed to
rebuild on another block of land.
10. Wit h respect to the claims handling, the Applicant has expressed extreme
dissatisfaction due to the numerous delays experienced and the fact that
the property still remains unrepaired over two and a half years after the
event . His wife is seventy one and he i s seventy three and that due to the
protracted nature of the dispute a long planned trip to England to celebrate
their fiftieth wedding anniversary in July 2013 with remaining family
members there, had been cancelled. This reflects some of the distressing
disruptions this dispute has caused.
Summary of FSP’s position
11. The FSP relies upon the engineer s’ reports it has obtained to substantiate
its position that the slab is structurally sound and the damage is repairable.
In particular, it considers its decision to repair the damage after the
foundation and slab has stabilised to be reasonable given the lifetime
guarantee it provides in this regard.
12. On 6 February 2013, the FSP completed a review of the Applicant’s claim
and maintained that the scope of works for repairs was correct and that any
repairs authorised would come with a lifetime guarantee. The FSP
maintained its decision to repair the damage to the property as per the
scope of works.
13. After a further report from S engineer, the FSP now maintains the property
should be monitored and as it has not completed this testing, it would not
Case No: 307550 Determination Page 3 of 11
commence repairs. Once it has confirmed that the foundation soil is dry and
no further movement would occur, repairs can then commence.
14. The FSP therefore relies on the above and the following policy provisions
with respect to its decision regarding the claim:
“ How we settle your claim
We choose how your claim is settled
If we agree to pay a claim for loss, theft or damage to your home or contents,
we will decide if we will:
repair damage new for old or
replace home or contents new for old or
pay you what it would cost us to repair or replace your home or contents
new for old.
…
Lifetime guarantee on home repairs
When we repair or rebuild your home, we guarantee the quality of materials
and workmanship of that work for the lifetime of your home if we:
authorise and
arrange and
pay the builder or repairer directly for this work.
What we guarantee
We guarantee the material used and standard of the workmanship to be free
of defects. If a defect arises in the lifetime of your home as a result of poor
quality workmanship or use of incorrect materials, then we will rectify the
problem. ”
15. In regards to the claims handling, the FSP acknowledged the Applicant did
not receive the lev el of service expected and regrets that this occurred.
However, it submits that due to the extent and complexity of the damage
sustained as well as the required repairs, some delays were unavoidable .
Issues
16. Whether the FSP’s decision with respect to the cl aim is fair in all the
circumstances and consistent with its policy obligations.
17. Whether the handling of the claim by the FSP has caused undue delay,
inconvenience and stress to the Applicant.
Reasons for decision
18. As advised to the parties, due to the nature of the dispute, the matter has
been referred to the Panel for Determination in line with the Operational
Case No: 307550 Determination Page 4 of 11
Guidelines to the Service’s Terms of Reference . This dispute has not been
the subject of a FOS Recommendation and has proceeded directly to
Determination.
19. The Panel is satisfied that there has now been a full exchange of material
between the parties and each party has had an opportunity to address the
issues that arise from the material exchanged.
20. In view of the delays in this matter and allegations regarding the poor
claims handling, it is worth looking at how the claim progressed.
21. After the claim was lodged, the FSP obtained a report from “ MF ” dated 11
March 2011, MF identified the damage to the house resulted after torrential
rain and acceptance of the claim was recommended. File notes record that
on 14 March 2011, a building consultant was to be appointed to inspect and
report on the cause and supply a scope of works. On 26 March 2011, file
notes record acceptance of the claim and advice that a builder had been
appointed to establish a scope of works.
22. On 26 April 2011 the assessment report was received by the FSP from
WW. The FSP then determined to decline the claim. The FSP’s file notes
record that the Applicant was aware that excessive watering of the lawn
was the cause of the problem and that the claim is declined. No
correspondence is recorded as being sent to the Applicant. It is clear from
the Applicant’s information that the Applicant had never been informed the
claim was declined.
23. It was not until 23 August 2011 when the Applicant requested an update on
the claim, that the FSP notified the Applicant that the claim was denied. A
letter was issued on 23 August 2011 rejecting the Applicant’s claim.
24. The Applicant wrote to the FSP on 29 August 2011 requesting a review of
the decision. The request is detailed with reasoned argument to dispute the
FSP decision. On 19 September 2011, the Applicant called the FSP. The
Applicant advised that he had sent a letter to dispute the claim decision and
had not received a response. No explanation is given for the failure to
respond.
25. On 27 September 2011, AA engineers were appointed by the FSP to
inspect the property and provide a report on the cause of damage.
26. On 24 October 2011, the FSP’s file notes record that the Applicant
contacted the FSP following up the engineer’s report. According to the file
notes, the engineer had attended the Applicant’s property on 18 October
2011.
27. According to a further notation in the FSP’s file notes on 25 October 2011,
they were informed that the engineer wished to appoint a geotechnical
consultant.
Case No: 307550 Determination Page 5 of 11
28. The next file note is recorded on 28 December 2011. There is no indication
of any prior follow up by the FSP with either the engineer or the
geotechnical consultant. The file note records based on an email that they
were still awaiting a report from the engineer and that the engineer had
suggested using a geotechnical engineer. No geotechnical engineer was
appointed at that stage. On 10 January 2012, the file notes indicate
authority was sought for a geotechnical engineer to attend. There is no
explanation for the delay.
29. On 2 February 2012, it appears from the file notes that the geotechnical
engineer had not been appointed. There appears to have been a
breakdown in communication between the FSP and their engineer as
nothing appears to have occurred by that time.
30. On 3 April 2012, there is a file note that the engineer’s report stated that it
may take up to 12 months for the soil moisture levels to return to
equilibrium. A second note on the same day states that the FSP contacted
the Applicant to advise the engineer had confirmed damage as a result of
the storm and not from excessive watering of the lawns. An assessor was
to attend to assess the scope of works. It is unclear from the file notes just
when the FSP received its scope of works.
31. On 9 August 2012 there is a file note indicating the FSP had sent copies of
the engineering report to two building service companies for quotations. On
21 August 2012 there is reference to quotations obtained and the variation
in estimates.
32. The next notification was on 11 September 2012 noting the property would
require another 12 months minimum drying time. The notation confirms that
both quotes were based on damage assessed in March 2012 and that
further damage had occurred since, due to the drying process. A revised
quotation was received on 16 November 2012. On the 23 November 2012
an authority for the repairs to proceed was sent to the preferred contractor.
33. The Applicant disputed the scope of works. It was not until 21 March 2013
that the FSP arranged for an alternative engineering report. The report from
S was received in May 2013. In the initial Notice of Response from the FSP
dated 13 May 2013, the FSP maintained its decision to repair the property.
34. In a subsequent Notice of Response dated 29 July 2013, the FSP, referring
to the engineers ’ report, noted that testing needed to be done to monitor
the movement of the slab before commencing repairs. It had not completed
its testing. There is no evidence of any arrangements made for the testing
to be undertaken.
35. As can be seen from the above there were considerable delays in the FSP
dealing with the issues in this claim to this time. Whether these delays are
justified needs to be considered against the information obtained by the
FSP.
Case No: 307550 Determination Page 6 of 11
36. The initial report by WW is dated 21 March 2011. WW is a building
surveyor and identifies excessive moisture as the cause. WW also
recommends checking the drains, monitoring the cracks and decreasing
water use.
37. The next report is from C dated 22 March 2012. It provides the following:
The claim for consideration under the storm rainwater section of the
policy should be considered.
C had handled some 300 claims of this nature in Mildura and the
surrounds from the 4/5 February 2011 storm, all of which had the same
or similar cause and all considered by adjurors on the same basis,
namely localised stormwater run-off.
38. The report referred to the engineering report from AA engineers dated 19
March 2013. It noted that as some 13 months had now elapsed since the
storm, that the Applicant may have some observations as to whether the
building had stabilised or not. It also referred to a geotechnical report.
39. The report from AA engineering recommends the defects be regularly
monitored until all movements have stabilised prior to undertaking any
repair works. It noted that it may take up to 12 months for the soil moisture
levels to return to equilibrium and for building movements to stabilise.
40. The Panel notes this report is more than 12 months after the storm event.
41. The geotechnical report of March 2012 commented that most likely the
cause of settlement was due to the softening of the founding material
through increase moisture content in the soil. A possible cause of the
moisture content was inundation (flood) rather than isolated watering of
front and rear or a leaking pipe.
42. A report from C dated 28 June 2012 refers to the last inspection of the
Applicant’s property occurring on 19 April 2012 and the Applicant providing
a list of defects in the home which were considered to be fresh as a
consequence of movement associated with the storm event. C was
satisfied the listing provided by the Applicant was fair and reasonable and a
sound reflection of the damage caused in the instant. C arranged for
quotations to be obtained.
43. The FSP has exchanged a number of quotations including scope of works.
Attachment 12 in the Notice of Response includes a quotation from IB.
Attached to a builders’ evaluation section are the following comments about
the work required and the uncertainty.
Quotations observation
None of the builder’s knew how best to tackle the work.
Case No: 307550 Determination Page 7 of 11
They concentrated on front to rear movement of the slab. The lateral
door frames out of alignment also indicate side to side movement which
I believe has not been considered. I suggest the slab is significantly
twisted and should be replaced. If not replaced, I suggest the main
frame is under stress and will continue to flex indefinitely.
.... As I suspected, it will be a patch up job and a case of “hope for the
best”. Ongoing liability would be the result. I have no confidence in the
ability of any builder to restore the building to the original condition and
more importantly, to my satisfaction, that resigned to the fact I have no
choice.
Not unreasonable, as the house is new to expect replacement rather
than repair.
44. These comments may be comments from the Applicant although they are
not identified as such in the quotation but simply identified as an
attachment to the quotation.
45. The final report is from S building consultants dated 3 May 2013 and
follows inspection of the Applicant’s property and discussions with the
Applicant.
46. S noted the following:
“There is no visible evidence of structural damage to the stiffened raft floor
slab and it appears to be structurally sound. GHD measured the change in
offset from a 3M straight edge at numerous locations on the floor of the
house.
... No repairs to foundation floor slab are necessary and floor slab is
considered serviceable.
... The walls and roof structures appear visually to be structurally sound.
... It is apparent that only the front of the foundation has been subjected to
heave. This suggests that relatively more moisture may have seeped into
the foundation soils in this area. It is possible tha t during installation or even
during the initial heave that a drain pipe or water supplied pipe was
damaged causing water to leak in to the foundation soils. ”
47. The Panel notes that there is no costing to the attached scope of works nor
is there any recommendation with respect to further inspection of the
property to determine why the moisture levels at the front of the property
are so high and if in fact the initial heave has caused damage to a drainage
or water supply pipe.
48. The Panel notes from the reports by S and the geotechnical engineer “ GD ”
that a number of remedial actions to address or mitigate the heave and
monitor the movement of the foundation are recommended as follows:
Case No: 307550 Determination Page 8 of 11
CCTV inspection of sewer pipes and stormwater system to check for
leaks. Repair if necessary.
Check for leaks in water supply system and irrigation system, repair if
necessary.
Investigate service trenches that run close to the front of the house for
possible flow along bottom of trenches in to the foundation soils. If
necessary, excavate unsuitable back fill from service trenches and
replace with compacted material similar to clay foundation soils.
Take measures to dry out the foundation soils at the front of the house
and allow them to reach stable moisture content. It may be necessary
to minimise or even cease watering of the lawn and plants to achieve
this. In addition, measures should be taken to minimise the seepage of
water through the paving into the foundation soils.
Monitor crack widths at interior walls for six to twelve months to detect if
heave is reversing. Check monthly the level of the floor inside at the
front door relative to the local datum in photo 30.
49. It is unclear why such strategies were not adopted in the first place. If you
look at the first report from WW, he recommends checking the pipes and
monitoring the cracks. The FSP was on notice at this time. Over two and a
half years have passed since and the FSP’s experts have now conceived a
strategy to eliminate all potential factors of moisture entering the soil.
50. It is unclear what, if any action has been taken by the FSP, to now
implement this strategy. Th e Panel accepts the Applicant’s concerns
expressed not only as to the claims handling process adopted but also the
FSP’s proposals with respect to the settlement of the claim are justified.
51. However, the Panel accepts based on the expert evidence now presented
that most likely the Applicant’s property can be repaired. Four appropriately
qualified experts have all inspected the property and agreed that the
damage can be repaired. Their findings are not contradicted by any other
information despite the Applicant expressing concern as to the process.
52. Based on the available evidence, it appears the continued issues of soil
movement are likely associated with additional w ater ingress which GD’s
strategy will address.
53. Although the Panel acknowledges the Applicant’s concern, in the absence
of any expert evidence to the contra view, the Panel accepts that the
strategy proposed by GD is appropriate. The Panel determines that the
FSP must upon acceptance of this Determination proceed immediately to
implement the strategy provided in GD’s report , including the inspection of
the sewer pipes and stormwater system, the checking of the water supply
system and irrigation system and repair if necessary. Investigation of the
relevant service trenches, monitoring crack widths and the interior walls
and taking measures to dry out the foundation soils at the front of the house
and allow them to reach a stable moisture content.
Case No: 307550 Determination Page 9 of 11
How the claim is to be settled
54. S provided a scope of works with their report, which is supported by the
remedial measures set out in GD’s report and i s consistent with the balance
of the expert evidence. It therefore appears to set out the appropriate
course of action in the circumstances .
55. S’s scope of works if followed , could result in yet another year of waiting for
the foundation movement to settle and protracting what has already been a
significant delay for the Applicant. The Panel is not satisfied based on the
scope of works that if the actions recommended by GD are taken out
immediately, that it would necessarily mean a further 12 month waiting
period for the foundation movement to settle , but recognises this is possible
and that the Applicant may not wish to wait for this process to be
completed. The Panel recognises that given the significant delays to date, it
may be unfair on the Applicant who has now lost faith in the FSP’s handling
of the matter to insist on the FSP proceeding with S’s scope of works.
56. In the circumstances, the Panel accepts that the Applicant may choose the
preferred method of settlement and have the claim cash settled.
57. In the event the claim is cash settled, then any cash settlement must be
based on the costs that would be likely to be incurred in the implementation
of the full mitigation strategy as suggested by GD and the repairs as
suggested by S. In cash settling the dispute, the FSP’s lifetime guarantee
on work required would not apply.
58. In the Panel’s view, it is appropriate that two quotations be obtained from
contractors who would be prepared to do the work on behalf of the
Applicant, directly at the rate quoted, if working directly for the Applicant.
The quotation should be based on S’s scope of works and GD’s mitigation
strategy. In the event that there is a discrepancy between the quotations,
then the Panel considers it is fair in all the circumsta nces that the average
of the two quotations should be agreed as the cash settled amount. The
Panel considers this appropriate given the fact that S’s scope of works is
fairly extensive and allows for the potential additional costs which may not
be adequately accounted and/or adjusted for (e.g. the repairs to the
stormwater and sewer pipes). Given the Applicant’s experience as to date,
the Panel considers such potentially contentious issues should be
minimised as much as possible.
59. In the Panel’s view, it wou ld be appropriate for each party to engage a
contractor to provide a quote. In the event that the Applicant does not wish
to engage one himself then he should notify the FSP who should then
obtain the two quotations.
Interest
60. Pursuant to Section 57 of the Insurance Contracts Act 1984 , interest is
payable on any cash settlement for the period commencing on the day as
Case No: 307550 Determination Page 10 of 11
from which it was unreasonable for the insurer to have withheld payment of
the amount and ending on whichever is the earlier of the following days:
a. The day on which payment is made;
b. The day on which payment is sent by post.
61. The Panel acknowledges that the FSP is entitled to proper investigation of
a claim and entitled in particular, given the circumstances of the current
dispute, to obtain appropriate engineering and geotechnical advice.
62. The Panel, however, considers the delays by the FSP in agreeing to
engage the experts and actually appointing and receiving the completed
reports unacceptable. The fact that the claim was first lodged in February
2011, yet the FSP did not notify the Applicant of the rejection of the claim
until August 2011, is totally unacceptable.
63. If the FSP had notified the Applicant on 26 April 2011 of its intention to
decline the claim, the Applicant would have then sought a review. The FSP
would have then obtained the relevant engineering reports to work towards
resolving the Applicant’s claim. It is unacceptable that it took the FSP until
April 2012 to notify the Applicant that the claim was accepted.
64. If the FSP had acted appropriately and efficiently, then a period of four
months from the initial lodgement of the claim would be a reasonable
period for the FSP to fully investigate the matter. Such time frame is
consistent with the General Insurance Code of Practice.
65. In the cir cumstances, having regard to S ection 57 of the Act, the Panel
considers it is fair in all the circumstances that interest should be paid from
26 June 2011 on any amount payable under a cash settlement .
Claims Handling
66. The Panel notes that under paragraph 9.3(b)(i), it can award compensation
of up to $3,000 in the following circumstances:
“…FOS may decide that the Financial Services Provider compensate the
Applicant for non-financial loss but only where:
(i) an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the Applicant’s expectation of
enjoyment or peace of mind has occurred .”
67. As can be seen from the issues raised throughout this Determination, the
FSP has taken an exceptionally long p eriod to respond to the Applicant’s
claim, it has taken over six months to decline the initial claim and a further
eight months to reach its IDR position. Fourteen months elapsed before the
Applicant was notified that the claim was accepted. On acceptance of the
claim, it has taken over twelve months to determine the scope of works and
in particular, identify the cause of the continued dampness at the property.
This is despite having the geotechnical report in March 2012 that
suggested possible causes.
Case No: 307550 Determination Page 11 of 11
68. In t he Panel’s view, the FSP’s conduct and in many respects, its failure to
take proactive measure to deal with the Applicant’s claim is not acceptable
nor in the reasonable contemplation of the parties when this insurance
contract was first arranged, regardless of the complexities involved in the
claim.
69. When taking all of factors into consideration, the Panel considers the FSP’s
handling of the claim has been significantly below the standards expected.
T he Panel accepts that due to the FSP’s mishandling, this has significantly
impacted and interfered with the Applicant’s peace of mind, particularly
given the insured property was a new home and the damage sustained due
to an insured event remains unrepaired 30 months after the event .
70. The Panel considers that an award up to the maximum amount of $3,000
under paragraph 9.3(b)(i) of the Terms of Reference is warranted and fair in
all the circumstances.
Determination
71. On the basis of the available information the Panel determines the
following:
a. The damage sustained to the property is able to be repaired and is not
required to be replaced or considered a total loss.
b. The Applicant has the option to either have the FSP repair the damage
pursuant to S’s scope of works or have the claim cash settled based on
these same scope of works.
c. If the Applicant opts to accept a cash settlement option, the parties are
directed to follow the process set out in this Determination.
d. In the event any aspect of the claim is resolved by way of cash
settlement, the FSP is to pay interest on a ny sum paid in accordance
with Section 57 of the Insurance Contracts Act 1984 from 26 June 2011
to the date when payment is affected.
e. In addition to the above, the FSP is to pay the Applicant $3,000 by way
of compensation for non-financial loss.