Determination 307550

Settlement method and scope of repairs for ground-movement building claim, with delays and poor handling

FirmFinancial Firm (Unknown - Insurer)
Decided2013-10-29
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

The insurer accepted a building claim for storm-related ground movement after a long and delayed investigation. AFCA allowed the insured to choose cash settlement based on expert scope of works, with interest, and ordered $3,000 non-financial loss.

Under section 57 of the Insurance Contracts Act 1984 and the General Insurance Code of Practice, an insurer must investigate promptly and pay interest on delayed cash settlement; the amount of cash settlement was left to be calculated from quotes.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 307550 Determination Page 1 of 11 Case number: 307550 General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim amount & Service 11 October 2013 Background 1. The Applicant holds a home insurance policy with the Financial Services Provider (FSP) for his residential property. The policy was incepted on 31 December 2009, which was shortly after its construction. 2. The policy was subsequently renewed for a further 12 months. During this period, the building was insured for a sum up to $276,000 and the contents for $158,000. Claims were subject to a $300 excess. 3. The Applicant lodged a claim with the FSP on 25 February 2011 for damage sustained to the building. The following description was noted by the FSP on its system: “ OI advised of House Movement due to Recent Heavy Rains - Cracking to Front External Brick Wall - Movement of Door Frames in living room & Master Bedroom - Cracking of Plaster Wall above Door Frames .” 4. Following an initial assessment and reliance on a report issued by builder “WW”, on 26 April 2011, the FSP denied liability on 23 August 2011. 5. On reviewing the decision, the FSP obtained an engineer’s report accompanied by a geotechnical report. Based on the reports, the FSP reversed its decision and accepted liability for the claim. The FSP proposed to undertake repairs once the foundation soil is dry and no further movement has occurred . The Applicant disputes the FSP’s decision and requests that all rep airs be commenced to return the building to its original condition or the FSP cash settle the claim. 6. In addition, the Applicant claims compensation for significant distress and inconvenience as a result of the delays experienced in the FSP’s handling of the claim. Summary of Applicant ’s position 7. The Applicant has disputed the FSP’s decision on the following bases: Determination Case No: 307550 Determination Page 2 of 11  He believes it is futile awaiting the soil to dry as it has been more than two years since the event occurred with no repairs being undertaken. In particular, an inspection by the first engineer “A” established the slab to be out of alignment by 40mm. At the next inspection by another engineer “S” a year later, the slab was out of alignment by 45mm. This shows the slab is not stabilising and is unlikely to ever do so.  The engineers’ reference to tolerance of the slab should be considered in context of the absence of damage. As damage is clearly evident and continues to occur, then the unevenness of the slab is unacceptable.  The FSP has continually sought to minimise expenses as evident by the fact that one of the scope of works provided for expansion joints above most doors. If this was allowed, it would reduce the value of the property. 8. Further movement has been observed in the store room pantry area in July 2013, suggesting that the slab is not restabilising, contrary to the FSP’s engineers ’ reports. 9. Based on the above, the Applicant submits the property cannot be repaired but instead a replacement option is more appropriate. In this regard, he submits that he should either be paid out the insured value or be allowed to rebuild on another block of land. 10. Wit h respect to the claims handling, the Applicant has expressed extreme dissatisfaction due to the numerous delays experienced and the fact that the property still remains unrepaired over two and a half years after the event . His wife is seventy one and he i s seventy three and that due to the protracted nature of the dispute a long planned trip to England to celebrate their fiftieth wedding anniversary in July 2013 with remaining family members there, had been cancelled. This reflects some of the distressing disruptions this dispute has caused. Summary of FSP’s position 11. The FSP relies upon the engineer s’ reports it has obtained to substantiate its position that the slab is structurally sound and the damage is repairable. In particular, it considers its decision to repair the damage after the foundation and slab has stabilised to be reasonable given the lifetime guarantee it provides in this regard. 12. On 6 February 2013, the FSP completed a review of the Applicant’s claim and maintained that the scope of works for repairs was correct and that any repairs authorised would come with a lifetime guarantee. The FSP maintained its decision to repair the damage to the property as per the scope of works. 13. After a further report from S engineer, the FSP now maintains the property should be monitored and as it has not completed this testing, it would not Case No: 307550 Determination Page 3 of 11 commence repairs. Once it has confirmed that the foundation soil is dry and no further movement would occur, repairs can then commence. 14. The FSP therefore relies on the above and the following policy provisions with respect to its decision regarding the claim: “ How we settle your claim We choose how your claim is settled If we agree to pay a claim for loss, theft or damage to your home or contents, we will decide if we will:  repair damage new for old or  replace home or contents new for old or  pay you what it would cost us to repair or replace your home or contents new for old. … Lifetime guarantee on home repairs When we repair or rebuild your home, we guarantee the quality of materials and workmanship of that work for the lifetime of your home if we:  authorise and  arrange and  pay the builder or repairer directly for this work. What we guarantee We guarantee the material used and standard of the workmanship to be free of defects. If a defect arises in the lifetime of your home as a result of poor quality workmanship or use of incorrect materials, then we will rectify the problem. ” 15. In regards to the claims handling, the FSP acknowledged the Applicant did not receive the lev el of service expected and regrets that this occurred. However, it submits that due to the extent and complexity of the damage sustained as well as the required repairs, some delays were unavoidable . Issues 16. Whether the FSP’s decision with respect to the cl aim is fair in all the circumstances and consistent with its policy obligations. 17. Whether the handling of the claim by the FSP has caused undue delay, inconvenience and stress to the Applicant. Reasons for decision 18. As advised to the parties, due to the nature of the dispute, the matter has been referred to the Panel for Determination in line with the Operational Case No: 307550 Determination Page 4 of 11 Guidelines to the Service’s Terms of Reference . This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 19. The Panel is satisfied that there has now been a full exchange of material between the parties and each party has had an opportunity to address the issues that arise from the material exchanged. 20. In view of the delays in this matter and allegations regarding the poor claims handling, it is worth looking at how the claim progressed. 21. After the claim was lodged, the FSP obtained a report from “ MF ” dated 11 March 2011, MF identified the damage to the house resulted after torrential rain and acceptance of the claim was recommended. File notes record that on 14 March 2011, a building consultant was to be appointed to inspect and report on the cause and supply a scope of works. On 26 March 2011, file notes record acceptance of the claim and advice that a builder had been appointed to establish a scope of works. 22. On 26 April 2011 the assessment report was received by the FSP from WW. The FSP then determined to decline the claim. The FSP’s file notes record that the Applicant was aware that excessive watering of the lawn was the cause of the problem and that the claim is declined. No correspondence is recorded as being sent to the Applicant. It is clear from the Applicant’s information that the Applicant had never been informed the claim was declined. 23. It was not until 23 August 2011 when the Applicant requested an update on the claim, that the FSP notified the Applicant that the claim was denied. A letter was issued on 23 August 2011 rejecting the Applicant’s claim. 24. The Applicant wrote to the FSP on 29 August 2011 requesting a review of the decision. The request is detailed with reasoned argument to dispute the FSP decision. On 19 September 2011, the Applicant called the FSP. The Applicant advised that he had sent a letter to dispute the claim decision and had not received a response. No explanation is given for the failure to respond. 25. On 27 September 2011, AA engineers were appointed by the FSP to inspect the property and provide a report on the cause of damage. 26. On 24 October 2011, the FSP’s file notes record that the Applicant contacted the FSP following up the engineer’s report. According to the file notes, the engineer had attended the Applicant’s property on 18 October 2011. 27. According to a further notation in the FSP’s file notes on 25 October 2011, they were informed that the engineer wished to appoint a geotechnical consultant. Case No: 307550 Determination Page 5 of 11 28. The next file note is recorded on 28 December 2011. There is no indication of any prior follow up by the FSP with either the engineer or the geotechnical consultant. The file note records based on an email that they were still awaiting a report from the engineer and that the engineer had suggested using a geotechnical engineer. No geotechnical engineer was appointed at that stage. On 10 January 2012, the file notes indicate authority was sought for a geotechnical engineer to attend. There is no explanation for the delay. 29. On 2 February 2012, it appears from the file notes that the geotechnical engineer had not been appointed. There appears to have been a breakdown in communication between the FSP and their engineer as nothing appears to have occurred by that time. 30. On 3 April 2012, there is a file note that the engineer’s report stated that it may take up to 12 months for the soil moisture levels to return to equilibrium. A second note on the same day states that the FSP contacted the Applicant to advise the engineer had confirmed damage as a result of the storm and not from excessive watering of the lawns. An assessor was to attend to assess the scope of works. It is unclear from the file notes just when the FSP received its scope of works. 31. On 9 August 2012 there is a file note indicating the FSP had sent copies of the engineering report to two building service companies for quotations. On 21 August 2012 there is reference to quotations obtained and the variation in estimates. 32. The next notification was on 11 September 2012 noting the property would require another 12 months minimum drying time. The notation confirms that both quotes were based on damage assessed in March 2012 and that further damage had occurred since, due to the drying process. A revised quotation was received on 16 November 2012. On the 23 November 2012 an authority for the repairs to proceed was sent to the preferred contractor. 33. The Applicant disputed the scope of works. It was not until 21 March 2013 that the FSP arranged for an alternative engineering report. The report from S was received in May 2013. In the initial Notice of Response from the FSP dated 13 May 2013, the FSP maintained its decision to repair the property. 34. In a subsequent Notice of Response dated 29 July 2013, the FSP, referring to the engineers ’ report, noted that testing needed to be done to monitor the movement of the slab before commencing repairs. It had not completed its testing. There is no evidence of any arrangements made for the testing to be undertaken. 35. As can be seen from the above there were considerable delays in the FSP dealing with the issues in this claim to this time. Whether these delays are justified needs to be considered against the information obtained by the FSP. Case No: 307550 Determination Page 6 of 11 36. The initial report by WW is dated 21 March 2011. WW is a building surveyor and identifies excessive moisture as the cause. WW also recommends checking the drains, monitoring the cracks and decreasing water use. 37. The next report is from C dated 22 March 2012. It provides the following:  The claim for consideration under the storm rainwater section of the policy should be considered.  C had handled some 300 claims of this nature in Mildura and the surrounds from the 4/5 February 2011 storm, all of which had the same or similar cause and all considered by adjurors on the same basis, namely localised stormwater run-off. 38. The report referred to the engineering report from AA engineers dated 19 March 2013. It noted that as some 13 months had now elapsed since the storm, that the Applicant may have some observations as to whether the building had stabilised or not. It also referred to a geotechnical report. 39. The report from AA engineering recommends the defects be regularly monitored until all movements have stabilised prior to undertaking any repair works. It noted that it may take up to 12 months for the soil moisture levels to return to equilibrium and for building movements to stabilise. 40. The Panel notes this report is more than 12 months after the storm event. 41. The geotechnical report of March 2012 commented that most likely the cause of settlement was due to the softening of the founding material through increase moisture content in the soil. A possible cause of the moisture content was inundation (flood) rather than isolated watering of front and rear or a leaking pipe. 42. A report from C dated 28 June 2012 refers to the last inspection of the Applicant’s property occurring on 19 April 2012 and the Applicant providing a list of defects in the home which were considered to be fresh as a consequence of movement associated with the storm event. C was satisfied the listing provided by the Applicant was fair and reasonable and a sound reflection of the damage caused in the instant. C arranged for quotations to be obtained. 43. The FSP has exchanged a number of quotations including scope of works. Attachment 12 in the Notice of Response includes a quotation from IB. Attached to a builders’ evaluation section are the following comments about the work required and the uncertainty. Quotations observation  None of the builder’s knew how best to tackle the work. Case No: 307550 Determination Page 7 of 11  They concentrated on front to rear movement of the slab. The lateral door frames out of alignment also indicate side to side movement which I believe has not been considered. I suggest the slab is significantly twisted and should be replaced. If not replaced, I suggest the main frame is under stress and will continue to flex indefinitely.  .... As I suspected, it will be a patch up job and a case of “hope for the best”. Ongoing liability would be the result. I have no confidence in the ability of any builder to restore the building to the original condition and more importantly, to my satisfaction, that resigned to the fact I have no choice.  Not unreasonable, as the house is new to expect replacement rather than repair. 44. These comments may be comments from the Applicant although they are not identified as such in the quotation but simply identified as an attachment to the quotation. 45. The final report is from S building consultants dated 3 May 2013 and follows inspection of the Applicant’s property and discussions with the Applicant. 46. S noted the following: “There is no visible evidence of structural damage to the stiffened raft floor slab and it appears to be structurally sound. GHD measured the change in offset from a 3M straight edge at numerous locations on the floor of the house. ... No repairs to foundation floor slab are necessary and floor slab is considered serviceable. ... The walls and roof structures appear visually to be structurally sound. ... It is apparent that only the front of the foundation has been subjected to heave. This suggests that relatively more moisture may have seeped into the foundation soils in this area. It is possible tha t during installation or even during the initial heave that a drain pipe or water supplied pipe was damaged causing water to leak in to the foundation soils. ” 47. The Panel notes that there is no costing to the attached scope of works nor is there any recommendation with respect to further inspection of the property to determine why the moisture levels at the front of the property are so high and if in fact the initial heave has caused damage to a drainage or water supply pipe. 48. The Panel notes from the reports by S and the geotechnical engineer “ GD ” that a number of remedial actions to address or mitigate the heave and monitor the movement of the foundation are recommended as follows: Case No: 307550 Determination Page 8 of 11  CCTV inspection of sewer pipes and stormwater system to check for leaks. Repair if necessary.  Check for leaks in water supply system and irrigation system, repair if necessary.  Investigate service trenches that run close to the front of the house for possible flow along bottom of trenches in to the foundation soils. If necessary, excavate unsuitable back fill from service trenches and replace with compacted material similar to clay foundation soils.  Take measures to dry out the foundation soils at the front of the house and allow them to reach stable moisture content. It may be necessary to minimise or even cease watering of the lawn and plants to achieve this. In addition, measures should be taken to minimise the seepage of water through the paving into the foundation soils.  Monitor crack widths at interior walls for six to twelve months to detect if heave is reversing. Check monthly the level of the floor inside at the front door relative to the local datum in photo 30. 49. It is unclear why such strategies were not adopted in the first place. If you look at the first report from WW, he recommends checking the pipes and monitoring the cracks. The FSP was on notice at this time. Over two and a half years have passed since and the FSP’s experts have now conceived a strategy to eliminate all potential factors of moisture entering the soil. 50. It is unclear what, if any action has been taken by the FSP, to now implement this strategy. Th e Panel accepts the Applicant’s concerns expressed not only as to the claims handling process adopted but also the FSP’s proposals with respect to the settlement of the claim are justified. 51. However, the Panel accepts based on the expert evidence now presented that most likely the Applicant’s property can be repaired. Four appropriately qualified experts have all inspected the property and agreed that the damage can be repaired. Their findings are not contradicted by any other information despite the Applicant expressing concern as to the process. 52. Based on the available evidence, it appears the continued issues of soil movement are likely associated with additional w ater ingress which GD’s strategy will address. 53. Although the Panel acknowledges the Applicant’s concern, in the absence of any expert evidence to the contra view, the Panel accepts that the strategy proposed by GD is appropriate. The Panel determines that the FSP must upon acceptance of this Determination proceed immediately to implement the strategy provided in GD’s report , including the inspection of the sewer pipes and stormwater system, the checking of the water supply system and irrigation system and repair if necessary. Investigation of the relevant service trenches, monitoring crack widths and the interior walls and taking measures to dry out the foundation soils at the front of the house and allow them to reach a stable moisture content. Case No: 307550 Determination Page 9 of 11 How the claim is to be settled 54. S provided a scope of works with their report, which is supported by the remedial measures set out in GD’s report and i s consistent with the balance of the expert evidence. It therefore appears to set out the appropriate course of action in the circumstances . 55. S’s scope of works if followed , could result in yet another year of waiting for the foundation movement to settle and protracting what has already been a significant delay for the Applicant. The Panel is not satisfied based on the scope of works that if the actions recommended by GD are taken out immediately, that it would necessarily mean a further 12 month waiting period for the foundation movement to settle , but recognises this is possible and that the Applicant may not wish to wait for this process to be completed. The Panel recognises that given the significant delays to date, it may be unfair on the Applicant who has now lost faith in the FSP’s handling of the matter to insist on the FSP proceeding with S’s scope of works. 56. In the circumstances, the Panel accepts that the Applicant may choose the preferred method of settlement and have the claim cash settled. 57. In the event the claim is cash settled, then any cash settlement must be based on the costs that would be likely to be incurred in the implementation of the full mitigation strategy as suggested by GD and the repairs as suggested by S. In cash settling the dispute, the FSP’s lifetime guarantee on work required would not apply. 58. In the Panel’s view, it is appropriate that two quotations be obtained from contractors who would be prepared to do the work on behalf of the Applicant, directly at the rate quoted, if working directly for the Applicant. The quotation should be based on S’s scope of works and GD’s mitigation strategy. In the event that there is a discrepancy between the quotations, then the Panel considers it is fair in all the circumsta nces that the average of the two quotations should be agreed as the cash settled amount. The Panel considers this appropriate given the fact that S’s scope of works is fairly extensive and allows for the potential additional costs which may not be adequately accounted and/or adjusted for (e.g. the repairs to the stormwater and sewer pipes). Given the Applicant’s experience as to date, the Panel considers such potentially contentious issues should be minimised as much as possible. 59. In the Panel’s view, it wou ld be appropriate for each party to engage a contractor to provide a quote. In the event that the Applicant does not wish to engage one himself then he should notify the FSP who should then obtain the two quotations. Interest 60. Pursuant to Section 57 of the Insurance Contracts Act 1984 , interest is payable on any cash settlement for the period commencing on the day as Case No: 307550 Determination Page 10 of 11 from which it was unreasonable for the insurer to have withheld payment of the amount and ending on whichever is the earlier of the following days: a. The day on which payment is made; b. The day on which payment is sent by post. 61. The Panel acknowledges that the FSP is entitled to proper investigation of a claim and entitled in particular, given the circumstances of the current dispute, to obtain appropriate engineering and geotechnical advice. 62. The Panel, however, considers the delays by the FSP in agreeing to engage the experts and actually appointing and receiving the completed reports unacceptable. The fact that the claim was first lodged in February 2011, yet the FSP did not notify the Applicant of the rejection of the claim until August 2011, is totally unacceptable. 63. If the FSP had notified the Applicant on 26 April 2011 of its intention to decline the claim, the Applicant would have then sought a review. The FSP would have then obtained the relevant engineering reports to work towards resolving the Applicant’s claim. It is unacceptable that it took the FSP until April 2012 to notify the Applicant that the claim was accepted. 64. If the FSP had acted appropriately and efficiently, then a period of four months from the initial lodgement of the claim would be a reasonable period for the FSP to fully investigate the matter. Such time frame is consistent with the General Insurance Code of Practice. 65. In the cir cumstances, having regard to S ection 57 of the Act, the Panel considers it is fair in all the circumstances that interest should be paid from 26 June 2011 on any amount payable under a cash settlement . Claims Handling 66. The Panel notes that under paragraph 9.3(b)(i), it can award compensation of up to $3,000 in the following circumstances: “…FOS may decide that the Financial Services Provider compensate the Applicant for non-financial loss but only where: (i) an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant’s expectation of enjoyment or peace of mind has occurred .” 67. As can be seen from the issues raised throughout this Determination, the FSP has taken an exceptionally long p eriod to respond to the Applicant’s claim, it has taken over six months to decline the initial claim and a further eight months to reach its IDR position. Fourteen months elapsed before the Applicant was notified that the claim was accepted. On acceptance of the claim, it has taken over twelve months to determine the scope of works and in particular, identify the cause of the continued dampness at the property. This is despite having the geotechnical report in March 2012 that suggested possible causes. Case No: 307550 Determination Page 11 of 11 68. In t he Panel’s view, the FSP’s conduct and in many respects, its failure to take proactive measure to deal with the Applicant’s claim is not acceptable nor in the reasonable contemplation of the parties when this insurance contract was first arranged, regardless of the complexities involved in the claim. 69. When taking all of factors into consideration, the Panel considers the FSP’s handling of the claim has been significantly below the standards expected. T he Panel accepts that due to the FSP’s mishandling, this has significantly impacted and interfered with the Applicant’s peace of mind, particularly given the insured property was a new home and the damage sustained due to an insured event remains unrepaired 30 months after the event . 70. The Panel considers that an award up to the maximum amount of $3,000 under paragraph 9.3(b)(i) of the Terms of Reference is warranted and fair in all the circumstances. Determination 71. On the basis of the available information the Panel determines the following: a. The damage sustained to the property is able to be repaired and is not required to be replaced or considered a total loss. b. The Applicant has the option to either have the FSP repair the damage pursuant to S’s scope of works or have the claim cash settled based on these same scope of works. c. If the Applicant opts to accept a cash settlement option, the parties are directed to follow the process set out in this Determination. d. In the event any aspect of the claim is resolved by way of cash settlement, the FSP is to pay interest on a ny sum paid in accordance with Section 57 of the Insurance Contracts Act 1984 from 26 June 2011 to the date when payment is affected. e. In addition to the above, the FSP is to pay the Applicant $3,000 by way of compensation for non-financial loss.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.