Home / Financial Firm (Unknown - Insurer) / Determination 302191
Determination 302191
Reimbursement of drainage work the applicant undertook on the FSP's suggestion
Summary
After an earlier FOS dispute, the applicant undertook $5,000 of drainage work that the FSP's expert had suggested, and a later engineer's report called the work totally erroneous. The Ombudsman reviewed the earlier outcome on new evidence and ordered the FSP to pay 50% of the cost, $2,500, without interest.
New engineering evidence arising after the Recommendation changed the nature of the drainage issue, and it would be unfair to let the earlier outcome stand, so costs were shared equally.
Issues
- Claim denial primary · upheld
“the FSP reimburse the Applicant $2,500”
- Misleading conduct secondary · not upheld
“I believe the FSP acted reasonably in communicating the need to undertake this work to the Applicant”
Subjects and remedies
home or building damagepay compensation
Text of the determination
Case No: 302191 Determination Page 1 of 7
Case number: 302191
General Insurance - Domestic Insurance - Home Building - FSP Decision
31 January 2013
Background
1. This dispute relates to water damage at the Applicant’s property. The
Financial Services Provider (FSP), as the insurer of the property at the time
of the damage, undertook a number of assessments and covered some of
the damage. Some aspects of the damage claimed was refused on the basis
the loss was not covered by the policy.
2. The disputed damage was the subject of a Recommendation by the Service
(238268), where after reviewing a variety of submissions and expert reports,
the case manager made the following recommendation:
“On the basis of the available information I recommend that:
The FSP has no obligation to reimburse the costs of drainage work at the
property.
The FSP should appoint a new engineer to review the history of the claim
and inspect the property and provide a report on any damage to the
property from moisture and whether the leaking stormwater pipe near the
media room and leaking bath pipe were the sole causes of the damage.
The conclusions of the report will dictate the FSP liability, in accordance
with the comments in paragraph 61 of this Recommendation.
The FSP liability with relation to furniture will be based on the findings of
the engineer’s report, in accordance with paragraph 64 of this
Recommendation.
The FSP has no liability with relation to compensation.”
3. Following the acceptance of the Recommendation by both parties, the FSP
appointed an engineer, who reported the remaining issues at the property
did not relate to an insured event.
4. However, the engineer also reported that the drainage work that had been
done at the property was not required and could have had no affect on the
moisture problems.
5. Following the post-Recommendation engineering report, the FSP refused
the remainder of the claim on the basis it had complied with the
Determination
Case No: 302191 Determination Page 2 of 7
Recommendation and there was no evidence an insured event caused the
loss. The FSP also made a payment of $3,905 towards the cost of rectifying
exploratory damage caused during the post- Recommendation engineer’s
inspection.
6. The Applicant was not satisfied with the outcome, maintaining the loss was
caused by the stormwater pipe. Further, she noted the engineer’s comments
that the drainage work was unnecessary. She also stated the FSP’s
engineer said he would undertake the rectification works of the damage
caused during his inspection and the $3,905 cash settlement from the FSP
did not cover the cost.
7. The FSP maintained it had complied with the Recommendation and the
matter was settled.
8. Following a review of the new information, the Service advised the Applicant
that the Recommendation had been complied with and therefore, the FSP
was not required to cover further damage to the building or contents under
the claim.
9. However, after reviewing the post- Recommendation engineering report’s
comments on the drainage issue, the case manager contacted the FSP to
advise that had this information been available at the time of making the
Recommendation, the decision on the drainage issue may well have been
different.
10. The case manager invited the FSP to review this aspect of the dispute again
in the hope of a mutually agreed resolution. The FSP advised it had
complied with the Recommendation and the Recommendation stated it was
not required to reimburse the Applicant for the drainage work.
11. The issues was referred to the Service’s General Insuranc e Legal Officer,
who wrote to the FSP to advise that the Operational Guidelines to the Terms
of Reference allow the Service decision to be reviewed if new evidence
comes to light which in fairness, may require an issues to looked at again.
The Legal Officer was of the view, that the new evidence from the engineer
warranted a further review.
Issue
12. Whether the FSP is required to reimburse the Applicant for drainage work at
the property, in light of the new evidence from the engineer.
Reasons for decision
13. As noted, this matter has been referred for an Ombudsman Determination to
review the issue of the whether the Applicant is entitled to reimbursement of
the cost of attending to drainage work that the FSP’s expert advised should
be completed to address the moisture issues at the property.
Case No: 302191 Determination Page 3 of 7
14. I note this Determination will only address the drainage issue. The FSP
appointed an engineer, in line with the Recommendation and the engineer
concluded the moisture issues arose from factors that were not covered
under the policy.
15. Accordingly, the FSP complied with the Recommendation and is not required
to offer further indemnity under the policy for any other issues raised in the
Recommendation.
FOS’s Operational Guidelines
16. I consider the following Operational Guidelines to the FOS Terms of
Reference apply to this dispute:
“ Disputes previously dealt with by FOS (5.1k))
FOS cannot consider a Dispute where:
■ the Dispute:
o raises the same events and facts; and
o is brought by the same Applicant
■ a s a Dispute “dealt with” earlier by FOS or a Predecessor Scheme; and
■ any additional events and facts raised in the Dispute are not sufficient to
warrant FOS’s consideration of the Dispute.
The reference to a Dispute “dealt with” earlier is explained below.
Additional events and facts raised in a Dispute that go beyond this exclusion
and which are sufficient to warrant FOS’s consideration of the Dispute arise
where:
■ the additional events and facts were central to the outcome of the Dispute
dealt with earlier (rather than surrounding or peripheral circumstances);
and
■ it would not be fair in all the circumstances to allow the outcome of the
earlier Dispute to stand.”
Summary of Previous Submissions and Recommendation on the drainage
issue
17. The Applicant said in the Dispute Form for dispute 238268 that:
“…The insurance company would no longer cover my media room until I
performed the work recommended by the engineer. I argued with them that
this is not what I wanted … I had no choice but to perform the work on my
backyard at a cost of $5000.00 to my family. The 1 metre trench was dug.
This did not fix the problem…”
18. At the time of the original dispute, the Applicant sought the following:
“Repayment of the costs of the work performed in my backyard that were
completely unnecessary.”
Case No: 302191 Determination Page 4 of 7
19. The Recommendation made by the case manager on 17 November 2011,
stated:
“42. In reviewing the evidence, I accept the FSP’s system notation gives th e
impression the drainage work would need to be done to prevent further
problems.
43. However, the notation also gives the impression the matter was being
cash settled so the Applicant could attend to the matter in her own time.
The notation does not indicate the Applicant was being forced to do the
drainage work before being paid.”
20. The Recommendation further dealt with other issues raised by the
Applicant in the Dispute Form. Both parties accepted the Recommendation.
As a result, the FSP appointed an eng ineer to inspect the Applicant’s
property.
21. The engineer’s report dated 15 February 2012 , made a number of findings,
including:
“Notwithstanding the findings and the request from the engineer for, the
grading of the yard of the rear of the property being undertaken, this is totally
erroneous as the property catchment area is approximately 12 metres by 10
metre and that this building slab is between 150 – 160 mm above the paving
to the external of the building.
Not only this, the brick as installed in this job (evident by the remaining bricks
of on site stacked) these are the 10 hole astral bricks and these bricks are not
capable of undertaking rising damp due to their construction and porous
nature.” (sic) bolding my emphasis
22. Having reviewed the file, my conclusion is that there is only one issue to
consider: the drainage issue. The other issues were dealt with and there is
no reason to revisit these matters given the engineer has concluded they do
not relate to an insured event.
23. The drainage issue is different given the engineer’s report obtained
subsequent to the Recommendation. This report categorised the work as
“totally erroneous”.
24. The Recommendation found there was “no tangible evidence the Applicant
was forced to do the work before being paid”. However, the current issue
with respect to the drainage issue is now different in nature.
25. The Recommendation said:
“39 . The engineer suggested that rather than undertaking full rectification
works, a trench should be dug and left open (if safe) to avoid further
expenses if it eventuated that the drainage is not the cause of loss.
40. The notation from the FSP’s claim syst em indicates the Applicant was
called to advise the claim should be refused due to seepage but she
would be cash settled for repairs to the media room so she could attend
to the drainage and repairs in her own time.
…
46. In considering all the evidence, I am not persuaded the FSP is required
to reimburse the Applicant $5,000 for the repairs. It would seem the
Case No: 302191 Determination Page 5 of 7
work will have improved the general drainage at the property and there
is no tangible evidence the Applicant was forced to do the work before
being paid.”
26. Had it not been for the recent engineer’s report which categorically stated
the drainage work was “totally erroneous”, the dispute would be finalised.
27. I note the FSP says in its most recent submission it is not responsible for any
costs the Applicant incurred in relation to the drainage matter. However,
there are aspects of this which should be examined in order to ascertain
whether the FSP’s contention is correct.
28. It is clear the Applicant undertook the work as a r esult of the FSP’s
suggestion. As stated in the Dispute Form, the Applicant “argued with them
[the FSP] that this is not what [she] wanted”, but she ultimately found she
“had no choice but to perform the work in [her] backyard”.
29. The engineer has introduced important information which was not available
to either party at the time the Recommendation was made.
30. Further, the Recommendation considered the issue without the benefit of the
recent engineer’s report. The Recommendation considered the completed
work was seemingly an improvement to the general drainage at the property.
Since there is new evidence that this is no longer the situation, the issue has
therefore changed in nature due to the engineer’s report.
31. In considering the comments made in the new engi neer’s report, I am
persuaded that the drainage work was “totally erroneous” and therefore the
Applicant has been put in a situation where she has undertaken works at the
property at a cost of $5,000 that were not required.
32. The FSP has argued that it provided the report suggesting the work should
be done, but the Applicant was not forced to undertake the work and she
was cash settled with no conditions attached and therefore had every
opportunity to consider whether the work was required.
33. In my view, this argument cannot be sustained. The comments from the
FSP’s own system notations, reportedly dated 17 May 2010, state:
“L/ADUSTER has recommended we discuss a cash settlement with the
insured as the rectification of the drainage around the house will be the
insured’s responsibility. Therefore once the repairs have been done to the
drainage the insured can carry out repairs to the media room…
…
PHONED and discussed this claim with insured, i advised insured the claim
should have been one for decline as we do not cover rising damp, however as
repairs have been authorised we will honour the claim and c/settle so
insured can carry out rectification to the drainage around the house …
…I advised the other offer would be to carry out repairs once she has
updated the drainage .” (sic) bolding my emphasis
Case No: 302191 Determination Page 6 of 7
34. In my view these notations clearly indicate the Applicant was given every
impression the FSP required her to carry out the suggested drainage work.
35. In reviewing the Recommendation, it dealt with the issue of whether the FSP
forced the Applicant to undertake the drainage work before settling the claim.
The Service’s case manager concluded the Applicant was not forced to do
the work before the claim was settled, but did draw a similar conclusion to
myself, that the FSP gave every impression the work needed to be done.
36. In considering the drainage issue, the FSP relied on expert opinion and
therefore at the time, I believe the FSP acted reasonably in communicating
the need to undertake this work to the Applicant.
37. However, the engineer after the Recommendation, with no prompting, has
categorically stated the work was “totally erroneous” and in consideration of
the fact the Applicant has been disputing this issue from the beginning, I am
persuaded that in the circumstances that the Applicant is entitled to some
reimbursement for this work.
38. After the Recommendation, the FSP was contacted and given the
opportunity to try and settle this issue without a further formal decision from
the Service. The FSP chose not to negotiate on the issue, leaving the
Service no choice but to forward the matter for determination. Not to do so
would leave the Applicant with a decision that in my opinion is essentially
unfair on the basis of the new evidence that came to light after the
Recommendation.
39. I am persuaded that the Applicant has relied upon the FSP statements and
carried out the work based on these statements to her detriment.
40. The Applicant has paid $5,000 to have the drainage work performed. The
engineer’s opinion now relied upon says this work was totally erroneous. I
recognise it is only an opinion and no doubt differing opinions could be
obtained given the earlier reports.
41. In the circumstances I do not believe it would be fair to find the FSP liable for
full reimbursement costs. I consider it fair in the circumstances that each
party bear 50% of the cost of the drainage work. As the cost was $5,000
then the FSP would be responsible for a contribution of $2,500 towards
those costs.
Determination
42. On the basis of the available information I determine the FSP reimburse the
Applicant $2,500.
Case No: 302191 Determination Page 7 of 7
43. I further determine that interest is not payable, given the unusual
circumstances of the dispute and that the new information did not come to
light until after the Recommendation was issued.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.