Denial of flood-affected commercial property claim as excluded flood

FirmFinancial Firm (Unknown - Insurer)
Decided2013-08-07
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A director's business claimed stormwater damage to its Queensland factory during the January 2011 flood, and the FSP declined the claim as flood. AFCA held most of the damage was excluded flood but ordered the FSP to meet loss from 100mm of inundation in the rear half of the factory, with the amount to be agreed and interest if cash settled.

Water mixing stormwater with overflowing river flood is deemed flood under the policy and case law, but the limited early stormwater pooling in the rear half is covered.

Issues

Subjects and remedies

natural disastersmall businesspay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 303687 Determination Page 1 of 9 Case number: 303687 General Insurance - Small Business/Farm Insurance - Commercial Property - FSP Decision - Denial of claim-Exclusion/ condition 14 June 2013 Background 1. The Applicant is a director of a business which holds a Business Insurance Policy with the Financial Services Provider (FSP). The policy provided defined events cover for the insured building up to $20,700, contents up to $56,925 and stock up to $46,575 subject to a policy excess of $250. 2. On or about 11 January 2011, the Applicant‟s business premise in Seventeen Mile Rocks, Queensland, suffered water inundation which resulted in loss. 3. The FSP declined the claim on the basis the loss arose from flood, which is an excluded cause of damage under the policy. 4. The Applicant disputes the declinature on the basis that the inundation first arose from storm water runoff, which is a covered event under the policy. Summary of Applicant’s position 5. The Applicant is represented by an insurance broker; for the sake of simplicity both the Applicant and the broker will be referred to jointly as „the Applicant‟ 6. The Applicant provides the following account of events leading up to the inundation based on its employee‟s experience:  The factory is not situated immediately adjacent to the river and there is a depression between the river bank and the factory where the water collects. It is estimated that runoff water would have been between 0.5m to 1.2m before the river water made an impact and reached 3m, as at 5am on Wednesday 12 January 2011 the water was approximately 1.8m over the factory and the river water had not quite joined the inland water. (sic)  They left the premise at around 3-3.30pm on Tuesday 11 January 2012 (sic). The storm water was pooling in the adjacent “C Road”. The insured left the premise to avoid being stranded by the rising stormwater runoff in C Road. Determination Case No: 303687 Determination Page 2 of 9  At the time of departing the premise, it was obvious the stormwater was not getting away.  Runoff stormwater entering from C Road into “B Street” was observed in the early evening of Tuesday 11 January 2011. At that time no flood water from the Brisbane River was entering B Street.  It is noteworthy that C Road has been subject to stormwater flooding i n 2010 following heavy rainfall and it is understood that around December 2010, vehicles had been submerged by stormwater flooding. Further, even during normal rainfall the back of the factory floor always has water come in to about a quarter of the factory but dries within 2 days.  At 5am on Wednesday 12/1/12 (sic) an employee of the Applicant returned to the property via canoe. At this time the water was 1.8m above floor level of the property (height of door frame). The employee estimated the water level in the river was about 1m below the water level at the property at the time.  The cause of the initial inundation remains in dispute and the insured remains adamant that damage to the internal fit-out, contents and stock was the result of initial inundation of the insured premise by storm water runoff, which occurred prior to flood water from Brisbane River entering B Street. 7. The Applicant states that rain and stormwater initially inundated the property and damage was caused prior to floodwater entering the property. The stormwater entered from C Road and the new housing estate site in B Street. 8. The Applicant notes that there is authority to suggest that in the case of two or more independent proximate causes, that at least a portion of the damage should be covered. The Applicant relies on Elilade Pty Ltd v Nonpareil Pty Ltd [2002] in this regard. 9. The Applicant has noted the submission by the FSP and responds as follows: a. The ICA report relied on by the FSP specifically states that local factors are required to be taken into consideration in hydrologic modelling of a storm event and local stormwater drainage issues. b. The FSP did not initially engage its own hydrologist to investigate, which the Applicant considers a breach of clause 3.4(1) and (2) of the General Insurance Code of Practice. It is further a breach of the duty of utmost good faith under section 13 of the Insurance Contracts Act (1984) (the Act). c. The individual hydrology report was undertaken 16 months after the fact. d. The Applicant refutes the finding that the premise could not have been inundated above floor level by stormwater runoff. The stormwater runoff entering the premises to a height of around 0.9m would have caused significant damage to the internal fit out, contents and stock. Case No: 303687 Determination Page 3 of 9 e. The Applicant argues that it is possible that the initial inundation of the area was caused by stormwater runoff unable to drain away. She also notes that the hydrology report does not address the stormwater runoff from the new Housing Estate site in B Street. . f. The hydrology report ignores vital factual and topographical information suggesting runoff from C Street, the back of the factory and from the new estate being the primary cause of damage. Summary of FSP’s position 10. The FSP relies on the following policy terms and conditions: “What we cover Loss or damage to your property at your premises caused by one or more of the following insured events: 7. Wind or water (including snow, sleet, hail and tsunami). What we exclude We will not pay: Loss or damage: ... i. Caused by flood, the sea, tidal wave, high water, unless the damage is caused by or arises directly from a seismic disturbance... ... 12. Accidental Damage. … What we exclude … Loss or damage which is insurable under any other section of the policy whether effected or not, or loss or damage which is excluded under any other section of the policy … Definitions Word … Flood Meaning: The inundation of normally dry land by water escaping or released from the normal confines of any natural water course or lake, whether or not altered or modified, or of any reservoir, canal or dam.” Case No: 303687 Determination Page 4 of 9 11. The FSP has submitted an assessor‟s report from “C” dated 9 February 2011, entitled “First report – flood damage claim” from which the Panel notes the following:  The Brisbane River is located a few blocks east of the risk premise.  The river breached its banks and inundated surrounding low lying areas of Seventeen Mile Rocks/Jindalee during the early hours of 12 January 2011.  The assessor was advised that by 5am (12 January 2011) flood waters had reached a depth of approximately 2 metres at the risk site causing extensive property damage.  The floor level of the risk premises is similar to street level. 12. The FSP has enclosed a report from its hydrologist “W” from which the Panel notes the following:  The subject property is located on relatively flat land about 350m from the Brisbane River. Stormwater runoff from B Street is collected in a pipe stormwater drainage system that discharges to the Brisbane River.  W obtained the following information from “M”, an employee of the Applicant: a. M left the property at about 3:30pm on Tuesday 11 January 2011. There was no water on or around the property at that time. b. M attempted to return to the property at about 5am on Wednesday 12 January, but C Street was inundated and he was not able to reach the property. c. M paddled to the property in a canoe. The water was about 1.8 m above floor level at the property at that time. d. M estimated that the water level in the river was about 1 m lower than the water level at the subject property. e. The peak water level was about 3m above the lower floor level. f. M returned to the property on Friday 13 January. g. The drainage in C Street is quite poor. In the years that he has been working at the property, he has seen water back up in B Street, but it has never come into the factory before. h. Based on information from Brisbane City Council, the peak water level in the vicinity of the subject property was about 11.6m AHD. Based on the observed peak depth of inundation above floor level (approximately 3m), the floor level of the subject property is approximately 8.6m AHD. W calculates the Brisbane River water levels would have reached the floor level of the subject property at approximately 0100 hours on Wednesday 12 January 2011. i. The peak rainfall intensities recorded on 11 January 2011 were not exceptional. Based on the relatively low intensity of rainfall and the timing of inundation, the subject property could not have been inundated above floor level by stormwater runoff. Similar Case No: 303687 Determination Page 5 of 9 rainfall intensities would have occurred numerous times in the past, without any inundation of the subject property above floor level. In addition, the peak rainfall intensity occurred about 4 hours before the property was vacated and no inundation was observed prior to evacuation of the property. j. Brisbane River flood levels would have reached the floor level of the subject property at about 0100 hours on 12 January, about 5 hours after rainfall in the area had ceased. It is possible that the initial inundation of the area surrounding the subject property was caused by backflow of floodwater from the Brisbane River through the stormwater pipe drainage system, just prior to inundation by direct overland flow of floodwater. 13. The FSP submits its policy wording is clear and unambiguous. 14. The FSP contends that whether the Applicant‟s property was inundated by overland flow or surcharging drains or both that the policy would not respond. This is because the water escaping from the drain is sourced from the nearby flooding watercourse as this is water which has „escaped‟ from the watercourse. 15. Further, if the rainwater runoff inundation occurred at the same time as flood then pursuant to the Wayne Tank principle both sources of inundation would be excluded. 16. The FSP submits that all the information sources available indicated that the insured property was inundated by floodwaters from the overflow and backwater flooding of the Brisbane River and that its decision to deny the Applicant‟s claim was justified. The rainfall data d oes not support the Applicant‟s property as being inundated above ground level by stormwater runoff. Issue 17. Whether the FSP was entitled to decline the Applicant‟s claim for water inundation. Reasons for decision 18. As advised to the parties, this dispute has been referred directly to a Panel for determination. The decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in insurance industry matters and a representative with extensive experience in consumer claims. 19. There has been an exchange of material between each party and the Panel is satisfied each party has had an opportunity to reply to the issues raised. Case No: 303687 Determination Page 6 of 9 20. The Panel has read each party‟s submissions and materials and will only refer to the relevant submissions and materials raised. 21. On 4 June 2013, the Panel Chair Ombudsman attended on site, where he met with the Applicant and representatives of the FSP. 22. It is not in dispute the policy provides cover for loss or damage caused by water, including rainwater. Further, it is not in dispute that the policy excludes loss or damage caused by flood. 23. What is in dispute is whether the water that first inundated the premise and caused damage to the insured property was rainwater or floodwater. 24. Having considered the construction of this policy, the Panel notes that the onus is on the Applicant to show on the balance of probabilities the damage was caused under „event 7‟ by „w ater ’, in this case rainwater (which was not also by floodwater). The Panel notes that although Accidental Damage is available under the policy, this event is not enlivened where the circumstances of the loss are covered or excluded by another section of the policy, in this case „wind or water‟ . 25. The Panel notes the Applicant has provided evidence that ordinary rainfall would cause flooding around and sometimes within the business premise. According to M, the water was between 1.5m and 1.8m above floor level at the property at the time of his visit at between 5.00am and 6.00am on 12 January 2011. However, the water level in the river was about 1m lower than the water level at the subject property. The peak water level was about 3m above the lower floor level. 26. During the site visit, M confirmed that during the day, 11 January 2011, water had seeped in through the rear of the factory and was pooling on the concrete slab to a point about half way in the factory, from its rear. 27. This pooling of water in the factory‟s rear, was prior to a ny inundation from the pooling of water from C Street or inundation from the river itself. 28. The Panel notes that the Applicant evacuated at approximately 3-3.30pm on Tuesday 11 January 2011. Accordingly, it is unknown what time the further inundation occurred or the precise source of the inundation. The Panel does note that there was reported to be substantial water pooling in the depression in C Street prior to overland flooding. 29. The Panel Chair Ombudsman observed that the area behind the factory slopes up sharply towards SMR Road and away from the factory. 30. In this regard, the Panel notes the rainfall data that confirms the rainfall amounts throughout 11 January 2011, consistent with the Applicant‟s evidence of seepage through the rear of the factory. 31. The Panel accepts that the initial seepage of water from the rear to about half way within the factory was as a result of rain water runoff from the steepness of the slope behind the factory. Case No: 303687 Determination Page 7 of 9 32. However, the Panel notes that this inundation, at the time when the Applicant left (3.30pm 11 January 2011), consisted of only minor pooling to the back half of the factory. 33. The Panel accepts the Applicant would have suffered some loss as a result of this inundation, as the Panel Chair Ombudsman observed many stock and parts items were stored at ground level. 34. The Panel is prepared to allow coverage for loss and damage to a level of inundation of 100mm, for items kept at ground level and only for the rear half of the factory. 35. The Panel has no information to assess the Applica nt‟s loss in this regard and urges the parties to work cooperatively to assess the extent of the Applicant‟s loss. 36. In the event the parties cannot agree upon the extent of the loss, the parties may refer the matter back to the Service for further consideration. 37. The issue for the Panel is now the question of any further inundation of the subject property. 38. The Applicant contends that it is possible that further inundation was caused by storm water, unable to drain away. 39. In contrast, the only expert evidence, from W, concludes that the rainfall levels were not significant and that it was water surcharging from the stormwater drains and overland riverine water that caused the initial and peak inundation of approximately 3 metres above floor level. 40. The Panel notes the rainfall data does not suggest that the stormwater inundation was of itself responsible for the whole of the inundation and nor is the Applicant suggesting it did. The Applicant states that water has previously pooled in the area and that the drainage in the street is poor. 41. It is not clear whether the area of pooling was where the drains are located. W notes that it is possible that water would have surcharged from the drain shortly prior to the overland flow and as such this scenario cannot be disregarded. The Panel cannot rule out that the witness was viewing pooling caused by surcharging stormwater drains, as the Panel accepts that there were some drainage issues in the area. 42. However, the Panel is perplexed that the witness stated the level of inundation (runoff) at the property was still 1 metre above the level of the river at 5.00am, on 12 January 2011. Such a conclusion is not supported by the data available, which estimates that the floor level of the property would have been at the same level as the river, by about 1.00am on 12 January. 43. Having considered the evidence provided by each party and in the absence of any direct eyewitness evidence at the time of the initial inundation, the Panel must rely on the other evidence available, namely the assembled hydrological data. Case No: 303687 Determination Page 8 of 9 44. Noting that the Panel Chair Ombudsman attended on site and observed the topography of the local area, the Panel is satisfied that at 5.00am the inundation of the property was to a level of approximately 1.5 metres above floor l evel. Given the Panel Chair Ombudsman‟s observations of the local topography, the Panel is of the view that the river level is likely to have been at the same level as the inundation at the property. 45. Further, i n the Panel‟s view, on the balance of probabilities the initial water inundation from the factory‟s front, was likely caused by a mixture of pooling rainwater, surcharging stormwater drains and overland inundation. 46. The policy does indicate water which has escaped from a watercourse or canal is deemed flood. Kirby J in the case of Provincial Insurance Australia v Consolidated Wood Products (1991) 25 NSWLR 541 considered the meaning of canal and storm water channel and preferred the Macquarie Dictionary definition for canal and stormwater channel which were: “Canal An artificial waterway for navigation draining, irrigation, etc A channel or watercourse Stormwater Channel An artificial passage from stormwater and floodwater; floodway. Also, stormwater canal, s tormwater drain.” 47. Accordingly, the policy definition and common law definition of flood, includes water which has surcharged from a stormwater drain. 48. Second, the courts have determined that water which is unable to drain into a river because it was in flood is deemed to be flood water. The authority for this ruling is K Sika Plastics v Cornhill Insurance (1982) 2NZLR 50CA . In that case His Honour Justice Cooke in part stated: “In ordinary and natural language, I think that a watercourse is said to overflow its normal banks when all the water that would not otherwise drain into it cannot be contained in it because it is full. All the surplus water is then overflow no matter whether or not it has at one time been within the banks and then forced out.” 49. Whilst the Panel agrees that the Elilade case can be utilised in the event of consecutive inundations which arise from independent causes, there is insufficient evidence to establish that this did occur. There is no other expert opinion proffered to contradict W‟s analysis of the rainfall data, river data or topographical/location analysis of the cause of inundation to the Applicant‟s property. W has categorically stated that the rainfall data indicates stormwater runoff was not sufficient to inundate the property above ground level. To the extent this is correct then rather than consecutive causes ( Elilade’s Case), this would be characterised as concurrent causes ( Wayne Tank’s Case). 50. The observations of the Applicant‟s employees were that water was pooling, but there is no reliable contemporaneous evidence as to the origins or nature of this pooling water. Case No: 303687 Determination Page 9 of 9 51. It is established law (see Eastern Suburbs Leagues Club v Royal & Sun Allianz Australia Limited) that the mixture of stormwater and flood water is deemed flood water. 52. After careful analysis of the available material, the Panel concludes that the damage claimed was caused by flood water as defined and is not covered by the policy. 53. The Panel further notes the assertions by the Applicant regarding the FSP‟s failure to properly and transparently review the claim in accordance with the General Insurance Code of Practice. The Panel is also mindful of the specific clause 4 of the General Insurance Code of Practice relating to catastrophes and disasters that was applicable at the time of loss and claims handling. It is noted that the Code recognises the inherent difficulties in dealing with a high volume of claims which results from such an event. Clauses 4.3 and 4.4 state: “4.3 Due to the large number of claims we may not be able to meet all standards of this Code following a catastrophe or disaster. 4.4 We will establish our own internal processes for responding to ca tastrophes and disasters” 54. The Panel notes that due to the number of claims and the limited number of hydrologists, many insurers did opt to review claims solely on the basis of the ICA hydrology report. The Panel understands that from an Applicant‟s point of view this may be unsatisfactory. However, the Panel cannot find in the circumstances that the Code has been breached. Determination 55. The Panel determines that the FSP is to meet the Applicant‟s claim for loss and damage arising from an inundation to a level of 100mm above the floor level of the rear half of the Applicant‟s factory. 56. Should the FSP elect to cash settle this aspect of the claim, the FSP is to pay interest on the cash settlement from the date of denial of the claim, to the date of settlement of the claim and in accordance with the Insurance Contracts Act 1984. 57. On the basis of the available information the Panel determines that the FSP was entitled to decline the balance of the Applicant‟s claim for inundation.