Determination 302191

Reimbursement of drainage work the applicant undertook on the FSP's suggestion

FirmFinancial Firm (Unknown - Insurer)
Decided2013-03-06
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$2,500
Non-financial loss—
Amount claimed$5,000
SourceAFCA PDF

Summary

After an earlier FOS dispute, the applicant undertook $5,000 of drainage work that the FSP's expert had suggested, and a later engineer's report called the work totally erroneous. The Ombudsman reviewed the earlier outcome on new evidence and ordered the FSP to pay 50% of the cost, $2,500, without interest.

New engineering evidence arising after the Recommendation changed the nature of the drainage issue, and it would be unfair to let the earlier outcome stand, so costs were shared equally.

Issues

Subjects and remedies

home or building damagepay compensation

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 302191 Determination Page 1 of 7 Case number: 302191 General Insurance - Domestic Insurance - Home Building - FSP Decision 31 January 2013 Background 1. This dispute relates to water damage at the Applicant’s property. The Financial Services Provider (FSP), as the insurer of the property at the time of the damage, undertook a number of assessments and covered some of the damage. Some aspects of the damage claimed was refused on the basis the loss was not covered by the policy. 2. The disputed damage was the subject of a Recommendation by the Service (238268), where after reviewing a variety of submissions and expert reports, the case manager made the following recommendation: “On the basis of the available information I recommend that:  The FSP has no obligation to reimburse the costs of drainage work at the property.  The FSP should appoint a new engineer to review the history of the claim and inspect the property and provide a report on any damage to the property from moisture and whether the leaking stormwater pipe near the media room and leaking bath pipe were the sole causes of the damage.  The conclusions of the report will dictate the FSP liability, in accordance with the comments in paragraph 61 of this Recommendation.  The FSP liability with relation to furniture will be based on the findings of the engineer’s report, in accordance with paragraph 64 of this Recommendation.  The FSP has no liability with relation to compensation.” 3. Following the acceptance of the Recommendation by both parties, the FSP appointed an engineer, who reported the remaining issues at the property did not relate to an insured event. 4. However, the engineer also reported that the drainage work that had been done at the property was not required and could have had no affect on the moisture problems. 5. Following the post-Recommendation engineering report, the FSP refused the remainder of the claim on the basis it had complied with the Determination Case No: 302191 Determination Page 2 of 7 Recommendation and there was no evidence an insured event caused the loss. The FSP also made a payment of $3,905 towards the cost of rectifying exploratory damage caused during the post- Recommendation engineer’s inspection. 6. The Applicant was not satisfied with the outcome, maintaining the loss was caused by the stormwater pipe. Further, she noted the engineer’s comments that the drainage work was unnecessary. She also stated the FSP’s engineer said he would undertake the rectification works of the damage caused during his inspection and the $3,905 cash settlement from the FSP did not cover the cost. 7. The FSP maintained it had complied with the Recommendation and the matter was settled. 8. Following a review of the new information, the Service advised the Applicant that the Recommendation had been complied with and therefore, the FSP was not required to cover further damage to the building or contents under the claim. 9. However, after reviewing the post- Recommendation engineering report’s comments on the drainage issue, the case manager contacted the FSP to advise that had this information been available at the time of making the Recommendation, the decision on the drainage issue may well have been different. 10. The case manager invited the FSP to review this aspect of the dispute again in the hope of a mutually agreed resolution. The FSP advised it had complied with the Recommendation and the Recommendation stated it was not required to reimburse the Applicant for the drainage work. 11. The issues was referred to the Service’s General Insuranc e Legal Officer, who wrote to the FSP to advise that the Operational Guidelines to the Terms of Reference allow the Service decision to be reviewed if new evidence comes to light which in fairness, may require an issues to looked at again. The Legal Officer was of the view, that the new evidence from the engineer warranted a further review. Issue 12. Whether the FSP is required to reimburse the Applicant for drainage work at the property, in light of the new evidence from the engineer. Reasons for decision 13. As noted, this matter has been referred for an Ombudsman Determination to review the issue of the whether the Applicant is entitled to reimbursement of the cost of attending to drainage work that the FSP’s expert advised should be completed to address the moisture issues at the property. Case No: 302191 Determination Page 3 of 7 14. I note this Determination will only address the drainage issue. The FSP appointed an engineer, in line with the Recommendation and the engineer concluded the moisture issues arose from factors that were not covered under the policy. 15. Accordingly, the FSP complied with the Recommendation and is not required to offer further indemnity under the policy for any other issues raised in the Recommendation. FOS’s Operational Guidelines 16. I consider the following Operational Guidelines to the FOS Terms of Reference apply to this dispute: “ Disputes previously dealt with by FOS (5.1k)) FOS cannot consider a Dispute where: ■ the Dispute: o raises the same events and facts; and o is brought by the same Applicant ■ a s a Dispute “dealt with” earlier by FOS or a Predecessor Scheme; and ■ any additional events and facts raised in the Dispute are not sufficient to warrant FOS’s consideration of the Dispute. The reference to a Dispute “dealt with” earlier is explained below. Additional events and facts raised in a Dispute that go beyond this exclusion and which are sufficient to warrant FOS’s consideration of the Dispute arise where: ■ the additional events and facts were central to the outcome of the Dispute dealt with earlier (rather than surrounding or peripheral circumstances); and ■ it would not be fair in all the circumstances to allow the outcome of the earlier Dispute to stand.” Summary of Previous Submissions and Recommendation on the drainage issue 17. The Applicant said in the Dispute Form for dispute 238268 that: “…The insurance company would no longer cover my media room until I performed the work recommended by the engineer. I argued with them that this is not what I wanted … I had no choice but to perform the work on my backyard at a cost of $5000.00 to my family. The 1 metre trench was dug. This did not fix the problem…” 18. At the time of the original dispute, the Applicant sought the following: “Repayment of the costs of the work performed in my backyard that were completely unnecessary.” Case No: 302191 Determination Page 4 of 7 19. The Recommendation made by the case manager on 17 November 2011, stated: “42. In reviewing the evidence, I accept the FSP’s system notation gives th e impression the drainage work would need to be done to prevent further problems. 43. However, the notation also gives the impression the matter was being cash settled so the Applicant could attend to the matter in her own time. The notation does not indicate the Applicant was being forced to do the drainage work before being paid.” 20. The Recommendation further dealt with other issues raised by the Applicant in the Dispute Form. Both parties accepted the Recommendation. As a result, the FSP appointed an eng ineer to inspect the Applicant’s property. 21. The engineer’s report dated 15 February 2012 , made a number of findings, including: “Notwithstanding the findings and the request from the engineer for, the grading of the yard of the rear of the property being undertaken, this is totally erroneous as the property catchment area is approximately 12 metres by 10 metre and that this building slab is between 150 – 160 mm above the paving to the external of the building. Not only this, the brick as installed in this job (evident by the remaining bricks of on site stacked) these are the 10 hole astral bricks and these bricks are not capable of undertaking rising damp due to their construction and porous nature.” (sic) bolding my emphasis 22. Having reviewed the file, my conclusion is that there is only one issue to consider: the drainage issue. The other issues were dealt with and there is no reason to revisit these matters given the engineer has concluded they do not relate to an insured event. 23. The drainage issue is different given the engineer’s report obtained subsequent to the Recommendation. This report categorised the work as “totally erroneous”. 24. The Recommendation found there was “no tangible evidence the Applicant was forced to do the work before being paid”. However, the current issue with respect to the drainage issue is now different in nature. 25. The Recommendation said: “39 . The engineer suggested that rather than undertaking full rectification works, a trench should be dug and left open (if safe) to avoid further expenses if it eventuated that the drainage is not the cause of loss. 40. The notation from the FSP’s claim syst em indicates the Applicant was called to advise the claim should be refused due to seepage but she would be cash settled for repairs to the media room so she could attend to the drainage and repairs in her own time. … 46. In considering all the evidence, I am not persuaded the FSP is required to reimburse the Applicant $5,000 for the repairs. It would seem the Case No: 302191 Determination Page 5 of 7 work will have improved the general drainage at the property and there is no tangible evidence the Applicant was forced to do the work before being paid.” 26. Had it not been for the recent engineer’s report which categorically stated the drainage work was “totally erroneous”, the dispute would be finalised. 27. I note the FSP says in its most recent submission it is not responsible for any costs the Applicant incurred in relation to the drainage matter. However, there are aspects of this which should be examined in order to ascertain whether the FSP’s contention is correct. 28. It is clear the Applicant undertook the work as a r esult of the FSP’s suggestion. As stated in the Dispute Form, the Applicant “argued with them [the FSP] that this is not what [she] wanted”, but she ultimately found she “had no choice but to perform the work in [her] backyard”. 29. The engineer has introduced important information which was not available to either party at the time the Recommendation was made. 30. Further, the Recommendation considered the issue without the benefit of the recent engineer’s report. The Recommendation considered the completed work was seemingly an improvement to the general drainage at the property. Since there is new evidence that this is no longer the situation, the issue has therefore changed in nature due to the engineer’s report. 31. In considering the comments made in the new engi neer’s report, I am persuaded that the drainage work was “totally erroneous” and therefore the Applicant has been put in a situation where she has undertaken works at the property at a cost of $5,000 that were not required. 32. The FSP has argued that it provided the report suggesting the work should be done, but the Applicant was not forced to undertake the work and she was cash settled with no conditions attached and therefore had every opportunity to consider whether the work was required. 33. In my view, this argument cannot be sustained. The comments from the FSP’s own system notations, reportedly dated 17 May 2010, state: “L/ADUSTER has recommended we discuss a cash settlement with the insured as the rectification of the drainage around the house will be the insured’s responsibility. Therefore once the repairs have been done to the drainage the insured can carry out repairs to the media room… … PHONED and discussed this claim with insured, i advised insured the claim should have been one for decline as we do not cover rising damp, however as repairs have been authorised we will honour the claim and c/settle so insured can carry out rectification to the drainage around the house … …I advised the other offer would be to carry out repairs once she has updated the drainage .” (sic) bolding my emphasis Case No: 302191 Determination Page 6 of 7 34. In my view these notations clearly indicate the Applicant was given every impression the FSP required her to carry out the suggested drainage work. 35. In reviewing the Recommendation, it dealt with the issue of whether the FSP forced the Applicant to undertake the drainage work before settling the claim. The Service’s case manager concluded the Applicant was not forced to do the work before the claim was settled, but did draw a similar conclusion to myself, that the FSP gave every impression the work needed to be done. 36. In considering the drainage issue, the FSP relied on expert opinion and therefore at the time, I believe the FSP acted reasonably in communicating the need to undertake this work to the Applicant. 37. However, the engineer after the Recommendation, with no prompting, has categorically stated the work was “totally erroneous” and in consideration of the fact the Applicant has been disputing this issue from the beginning, I am persuaded that in the circumstances that the Applicant is entitled to some reimbursement for this work. 38. After the Recommendation, the FSP was contacted and given the opportunity to try and settle this issue without a further formal decision from the Service. The FSP chose not to negotiate on the issue, leaving the Service no choice but to forward the matter for determination. Not to do so would leave the Applicant with a decision that in my opinion is essentially unfair on the basis of the new evidence that came to light after the Recommendation. 39. I am persuaded that the Applicant has relied upon the FSP statements and carried out the work based on these statements to her detriment. 40. The Applicant has paid $5,000 to have the drainage work performed. The engineer’s opinion now relied upon says this work was totally erroneous. I recognise it is only an opinion and no doubt differing opinions could be obtained given the earlier reports. 41. In the circumstances I do not believe it would be fair to find the FSP liable for full reimbursement costs. I consider it fair in the circumstances that each party bear 50% of the cost of the drainage work. As the cost was $5,000 then the FSP would be responsible for a contribution of $2,500 towards those costs. Determination 42. On the basis of the available information I determine the FSP reimburse the Applicant $2,500. Case No: 302191 Determination Page 7 of 7 43. I further determine that interest is not payable, given the unusual circumstances of the dispute and that the new information did not come to light until after the Recommendation was issued.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.