Home / Financial Firm (Unknown - Insurer) / Determination 302762

Determination 302762

Claim amount - replacement floor tiles

FirmFinancial Firm (Unknown - Insurer)
Decided2013-10-23
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$21,340
Non-financial loss—
Amount claimed$97,000
SourceAFCA PDF

Summary

After a hailstorm damaged the applicant's home, the FSP chose to repair and proposed alternative floor tiles instead of the original discontinued tiles. AFCA found the alternative complied with the policy, gave the applicant the option of a $21,340 cash settlement, ordered rectification of defective repairs and incidental costs, and refused non-financial loss.

The policy's obligation to 'try to match' materials is a best-endeavours obligation, so cost and availability of an appropriate substitute can be weighed against the original tiles.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 302762 Determination Page 1 of 10 Case number: 302762 General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim amount 29 August 2013 Background 1. This dispute follows the review of a Recommendation issued on behalf of FOS on 19 June 2013. The Recommendation was rejected by the Applicant. 2. The Applicant held a home insurance policy with the Financial Services Provider (FSP) which was current at the time of the loss. 3. On 3 January 2012, the Applicant lodged a claim under the policy for water damage to his house caused by the 2011 Christmas Day hailstorms. 4. The FSP accepted the Applicant’s claim and elected to repair the damage to his property. However, a dispute arose in relation to the replacement floor tiles to be used to complete the repairs. 5. The original floor tiles are only available by special order subject to a minimum order size significantly larger than that required to complete the repairs. Accordingly, the FSP has sought to replace the flooring with alternative tiles which are not subject to a minimum order condition. 6. The Applicant disputes the FSP’s approach and says that, as the original tiles are available, the FSP should be required to obtain and install them regardless of the additional cost . 7. The Applicant also seeks rectification of certain other repairs carried out by the FSP which he says have not been completed in a satisfactory manner, together with compensation for delays and inconvenience experienced in the handling of his claim. Summary of Applicant’s position 8. The Applicant says that:  in taking out the policy, he relied on a brochure published by the FSP which provides directions as to how to assess an appropriate level of cover. He says that the brochure evidences that the policies issued by the FSP provide indemnity based on the standard of materials used in the home and the FSP prices cover on this basis; Determination Case No: 302762 Determination Page 2 of 10  in order to fully indemnify him for his loss, the FSP is required to repair his home using the original tiles (subject only to the limit imposed by the total sum insured). The original materials should be used in order to maintain the aesthetics of the property, ensure that the technical specifications of the current flooring are achieved and preserve the value of the property as a whole;  the terms of the policy require the FSP to try to match the materials used to repair his home with the original materials and to repair the home to a condition as close to new as possible. This does not allow the FSP to select an alternative flooring material in lieu of matching the existing tiles where these are available;  the original tiles are “available” as they can be obtained through a special order. The FSP is not entitled to use an alternative flooring material merely because of the costs involved in obtaining the original tiles and in seeking to do so, the FSP is breaching its duty of good faith;  once the FSP elected to repair his home, it is bound by this election and cannot subsequently decide to offer a cash settlement for the flooring component of the repairs merely because this has turned out to be more expensive than initially anticipated; and  when the FSP elected to repair his home, it also elected to match the existing flooring. This is supported by the terms of the building contract entered into with the FSP’s bu ilder and the FSP should not be able to resile from this position. 9. The Applicant seeks to have the flooring replaced using the original tiles and for the FSP to attend to all incidental matters such as disconnection of plumbing equipment, removal and storage of furniture and compensation for alternate accommodation. The Applicant also seeks to have the FSP rectify all other elements of the repair works which the FSP has previously acknowledged as unsatisfactory, as this has been deferred until the flooring repairs are completed. 10. The Applicant also seeks compensation of $12,000 for non-financial loss incurred due to the FSP’s handling of his claim. The Applicant says he has experienced delays and inconvenience, having regard to the time and effort required to deal with and respond to the FSP’s actions, as well as the inconvenience of works still being outstanding more than 18 months after the claim was lodged. Summary of FSP’s position 11. The FSP says that:  the policy is not a policy of reinstatement and the FSP is only required to repair the damage to the Applicant’s home, not to “reinstate” the home using the exact same products; Case No: 302762 Determination Page 3 of 10  the terms of the policy provide the FSP with a discretion to use either the original materials or the “nearest equivalent available”, in order to repair the Applicant’s home. Based on the terms of the policy, the FSP is only required to match the underlying material from which the tiles are made (which in this case is rubber);  the original tiles are no longer in production and while the y can be obtained by way of a special order, this does not mean that they are “available”. The terms of the policy do not require the FSP to go to the extent of placing a special order;  given the minimum order size, the cost of obtaining the original tiles is grossly unreasonable and does not reflect the actual cost to repair the damage;  the references to “matching” in the building contract refer to ensuring a consistent appearance with the existing tiles, rather than using the original tiles to complete the repairs; and  under the policy, the FSP is entitled to elect to cash settle the Applicant’s claim for the flooring and can do so provided that no work on the flooring has commenced. The FSP has no choice but to offer a cash settlement if the Applicant will not allow repairs to proceed unless the original tiles are used. 12. Accordingly, the FSP says that it is entitled to repair the damage to the Applicant’s floor using a flooring product which is similar to, but not exactly the same as the original tiles. 13. T he FSP says that any delays in settling the Applicant’s claim have been caused by the Applicant’s refusal to allow the FSP’s service providers to carry out the repair work in accordance with the terms of the policy. Issues 14. Whether the FSP is required to use the original tiles to repair the damage to the floor of the Applicant’s home. 15. Whether the Applicant is entitled to compensation for non-financial loss due to the FSP’s handling of his claim. Reasons for decision 16. I am satisfied that there has been a full exchange of material between the parties and that each party has had the opportunity to address any issues raised therein. Case No: 302762 Determination Page 4 of 10 17. The parties have provided extensive submissions which I have reviewed in their entirety. However, for the sake of brevity, in this Determination I will only refer to submissions made by the parties to the extent that I consider them to be directly relevant to my decision. 18. The following matters are not in dispute:  the original rubber floor tiles (Norament Luxor 4627) used in the Applicant’s home are manufactured in Germany ;  the original tiles are no longer in production but are available by special order, subject to a minimum order size of 400 square metres;  the cost of obtaining and installing th e tiles is approximately $85,000 (given the minimum order size); and  the area of the Applicant’s home to be retiled is approximately 64 to 70 square metres . 19. The FSP argues that the cost of using the original tiles to repair the Applicant’s property is unr easonable and therefore it is entitled to use an alternative tile. The FSP has proposed using either Norament Luxor 4766 or Norament Luxor 4900, each of which appears to be made from the same materials as the original tiles, but is not of precisely the same colour and pattern. The Applicant rejects these suggested alternatives in place of the original tiles. 20. Accordingly, the primary issue to be considered is the nature and content of the FSP’s obligation to repair the Applicant’s property and in particular, whether, in the current circumstances, this requires the FSP to use the original Norament Luxor 4627 tiles. Election to repair 21. The Applicant’s policy states that where his home suffers loss or damage, the FSP will decide whether to:  repair;  rebuild; or  pay the cost to repair or replace the part of the home that suffered loss or damage. 22. It is not disputed that, following lodgement of the Applicant’s claim, the FSP elected to repair the damage to the Applicant’s home. Once the FSP made an election to r epair the Applicant’s home (rather than to cash settle him for the cost of the repairs), it was obliged to complete the repairs in accordance with the terms of the policy. At this point, the FSP effectively assumed the financial and other risks associated with completing the repairs. Case No: 302762 Determination Page 5 of 10 Obligation to repair 23. Under the Applicant’s policy, the obligation to repair is an absolute obligation. This is consistent with an insurer’s obligation to indemnify the insured for loss or damage sustained. However, the obligation to repair does not of itself necessarily require the insurer to “reinstate” the damaged property, so that post-repair the insured property is in all respects exactly the same as it was pre-repair. In order to determine the nature and extent of the FSP ’s obligation to repair, it is necessary to have regard to the specific terms of the policy. 24. I note that the Applicant says that, by entering into the building contract and through its subsequent conduct, the FSP has not only elected to repair the damage but has elected to match the existing tiles. I do not accept that the actions of the FSP referred to by the Applicant have this effect. 25. While the scope of work in the building contract refers to the supply and laying of floor tiles “to match existing”, it is not apparent that the use of the expression “match” in this context refers to anything more than the need to ensure that the appearance of the replacement tiles was consistent with (but not necessarily identical to) that of the existing tiles. 26. The actions of the FSP in seeking to match the existing tiles were consistent with its obligation under the policy to “try to match” the repair materials (as discussed further below). However, absent some form of estoppel argument (which the Applicant has not adva nced), the FSP’s actions in seeking to comply with its obligations under the policy cannot result in it being required to do anything more than it would otherwise be required to do under the terms of the policy itself. Replacement benefit 27. The Applican t’s policy includes “replacement benefit” and therefore, in repairing the damage to his home, the FSP is required to comply with the following provision: “We will repair or rebuild the part of your buildings that suffered the loss or damage to a condition as close as possible to when new, but not better.” 28. The purpose of the above provision is to clarify that the FSP must repair the property so as to ensure that the repaired property reflects the condition of the damaged property when new, rather than its co ndition at the time of the loss. However, I do not accept that the above provision necessarily requires the FSP to use the original product when carrying out repairs. 29. The expression “condition” refers to the state of the property at the relevant time. Accordingly, the relevant provision is intended to ensure that any decline in the condition of the property due to factors such as wear and tear and gradual deterioration are not taken into account for the purpose of determining the standard which the FSP is required to meet in carrying out repairs. Case No: 302762 Determination Page 6 of 10 Obligation to match 30. The Applicant’s policy states that, where the FSP carries out repairs, it will: “try to match any material used to repair [the] buildings with the original materials or nearest equivalent availa ble to the original materials”. 31. Both parties have provided a number of suggested alternative constructions of this provision, in support of their arguments as to whether it does or does not require the FSP to use the original tiles in the current circumstances. 32. It is helpful to have regard to the following well-known statement by Gleeson CJ ’s regarding the construction of insurance contracts, in the case of McCann v Switzerland Insurance Australia Ltd (2001) 11 ANZ Ins Cases 61- 479: “A policy of insurance, even one required by statute, is a commercial contract and should be given a businesslike interpretation. Interpreting a commercial document requires attention to the language used by the parties, the commercial circumstances which the document addresses, and the objects which it is in tended to secure.” 33. Unlike the obligation to complete repairs, the obligation to match the materials used to repair the property is not an absolute obligation – the policy merely requires that the FSP “try” to do so. In my view, this is in the nature of a “reasonable endeavours” or “best endeavours” obligation (noting that Australian courts to date have not identified any substantive difference between the two). 34. In Transfield Pty Ltd v Arlo International Ltd (1980) 144 CLR 83, Mason J stated that a best endeavours obligation: “ prescribed a standard of endeavour which is measured by what is reasonable in the circumstances, having regard to the nature, capacity, qualifications and responsibilities of the [contracting party] viewed in the light of the particul ar contract” . 35. The extent to which a “best endeavours” obligation may be limited in particular circumstances is reflected by the decision in Transfield . In that case, the High Court held that one party’s obligation under a licence agreement to use “best endeavours” to sell the product manufactured by the other party did not prevent the first party using its own product when carrying out works under a construction contract with a third party. 36. Accordingly, in considering the nature and extent of the FSP’s “matching” obligation, it is necessary to have regard to the circumstances of the FSP, viewed in the context of the policy of insurance. 37. In his submissions, the Applicant says that the standard of behaviour imposed by the expression “try” cannot be determined based on a strict cost based test. While I agree that cost is not the only factor, I consider that it can be a relevant factor in determining to what lengths it is reasonable to expect an insurer to go, when seeking to match repair materials. Other factors which may be relevant include the inconvenience and/or delay associated Case No: 302762 Determination Page 7 of 10 with trying to match materials (although this does not appear to be relevant in the current dispute) and/or the availability of an appropriate substitute. The assessment of what is “reasonable” necessarily involves consideration of the facts and circumstances of each particular case. 38. In the circumstances of the current dispute, I do not consider that it is reasonable to require the FSP to acquire the original Norament Luxor 4627 rubb er tiles in a quantity which vastly exceeds the number of tiles required to repair the damage to the Applicant’s property, where doing so will require the FSP to incur significant additional expense, in both a relative and a bsolute sense. In these circumst ances, the issue is of a materially different scale than in the example referred to in the Applicant’s submissions , where it is expected that an insurer will fund the cost of a full tin of paint, even where only a very small proportion of that amount will actually be used to undertake repairs . 39. In the current circumstances, the availability of an alternative material is also relevant. The Applicant has referred to the particular technical specifications of the Norament Luxor tile. The alternative tile proposed by the FSP is a tile of the same make, but of a slightly different colour and pattern. I have reviewed online photographs of both the alternatives (4766 and 4900) proposed by the FSP and the original tile (4762) and consider that 4766 (in particular) appears very similar in colour and design to the original tile 4762. 40. In his submissions, the Applicant says that only cost constraint to which the FSP can properly have regard in completing the repairs is the total sum insured. I do not accept this position. The sum insured imposes a limit on the total amount for which the FSP is required to indemnify the Applicant under the policy and the FSP is not entitled to depart from its absolute obligation to complete the repairs to the Applicant’s property merely on the basis that doing so is too expensive. However, for the reasons outlined above, the obligation to “try to match” is a “best endeavours” rather than an absolute obligation and therefore it is appropriate to have regard to cost (as well as other factors) in considering what will be required of the FSP in order to satisfy this obligation. 41. In my view, having regard to the disproportionate costs associated with acquiring the original tiles does not constitute the imposition of an arbitrary and uncertain cost- based limit on the FSP’s obligations. Rather, it seeks to give effect to the words of the policy as written and in particular, the expression “try to match” where used in the relevant provision. 42. Accordingly, in light of the significant costs involved in obtaining the original tiles and the availability of an appropriate alternative, I find that the FSP has complied with its obligations to “try to match” the replacement tiles, by proposing the use of Norament Luxor 4762. 43. I note that I have assumed for the purposes of the above discussion that the “matching” provision requires the FSP to try to match the replacement materials to the original material, rather than the nearest equivalent available. While I consider that this to be the better view of the pro vision, I Case No: 302762 Determination Page 8 of 10 have not explored the issue in detail for the purposes of this Determination as it is not critical to my final decision. 44. Finally, I note that the Applicant has referred to a brochure issued by the FSP to provide guidance to customers as to how to determine an appropriate sum insured. The Applicant says that he relied on representations and warranties in this brochure to the effect that the policy would provide indemnity for the full cost of replacing his existing floor tiles. 45. I do not accept that the brochure referred to by the Applicant contains representations and warranties to this effect. The brochure assists customers to determine an appropriate sum insured, based on the cost of rebuilding given the particular features of their home. In my view, it is intended to draw customers’ attention to the fact that homes with high quality finishes and design features will cost relatively more to rebuild and therefore customers should ensure that the sum insured under their policy is sufficiently high. 46. The current dispute does not turn upon whether or not the sum insured under the Applicant’s policy was sufficient (see paragraph 40 above). There is nothing in the relevant brochure which states that, in repairing damage to the insured property, the FSP must use the original products. While the FSP is obliged to repair the property using products of an equivalent standard, this is satisfied by the use of an alternative Norament Luxor tile. Cash settlement 47. It is clear from his submissions that the Applicant is understandably very concerned to maintain the appearance of his home, which is architect designed and finished to a very high standard. 48. While I have found that the FSP’s proposed use of the alternative Norament Luxor tile to repair the damage complies with the terms of the policy, it is possible that the Applicant may nevertheless prefer to make arrangements to obtain and install the original tiles. Given that the FSP has already offered a cash settlement at an earlier stage in the claims process, I consider that the Applicant should be entitled to choose to be cash settled for an amount equal to the cost of supplying and installing the Norament Luxor 4766/4900 tiles, as reflected in the quote for $21,340 quote dated 12 October 2012 obtained by the FSP and provided to the Applicant during the course of this dispute. Other issues 49. The Applicant says that, in repairing the damage to the tiles, the FSP should be required to attend to all incidental matters such as disconnection of plumbing equipment, removal and storage of furniture and compensation for alternate accommodation. Case No: 302762 Determination Page 9 of 10 50. The FSP has not disputed this aspect of the Applicant’s cl aim. Accordingly, I find that, subject to the terms of the policy, the FSP should be required to bear the cost of the matters identified by the Applicant, subject to any restrictions or limitations which apply under the terms of the policy. If the Applicant elects to be cash settled, the cash settlement should include appropriate provision for these items to be determined by the FSP, based on the costs it would anticipate occurring were it responsible for funding these items directly. Any amount paid in respect of alternative accommodation should be subject to the provision of appropriate invoices by the Applicant. 51. The Applicant also seeks rectification of certain repairs carried out by the FSP to other damaged parts of his property. The FSP has acknowledged that these repairs were defective and has agreed to arrange for rectification. 52. The Applicant seeks compensation for non-financial loss due to the delays and inconvenience associated with the handling of his claim. 53. In large part, the delays and inconvenience experienced by the Applicant have been a consequence of the current dispute, as the progress of repairs has been delayed while the parties disputed the particular tiles to be used. As I have found for the FSP on this issue, I am not satisfied that the Applicant should be entitled to compensation for non-financial loss. Determination 54. On the basis of the available information I determine that:  the FSP is entitled to repair the damage to the floor of the Applicant’s home using Norament Luxor tiles (model 4766 or 4900);  if the Applicant accepts this Determination, the Applicant is entitled to choose to have the FSP: a. repair the property using Norament Luxor tiles model 4766 or 4900 (as chosen by the Applicant); or b. cash settle the Applicant for the amount of $21,340, being the quoted cost of supplying and installing the Norament Luxor tiles;  the FSP is to bear the costs of incidental matters associated with the supply and installation of the replacement tiles, in accordance with the terms of the policy. If the Applicant is cash settled, the amount of the cash settlement is to be increased to include a reasonable estimate for such items, provided that any amount paid in respect of alternative accommodation will be subject to the provision of relevant invoices by the Applicant;  the FSP is to arrange for the rectification of previous unsatisfactory repair works; and Case No: 302762 Determination Page 10 of 10  the Applicant is not entitled to compensation for non-financial loss due to the FSP’s handling of his claim.