Text of the determination
Determination
Case No: «reference_id» Determination Page 1 of 14
C ase number : 302665 30 June 2014
1 Overview
1.1 Dispute
The dispute concerns the business loan which the Financial Services Provider
(the FSP) provided to the Applicant to assist it in the purchase of the accounting
practice (the SH business). The issues involved in this dispute include whether:
There was a delay caused by the FSP in the approval of the Applicant’s
business loan;
The FSP engaged in maladministration in lending when it approved the
business loan;
The terms and conditions of the business loan approval were unjust or
unconscionable;
The Applicant breached any of the financial and/or non financial covenant
conditions;
The FSP misled the Applicant about the approval of a computer equipment
finance facility; and
The FSP provided genuine consideration to the Applicant’s request for
hardship assistance.
1.2 Issues and key findings
Did the FSP cause unreasonable delay in the loan approval?
The FSP did not unreasonably delay the settlement of the business loan. It was
unreasonable for the Applicant to expect a seven day turnaround from the time
when it first approached the FSP on 23 June 2008 for the preparation of request,
submission for approval, documentation preparation and the satisfaction of the
conditions of approval prior to settlement. A chronological table setting out key
dates in the loan application process is set out in section 3 below.
Should the FSP have provided the business loan?
The FSP acted as a diligent and prudent lender when it approved the business
loan for the Applicant. The request for finance was prepared on behalf of the
company by the director who was a qualified accountant and had been employed
by the SH business that the Applicant was purchasing.
Were the terms and conditions of the business loan approval unjust or
unconscionable?
The terms and conditions of the business loan were not unjust or unconscionable.
T he FSP’s approval conditions were deta iled in its offer letter and subsequent
Case No: 302665 Determination Page 2 of 14
variation letters to the Applicant prior to the preparation of documents and
advancement of the funds. The Applicant had the choice of either accepting or
declining the FSP ’ s offer and by accepting the FSP’s offer, t he Applicant agreed
to the terms and conditions of the loan offer.
Did the Applicant breach any of the financial and/or the non financial
covenant conditions?
The Applicant did breach one of the financial covenants and hence, there was as
“event in default” due to the Applicant not meeting the required interest cover ratio
for each financial half year (which was required to be kept at a minimum ratio of
3.5:1).
On 3 November 2011, the FSP issued the Applicant with a “Notice of Failure to
Perform” due to th e Applicant ’s failure to provide financial reports, satisfy the
financial covenants and other conditions. Both parties agree that the Applicant
was not in arrears on the business loan, however the business loan conditions
included financial and non financial covenants which had not been complied with.
Did the FSP mislead the Applicant about the computer finance approval ?
No, the FSP advised the Applicant on 21 June 2010 of its pre approved finance
for a total amount of $25,000 for computer equipment and a server.
Did the FSP comply with its obligations to assist the Applicant with its
financial difficulty?
The FSP made reasonable attempts to assist the Applicant in response to its
financial difficulty, and no compensation is payable in relation to this aspect of the
dispute.
1.3 Determination
The Determination is in favour of the FSP.
The FSP is not required to pay compensation to the Applicant.
In the circumstances, it is appropriate that within 30 days of the date of this
Determination the Applicant be given the opportunity to provide a realistic
repayment plan to the FSP in relation to the outstanding debts that will result in
the repayment of the debts within a reasonable timeframe, which is acceptable to
the FSP, or to refinance the loans.
If the Applicant is unable to provide a reasonable repayment plan as outlined
above, which is acceptable to the FSP within that 30 day period, then the FSP is
entitled to recommence recovery action once the file for this dispute is closed.
Case No: 302665 Determination Page 3 of 14
2 Reasons for Determination
2.1 Did the FSP cause unreasonable delay in the business loan
approval?
The FSP did not cause an unreasonable delay in the business loan approval
The Applicant and the vendor (the BH business vendor) first met with the FSP on
23 June 2008 to discuss the Applicant’s funding requirements for the purchase of
the BH business.
The FSP’s contemporaneous documents show that the first lending submission
was dated 3 July 2008 and was approved on 9 July 2008. However, the lending
submission required a number of amendments due to the loan term, required
valuations, the director’s life insurance assignment and due diligence
requirements. The Applicant accepted the FSP ’s “Variation Letter” on 17
September 2008 and the loan drawdown occurred on 25 November 2008. A
chronological table setting out key dates in the loan application process is set out
in section 3 below.
In making this Determination I have reviewed the FSP’s le nding file and lending
policy applicable at the time of the loan application. I have also taken into
account the advice of FOS’s Banking Specialist who has had extensive
experience in the banking and financial services industry. She regularly provides
FOS with advice about banking and financial services practice and procedure and
what constitutes good industry practice
I agree with my Banking Specialist ’s view that the Applicant ’ s expectation of “a
handover” date of the BH business to occur on 1 July 2008 was an unrealistic
expectation (in regard to the time required for the FSP to complete its approval
and documentation process) and did not accord with industry practice. The FSP
had to complete its assessment of the loan application, approve the request,
prepare the documents and to ensure that the conditions of approval were met
prior to advancement of the funds during the period in question. In particular I
note that:
The funding request discussion was seven days away from the end of the
financial year;
The approval required the valuation of the accounting practice;
The approval required the completion of a due diligence assessment of the
accounting practice;
The preparation of the Deed of Postponement was part of the FSP’s security
requirements. It detai led the Applicant’s and the vendor’s agreement that the
debt level owed to the vendor would not reduce below $300,000, without the
FSP’s consent ;
The assignment of the director’s life insurance policy was required; and
There was a refinance to a related legal entity of an existing investment loan
with another lender that required the valuation of the security property to be
conducted.
Case No: 302665 Determination Page 4 of 14
Based on the available information including the Banking Specialist’s comments ,
my view is that the FSP did not unreasonably delay the business loan approval
process.
2.2 Should the FSP have provided the business loan?
The FSP did not make an error when it provided the business loan
The FSP’s business loan assessment and approval was based on the information
prepared and supplied by the director who was a qualified accountant and had
been employed by the BH business for the last six years.
My Banking Specialist reviewed the FSP’s lending files and notes that the
financial information provided and used by the FSP in its debt servicing
calculations remained consistent from the original submission through to
settlement. Based on that information, the Applicant could service the business
loan. In the Banking Specialist’s view there were no “red flags” evident that would
have required the FSP to conduct any further enquiries about the information
provided. T he FSP’s approval of the business loan was within the FSP’s lending
criteria as set out in its policy and consistent with prudent lending practices.
Based upon the available i nformation in this dispute (inclusive of my Banking
Specialist’s views), I am satisfied that the Applicant could service the business
loan at the time of the loan application.
2.3 Were the FSP’s approval conditions of the business loan unjust or
unconscionable?
Credit risk assessment decisions about lending and security
I do not have the power under the FOS Terms of Reference to consider disputes
about a financial services provider’s credit risk assessment of a borrower or
security. Th is means that I cannot review the FSP’s lending criteria or any
precondition for the granting of the business loan, such as the FSP’s security
requirement to assign the director’s life insurance policy.
The business loan approval conditions were clearly expressed in the
business loan offers
The FSP’s letter of offer to the Applicant dated 1 August 2008 , and variation letter
dated 12 September 2008 and 12 December 2008, outlined approval conditions
that it required the Applicant to agree to - and meet - prior to the FSP providing
the loan funds. Among the conditions were its requirements relating to:
Security including the Deed of Postponement;
Financial reports;
Financial covenants including default with compliance with financial
covenants;
Conditions precedent; and
Other conditions.
Case No: 302665 Determination Page 5 of 14
The Applicant had an opportunity to consider the terms and conditions of the
offer. If the Applicant was in doubt about the meaning of those terms, then the
Applicant was able to obtain independent legal or financial advice. The FSP is not
the fiduciary of the Applicant and so was not obliged to provide advice about how
the Applicant should protect its interests.
As the relationship between the FSP and the Applicant was an ordinary
commercial one of lender and borrower, there was no special obligation imposed
upon the FSP to ensure the Applicant understood all aspects of the offer before
agreeing to it. If the Applicant had concerns about any aspect of the loan contract,
it was able to seek independent legal and financial ad vice from an independent
adviser. It was up to the Applicant to accept or reject the business loan offer.
The Deed of Postponement terms and conditions
The Applicant claims that the Deed of Postponement dated 25 November 2008
had terms and conditions that were unconscionable and unfair and placed the
Applicant in an impossible position of being able to satisfy both the FSP approval
conditions and its obligations under the vendor finance agreement. As noted
above, the Deed of Postponement was a document entered into between the
Applicant, the vendor and the FSP whereby both parties agreed not to reduce the
level of debt owing to the vendor below $300,000.
The elements considered by a court when assessing whether there has been
unconscionable conduct are generally:
Whether one party (the weaker party) at the relevant time suffered from a
special disadvantage or disability which affected their ability to protect their
own interests;
Whether the other party (the stronger party) must have known or should
reasonably be expected to have known of that disadvantage or disability at the
time;
Whether, acting on that knowledge, the stronger party took advantage of the
weaker party's disadvantage or disability in circumstances where it is
considered to be unconscionable for it to have done so; and.
Whether any undue influence, pressure or tactics were used by the lender. It
must be conduct of the lender that placed the consumer under pressure,
rather than just the prevailing circumstances.
The Applicant claims that the FSP was aware of the terms and conditions of a
third party agreement (the vendor agreement) between the Applicant and the
vendor, which required annual repayments of $60,000 over five years. Hence, it
says that the FSP was aware that the Applicant could not satisfy the Deed of
Postponement condition that the debt amount not reduce below $300,000.
The FSP files provided to FOS , including the meeting notes, do not indicate that
the FSP obtained a copy of the vendor agreement or was aware of the terms and
conditions prior to the business loan settlement.
I note that in October 2009, the annual review of the company facilities included a
request to allow a repayment up to $60,000 per annum in principal to the vendor
Case No: 302665 Determination Page 6 of 14
under the vendor agreement which the FSP declined until all covenants were met
and the ATO arrears were reduced.
In this case, the director of the Applicant and the vendor are professional
accountants and it would be reasonable to assume that they would have an
understanding of their obligations under an agreement. The vendor agreement
was a separate arrangement that did not involve the FSP.
In conclusion it has not been established that the FSP was aware of the terms
and conditions of the vendor agreement prior to the business loan offer and in any
event, it was a matter for the Applicant to assess the impact of the FSP ’s offer on
its private arrangements.
The Deed of Postponement is valid
On 25 November 2008, the Applicant (the borrower), the vendor (the Postponer)
and the FSP signed two versions of the Deed of Postponement. The difference
between the two versions of the Deed of Postponement was the amount of debt
referenced as being due to the vendor and to which both parties agreed would not
reduce below a certain level. In one of the deeds the amount was shown as $1.5
million and the other the amount shown was $300,000.
I am satisfied that the Deed of Postponement referencing the Applicant’s debt to
the vendor of $300,000 (being the amount of the vendor loan) is valid and the
other Deed of Postponement containing an incorrect figure could be rectified at
law. The Applicant entered into the deed to give the FSP a priority in repayment,
that is, the Applicant and the vendor agreed that the company’s debt to the
vendor would not be less than $300,000 without the FSP ’ s consent. Hence, the
Applicant and the vendor had to obtain the FSP’s consent to any repayment of the
vendor finance.
The Applicant is bound by the terms of the Deed of Postponement.
2.4 Did the Applicant breach any of the financial and/or the non
financial covenant conditions?
The Applicant breached the covenant conditions
The FSP’s correspondence to the Applicant shows that it first raised a financial
covenants breach on 1 December 2009 following receipt of the company’s June
2009 financial accounts. The FSP sent the company a “Notice of Event Default”
stating that the company’s 30 June 2009 financial accounts did not meet the
interest cover ratio requirement of a minimum ratio of 3.5:1. However, at this
stage the FSP did not propose to take any action in respect of the default but
reserved its right to take any action in the future.
The Applicant in its response to FOS dated 10 March 2014, said that the director
calculated that the interest cover ratio based on the 2009 financial accounts was
approximately 3:1 and acknowledged that it did “fall short” of the covenant, but
Case No: 302665 Determination Page 7 of 14
that it could be explained. At the time the Applicant discussed its concerns about
the interest cover ratio with the FSP.
O n 3 November 2011, the FSP issued the Applicant a “Notice of Failure to
Perform” (the notice) because the company had failed to meet the terms and
conditions of the business loan that required:
Financial reports to be provided within 30 days of request;
Financial covenants to maintain average debtor days with 70 days and the
minimum interest cover ratio at 3.5:1;
Provision of ATO Running Statements on a half yearly basis;
The debt level owing to the vendor was not to reduce below $300,000 as per
the Deed of Postponement.
On 8 February 2012, the FSP wrote to the Applicant to advise that the issues
identified in the notice had not been adequately addressed and requested that the
director contact it by 16 February 2012.
On 2 August 2012, the FSP issued the Applicant its “Demand” notice seeking
repayment of the business loan facilities.
On the basis of the available information the Applicant had breached the non
financial and other covenants. I note that the Applicant agrees that the interest
cover ratio was at 3.1:1 based on the June 2009 financial accounts and
accordingly was below the minimum ratio: The Applicant further agrees that it
provided the FSP with its June 2011 management accounts on 21 November
2011, which breached the required covenant period of within 30 days of the end
of the financial year.
2.5 Did the FSP mislead the company about the computer finance
approval?
A financial services provider has an obligation not to mislead a customer
The prohibition against misleading and deceptive conduct in relation to the
provision of financial services arises under the common law and section 12DA of
the Australian Securities and Investments Commission Act 2001 (Cth) (ASIC Act).
This section
provides:
“A corporation must not, in trade or commerce, engage in conduct in relation to financial
services that is misleading or deceptive or is likely to mislead or deceive.”
Investigating a misleading conduct claim
In order to consider the matter it is necessary to first establish whether the
financial services provider’s conduct was in fact misleading. Once this is
established then the remedy for misleading conduct is not to make the promise
come true. Instead, the question to be asked is how much worse off was the
Case No: 302665 Determination Page 8 of 14
Applicant as a result of relying on the representation, compared to the position it
would have been in had the misrepresentation not been made.
The FSP approved equipment finance and advised the Applicant
In this dispute the Applicant alleges the FSP misled it about the approval of the
computer equipment finance facility. Consequently the Applicant failed to pay Dell
computers when requested (using that facility) and the Applicant had to use its
overdraft facility which was at a higher annual interest rate for the payment.
The available information shows on 21 June 2010, the FSP advised the Applicant
of its pre approval of the computer equipment finance with a limit of $25,000.
The information provided by both parties supports the conclusion that the
equipment finance was approved and the Applicant was adequately advised of
that, but it appears that the Applicant did not proceed to use the funds. Hence the
Applicant has not established that the FSP misled it about the computer
equipment approval or availability of funds. The communications between the
parties is summarised below in section 3.
2.6 Did the FSP comply with its obligations to assist the Applicant
with its financial difficulty?
The FSP has obligations to assist a small business
The FSP has an obligation to assist a small business in financial difficulty.
Whether an FSP is able to provide ongoing assistance will be substantially
influenced by the ability of the small business to demonstrate its ongoing viability.
If the small business is unable to demonstrate ongoing viability based on
reasonably tested information, then I would not expect the FSP to accept further
risk. In such circumstances, the assistance required may be to provide a
reasonable time to refinance or work with the business to achieve an orderly
winding up of the business.
The FSP complied with its obligations before the FOS dispute was lodged
The Applicant was not experiencing financial difficulty in November 2011 when
the FSP issued notice of failure to perform and nor had the Applicant approached
the FSP for assistance in this regard. The business loan and business overdraft
were not in arrears. The notice of failure to perform issued was in November 2011
due to the Applicant’s contravention of the financial reports, financial covenants
and other conditions.
I am satisfied that the FSP’s offer letter and contract documents clearly outlined
the terms and conditions of the business loan facilities. I am also satisfied that as
a consequence of the Applicant being in breach of those terms, the FSP was
entitled to exercise its right to issue the Applicant with a notice of default.
A table setting out the assistance provided to the Applicant by the FSP during
2012 is contained in section 3.3 below.
Case No: 302665 Determination Page 9 of 14
Based on all of the available information in this dispute, I am satisfied that the
FSP complied with its obligations to assist the Applicant as a customer
experiencing financial difficulty before the FOS dispute was lodged.
Was the FSP entitled to issue its demand notice
I am satisfied that the FSP had put the Applicant on notice of a default under the
terms and conditions of its business loan initially on 1 December 2009, at which
point it reserved its right to take action in the future.
On 8 February 2012, the FSP wrote to the Applicant stating that further to its
Notice of Failure to Perform issued on 3 November 2011, that it was proceeding
with the recovery of the business loan facilities and the related investment loan
balances in full.
The FSP’s assessment of the Applicant’s facilities and those of the related group
entities, prior to the issuance of the performance notice states, among other
issues, that the FSP was concerned about:
The ATO arrears and that little progress had been made to address those
arrears over the previous two years;
An acceptable solution to the ATO arrears had not been identified;
Interest cover breaches;
Aged debtors; and
Deed of postponement threshold breach.
My Banking Specialist has advised that a lender does not look favo urably on
customers who have ATO arrears or debt. It is generally accepted good industry
practice and prudent lending to scrutinise a customer’s statutory payments
position. In this case the company’s ATO transaction statement shows the
balance as:
December 2008 – nil
December 2009 – nil
November 2011 - to approximately $150,000.
I agree with my Banking Specialist ’s view that it appears that the Applicant
appears to have made repayments of the vendor’s finance rather than the
commitments to the ATO.
The FSP’s demand notice dated 2 August 2012 was sent to the Applicant after
the FSP worked with the Applicant over an extended period to allow it to refinance
or otherwise repay its debts.
Based on all the available information I am satisfied the FSP was entitled to issue
its demand when it did.
I note that FOS cannot review the customer service issues raised by the Applicant
as it does not have the power to consider disputes about the general level of
service provided by an FSP. We consider disputes relating to customer service
are more appropriately dealt with by the FSP itself. This is because the level of
customer service is influenced by the FSP’s policy on a number of issues such as
staff levels and training.
Case No: 302665 Determination Page 10 of 14
2.7 Liability for the outstanding debts
As at 17 June 2014, the Applicant’s balance, arrears and last payment made
since the lodging of the dispute with FOS were:
The business loan $208,738.29 with arrears of $35,556.89 with a
payment of $3,950.24 made on 25 March 2013 and on 29 May
2014;
The business overdraft $29,715.05 with nil arrears and the last
payment of $5,000 was made on 19 June 2014.
The related entity investment loan balance was $367,638.09 with $25,422.12 and
with a payment of $4,650.47 on 27 December 2013 and on 25 February 2014.
In these circumstances, it is appropriate that within 30 days of the date of this
Determination the Applicant be given the opportunity to provide a realistic
repayment plan to the FSP in relation to the outstanding debts that will result in
the repayment of the debts within a reasonable timeframe, which is acceptable to
the FSP, or to refinance the loans.
If the Applicant is unable to provide a reasonable repayment plan as outlined
above which is acceptable to the FSP, then the FSP is entitled to recommence
recovery action once our file is closed.
Case No: 302665 Determination Page 11 of 14
3 Supporting information
3.1 Key dates in the application process
Date Action
23 June 2008 Applicant emails the FSP’s representative to thank
her for meeting with them. It attache d copies of the
business:
o Aged debtors report;
o Last six months working account bank
statements;
o Company extract;
o ATO registrations.
3 July 2008 FSP credit memorandum shows approval of the
facilities to:
o The Applicant to purchase the business
for a cost of $600,000. The FSP was to
provide funding of $450,000 consisting
of two business loans and vendor terms
of $150,000;
Approval was subject to among other conditions of :
o The valuation of the business being
purchased not to be less than $600,000;
o Confirmation of insurance cover for the
director to a value a value of not less
than $600,000 be assigned to the FSP;
o The Applicant could not raise any
further outside borrowing without the
FSP’s knowledge and consent;
o To provide financial statements within
30 days of request;
o The Applicant interest cover for each
financial half year not to be less than
3.5:1;
o The Applicant was to maintain average
debtor days within 70 days.
29 July 2008 The Applicant’s business loan was reduced to
$300,000 due to the Applicant ’ s request to change
the approval condition of the business valuation to a
“due diligence on the practice prior to settlement”.
The vendor loan was also increased to $300, 000
and was reflected in the Deed of Postponement.
19 August 2008 T he FSP sends the director the due diligence
questions in anticipation of their meeting.
29 September 2008 The FSP’s “Due Diligence Ready Reckoner” was
completed.
Case No: 302665 Determination Page 12 of 14
12 November 2008 The FSP accepted the director’s life insurance
assignment.
21 November 2008 The director signed the life insurance assignment
document.
12 December 2008 The FSP approved an overdraft facility of $30,000
3.2 Summary of the computer finance approval correspondence
Date Action
21 June 2010 The FSP’s representative emails the Applicant to say
it can split the equipment finance limit of $25,000
into two contracts. One contract for $7,500 to be
completed now and the remaining amount for the
server to be financed in three months time.
23 June 2010 The Applicant emails Dell computers with the FSP’s
representative contact details in relation to the
computer equipment finance.
25 June 2010 The FSP’s representative emails the Applicant to say
that she has forwarded a letter to Dell confirming
finance totalling $25,000 has been approved.
20 August 2010 The FSP emails the Applicant seeking an update on
a number of matters including as to whe ther it was
going to proceed with the computer equipment
finance.
3.3 Table of assistance provided to the Applicant
Date Action
21 February 2012 The FSP’s manager (the manager) emails the
Applicant referring to their meeting of the previous
da y. The manager says that t he FSP will continue to
reserve its rights in relation to the existing defaults
and will defer taking any further action until 7 March
2012 to allow time for the App licant written proposal
as to why the FSP should not proceed with it s
decision to sever the relationship. It further notes
that the business loan arrears were $1,079.73
8 March 2012 The director send s the manager the Applicant’s
financial information up until t he end of December
2011.
9 and 19 March 2012 The manager emails re the outstanding arrears.
29 March 2012 The manager emails the director that the business
loan arrears have been cleared but the related
Case No: 302665 Determination Page 13 of 14
investment loan was in arrears by $10,893.75. He
al so says that the FSP has declined his request to
retain the business loan facilities with it due to the
ongoing arrears and the previous issues identified.
He requests that he be provide d with the Applicant ’s
written intentions (within 7 days) as to how th e
facilities would be repaid otherwise he will issue
demands in relation to the existing defaults.
29 March 2012 The director emails the manager to say that he will
pay $3,200 with the balance of the arrears to be
repaid by early the following week.
The manager emails him back to say that the above
won’t change the FSP’s requirement for severing the
relationship.
The director responds to say he was “aware of that”
and he will commence investigating other options.
17 March 2012 The FSP emails details of t he arrears amount and
ask for a repayment proposal and for an update on
the refinance of the facilities.
2 July 2012 The manager sends the director an email saying it
has not received a response to its above email and if
he does not respond by 9 July 2012 , it will take
action in relation to the previously flagged default.
17 September 2012 The director emails the FSP to say that he has had
positive feedback on relation to its refinancing
request with another lender.
18 September 2012 The director emails the FSP to say that he is working
to finalise the refinance with the other lender. He
also says he does not understand how it got to this
situation over “some very minor breaches” and asks
if there is any avenue for the FSP to review its
position and that he can’t rule lodging a complaint
with FOS.
2 October 2012 The FSP ’s representative asks whether there are
any updates on the refinance. He also says that he
can refer the matter for an independent review to an
FSP customer Advocate and the Applicant has the
option of lodging a FOS dispute.
11 October 2012 The director wrote to the FSP’s customer advocate
outlining its concerns and asking that:
o The Applicant’s situation be
independently reviewed as to the FSP’s
treatment of its account which it
believes has not been fair or in
accordance with its policy;
o Provide it with sufficient additional time
for the refinance to proceed.
12 October 2012 The customer advocate emails the director referring
Case No: 302665 Determination Page 14 of 14
to their recent conversation and her understanding
that:
o His main request was to place the
enforcement proceeding on hold and to
provide the Applicant with additional
time to obtain refinance. As well as a
request to investigate customer service
issues, the settlement of the loan in
2008 and the loan struc ture;
o In her view the FSP had acted
reasonably in commencing enforcement
proceedings and in providing him an
extension in order to finalise his
obligations;
o She will investigate the issues raised by
the Applicant but will not be
recommending that the enfor cement
action be suspended;
o The Applicant will lodge a dispute with
FOS.
24 October 2012 The Applicant lodged dispute with FOS.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.