Denial of storm damage claim to in-ground pool under seepage exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2013-09-24
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants claimed for storm damage to their in-ground pool, which the FSP declined under the water seepage exclusion. AFCA found the exclusion applied and ordered no payment or compensation.

Where a covered storm and an excluded seepage cause both contributed, the excluded cause was the predominant cause and defeated the claim.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 306505 Determination Page 1 of 11 Case number: 306505 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim 20 September 2013 Background 1. I have reviewed all the material submitted by the parties and save where I make note specifically, I am satisfied the background as set out in the Recommendation is accurate and is as follows. 2. The Applicants (M and P) held a Home Building and Contents insurance policy (the policy) with the Financial Services Provider (FSP). 3. A claim was lodged under the policy for replacement of an in-ground fibreglass swimming pool (the pool) due to damage claimed to be the result of a violent storm in the area. 4. The FSP declined the claim on the basis the cause for the damage was excluded from cover under the policy. 5. The Applicants remain dissatisfied with the FSP‟s decision to decline the claim and are seeking complete indemnity for their loss. 6. The Applicant did not agree with the FSP‟s decision, hence the dispute which was the subject of a Recommendation. The Recommendation was in favour of the FSP and was not accepted by the Applicants. The FSP accepted the Recommendation. In the circumstances, the matter has been referred to me for Determination. Summary of Applicants’ p osition 7. I have reviewed all the material submitted by the parties and save where I make note specifically, I am satisfied the Applicants‟ position as set out in the Recommendation is accurate and is as follows. 8. The fibreglass pool was installed about 28 years ago. The Applicants had the pool resurfaced as the gel coat was beginning to deteriorate. The pool was otherwise structurally sound. They engaged pool specialists „AP‟ to undertake the works after research abut AP‟s qualifications and competence to do the work. Determination Case No: 306505 Determination Page 2 of 11 9. On 31 May 2012, AP commenced the works which included removal of the hydrostatic pressure valve, propping of the pool walls and draining of the pool. Whilst the pool was drained, a violent storm occurred in the area on 12 June 2012 which resulted in the damage to the pool which is the subject of this claim. 10. The male Applicant noticed the damage on the morning of 13 June 2012. He noticed “that the north facing side of the pool was bellied out each side of the supporting prop.” Further inspection “revealed the pool structure had spilt.” 11. The Applicants made a claim on the FSP. The FSP sent an assessor and an engineer to assess the damage. 12. The Applicants are dissatisfied with the FSP‟s decision to decline their claim and note that during the course of the claim, the FSP altered its basis to decline indemnity to them on several occasions. 13. They maintain its latest/final reason for declining the claim is remarkably inconsistent and conflicting with its previous positions and reasons (over previous seven months) for not offering them co ver under the policy. 14. Until recently, the FSP having commissioned consultants to the claim including an engineer, had made no reference to the damage claimed to be due to seepage or water running through earth. In fact, he says the “probable violent rain e vent on 12 June may have ultimately caused slumping of the backfill material.” 15. The Applicants dispute the FSP‟s basis for declining the claim and maintain that the damage was due to the violent storm that occurred, ie it was responsible for the saturation of the pool‟s backfill causing it to slump. They have never had water seepage or water running issues in the previous 44 years living at the property. They have had no maintenance issues with the pool, no fault which existed before the damage occurred nor is there any wear and tear to the pool. 16. If the damage was due to seepage or running water, they say one would expect this to occur over the many years the pool has remained in place or within the two weeks the pool was empty before the violent storm took place. Further, if there was such an issue one would expect the damage to have worsened in the seven months following the date of loss in which the pool has remained empty. 17. The pool does have a drainage system and the outlet for the system is evident in t he photographic evidence made available by the FSP‟s appointed engineers “DP”. This outlet system would relieve any hydrostatic pressure. 18. In respect to propping of the pool, the Applicants maintain there are no industry standards regarding bracing of the p ool‟s walls. Most contractors do not brace the walls at all when undertaking maintenance works or they use a plank of wood. No damage occurred to the pool in the 13 days the prop was Case No: 306505 Determination Page 3 of 11 in place before the violent rain and no further damage occurred after the rain event while the prop was in place. 19. AP assessed the risk and took particular steps to minimise the risk by installing a steel acro prop before removing the hydrostatic pressure valve (HPV) and emptying the pool. These actions are their best practice in the absence of any formal industry standards. 20. The Applicants maintain that had the violent storm event on 12 June 2012 not occurred there would not have been any resultant damage to the pool. 21. The Bureau of Meteorology (BOM) records show that immediately before the event there was 71.8mm which is classified by BOM as “violent.” 22. The Applicants are seeking for the FSP to replace the pool in line with the relevant provisions of the policy and make good any damage that may occur during the replacement procedure. They are also seeking compensation from the FSP in the amount of $8,000 for a number of issues including complications and stress introduced to their daily and social activities. They have been a genuine loyal customer of the FSP for over 50 years. 23. The Applicants rejected the Recommendation and provided no further documentary information in support of their position but wrote two letters dated 26 June 2013 and 14 July 2013. 24. They essentially reiterate their view that the damage was caused by the storm ev ent. They rely on the FSP‟s engineer‟s report in this regard. They repeat the damage occurred overnight when the soil slumped due to inundation of rain during a storm. They say if there was seepage, the damage would have occurred in the weeks prior to when the pool was emptied and before the storm event. Summary of FSP’ s position 25. I have reviewed all the material submitted by the parties and save where I make note specifically, I am satisfied the FSP‟s position as set out in the Recommendation is accurate and is as follows. 26. It is a general principle of insurance law that the onus rests with the claimant to establish that the loss claimed falls within the scope of cover available to them under the policy. Where the claimant is successful in establishing such, the onus shifts to the FSP to establish an entitlement to decline indemnity on the basis of a policy exclusion(s). 27. The FSP accepts that the Applicants have established, on the balance of probabilities, that the damage is due to an event insured under the policy “Storm and Flood” but the storm must be the predominate cause of the loss sustained. The onus then rests with the FSP to establish, on the balance of probabilities, that a policy exclusion applies to defeat the claim or that another uninsured event caused the damage. Case No: 306505 Determination Page 4 of 11 28. The FSP maintains it commissioned the services of engineers to inspect and report on the cause and extent of the damage to the pool. It is clear from DP‟s report that the damage is due to storm water which has seeped through the earth and hydrostatic pressure has been applied to the pool walls causing the bulge and resultant fracture. 29. Further, the report also refers to the possible absence of a drainage system and the fact that the pool was emptied without adequate propping which are contributing factors to the loss. The Product Disclosure Statement (PDS) clearly and unambiguously states how the policy does respond to the insured event “Storm and Flood”. Also, it clearly explains how the policy responds to loss or damage arising from hydrostatic pressure/activity. 30. Therefore, on the basis of the available evidence, the FSP maintains it is not required to provide indemnity to the Applicants for the damage to the pool under the claim as the draining of the pool and the subsequent method of support utilised by AP was the underlying and predominate cause of the loss which is not an event covered under the terms of the policy. 31. The FSP relies on the following policy provisions: “ Page 19 - 1. Storm and flood We cover loss and damage caused by storm and flood e.g. rain, wind, hail, storm and damage caused by flooding from rivers, streets and canals. … We do not cover  damage by actions or movements of the sea but we will cover damage caused by:  a tsunami  storm surge if it occurs at the same time your home or contents are damaged by a storm or flood  retaining walls, garden borders and free standing walls the surface of a tennis court  wharf, jetty, pontoon or sea wall  water in a tank, swimming pools or spas or their liners or covers  the cost of cleaning mud or debris out of tanks, swimming pools or spas  damage to swimming pools and their parts or underground tanks caused by water leaking down the sides, against the sides, or getting underneath them  paint when there is no structural storm damage to other parts of the home  gates, fences or wall fences that were in a state of disrepair which would have been obvious to a reasonable person before the damage occurred. … Page 46 - We do not cover loss or damage : Seepage of water through the earth Case No: 306505 Determination Page 5 of 11 Caused by water seeping or running:  through the earth (sometimes called hydrostatic water seepage)  through or down the sides of earth or earth fill that is up against your home  down the sides or underneath swimming pools or spas causing them to move, change shape or lift or leaking through their hydrostatic valves  against or through retaining walls and forcing them to move or crack. ” 32. The FSP accepted the Recommendation and did not provide any further documentary information in support of its position save to rebut the Applicants in the Recommendation response dated 31 July 2013. The FSP agrees the Applicants have a prima facie claim but deny the claim due to the policy exclusion of water seepage through the earth and down the sides of the pool. The FSP contends the engineer supports its position. Issue 33. Whether the FSP was entitled to decline indemnity to the Applicants in line with the relevant policy limitations. Reasons for Decision 34. There has been an exchange of material between each party, and I am satisfied each party has had an opportunity to reply to the issues raised. 35. Each FOS case is decided on its merits, taking into account the facts of the case. I have reviewed all the material submitted by the parties both before and after the Recommendation was issued, in order to reach my decision. I will only refer to the relevant submissions and materials raised. 36. Insurance law provides that as the Applicants are seeking a benefit under the policy, they have the burden of establishing on the balance of probabilities that the cause for the damage claimed falls within the cover provided by the policy. Once established, the onus of proof the n shift to the FSP to establish the claim falls within an exclusion from cover or that the claim can otherwise be denied. 37. I note from the material provided it is not in dispute that:  The Applicants held a home building and contents insurance policy with the FSP at the time of loss.  The FSP provided and the Applicants received the relevant policy documentation including the PDS prior to the loss.  The policy provided cover for the listed insured events including „Storm and flood‟, and which are subject to the specified policy limitations. Case No: 306505 Determination Page 6 of 11  The Applicants‟ pool sustained damage whilst undergoing maintenance works and after the occurrence of a violent storm.  The damage to the pool cannot be repaired and the pool must be replaced. 38. The parties rely on material from experts and consultants. The material has been exchanged and therefore I will only set out the information from the reports I find relevant in providing this Determination. I have reviewed all the material submitted carefully and save where I make note specifically, I am satisfied the position as set out in the Recommendation is accurate and is as follows: Assessor’s Report dated 21 June 2012  AP told the Applicants the damage was not as a result of the repair process and in any event as per the contract, AP was not liable for damage to the pool.  The pool and surrounding pebblecrete paths seem to be in a satisfactory condition with no visible cracking or openings to allow water to leak down the sides.  The assessor could not determine the cause of the damage and recommended the appointment of an engineer.  The assessor took photographs of the pool to which I will refer later.  The assessor subsequently reviewed the report from the engineer and concluded the FSP can deny the claim because of the policy exclusion of seepage; the Applicants have a claim against AP due to insufficient bracing methods used while the pool was in a dry state; and the pool is completely destroyed and will require complete replacement. DP (Engineer) “Cause of damage to in -ground fibre class swimming pool” dated 24 July 2012  A site visit was undertaken on 4 July 2012.  The visit consisted of a walk over style visual inspection of the affected areas only, in the presence of the Applicant M. No physical or destructive testing was conducted.  The pool is about 8 metres in the east west direction and 3m wide. It had a uniform depth of about 1.4m.  The pool is surrounded by pebblecrate concrete paving. There is landscaping to the north side of the pool.  He noted the pipe which collects the flow of water on the site next door. He said it is not known if there is a dedicated backfill drainage system around the walls of the pool to collect and disperse any water build up and prevent the build up of hydrostatic pressure, although he notes the comment by the insured that there is one along the north side. (The Case No: 306505 Determination Page 7 of 11 Applicants have referred in submissions to photo 6 and the photograph of the vent of the overflow pipe in the paving there).  DP analysed the BOM data and noted the recorded rainfall on 11 and 12 June 2102 as 36.8mm and 62mm – the latter would be classified as heavy /violent.  The pool was constructed around 1984 and DP does not know if the pool complied with the relevant standards and its capacity to withstand external loads is unknown. He did not know if the paving is connected to the pool shell. Unless it was designed such that it ‟s shell alone is structurally sufficient to withstand external forces, it could distort in shape and become overstressed with local collapse if the forces acting on its earth face are sufficiently high.  DP‟s opinion is that as the pool was constructed about 28 years ago, it had probably reached the end of its serviceable life. Most new pools typically have a 25 year warranty.  DP took photographs and observed the fall of the property; the landscaping to the north side of the pool; the prop at about mid length running between the south and north walls; the north wall which had a significant bulge and was fractured close to the prop; the south wall which was also bulged but to a lesser magnitude; the hydrostatic relief valve had been removed and the east wall was undamaged.  DP formed the opinion that the cause of the bulging and cracking damage to the long walls of the pool may have been the result of the saturation with water of the (unknown) backfill material around the pool due to:  Action of rainwater infiltrating directly into the lawn and garden beds to the north, south and west of the pool, together with sub- surface flow of water from the rain. The probable violent rain of 12 June 2012 may have ultimately caused slumping of the backfill material (which is unknown) against the external walls of the pool.  The inward bulging of the long walls of the pool indicate they were subjected to a net force acting inwards. This force being the difference between the sum of the forces of earth pressure and hydrostatic pressure of the build up of water on the backfill side. He posits there was also a possible absence of a dedicated drainage system in the backfill to disperse the water and prevent the build up of pressure especially as there was no water in the pool.  The temporary propping of the walls at mid length was not sufficient to prevent the movement of the walls. At a minimum there should have been a timber spreader plate between the pool wall and the prop to spread the load over a larger area and additional props installed to further reduce the reaction loads at each prop. Case No: 306505 Determination Page 8 of 11  The bulging in the south wall was less than the north wall because there was no direct infiltration of rainwater into the backfill behind the wall due to the presence of the neighbouring building.  The short east and west walls are undamaged as they were subject to a lesser net action because of their shorter lengths and the support afforded by the long walls.  The damage to the pool requires it to be replaced as it is not possible to repair the pool. Letter from AP dated 24 October 2012  AP has been in the pool resurfacing business for nearly six years, having completed over 450 pools in this time.  During this time they have never experienced a pool wall collapse.  On this occasion, they entered the pool and installed a number 3 steel acrow prop jack, removed the hydrostatic valve and the emptied the pool.  There is no industry standard regarding the bracing of fibreglass pools and in the main most contractors do not brace at all or if they do, they use a piece of wood.  The care taken by AP in draining and bracing of the Applicants‟ pool was second to none.  The pool stood for several days whilst it was raining with no ill effect. The damage occurred during a major weather event and has not got worse since.  The application of timber spreaders and additional props would make it impossible to resurface a pool and creates a hazardous and dangerous work environment. June 2012 rainfall  I note there was some rain on 3, 4 and 5 June 2012 and significant rainfall on 11 and 12 June 2012. Photographs  In a note describing the background to this dispute, the Applicants say that AP inspected the pool on 11 July 2102 and collected the prop. AP told the Applicants the damage was caused by soil movement due to the violent rain event and that if the damage had been caused by hydrostatic pressure, the floor of the pool would also have been damaged.  In a letter dated 3 February 2013, the Applicants addressed the adequacy of the propping of the pool and produced photographs from a neighbour‟s pool and from AP. The photographs show no propping or spreader plates were used in those jobs. The Applicants also contend Case No: 306505 Determination Page 9 of 11 that the photos show that “it is obvious that it would be impractical to actually resurface a pool with props and spreader plates in place.”  I have also considered photographs from the assessor. They show no damage to the pool surrounds and damage at the site of the props (large cracks in the side of the pool).  The engineer took photographs too and I have considered them carefully and they are referred to above in the summary of his report. Analysis 39. The FSP does not deny that the damage was caused by an insured event - storm. It accepts that the onus therefore falls to it to prove on the balance of probabilities that the claim can be refused because of policy exclusions or another uninsured event. 40. I have carefully considered all the material provided and the photographs. In my view, the opinion of DP establishes on the balance of probabilities, the evidence necessary for the FSP to deny the claim relying on the policy exclusions as his expert opinion is that the damage done to the pool was caused by water leaking against the sides of the pool. The water had come from the heavy rainfall the day before the collapse. 41. Further his evidence supports the contention that the damage to the pool was caused by seepage of water through the earth and down the sides of the pool causing the sides of the pool to move or crack. 42. When I consider the report of DP, in my view, the damage may not have occurred if the pool had been full, or if, once the pool was emptied, if the sides of the pool had been adequately supported by AP or if there was an adequate in ground drainage system in place. 43. The Applicants point to an overflow pipe in the North West corner of the pool but there is no evidence that this was an adequate in ground drainage system. 44. The Applicants and AP defend the support system created by AP and I accept it may have been the normal and usual way to do this work. However, it was not adequate on this occasion when the pool was empty and there was significant rainfall which caused a build up of water in the backfill material. 45. In my view, once the rain begun it may have been prudent for PD to attend and further support the pool sides and then remove those supports to do the actual work once the rain had stopped and the backfill drained. 46. In all the circumstances, where the opinion of DP and AP differ, I prefer the opinion of DP because DP is independent and has no interest in the outcome and no need to defend the work he has done, unlike AP. Case No: 306505 Determination Page 10 of 11 47. I do not find it incongruous that the Applicants say they have never had water seepage problems in the past - what happened here was an unfortunate confluence of events – heavy rainfall and the pool was empty. No doubt in the past, when there was heavy rainfall, the pool was full and the water in the pool served to push and balance the water outside the pool in the backfill. 48. Likewise no damage occurred to the pool in the 13 days the prop was in place before the violent rainfall as the backfill was not sufficiently saturated until after the rainfall on 12 June 2012. 49. The FSP accepts that the Applicants have established that the damage was caused by the storm but says that the storm must be the predominate cause of the loss sustained for the claim to be met. I agree. 50. In support of its position I prefer the well established law (articulated in Wayne Tank and Pump Co. Ltd v Employers’ Liability Assurance Corp. Ltd. [1973] 3 AII E.R. 825) that where there are two effective causes of a loss, one of which is excluded and one which is included in an insurance policy, the excluded clause operates to over-ride the included clause and defeats the claim. 51. Accordingly in this matter, in my view, the excluded clauses referred to above override the storm damage event and defeat the claim. Conclusion 52. In the absence of evidence to the contrary, I am satisfied the FSP has established, on the balance of probabilities, that the circumstances resulting in the loss claimed are excluded from cover. Other matters 53. The Applicants complain that the FSP altered its basis to decline indemnity. I agree the first letter of denial was less than satisfactory but I am of the view that the letter dated 27 September 2012 remedied the situation. 54. I note the Applicants claim for compensation under the policy arises from the FSP‟s claims management and decision in respect to their claim. I have considered the material carefully and the time taken to assess the claim and to make a decision. I note the claim was made 13 June 2012, the assessor attended 21 June 2012 and engineer attended 4 July 2012. The engineer wrote a report on 24 July 2012 and the assessor reported to the FSP on 31 July 2012. 55. The FSP communicated its decision to refuse the claim on 13 August 2012 confirmed by its IDR decision on 27 September 2012. 56. In my view, this is sufficiently timely and in general accordance with industry standards. In the circumstances of the decision and the time it took to make it, I do not think there is scope for compensation to be paid by the FSP to the Applicants. Case No: 306505 Determination Page 11 of 11 Determination 57. On the basis of the available information and for the reasons stated, I determine that the FSP was not obliged to provide indemnity to the Applicants for the damage to the swimming pool under the policy terms and conditions.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.