Text of the determination
Case No: 303533 Determination Page 1 of 9
Case number: 303533
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Method of Repair - Claims Handling - Compensation
20 March 2014
Summary
Description
A claim under a Home Building Insurance Policy for loss following
storms/floods.
Basis of Determination
A consideration of how the policy provisions apply to the alternate
methods of repair.
Determination
The FSP is required to carry out repairs in accordance with the method
elected by the Applicant.
Background
1. The Applicant held a home building insurance policy with the Financial
Services Provider (FSP) covering her residential address. The policy was
incepted on 27 May 2000, renewed annually and was current at the time of
the loss occurring.
2. On 7 February 2011, the Applicant contacted the FSP to lodge a claim for
cracking which had occurred to the internal walls of the home, which the
Applicant believed had arisen as a result of recent storms/floods in the area.
3. After considering the cause and extent of the loss, the FSP agreed to accept
the claim and requested building firm “B” engage an engineer to prepare an
appropriate scope of works (SoW) for the repairs required. After considering
the SoW prepared by B, under which alternate repair methods titled „method
one‟ and „method two‟ were outlined, the FSP authorised B to undertake
repairs in accordance with proposed „method two‟.
4. The Applicant is dissatisfied with the method of repair accepted by the FSP
and prefers that „method one‟ be utilised in the repair of her home.
Determination
Case No: 303533 Determination Page 2 of 9
Summary of Applicant’s position
5. The Applicant says the only acceptable method of repair for her home is
conventional underpinning of the home, with reconstructing the double brick
internal walls atop the pillars.
6. The second method of repair, as approved by the FSP, is not acceptable as
it involves replacing internal brick walls with timber. The FSP has not
provided a legitimate reason for choosing this method of repair, other than
that it will be a less costly method.
7. However, she wishes to maintain the integrity of her home as it is heritage
listed. This will not be achieved with the FSP‟s method of repair and the
FSP‟s own builders told her any other engineer would only approve method
one for the repairs. It is her right under the FSP‟s polic y to have her home
reinstated to its original condition.
8. The FSP has delayed and stalled her claim for over two years and has done
nothing but try to avoid its obligations under the policy. She does not believe
the FSP has the expertise or skill to deal with such a large claim and they
are not committed to developing a proper SoW to repair her home.
9. The FSP has caused her untold stress and anxiety with the manner in which
it has managed her claim. The initial devastation of the event has been
compounded by the FSP‟s failure to repair her home in a timely manner. She
is therefore also seeking compensation for the manner in which the FSP has
managed her claim.
Summary of FSP’s position
10. The FSP says it has engaged the services of a qualified engineer from B
who inspected the damage to the property and prepared a de tailed SoW of
the repairs required. Accordingly, it is prepared to authorise and undertake
works to the home in accordance with the SoW prepared by B; however the
Applicant has refused to agree to the SoW to allow works to commence.
11. B considered there were two methods available for repair, however advised
method two was preferred as it was less invasive, would better preserve the
integrity of the home and was able to be provided with a guarantee. Method
one, however, whilst replacing the existing internal brick walls with brick, was
a more costly and invasive repair method which would see both the roof and
the external walls requiring removal. Further, due to the existing pillars being
no longer able to support the weight of brick internal walls, any new brick
walls would be structurally unsound and prone to failure; therefore a
guarantee on the repairs would not be able to be provided without significant
other works undertaken.
12. The FSP says it is entitled to rely on the findings of its engineer to conclude
that method two constitutes a proper repair of the home. The Applicant has
not provided any evidence to suggest why method one should be utilised
Case No: 303533 Determination Page 3 of 9
other than that it is her preferred method. Accordingly, the FSP submits it is
entitled to rely on the findings of its engineer to proceed with repair utilising
method two.
13. The FSP acknowledges the proposed method of repair utilises different
materials in the repair to that which was originally in place. However, the
home was constructed in approximately 1900 and utilised bluestone pitchers
as footings, which are no longer compliant with the building codes
applicable. Therefore replacement of the brick walls with timber would
ensure the structural integrity of the home.
14. The FSP relies on the following policy provisions contained within the
Product Disclosure Statement (PDS), which the Applicant does not dispute
receiving:
“ What we will pay – new for old
Repairing or rebuilding your building
If your home building is damaged during the period of cover by an insured
event, we will decide if the damage:
can be properly repaired, or
is so severe that we reasonably believe your building will need to be rebuilt.
Repairing your building
When we establish that your home building can be properly repaired, we will
decide to:
repair it, or
pay the cost of repairing it.
When we repair your building, we will use new materials.
We will make reasonable endeavours to match materials. Where this does not
achieve an exact match, materials that in our opinion match the damaged or
lost materials as near as reasonably practicable will be used. We will not pay
to replace undamaged materials or any undamaged part of them to achieve a
match. ”
Issues
15. Whether the FSP‟s method of repair fulfils its obligations under the terms of
the policy.
16. Whether the Applicant is entitled to compensation for the manner in which
the FSP has managed her claim.
Reasons for decision
17. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with the Operational Guidelines to the FOS Terms of
Reference. This is due to the circumstances of the dispute. This dispute has
Case No: 303533 Determination Page 4 of 9
not been the subject of a FOS Recommendation and has proceeded directly
to Determination.
18. This dispute has been determined by a Panel consisting of an Ombudsman
and two Panel members with extensive experience in insurance matters and
consumer claims.
19. An exchange of information has taken place between each party and each
party has had the opportunity to address any issues raised.
20. It is not disputed between the parties the Applicant suffered a loss from a
risk insured against or that the FSP has accepted her claim and is prepared
to undertake the repairs to the home. However, a dispute has arisen
between the parties as to the proposed method of repair to be utilised.
Expert reports
21. In his report of 15 May 2013, B outlined two potential methods of repair that
could be used for the home. Method one involves installing underpinning
bored concrete piles with reconstructed brick walls on the new concrete
footings. Method two involves the construction of concrete strip footings with
new timber walls atop them.
22. B has outlined the advantages and disadvantages of each method in his
report and has concluded that method two constitutes the most effective and
complete method of repair, as well as the least disruptive.
23. The Panel has considered the reports on file from the two prior engineers
en gaged to inspect the home and notes that both firms “H” and “F” also did
not recommend the home be underpinned due to the potential for other
damage to be occasioned to the home in the process. H considered
cosmetic repairs to the internal walls and re-levelling of the floors to be
sufficient, whereas F recommended the home be jacked up and the bearers
„packed‟ to re -level the property. However, F deferred to an engineer with
specialist knowledge of such issues to determine an appropriate method of
repair and it was on this basis that B was engaged.
24. The front section of the existing home is constructed with internal walls
consisting of a single skinned brick wall covered with plasterboard. These
are supported by bluestone foundations and there does not appear to be any
dispute between the parties that the bluestone foundations cannot be used
in the repair as these materials are no longer compliant with the building
codes applicable today.
25. In his report of 11 April 2012, written after access to the subfloor was gained
to inspect the area, F states that:
“the type and dimension of the subject footings do not comply with the current
building code for a CLASS P footing as per AS2870. [F] notes that the
bluestone footings have no adequate strength or stiffness to resist any soil
movements. Furthermore, due to the brittle nature of the internal wall finishes,
very slight foundation movements will result in wall cracking”.
Case No: 303533 Determination Page 5 of 9
26. Accordingly, the supporting foundations must be constructed of different
material. The FSP‟s p olicy provides that where an exact match cannot be
achieved, materials that match as closely as possible will be used in the
repair of the home. Without any evidence to the contrary, the Panel accepts
B‟s recommendation that concrete footings are the most practical match for
the existing bluestone footings.
27. However, the question then arises as to whether the newly constructed
footings should be concrete piles or concrete strip footings. The Panel has
considered the information on file and notes that none o f the experts, who
have inspected the home, have commented on what constitutes the
construction of the foundations that are in the centre of the home. Whilst it is
clear the perimeter of the property is constructed of concrete strip footings,
the Panel is unable to determine if this is consistent throughout the property
or whether the centre of the home is atop bluestone pillars.
28. However, there is no dispute the internal wall linings are constructed of a
single skin brick wall. The FSP‟s policy commits it to repairing the home with
materials that match as closely as possible to the original:
“ We will make reasonable endeavours to match materials. Where this
does not achieve an exact match, materials that in our opinion match
the damaged or lost materials as near as reasonably practicable will be
used ”
29. On any reasonable understanding of these words, alternatives would only be
used where the original materials are no longer available or are no longer
suitable for the purpose, for example due to changes in building codes. The
effect of the FSP‟s preferred method of repair would result in the
replacement of internal brick walls with timber walls. In the Panel‟s view this
does not provide a match as contemplated by the policy wording; clearly the
materials proposed cannot be said to be the same or similar materials. The
meaning of the words are clear and the interpretation of such words has
been considered by the courts.
30. A summary of the relevant principles is found in the judgement of Williams J
in Messagemate Aust Pty Ltd v National Credit Insurance (Brokers) Pty Ltd
& Ors (“Messagemate”) [2002] SASC 327 at 40:
“An insurance policy is a species of commercial contract. It must be
interpreted so as to give the words used their ordinary meaning. The primary
duty of a court is to discern from the language, structure and apparent
purpose of the document what it means. A court should give the words used
their ordinary operation. The Court is to search for the meaning of the words
used. If in those words there is only one meaning, a court may not reject it
simply because it regards the result as unfair or otherwise undesirable.
Johnson v American Home Assurance Co [1998] HCA 14 ; (1998) 192 CLR
266 , per Kirby J at p272.
McCann v Switzerland Insurance Australia Ltd [2000] HCA 65 ; (2000) 176
ALR 711 at 716 & 725-7.
Case No: 303533 Determination Page 6 of 9
Where a word or a phrase has a settled meaning in insurance contracts, the
Court will hesitate before departing from that meaning.” Johnson v American
Home Assurance Co supra.
31. Accordingly, the FSP is required, by the terms of its own policy, to replace
the internal walls with single skin brick walls. By extension, the supporting
foundations must be of adequate strength to support the brick walls,
meaning the FSP is therefore required to install the concrete piles.
32. Whilst the Panel has carefully considered the report from B and accepts that
it is persuasive and compelling in concluding that method two is the least
invasive, most cost effective and better method for repairs, it does not fulfil
the policy requirements to repair the property on a „like for like‟ basis, using
materials that match as closely as possible to the original. The FSP has not
advanced an argument to suggest the same or similar bricks are no longer
available to repair the home and accordingly, the Panel accepts they are
available.
33. Were the Applicant mindful to accept method two as a reasonable alternative
for the repairs required, then the parties could investigate the possibility of
working together to utilise this method to repair the home.
34. However, she is not so inclined. The Applicant has made it quite clear she is
unwilling to accept the replacement of the brick walls with timber and there is
nothing in the policy terms which would compel her to; on the co ntrary, the
policy terms commit the FSP to using the closest available materials to
repair the home, which in this case would be the use of bricks to construct
the internal walls and by extension, the construction of appropriately
compliant pillars/foundations and the associated works this would entail.
35. Accordingly, after considering all of the available information, the Panel
considers that method one most closely fulfils the FSP‟s obligations pursuant
to the terms of the policy and it is this method the FSP is required to
authorise in the repair of the home.
36. In the Panel‟s view it also is important to note that on 6 March 2014 the
Panel Chair Ombudsman attended at the subject premises with the
Applicant together with two representatives of the FSP and the engineer who
prepared the report for building firm B.
37. This meeting was arranged by the Service for the purposes of the engineer
explaining the two methods for the repair of the Applicant‟s home.
38. At the meeting, the engineer explained that after careful consideration of the
evidence concerning the damage to the Applicant‟s home and a
consideration of how that damage may be resolved, which resulted in
method one being considered, the engineer himself, concluded that the
complexities and risk of further damage associated with method one meant
that he should consider methods and alternate ways to attend to the repair of
the Applicant‟s home.
Case No: 303533 Determination Page 7 of 9
39. The engineer confirmed that method two was a solution that he had devised
because of the complexities associated with method one, including the need
to remove at least part of the roof and the wall that runs along (A) Street.
40. The engineer further explained that because of the complexities associated
with the work required by method one, it was unclear and uncertain as to
what associated difficulties and extra work may arise as a result of the work
required to complete method one.
41. The engineer was of the view that method one would certainly take much
longer to complete than method two and that an estimate for method one
would be approximately one year, rather than the four month period
contemplated by method two.
42. At this point, it is necessary to note that the Applicant maintained that she
had been advised that method one could be completed within a six month
period.
43. The Panel notes that there is no evidence to support this view and that the
FSP‟s responsibility to complete the work is only to the extent of reasonable
industry practice. This means that if the work could be completed in a faster
timeframe by the use of increased labour or machinery, if that increased
labour or machinery exceeded reasonable industry practise, then the
Applicant would be responsible for any additional or associated costs.
44. The engineer further explained that as part of method one, the wall which
runs along (A) Street would have to be substantially removed and could not
be restored to the same situation and appearance as currently exists and it
is unlikely that the same bricks could be used or that the grouting would be
even or match any part of the wall which did not have to be demolished.
45. Further, the engineer explained that he was of the view that method two
would provide interior walls which were acoustically better than the current
interior walls and that save for the fact that the Applicant would k now that the
composition of the interior walls was actually wooden, an observer would be
unaware of this fact as the interior walls‟ exterior would be covered in high
quality plaster.
46. In this regard, the Panel notes that the rear section of the home has been
more recently built and the interior walls in this section also have wooden
interiors which are covered by plaster.
47. The engineer was at pains to explain the interior walls contemplated under
method two for the front section of the home, would be of far superior quality
to the interior walls at the rear section of the home.
48. Finally, the Panel Chair Ombudsman advised the Applicant that if there were
non-insured event maintenance issues which needed to be attended to prior
to or during the rectification work, then the Applicant would be responsible
for the cost of those non-insured event maintenance issues.
Case No: 303533 Determination Page 8 of 9
49. The engineer confirmed that he had not turned his mind to this issue and
was unable to provide advice as to whether in fact there were any non-
insured event maintenance issues.
50. The Panel wishes to make it clear that the material presented does not
confirm that there are any non-insured event maintenance issues. However
the Panel‟s considerable experience in dealing with other similar cases,
gives rise to its concern that there may be non-insured event maintenance
issues that flow from the rectification work or that are needed to be
completed prior to the commencement of the rectification work . Therefore, it
is important the Applicant is aware of her responsibility in this regard, prior to
her making a final decision about this matter.
51. The Panel is grateful that the Applicant and the engineer made themselves
available for the meeting.
52. The Panel Chair Ombudsman is satisfied that the engineer had the
opportunity to explain to the Applicant, to the FSP‟s representatives and to
the Panel Chair Ombudsman, the respective merits and pitfalls of method
one and method two.
53. The Panel is also satisfied that the Applicant, in accordance with her rights
under the policy, has instructed the FSP to proceed with the rectification of
her property consistent with method one.
54. The Panel determines that the FSP is required to rectify the damage to the
Applicant‟s premises in accordance with method one.
55. The Panel also notes that as a result of the rectification work, during the
period which the premises are uninhabitable, the FSP is required to pay the
reasonable cost of comparable temporary accommodation for a period up to
a maximum of 12 months. For the sake of clarity, should the premises
remain uninhabitable for more than 12 months, the Applicant may be
responsible for accommodation costs, once that FSP‟s obligation has been
exhausted.
56. The Panel also notes that the building policy does not specifically provide for
removal and storage of contents costs.
57. Whilst the Panel has not been asked to resolve this issue, it appears that the
Applicant also holds a contents policy with the FSP. That contents policy
appears to provide coverage for removal and storage of contents costs, but
again, those costs are limited to a maximum of 12 months.
Is the Applicant entitled to compensation as a result of the FSP’s handling of
the claim?
58. The Panel has also considered whether the Applicant is entitled to
compensation pursuant to the FOS Terms of Reference 9.3b (the Terms).
The Applicant is seeking compensation for emotional stress she states has
been caused by the FSP‟s handling of the claim.
Case No: 303533 Determination Page 9 of 9
59. It is accepted that to some degree, all insurance claims are stressful and
inconvenient. In order to consider an award of compensation for either
consequential financial or non-financial loss under the Terms, the Panel
must be satisfied some action of the FSP has caused an unusual degree or
extent of physical inconvenience, time taken to resolve the situation or
interference with the Applicant‟s expectation of enjoyment or peace of mind.
The simple passage of time is not, of itself, a sufficient trigger for an award of
compensation.
60. The circumstances of the damage to the Applicant‟s home are such that
several experts were required to inspect the home and present their findings
to the FSP in order that the FSP could adequately determine its liability
under the terms of the policy. It is noted that destructive testing and
geotechnical testing was required and the subfloor was required to dry out
sufficiently, before a SoW could be prepared.
61. Whilst the FSP‟s conduct of the claim could certainly have been handled
better in some instances, in particular the delays experienced between F‟s
inspection in April 2012 and the FSP‟s decision to indemnify the Applicant in
November 2012, the Panel is not persuaded it so mishandled the claim, such
as to justify an award of compensation pursuant to the Terms.
62. The home remained habitable in the meantime with only minimal loss of
amenity due to the cracked walls and uneven floors. It is accepted this was
no doubt inconvenient, however, in the Panel‟s view this does not constitute
an unusual degree of inconvenience such that an award of compensation is
warranted in the circumstances.
63. Accordingly, the FSP‟s handling of the claim was reasonable in the
circumstances and therefore an award of compensation is not appropriate.
Determination
64. On the basis of the available information the Panel determines:
The FSP is required to utilise method one in the repair of the home;
and
The Applicant is not entitled to compensation for the manner in which
the FSP has managed her claim.