Text of the determination
Case No: 306849 Determination Page 1 of 16
Case number: 306849
General Insurance - Domestic Insurance - Home Building - Service - Delay in
claim handling
18 March 2014
Summary
Description
Home and Contents policy dispute following a claim for water damage
lodged in November 2011. Dispute has arisen as to the extent of
liability, the FSP declining aspects of the claim due to policy exclusions.
Basis of Determination
The property was water damaged in November 2011.
Numerous expert opinions were obtained by both parties.
The weight of the expert evidence establishes on the balance of
probabilities the damage sustained was due to an insured event.
Determination
The FSP is to meet its liability in accordance with the terms of the
policy and cash settle the Applicants‟ claim based o n the cost of repairs
required as per the scope of works 1 and 2, the costs of repair/
replacement of the carpets and either cash settle the cost of the
accommodation in advance or as incurred.
Background
1. The Applicants hold a home insurance policy with the Financial Services
Provider (FSP) that commenced on 9 July 2007 providing complete
replacement cover and contents cover of $44,500. An excess of $400
applies to the claim.
2. On 27 November 2011, the Applicants lodged a claim for damage to the
substructure of the home, the FSP recording the following description of the
damage:
“I was under the house and i have noticed a large hollow. I am not sure what
has caused this, we may have a leak under the house.” [sic]
Determination
Case No: 306849 Determination Page 2 of 16
3. The FSP initially considered damage had been occurring due to water runoff
coming from a neighbouring property and agreed to indemnify the Applicants
for the resultant damage.
4. The FSP subsequently determined the damage was not related to an
insured event covered under the policy, however, due to the delays in
processing the claim, the FSP agreed to offer limited coverage for the areas
of the Applicants‟ home it had previously accepted as covered and provided
compensation of $2,000 for delays in finalising the claim.
5. The Applicants seek a review of the FSP‟s decision.
Summary of Applicants’ position
6. The Applicants reject the scope of works prepared by “JLG” and relied upon
by the FSP in its proposal for part settlement of their claim on the basis that:
The Applicants‟ engineer, “RB” has indicated that the founding depth of
all footings is to be a minimum of 2.4 metres.
On 17 September 2013 the FSP accepted RB‟s recommendations in
respect of footing depth.
They believe they are entitled to indemnity for replacement of all
stumps at the property (at a depth of 2.4 metres).
7. The Applicants reject the FSP‟s proposal to only indemnify them for those
works provided in JLG‟s “scope of works 1” on the basis the FSP has
classifi ed the matters in “scope of works 2” as being building defects and
maintenance related matters.
8. The Applicants say the delays in resolving their claim has resulted in
additional damage to the property, with movement continuing to occur as a
result of the footings undermined by the storm water runoff.
9. The Applicants seek indemnity for the full extent of the damage to their home
(as set out in scopes 1 & 2) on the basis of their engineer‟s assessment that
“the movement component caused by the event is somew here in the order of
90% plus of the house’s total area.”
10. The Applicants do not agree to JLG being retained to undertake the works
and are prepared to resolve the matter on the following basis:
a. Receiving an acknowledgement from the FSP that an insured event
has occurred for which they are entitled to indemnity under the policy.
b. Cash settlement for the works identified in both scopes 1 & 2 (including
allowance for the cost of replacement stumps at a minimum footing of
2.4 metres).
c. Reimbursement of $3,030.50 for works associated with the installation
of an „Ag drain‟ along the length of their property, carried out as per the
FSP‟s expert‟s initial recommendations.
Case No: 306849 Determination Page 3 of 16
d. Repair/replacement of their carpet which has lifted and been damaged
as a result of the underlying structural damage.
e. Indemnity by way of cash settlement in respect of alternative
accommodation, garden reinstatement, removal costs and storage.
f. Compensation for non-financial loss for delays and failure by the FSP
to handle their claim effectively.
Summary of FSP’s position
11. The FSP initially accepted that there was resultant damage at the property
caused by surface run off from a neighbouring property.
12. However, after receiving additional expert material, the FSP has determined
that the damage to the insured property has not been caused by an insured
event. Rather the FSP considers the damage to the property to be the result
of subsidence and stump failure that has existed for an extended period of
time.
13. Whilst the FSP maintains the Applicants are not entitled to indemnity under
the policy, it has nonetheless agreed to indemnify them for the damage it
initially accepted as being damage caused by stormwater runoff.
14. As the damage to the south western area of the building was
predominately caused by subsidence/stump failure (and the FSP has not
previously accepted liability for these areas of the property) the FSP says the
damage to the two bedrooms, study and north side of the lounge are
excluded. It has also identified other areas of cracking and pre-existing
damage which it says are not resultant damage of stormwater run-off.
15. The FSP refers to these excluded aspects of the damage as being
„maintenance works‟, and they are described accordingly in the second
scope of works that has been prepared.
16. On receiving final quotations in respect of the final scope of works for the
accepted items, the FSP has offered to cash settle the Applicants in the sum
of $56,252.11, based on a quote from its builder, JLG.
17. The FSP believes cash settlement is the only option as the Applicants have
indicated they intend to carry out the identified maintenance (or excluded)
works at the same time as the accepted works.
18. The FSP accepts liability for any carpet requiring repair or replacement as a
result of the claim related building repairs.
19. It also accepts liability for the costs associated with alternative
accommodation for the Applicants and their pets during the repairs and has
indicated it is willing to work with the Applicants to source suitable
accommodation for this period.
Case No: 306849 Determination Page 4 of 16
20. In respect of the Applicant s‟ submissions that the FSP‟s delays in processing
the claim has resulted in further damage to the property the FSP says the
onus is on the Applicants to prove this, and they have not done so.
21. In respect of the Applicants submissions that the compensation provided to
date is insufficient, the FSP says its decision to partly indemnify them for the
claim although it is specifically excluded from cover is compensation enough
for their delays in assessing the claim.
22. In any event, the Applicants have been provided with compensation of
$2,000 due to delays in finalising the claim. Further, the engineering expert
“FE” has stated that the correct remedy for damage suffered in these
circumstances is to allow sufficient time for a drying out period, such that soil
moisture levels have returned to pre -event conditions. Therefore, whilst the
FSP admits there has been a significant delay in settling the claim, due to
the required drying out period, had the claim been settled earlier, repairs
would not have been able to commence for a period of 12-18 months, as soil
movement was continuing during that time.
23. The FSP has agreed to reimburse the Applicants for the expert report costs.
Payment of $3,146.00 has now been issued to them. The FSP has also
reimbursed the Applicants for $497 for works associated with their pathway.
Issues
24. Whether the damage was caused by an insured event under the policy.
25. Whether the FSP is entitled to deny coverage for the two bedrooms, study
and north side of the lounge.
26. Whether the Applicants are entitled to any further compensation pursuant to
paragraph 9.3(b)(i) of the Financial Ombudsman Service (FOS) Terms of
Reference.
Reasons for decision
27. Due to the nature of the dispute, it has been directly referred to the Panel for
Determination in accordance with the Operational Guidelines to the Financial
Ombudsman Service‟s (FOS) Terms of Reference.
28. The Panel consists of an Ombudsman and two Panel Members with
extensive experience in insurance industry matters and consumer claims.
29. Having reviewed the available evidence, the Panel notes:
The Applicants‟ home is estimated to be about 50 years old and the
Applicants have lived there since 2007.
Case No: 306849 Determination Page 5 of 16
There is no evidence to suggest that the home had prior incidences of
movement or cracking since purchased by the Applicants. These
issues appear to have first surfaced sometime in November 2011.
The Applicants lodged their claim on 27 November 2011. Initial
investigations indicated the cause of the damage was storm water
runoff from the neighbouring property. Several months later it was
identified that the source of the runoff included a defective stormwater
drain at the neighbouring property. It is unknown how long the drain
issue had been occurring, however it has now been rectified.
The Applicants were first advised by the FSP that its expert had now
determined that the damage to their property did not arise from an
insured event on 28 December 2012, 13 months after claim lodgement.
Ongoing movement of the structure has occurred since lodgement of
the claim. This has been verified by various experts who have
inspected the property at various stages throughout the dispute.
The Applicants have continued to keep the FSP informed of the
additional issues that have arisen as a consequence of the continued
movement, including the inability to close external doors and properly
secure the property.
30. The first issue for the Panel to consider is whether the proximate cause of
the damage to the Applicants‟ home is the stormwater runoff, and therefore
whether an insured event has occurred. If so, the next consideration for the
Panel is the extent of damage that has been caused by that insured event.
Expert Evidence
31. The parties have each provided expert evidence in respect of the cause of
the damage and appropriate scope of works. The key points of these reports
are set out below.
FSP’s Expert Evidence
32. The FSP‟s initial assessment report, dated 3 January 2012 provides the
following opinion:
“Water has caused soi l under the sub-floor to erode away around some of the
perimeter stumps on the LHS & under the concrete side paving. ...
Io‟s home is showings signs of movement between the kitchen/laundry areas
with obvious slops to the tile kitchen floor between the island bench and
laundry door. ...
Standing at the front of the decking one can see the decking also slopping
back towards the back wall & leaning towards the laundry. The laundry door
can no longer be opened due to the movement and the back double doors
have had to be planed so that they can be closed/opened.
There are a few concrete stumps under the decking which have cracked. Mr
Io stated that he has had the stumps looked at by a re-stumper who stated
that the home is shifting and requires re- stumping. ...” (sic)
Case No: 306849 Determination Page 6 of 16
33. The FSP‟s engineer “HCE” prepared a report dated 22 February 2012 which
states:
Cracking and movement is occurring of the kitchen and laundry area at
the rear south-west corner of the house and it was indicated by the
owner that these problems have recently occurred.
The kitchen and laundry floor appear out of level. Doors in this area are
out of square, cracks are evident in the door architraves, and the
kitchen bench is out of level.
The built in cupboard doors in the north-east corner bedroom are out of
square, wall tiles and wall lining of the south side wall of the bathroom
are cracked, and the floor of the family room at the rear north-west
corner of the house is out of level.
Collapse and washing away has occurred of the foundation material
around a few stumps below the south-west corner of the house, and
also of the soil below the concrete paving adjacent to the south side of
the house at the south-west corner.
Collapse and washing away has occurred of the foundation material
around the old gully trap and an adjacent stump below the kitchen floor.
The timber stumps are generally in a good condition with only minor
decay occurring of the stumps immediately below the surface. A
concrete stump is evident below the family room which was installed
after the house was built to repair previous movement of the floor of the
family room.
According to the geological map the soil in the area is a Quaternary
Basaltic Clay which is a classified as a highly reactive clay site (class
H). Seasonal changes in moisture content of the foundation material
can cause up to 65mm movement at the surface of the soil.
The cracking and movement evidence of the residence is typical of
problems that can occur due to differential movement of the stumps
due to seasonal changes in the moisture content of the foundation
material.
A considerable amount of rain has fallen in late 2010 and early 2011
which have resulted in changes in the moisture content of the
foundation material from a long period of drought to normal rains .
Therefore the general cracking and movement evidence in the house
has resulted due to changes in the moisture content of the foundation
material. The cracking and movement of the laundry and kitchen area
is a result of collapse and washing away of the foundation materials
which has resulted in the stumps losing support and subsequent
cracking and movement has occurred.
The saturation of the foundation material has resulted from surface
runoff during recent heavy rainfall draining to below the south-west
corner of the house. The surface run off is from a combination of the
adjacent southern property and of the subject property.
Case No: 306849 Determination Page 7 of 16
34. The above expert carried out a further site inspection on 4 June 2012. This
inspection was subsequent to the Applicants becoming aware of the
stormwater drain issue at the adjoining property. In their further report dated
12 July 2012, HCE states:
A recent plumbing investigation has revealed that issues with the
neighbour‟s stormwater drain had resulted in stormwater backing up
and flowing into the sub-floor space below the insured premises over
an unknown period of time. The stormwater drain has since been
removed and replaced.
This was the main stormwater drain which collected all of the roof
stormwater so the amount of water escaping from the drain would have
been considerable.
Cracking and movement of the kitchen and laundry area has worsened
since the initial inspection with cracks occurring of the floor tiles. The
powder room which adjoins the east end of the kitchen showed a
noticeable fall of the floor and gaps occurring between the top of the
vanity unit and the tiled splashback.
The family room showed the doorway is out of square and cracks
evident around chimney mantel. The chimney is out of plumb with
rotation of the chimney occurring in a northerly direction, away from the
area where washing away of foundation material has occurred.
Noticeable fall of hallway floor towards the south. Evidence of bowing
of the wall lining and skirting of the south side wall near the kitchen
doorway and hairline cracks in this area is also evident.
The bathroom door is binding and cracks are occurring in the tile grout
of the shower recess and floor tiles in this room.
The study shows a fall of the floor towards the centre of the room.
The main bedroom has hairline cracks occurring of the ceiling cornice
above the window and cracks between the door jam and architraves.
Bedroom two showed a horizontal crack in the wall lining above the
window and the sliding doors of the built in cupboard are out of square.
The timber deck at the rear of the laundry showed a noticeable fall
towards the laundry.
Inspection of the sub-floor space showed additional washing away and
collapse of the foundation material below the kitchen and laundry area.
The extent and severity of the cracking movement had worsened due
to the additional washing away and collapse of the foundation material.
The movement which has occurred due to the collapse of foundation
material has now extended to include the powder room, bathroom,
timber decking, hallway and south end of the family room.
However, the cracking and movement that has occurred of the two front
bedrooms, study, and north end of the family room (including chimney)
have not been attributed to the washing away of foundation material as
Case No: 306849 Determination Page 8 of 16
these areas are well away from the area where the collapse has
occurred.
35. The FSP retained an alternative engineering firm, “FE”, due to delays by
HCE in providing additional reports requested of them. In their report dated
17 December 2012, FE state:
Inspections of the property were carried out on 6 November 2012 and 8
December 2012.
The site elevation drops approximately three (3) metres from the drive
entry at the street to the rear northwest corner of the property. The site
also has a slight cross slope from north to south of approximately 500
mm.
The Applicants had not undertaken any significant work on the
structure other than painting of the internal finishes in 2010. They had
added the rear deck shortly after purchase of the property.
The additional damage to the upper level section of the structure, the
damage to the powder room, and damage to the north and east faces
of the Applicants‟ home are not a res ult of the drainage event.
FE concluded:
- The settlement of the upper level flooring is a direct result of poor
construction and long term lack of maintenance and was present
prior to the drainage event.
- The settlement of the powder room near the shower is the result of
long term water infiltration due to the lack of maintenance of the
shower waterproofing system and was present prior to the drainage
event.
- The settlement of the southwest corner of the structure is the result
of poor construction practice, failure to properly dispose of the clay
pipe and overflow relief gully beneath the structure and general lack
of maintenance to properly drain stormwater.
- The settlement of the southwest corner of the structure was for the
most part present prior to the drainage event as a result of long term
drainage problems and general lack of maintenance at this area
though it may have worsened as a result of the 2011 drainage
event.
- There is a general lack of cracking present in the brittle plasterboard
linings and movement-sensitive architrave framings, indicating long
term, slowly developing structure movement that was present prior
to the drainage event.
36. The FSP engaged a firm of building consultants “SBC” to provide a further
causation report. Their report, dated 24 December 2012 concludes:
- The damage to the south western area of the building is
predominately the result of subsidence and stump failure that has
Case No: 306849 Determination Page 9 of 16
existed and been ongoing for an extended period of time. On the
balance of probabilities this subsidence and stump failure has been
exacerbated by the drainage issue in the neighbouring property
over the same period.
- The decline in the levels and the resultant damage throughout the
remainder of the residence is not the result of the drainage issue, it
is the result of the combination of the normal settlement of the
foundation material over an extended period of time, the normal
decay of the Red Gum timber stumps over a period of time and
defective building practices.
- Taking into consideration the degree of movement and subsidence
to the building, it is not practical at this stage to accurately quantify
or predict the extent of the repairs that will be required following
restumping and re-levelling works.
37. A further report obtained from FE dated 9 August 2013 provides:
The ground has continued to move, especially due to the hot dry period
between the surveys undertaken by them.
Deformations of the building existed prior to the drainage event.
The building movement is mostly long term. This is based on evidence
of previous remedial works including re-stumping and re-levelling. Lack
of internal defects and wall cracking indicates previous internal repairs
suggesting the building has been affected by long term movement and
distress.
This expert agrees with the suggestion by RIB that a stump rotation
mechanism exists however this can also be attributed to poor
workmanship/construction.
It is reasonable to assume that the stumps were originally installed
verti cal and plumb and that the “out of plumbness” would most likely
have been caused by foundation soil movement.
The differences in floor levels taken by FE and the Applicants‟ expert
RIB were carried out 7 months apart with an extremely hot and dry
summer in between. These differences suggest that drying effects of
reactive soils have resulted in footing settlement.
Rotting of timber stumps is a prolonged process, resulting from a long
term lack of adequate drainage and a lack of maintenance.
38. Finally, FE have provided a supplementary report in response to the
Applicants‟ expert evidence, dated 5 September 2013, which states:
“In response to the request for further comment on the depth of reconstructed
stumps, as discussed by [RIB], we offer the following comments;
[FE] agrees with [RIB] that a founding depth of the order of 2.4m is required
for any new stump/footing construction for this site, based on the current
geotechnical and other information. (2.4m is measured from the soil surface to
the underside of the pad footing)
Case No: 306849 Determination Page 10 of 16
This depth of 2.4m is considered to be the required depth based on a “first
tier” engineering approach. [FE] notes that a more rigorous engineering and
geotechnical investigation and analysis may result in a lesser founding depth
than 2.4m being required, but it is not expected that the founding depth would
be significantly reduced in any case.
The comments made in item 7 of our response letter, dated 9/8/13, still
apply.”
Applicants’ Expert Evidence
39. The Applicants retained a civil e ngineer, “RIB” to inspect and report on the
damage to their property. In their first report dated 11 July 2013, RIB stated:
An inspection by the FSP‟s expert ALD has confirmed there was no
failure of the Applicants‟ plumbing system.
The property does not have a large amount of trees or foliage that
would cause an ongoing draining problem. Basic upkeep of the
property was above average.
The damage was caused by the stormwater system from the adjoining
property which followed the slope of the land down and went
underneath the Applicants‟ property. Water leaking from this system
scoured out and/or dissolved the softish clays underneath the insured
premises.
The bore log carried out by RIB indicated there was an overall dryness
at 3.15 depth indicating loss of moisture during the drought. The high
moisture on the upper level is strictly attributable to a leak and/or an
overflow as is noted from the adjoining property.
The soil is quaternary basaltic in origin and loses strength quite rapidly
when its moisture regime gets to around 45-50%. At 20-40% it swells
quite strongly and has good strength and is capable of lifting.
Relative levels of the flooring at the property were undertaken twice as
they did not correlate with those taken by the FSP‟s expert, FE. On this
basis, RIB have concluded that either the building has continued to
move since the FE report, or there is an error in FE‟s measurements.
As the leak has been corrected and the Applicant‟s have installed an
AG drain, the difference in levels could be attributed to drying out of the
soil.
The stumping system has failed quite dramatically as a consequence of
excess moisture and the further movement is a result of “ follow through
of the stumps continuing to drop as the soil gets drier and shrinks.”
There is ample evidence to suggest that the ground is drying out and
the stumps are dropping and will continue to do so. When they do this,
they rotate which gives the illusion that the stumps were not put in
correctly in the first place. This is not necessarily true. The ground does
not dry out uniformly and stumps as they drop away from the bearer
can rotate and distort.
Case No: 306849 Determination Page 11 of 16
HCE in their report have underestimated the extent to which the ground
had wetted up and the extent to which it was going to dry out and
continue to initiate movement.
Another consequence of water underneath timber stumped houses is it
accelerates the rotting out of the sole plates and can terminate the
functionality of a stump over a very short period.
RIB disagrees with the assertion by FMG that the plasterboard is brittle.
The event is recent as had the leak been occurring for a long period of
time the trees at the property would have been bigger and/or the
moisture regimes at depth would have been higher.
To rectify the property, a large part of the building needs to be re-
stumped, re-levelled and then repaired. The Building Commission
„Guide to Standards and Tolerances‟ require that floor levels be taken
back to a reasonable degree of trueness and level. Therefore it all has
to be re-levelled.
The stumps are to be put in at a greater level of depth and compliance
with Australian standards requires replacement of all stumps to the new
level of 2.0-2.4 metres.
40. A second report provided by RIB dated 28 August 2013, further provides:
It is possible that rapid drying out has occurred over the time period
between FE‟s level surveys and RIB‟s being undertaken as there has
been a hot dry summer in the interim and the source of water has been
repaired.
Further, the ground has a good slope and there is ample ventilation
under the floor. Nonetheless, the expert is surprised by the depth of dry
out over the short period that appears to have occurred.
Damage and movement has been caused by the drainage event and
re-levelling will be needed. It is inevitable that re-levelling will cause
further damage, the extent of which will be unknown until the works are
completed.
RIB accepts that the „excluded‟ area of the property has some evidence
of long term movement, however, the difference in levels taken only
seven months apart demonstrates vigorous and extensive movement
during that time.
Further, if it is accepted that the differences in levels indicate drying out
since the leak has occurred over a dry summer, then nearly 90% of the
house has been affected, not the 60% previously referred to.
As FE have asserted their levels are correct and RIB are confident
theirs are also correct it therefore means there is a major amount of
movement affecting the house which can only be caused by a
consequence of an abnormality such as drainage/ingress into the
ground.
Case No: 306849 Determination Page 12 of 16
Further, it would be necessary for the ingress to be “ massive” to
account for the amount of movement between the two relative levels
taken by FE and RIB.
The FSP ‟s offer to restump approximately 60% of the house is
inadequate as the failure has gone to at least 90% of the house, and
possibly the whole house based upon the relative levels and the extent
of change over a seven month period.
Correcting the building with shallow stumps or readjusting the existing
stumps will not lead to a satisfactory resolution as re-levelling will be
required if the building continues to move.
Proximate cause of damage
41. Having considered the expert evidence above, the Panel finds the weight of
the available evidence to be consistent with a view that the proximate cause
of the home‟s structural damage as well as its continued issues with
movement was the damaged storm water drain at the neighbouring property
as:
The damage to the home occurred initially at the south-western end
being the area, by virtue of the gradient/contour of the property, to
which the runoff from the neighbouring property flowed.
HCE concluded the extent and severity of the cracking movement had
worsened due to the additional washing away and collapse of the
foundation material between their two inspections in February and June
2012.
The rectification of the source of moisture, ie replacement of the
damaged pipe, and installation of the „Ag drain‟ along the len gth of the
Applicants‟ property have resulted in the rapid drying out of the
previously water affected sub-floor, evidenced by the dropping and
movement of the stumps in the usual course of drying out.
Early investigations ruled out any other source of moisture including
failure of plumbing or sewerage systems at the subject property. This
would presumably have included any leak from beneath the shower as
suggested by the FSP‟s experts. This is further supported by RIB‟s
investigations confirming there are no plumbing issues at the property.
The date of the stormwater pipe failure first occurring is unknown,
however the identification of damage to the Applicants‟ home and
lodgement of the claim shortly after a period of heavy rains is
consistent with and a persuasive explanation that the dominant cause
of the stump movement and loss of foundation soils, was the leaking
stormwater runoff drain.
There is limited evidence that the home previously had any issues with
movement, or cracking since purchased by the Applicants, who had
completed internal repainting in 2010. It would have been reasonably
expected that any pre-existing damage would have been identified
during these works.
Case No: 306849 Determination Page 13 of 16
As the home did not present with significant similar issues in the past, a
re asonable inference is that the home‟s alleged issues with improper
installation of the stumps or a failure to comply with building regulations
cannot reasonably be regarded as dominant (or proximate) causes of
the home‟s movement and cracking.
If such issues do in fact exist, they would already have been in
existence before the Applicants first began experiencing problems with
their home. Yet, notwithstanding the home being more than 50 years
old, it did not begin to develop significant problems until 2011, after the
stormwater issue is believed to have arisen.
Further, the extension to the decking added to the property shortly after
purchase by the Applicants was also affected by the loss of foundation
soils and found to be sloping towards the laundry. There has been no
indication that the footings of this structure are non-compliant with the
building regulations.
Evidence of replacement of some stumps and the existence of concrete
stumps in some areas are contrary evidence, as to any lack of
maintenance at the property, as asserted by the FSP.
42. The FSP relies on the alleged existence of „long term‟ rot to the subfloor
structure but its experts have not provided any explanation of the period
required for this to occur. The Panel notes however that the HCE report of
22 February 2012, states “( t)he timber stumps are generally in a good
condition with only minor decay occurring of the stumps immediately below
the surface.” This is in stark contrast to the findings of FE in their report of 17
December 2012, ten months later, that “(t)he timber stumps in the south west
corner of the subject structure have suffered long term exposure to water
which has caused the base of the stumps to rot.”
43. Accordingly, a reasonable explanation for this disparity in the findings of the
FSP‟s two experts could be that time period between the two inspections (or
the commencement and subsequent rectification of the leak) was of a
sufficient period for this damage to occur.
44. The Panel finds the evidence of the Applica nts‟ expert RIB, inclusive of soil
testing and confirmation of „drying out‟ occurring to be thorough and
persuasive. The persuasive nature of this evidence is reinforced by the
readiness of the FSP‟s expert FE to concede RIB‟s explanation for the
ongoing movement as being reasonable, including with respect to rotations
and “out of plumbness”, as set out in their further report dated 9 August
2013.
45. As the weight of evidence establishes that the home did not begin to develop
problems until after the stormwater leak developed and in the absence of
persuasive evidence to the effect that the property had been experiencing
these problems prior to this time, the Panel is satisfied that on balance, the
damage to the Applicants‟ premises was most likely caused by th e insured
event of:
Case No: 306849 Determination Page 14 of 16
“ Liquid escaping suddenly and unexpectedly from a:
water main, drain, fixed pipe, gutter, guttering, fixed tank or drain, sink, basin,
bath, shower, toilet or spa bath, ...”
46. As set out in RIB‟s evidence, further resultant damage is a n inevitable
consequence of the restumping works.
47. The materials indicate the FSP advised the Applicants against carrying out
any repair works, which may have prevented or at the very least limited the
extent of the ongoing movement/damage and in doing so, it has prevented
the Applicants from mitigating the extent of the ensuing loss.
48. On this basis, the Panel accepts that the FSP should be responsible for the
cost of rectifying any such damage on the basis that the FSP‟s delays in
dealing with the matter have resulted in additional movement (thus ongoing
internal damage).
49. Accordingly, the Applicants are entitled to indemnity for the full cost of the
required works to their property (including 90% of the cost of restumping
works based on RIB‟s evidence), as set out in both scopes of work 1 & 2,
and any additional movement related issues that have been identified since
the preparation of the most recent scope.
50. The Panel notes that the Applicants do not agree with JLG being retained to
undertake the works and seeks to cash settle the dispute. The FSP has also
indicated in its submissions that it believes the only option is for the matter to
be cash settled.
51. In the circumstances, the FSP should obtain a full quotation from JLG as to
the costs of conducting the full repairs as per the scope of works 1 and 2 and
likely costs of any resultant damage from the restumping process
52. The Panel accepts that in order to quote on the possible resultant damage
from the restumping process requires speculation, however, in view of the
desire of the parties that this matter be cash settled, the Panel believes it is
an appropriate process, in the circumstances
53. JLG should prepare the relevant quotations as if it were to be contracted by
the Applicants to conduct the repairs.
54. Once these quotations are available, the Panel determines the FSP is
entitled to cash settle the Applicants based on the quotation.
55. The Panel notes the FSP accepts liability for any carpet requiring repair or
replacement as a result of the claim related building repairs. Again, given the
desire of the parties to cash settle this dispute, the Panel determines that the
FSP obtain an assessment as to the likely costs of repair/replacement of the
carpets and upon obtaining a quotation with respect to same, cash settle the
Applicants on that basis.
Case No: 306849 Determination Page 15 of 16
56. The Panel notes the FSP accepts liability to cover the accommodation costs
for the Applicants and their pets whilst the repairs are being completed. The
Panel determines that in the alternative, the FSP may choose to either cash
settle the accommodation amount in advance or may determine, subject to
notification from the Applicants that the repairs had commenced, to arrange
alternative accommodation for the Applicants and their pets for the duration
of the repairs and to indemnify the Applicants for the associated removal and
storage costs that may be incurred.
57. Should the FSP choose to cash settle the accommodation costs in advance,
the FSP should obtain from JLG, an estimation as to the likely duration of the
repairs and an appropriate estimation as to the costs of accommodation and
cash settle on this basis.
Compensation for non-financial loss
58. The Applicants claim that as a result of the FSP‟s delays in assessing their
claim and the late denial of indemnity, they suffered stress, illness, and
inconvenience. Medical evidence was supplied to support this.
59. The FSP has conceded that some of the delays were unreasonable. In doing
so, the FSP has paid the Applicants an ex gratia payment of $2,000 which it
says is fair and reasonable compensation in the circumstances.
60. This dispute has been ongoing for over two years. It took the FSP some time
before reaching a decision to decline the claim and in fact, they did not
decline the claim until 13 months after lodgement. Whilst the Panel can
appreciate that this may occur in some circumstances, in this instance, the
Applicants were subjected to considerable inconvenience in facilitating
access to the property for the FSP‟s numerous experts who initially
supported their claim and subsequently revised their position,
notwithstanding the Applicants having been previously advised that the
policy would respond.
61. The maximum compensation available under paragraph 9.3 of the Terms of
Reference is $3,000. The ex-gratia payment of $2,000 by the FSP should in
the Panel‟s view, be offset against any such amount.
62. The Panel also considers despite the inconvenience suffered by the
Applicants, consideration needs to be given to the actual outcome of the
dispute. In this case, the Panel has determined the matter in favour of the
Applicants with cash settlement to be made based on the current scope of
works. The Panel also notes some delays were inevitable to allow for the
necessary drying out and settling of the property.
63. In these circumstances, the Panel is of the view that the ex-gratia payment
of $2,000 made by the FSP represents adequate compensation under
paragraph 9.3 of the Terms of Reference.
Case No: 306849 Determination Page 16 of 16
Determination
64. On the basis of the available information the Panel determines that:
a. The FSP is to meet its liability under the terms of the policy with respect
to the full costs of repairs set out in the scope of works 1 and 2 as
prepared by JLG, including the costs of restumping of the home to a
minimum footing of 2.4 metres. The FSP is entitled to cash settle the
claim on the basis of the quotation provided by JLG in accordance with
the above.
b. The FSP is to further obtain a quotation from JLG as to the likely costs
of additional damage that may occur during the restumping undertaken
pursuant to the scope of works 1 and 2. The FSP is entitled to cash
settle the Applicants‟ claim based on the quotation obtained or, should
the Parties agree, delay obtaining this quotation until the repairs
pursuant to scope of works 1 and 2 have been completed and then
cash settle this aspect of the claim.
c. The FSP accepts liability with respect to the costs of repairing or
replacing carpet damaged as a result of the building repairs and is to
obtain a quotation as to the likely costs of the repair and replacement of
the carpet. Upon receipt of the quotation, the FSP is entitled to cash
settle the Applicants for those costs.
d. Insofar as the Applicants are required to obtain alternative
accommodation for themselves and their pets during the duration of the
repairs, the FSP may either cash settle the accommodation costs in
advance subject to obtaining an appropriate estimation as to the likely
duration for repairs or in the alternative, attend to payment of these
costs subject to notification by the Applicants of the commencement of
the repairs and the repair duration being reasonable.
e. As the cash settlement amounts in this dispute are to be based on a
current scope of works and quotations, the Panel determines that
interest is not applicable in this case.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.