Adviser recommended SMSF invest in unregistered unit trusts he was director of, without disclosing risks
Text of the determination
Case No: 306258 Determination Page 1 of 8
Case number: 306258
Investments - Managed Investments - Mixed Asset Fund/s - Advice -
Inappropriate advice
16 April 2014
Summary
Description
This dispute is about advice given to the Applicants by Mr H, a director
of the Financial Services Provider (FSP). The advice was given to the
Applicants as trustees of a self managed superannuation fund (the
SMSF).
Basis of Determination
The claims about advice to invest in the MB Project, the TB Project and
the LCB Project (the B Projects) are excluded from the jurisdiction of
the Financial Ombudsman Service (FOS) under paragraph 5.1(l) of the
Terms of Reference (TOR).
By advising the Applicants to invest in the B No.1 Unit Trust and the S
Unit Trust (the Unit Trusts), the FSP breached its duties to the
Applicants and must compensate the SMSF for its loss.
Determination
The FSP must pay the SMSF $115,666 and interest.
Background
1. Mr H is an accountant and financial adviser. He assisted the Applicants to
set up the SMSF and prepared and audited the SMSF’s accounts.
2. The SMSF, following advice from Mr H, invested:
Determination
Case No: 306258 Determination Page 2 of 8
Date Investment Maturity Date Amount
May 2002 MB Project $42,000.00
June 2003 TB Project $119,500.00
June 2004 LCB Project $125,000.00
August 2007 B No. 1 Trust 15 April 2010 $50,000.00
August 2007 S Unit Trust 20 August 2010 $25,000.00
August 2007 B No. 1 Trust 20 August 2010 $25,000.00
May 2008 B No. 1 Trust 31 December 2008 $100,000.00
3. The B Projects were agribusiness investments. They were promoted by Mr
H through Information Memoranda, which stated the offering was a “small
scale offering ... limited to 20 or less participants and a maximum fund
raising of less than $2 million.”
4. The B Projects have not been successful, though it appears they are still in
operation and attempts have been made to sell the plantations.
5. During 2007 and 2008, Mr H sought contributions from investors of the B
Projects to fund the purchase of irrigation systems for the plantations. The
contributions were paid to two companies acting as trustees of the Unit
Trusts.
6. Mr H was the sole director of both trustee companies. The Unit Trusts were
offering returns of 10% and 12% per annum.
7. On 23 December 2008, the manager of the B Projects commenced
proceedings to recover unpaid management fees against an investor. This
led to all investors (including the Applicants) filing proceedings against the
manager in the Federal Court in 2009 for misleading or deceptive conduct
and breach of contract.
8. The manager pleaded that Mr H and the FSP (who were joined as parties to
the litigation) were proportionately liable for the investors’ losses (including
those claimed by the Applicants) on the basis that Mr H and the FSP had
engaged in misleading or deceptive conduct by reason that:
a. Mr H was the financial planner to the investors (including the
Applicants),
b. they had failed to advise the investors of “the risks associated with the
speculative nature of the investment” (sic),
c. Mr H was consulted about and approved the Information Memoranda,
d. they were the sole promoters of the B Projects, and
e. they had failed to provide complete copies of the Information
Memoranda to investors (including the Applicants).
9. On 20 December 2010, the Federal Court proceedings were settled and
discontinued with all parties agreeing to “release each other from all claims,
actions and suits of any kind whatsoever arising out of the subject matter of
the proceedings.”
Case No: 306258 Determination Page 3 of 8
10. The corporate trustees of the Unit Trusts did not pay the SMSF interest as
promised and the capital invested was not repaid at maturity.
11. The Applicants unsuccessfully requested Mr H to return the money invested
by the SMSF and to pay the promised interest.
Summary of A pplicant’s position
12. Mr H misled them to make, and failed to identify the risks associated with
investments in, the B Projects and the Unit Trusts.
Summary of FSP’s position
13. The FSP denies any misleading conduct on its part and says it is working
tirelessly to secure the return of funds to the SMSF and to other investors.
Issues
14. The issues raised in this dispute are:
a. Does FOS have jurisdiction to consider the claims made against the
FSP about the B Projects?
b. Has the FSP breached a duty owed to the Applicants?
c. Has the FSP’s conduct caused the SMSF to suffer a loss? If so, what
is the loss?
Reasons for decision
15. The Panel determines this dispute based on what it considers is fair in the
circumstances, having regard to the relevant law, good industry practice,
codes of practice and previous FOS decisions.
16. It has taken into account all the material submitted by the parties and is
satisfied that the documentation relied on to make this Determination has
been provided to both parties.
Are the B Project cl aims outside FOS’s TOR?
17. As a preliminary issue, it is necessary for the Panel to consider whether it
has jurisdiction to deal with the Applicants’ claims against the FSP in relation
to the B Project investments in light of the litigation referred to above.
18. Paragraph 5.1 of the TOR states:
“ 5.1 Exclusions from FOS’s jurisdiction
The Service may not consider a Dispute:
Case No: 306258 Determination Page 4 of 8
...
l) that has already been dealt with by a court ...”
19. When deciding whether a dispute has been dealt with by a court, FOS must
examine whether:
a. the nature and subject matter of the dispute and earlier court
proceedings were substantially the same
b. the dispute and the earlier court proceedings were between the same
parties in relation to the same events and facts, and
c. the earlier court proceedings were resolved either by final orders or
were resolved by agreement.
20. If all of the above criteria are met, then FOS may conclude that the dispute
has been dealt with by the court.
21. The Federal Court proceedings included allegations of misleading or
deceptive conduct and breach of contract in relation to the B Projects and
predominantly related to matters predating the Unit Trusts.
22. The allegations raised by the Applicants in this dispute in relation to the B
Projects would raise similar issues and, in particular, the extent to which the
conduct of Mr H and the FSP would give rise to a claim for compensation.
23. The Panel is satisfied the nature and subject matter of the Federal Court
proceedings and the B Project claims are substantially the same. The Panel
considers it is appropriate for FOS to refuse to consider this part of the
dispute, particularly in view of the limited information provided to FOS about
the terms of settlement, consistent with the confidentiality obligations of the
parties to the settlement.
Did the FSP breach a duty owed to the Applicants?
24. The Panel has concerns about the Mr H’s failure to disclose and advise on
the risk of the investment in the Unit Trusts. It is unclear from the information
on the file as to whether the Unit Trusts were managed investment schemes
that were required to be registered with the Australian Securities and
Investment Commission (ASIC).
25. A managed investment scheme is a scheme where:
a. people (members) contribute money to acquire actual, prospective or
contingent rights to benefits produced by the scheme whether
enforceable or not,
b. contributions are pooled or used in a common enterprise to produce
financial benefits for members, and
c. the members do not have day-to-day control over the operation of the
scheme. 1
1 Section 9 of the Corporations Act
Case No: 306258 Determination Page 5 of 8
26. The SMSF acquired:
a. 50,000 Class A23 Units issued by B No. 1 Trust for $1 each which
entitled the SMSF to receive three principal repayments of $16,667.00
plus interest (at 10% per annum) annually with the first payment due on
15 April 2008.
b. 25,000 Class A24 Units issued by B No. 1 Trust for $1 each which
entitled the SMSF to receive $806.68 per month principal and interest
payments from 20 September 2007 to maturity on 20 August 2010.
This represented a 10% per annum return.
c. 25,000 Class A7 units issued by S Unit Trust for $1 each which entitled
the SMSF to receive $806.68 per month principal and interest
payments from 20 September 2007 to maturity on 20 August 2010.
This represented a 10% per annum return.
d. 100,000 Class A25 Units issued by B No. 1 Trust for $1 each which
entitled the SMSF to 1% per month interest commencing 28 May 2008
and a maturity date of 31 December 2008.
27. The FSP submits that the money raised was used partly to provide
operational capital for the B Projects (specifically, to purchase irrigation
equipment). It appears that each unit class related to a separate project.
28. Based on the documents provided by the FSP, it seems the investors
(including the SMSF) contributed money, which was lent to the B Projects for
the purchase of irrigation equipment.
29. The B Projects were obliged, under separate loan agreements, to repay the
principal and interest to the Unit Trusts. The Unit Trusts had agreed to pay
the investors income return capital on maturity. Each member of each of the
B Projects was required to provide their interests in the projects as security
for the loans.
30. The investors in the Unit Trusts did not have day-to-day control over the
management of the monies lent to the Unit Trusts and used by the B
Projects. The financial accounts for each of the Unit Trusts also evidence the
pooling of funds from more than one contributor.
31. There is evidence (provided by the FSP) of investors (including the SMSF)
contributing money to acquire prospective rights to benefits produced by the
Unit Trust (in the form of interest payments and return of capital upon
maturity), that the contributions were pooled and that the members did not
have day-to-day control over the operation of the scheme.
32. The Panel is therefore satisfied on the balance of probabilities that each of
the Unit Trusts were (and presumably remain) managed investment
schemes as defined by the Corporations Act.
33. None of the Unit Trusts were registered managed investment schemes. As a
result, the investors did not have the benefit of the important investor
Case No: 306258 Determination Page 6 of 8
protections, including the additional governance and compliance
requirements.
34. It is the Panel’s view that Mr H, with his many roles in relation to the B
Projects and the Unit Trusts and as accountant, auditor and financial adviser
to the SMSF, acting with due care and skill should have:
a. disclosed the risks of investment in the Unit Trusts to the Applicants, in
particular the reduced investor protections, and
b. not recommended – whether by general or personal advice – or
otherwise promoted the Unit Trusts to the Applicants without clear
disclosure of these additional risks.
35. The Panel has concluded that the FSP breached duties it owed to the
SMSF.
36. It is not clear whether either of the Unit Trusts was required to be registered
with ASIC. The financial accounts for the S Unit Trust for the financial year
ending 30 June 2008 disclose that it had 23 unit holders. The accounts for B
No. 1 Unit Trust for the same financial year disclose that it had 33 unit
holders.
37. The Panel notes that the SMSF would be treated as a retail client, as it is a
regulated superannuation fund that holds less than $10 million net assets. 2
If, as appears to be the case, the Unit Trusts had more than 20 investors, at
least one of whom was a retail client, the Unit Trusts would have been
required to be registered with ASIC.
38. The Panel is concerned whether the Unit Trusts should have been registered
and were therefore not lawful but is unable to reach a conclusion on this
issue.
Causation and loss
39. On the balance of probabilities, the Panel considers the Applicants relied on
Mr H’s expertise as a financial adviser. T heir reliance was clearly misplaced.
40. The Panel is satisfied that the Applicants relied on Mr H and but for his
advice and conduct would not have invested in the Unit Trusts. The Panel is
satisfied that the Applicants did not contribute to the SMSF’s loss a nd have
taken all reasonable steps to mitigate that loss.
41. It is not clear what, if any, alternative investment would have been made by
the SMSF. The accounts for the SMSF for the year ended 30 June 2008
show that the SMSF had investments in shares ($102,796), in the Unit
Trusts ($187,500) and cash in a bank account ($216,565). The equivalent
statement of financial position for the year ended 30 June 2007 shows that
$477,891 was invested in cash, $120 in shares and $10,000 in unlisted unit
trusts.
2 Section 761G(7) of the Corporations Act
Case No: 306258 Determination Page 7 of 8
42. The SMSF’s investment strategy permitted a range of investments and
would not have prevented the Applicants from deciding to invest a significant
proportion of the SMSF’s assets in cash.
43. On the information provided and on the assumption that no money will be
repaid to the SMSF by the Unit Trusts, the losses suffered by the SMSF are:
Investment Capital Paid Less Capital
Returned
Less Income
Received
Loss
B No. 1 Trust $100,000.00 $0.00 $44,000.00 $56,000.00
B No. 1 Trust $25,000.00 $16,623.59 $3,543.41 $4,833.00
S Unit Trust $25,000.00 $16,623.59 $3,543.41 $4,833.00
B No. 1 Trust $50,000.00 $0.00 $0.00 $50,000.00
TOTAL $200,000.00 $33,247.18 $51,086.82 $115,666.00
44. The Panel is satisfied that but for the breach of duty to the Applicants, the
SMSF would not have invested in the Unit Trusts and would have retained
the money in cash at the bank. The Panel therefore orders the FSP to pay
the Applicants, in their capacity as trustees of the SMSF, $115,666 as
compensation.
45. The Panel also considers it fair that the FSP should pay the Applicants, in
their capacity as trustees of the SMSF, interest at the rate of 4% per annum 3
compounded annually from the following dates in relation to each of the
following amounts to the date of payment:
Amount Date interest is to be calc ulated from
$56,000.00 28 June 2012 4
$4,833.00 20 August 2009 5
$4,833.00 20 August 2009 6
$50,000.00 9 August 2007 7
46. If the Applicants accept this Determination in their capacity as trustees of the
SMSF, they agree to assign to the FSP all the SMSF’s rights and obligations
in respect of the Unit Trusts. The FSP must pay all incidental cost in respect
of the assignment including any transfer or assignment fee or duty. Such
assignment must occur within 14 days of payment by the FSP of the
compensation and interest detailed above.
47. The payment to the SMSF by the FSP is a settlement amount, not a
contribution or benefit.
3 This is approximately the average interest rate since 2009 paid by the relevant bank cash
management account used by the SMSF.
4 The date B No. 1 Unit Trust ceased making interest payments on this investment
5 The date B No. 1 Unit Trust ceased making interest payments on this investment
6 The date S Unit Trust ceased making interest payments on this investment
7 B No 1 Unit Trust had not made any interest or principal payments on this investment
Case No: 306258 Determination Page 8 of 8
Determination
48. On the basis of the available information the Panel determines that the FSP
is to compensate the SMSF.
49. The FSP must pay the Applicants in their capacity as trustees of the SMSF
$115,666 and interest as calculated in accordance with paragraph 45 of this
Determination.
50. The Applicants must assign the SMSF’s interest in the Unit Trusts in
accordance with paragraph 46 of this Determination.