Text of the determination
Case No: 299097 Determination Page 1 of 12
Case number: 299097
General Insurance – Domestic Insurance – Home Buildings and Contents –
Accidental damage cover – Policy exclusion – Flood – Section 35 Insurance
Contracts Act 1984
10 April 2013
Background
1. The Applicant has legal representation. For clarity and convenience, the
submission of the Applicant and her representative will together be referred to
as „the Applicant‟.
2. The Applicant insured her home building and contents under a Personal
Insurance Policy against accidental damage for $280,900 and $69,960
respectively. The policy incepted on 5 November 2004 and had been renewed
annually to 5 November 2011. In April 2009, it was amended to cover the
Applicant‟s home in Karalee, Queensland.
3. On 11 January 2011, the Ap plicant‟s home was inundated with water following
severe weather events in Queensland. Major damage was caused to the
building and contents.
4. Following investigation of the claim, the FSP refused liability on the ground the
loss was caused by flood, which is an exclusion under the policy.
5. The Applicant disputes the decision and seeks to have her loss covered under
the policy.
Summary of Applicant‟s Position
6. The Applicant understood that she was covered for all water damage while she
was residing in New South Wales but when she moved to Queensland her
policy cover was reduced without her being fully informed of this fact.
7. The Applicant maintains the FSP has failed to act with utmost good faith and
that the policy which was arranged through a broker who was an agent of the
FSP was arranged in the knowledge of the location of the Applicant‟s property,
that the agent would have been aware of the possibility of the property being
flooded and the agent failed to clearly inform the Applicant that the policy did
not include flood cover.
Determination
Case No: 299097 Determination Page 2 of 12
8. Further, the Applicant maintains the FSP has failed in its duty to clearly inform
the Applicant of the nature and extent of the relevant limitations and exclusions
relating to flood as required by section 35 of the Insurance Contracts Act 1984
(the Act).
9. The Applicant maintains that the policy does not adequately notify of the flood
exclusion.
10. Further, the Applicant submits that it is clear that her property was inundated as
a result of „storm or rainwater‟, rather than as the FSP contends, „flood‟. There
has been loss or damage to her property due to an event/s covered by her
policy and the FSP is liable to pay the total claim made by her.
11. At about 1630 hours on 11 January 2011, the Applicant and her family left their
property. At that time the water was just lapping a shed on the property. They
were prompted to leave by a flash flood warning by the SES. When they left her
property it was still raining heavily and it was difficult to see out of the car‟s
windscreen.
12. At about 1830 hours, a neighbour contacted her and informed her that water
was flowing through the windows of her home. Neighbours witnessed the
event and stated that water was running through her property and down to the
Bremer River from properties above her. After a time the water stopped moving
and started to back-up.
13. The Applicant submits that the water that affected her property was run-off from
storms and rain that had been affecting the area until about 3.00pm on 11
January 2011 and was running down off towards the Bremer River.
14. As a result, the Applicant contends that she should be compensated for the
damage caused by this water.
15. In respect of WRM‟s site specific hydrology report dated 10 October 2012, the
Applicant rejects its conclusions as the hydrologist interviewed a neighbour „F‟
whose home is 3-4 metres higher than hers and that residence was inundated
approximately 7 hours later on the Wednesday morning (12 January 2011)
whereas the Applicant‟s home was affected on the Tuesday. This is not an
acceptable report to have been submitted for the Applicant‟s property especially
when the dispute now seems to be about the timing of the damage to the
Applicant‟s home.
Summary of FSP‟s Position
16. On 5 November 2004, the Applicant entered into the Personal Insurance Policy
while she resided in New South Wales. On 8 April 2009, the Applicant
amended the cover to include Accidental Damage for a newly built home
situated in Queensland at the insured address.
17. On 12 January 2011, the Applicant submitted a claim for building and contents
damage arising from the Queensland floods.
Case No: 299097 Determination Page 3 of 12
18. The FSP appointed a loss adjuster to assess the damage and carry out a site
inspection. The loss adjuster reported that the cause of the damage was „flood‟.
19. The Applicant was present during the inundation and water first started entering
her property at about 4.30pm on 11 January 2011. The peak level of inundation
was 8 metres and the property was inundated for four days.
20. The loss adjuster stated that the water came from a gully situated in a natural
flood plain. The property is about 100m from the Bremer River.
21. The FSP acknowledges that „Flood‟ is a prescribed event and that its Personal
Insurance Policy is a „prescribed contract‟ for the purposes of Section 35 of the
Act.
22. The Applicant alleges that the FSP‟s PDS and policy wording document fails to
clearly inform.
23. The FSP submits that in Marsh v CGU Insurance Limited [2004] NTCA, the
Northern Territory Supreme Court set out the criteria that must be met by a
PDS document before it will satisfy the statutory obligation to clearly inform.
24. The three components of the duty are:
(a) the language used to express the exclusion is clear and unambiguous;
(b) a person of average intelligence and education is likely to have little
difficulty finding the exclusion; and
(c) a person of average intelligence and education is likely to have little
difficulty understanding the exclusion clause.
25. The FSP submits that the Applicant signed a declaration on or about 5
November 2004 stating that she received a copy of the FSP‟s policy PDS and
policy wording document.
26. The Applicant had six years prior to the flood event to familiarise herself with
the policy and seek cover with another insurer if she wished to insure her
building for flood.
27. The FSP contends that it has satisfied its statutory disclosure obligations under
Section 35 of the Act and it is entitled to rely on the „flood‟ exclusion clause to
deny cover under the policy.
28. The FSP contends that the Applicant‟s property was damaged by flood which is
an exclusion under the policy and the FSP is not liable for any loss or damage
arising out of the claim.
29. The FSP submits:
the initial above floor inundation of the property occurred at
approximately 2000 hours on 11 January 2011;
Case No: 299097 Determination Page 4 of 12
the cause of the inundation was flood waters from the Bremer River
which flowed back-up an unnamed watercourse located adjacent to the
Applicant‟s property;
this comes within the scope of the policy definition of „flood‟ and is
excluded from cover; and
the site specific report is consistent with the findings of the ICA
Hydrology Report and supports the view that flood was the cause of
damage to the Applicant‟s property.
30. The FSP relies on the following policy/contract provisions:
„Words with special meaning
...
“Flood” means the inundation of normally dry land by water escaping, or being
released from, the normal confines of a reservoir, natural watercourse or lake (whether
or not they have been altered or modified). Flood also includes water discharge from
any sewerage or waste water systems due to pressure induced by flood water.
...
SECTION A – HOME COVER
Subsections 1 and 2 – Building and Contents Cover
Accidental Damage Cover
We will pay for Accidental Loss or Damage to your Building or Contents at the Address
other than the Occurrences or items referred to in “What you are not insured for”.
...
SECTION A – HOME COVER
What you are not insured for
Under Section A – Home Cover we will not pay for:
...
2. Loss or damage to your property caused by:
a. Flood, the action of water from the sea, high sea water, tidal action or Tsunami;‟
Issues
31. Whether the FSP is entitled to rely upon the „flood‟ policy exclusion to deny
liability.
Reasons for Decision
32. Due to the nature of the dispute, the FOS has considered it appropriate to refer
the dispute directly to a Panel in accordance with the Operational Guidelines to
the FOS Terms of Reference. Thus, this dispute has not been subject to a FOS
Case No: 299097 Determination Page 5 of 12
Recommendation and has proceeded directly to Determination. The parties
have been previously advised that a Determination will be issued in this case.
33. This decision has been made by a Panel consisting of an Ombudsman and two
Panel members with extensive experience in insurance industry matters and
consumer claims.
34. There has been an exchange of material which the parties rely on. Each party
has had access to the material on which the other party bases its case. The
Panel has had regard to the material exchanged and the detailed submissions
made on behalf of the parties.
Was the Applicant misled into believing she was covered against flood
damage?
35. The Applicant initially incepted the policy of insurance on 5 November 2004
insuring her home located in New South Wales. In her Statutory Declaration
(SD) dated 5 December 2012, the Applicant submits that in late 2006 or early
2007, she submitted a claim for water damage caused by a broken water pipe.
She did not proceed with the claim but she was informed by the FSP‟s
representative that she was covered for water damage at this time.
36. Based upon this information the Applicant considered she was covered for loss
or damage caused by rain, burst water pipes, ground floods after rain, washing
machine overflows, or any kind of water damage.
37. The Applicant maintains that when she arranged cover for the home in Karalee
in 2009, she informed the FSP‟s representative of the nearby stormwater
easement and was informed that it would not make a difference to her policy.
38. It is the Applicant‟s conten tion that by making this reference, the FSP has
effectively misled her into believing that she was covered for all water damage
including flood.
39. The Panel notes that there is no suggestion that at any time did the FSP‟s
representative advise that the policy extended to cover flood. The FSP
representative has correctly identified that the policy extends to cover wa ter
damage sustained through a broken water pipe and/or stormwater runoff.
40. The Panel does not believe that the comments of the FSP can in this
circumstance be considered to be a misrepresentation. There is no suggestion
that the FSP‟s representative advised the Applicant that she was covered for all
forms of water damage.
41. The Panel notes that in respect of the broken water pipe, the FSP‟s
representa tive‟s advice at the time was correct.
42. Section 35(2) of the Act states that when a claim is made under a “prescribed
contract” for a “prescribed event”, an insurer cannot refuse to pay the claim
unless it can establish that it clearly informed its insured in writing that it would
not cover this event. Section 34 of the Act has defined the terms “prescribed
Case No: 299097 Determination Page 6 of 12
contract” and “prescribed event” by referring to the Insurance Contracts
Regulations 1985.
43. There is no dispute that a contract of insurance covering a p erson‟s home and
contents is a “prescribed contract” and damage due to flood is a “prescribed
event”.
44. The onus is therefore on the FSP to establish that it has clearly informed the
Applicant prior to the claim that it would not cover damage caused by “flood”.
This is generally done by an insurer providing a copy of its policy to its insured
which is meant to set out completely the rights and obligations of both parties
under the insurance contract.
45. Further, the Courts have supported this and particularly, in the case of Marsh v
CGU Insurance Ltd [2004] NTCA 1, Mildren J provided the following comments
that are particularly relevant to the operation of Section 35(2) of the Act:
“In Hams & Anor v CGU Insurance Ltd(2002) 12 ANZ Insurance Cases 61 -
525, Einstein J held that the provisions of s 35(2) of the Insurance Contracts
Act 1984 (Cth) could be met if the insurer provided to the proposed insured a
document such as the proposed policy, which contained the relevant wording.
I agree. … Whether the policy wo rding in fact "clearly informed" the insured
that there was no cover for flood is a question of fact to be determined by an
examination of the document in question. … Furthermore, the language of s
35(2) suggests that the proposed insured can be clearly informed merely by
providing the insured with a copy of the policy which shows the exclusion in
clear and unambiguous terms. … The answer to the question "is flood
covered" is easily ascertainable by any person of average intelligence
and education. ” (Panel emphasis)
46. The Applicant‟s Personal Insurance Policy insures home building and contents,
motor vehicle and boats. Page 2 of the Product Disclosure Statement (PDS)
clearly identifies where details of each insurance type can be found.
47. The Applicant submits that the PDS is misleading and deceptive. On pages 13,
14 and 15 what is covered under the defined events and accidental damage
covers, is explained. On page 16 under the heading „What you are not insured
for‟ under accidental damage are listed exclusions s pecific to Accidental
Damage policies.
48. At page 21 of the PDS the relevant flood exclusion appears under the
headings:
„SECTION A – HOME COVER
All Subsections
What you not insured for‟
„Loss or damage to your property caused by: a Flood...
This exclusion applies to all insurance covers under the Home Cover Policy.
The definition of „flood‟ is found on page 9 of the PDS. It is clearly identified
Case No: 299097 Determination Page 7 of 12
under the heading “Flood” followed clearly by what is meant by the word
„flood‟.
49. Having considered the policy terms and conditions, the Panel is satisfied that if
the Applicant had read the policy, she would have had little difficulty in finding
and understanding the extent of the limitations and exclusions in relation to
flood cover. In these circumstances, the Panel is satisfied that the FSP having
supplied the PDS to the Applicant has fulfilled its obligation pursuant to Section
35 of the Act to clearly inform the Applicant of the terms and conditions of the
relevant policy.
Cause of the Damage
50. The Applicant bears the onus of establishing a prima facie claim under the
terms of the policy. The policy provides cover for both building and contents for
accidental loss or damage. Accidental loss or damage is commonly described
as sudden or unexpected damage, not deliberate damage. There is no doubt
that the inundation of the Applicant‟s property on 11 January 2011 was sudden
and unexpected. The property was inundated to a level well above floor height.
The inundation of the property in such circumstances could not be considered
deliberate and in the circumstances the Panel is satisfied that the Applicant has
established a prima facie claim under the terms of the policy for accidental
damage.
51. The onus is therefore on the FSP to establish on the balance of probabilities
that it is entitled to rely upon the flood exclusion referred to in the policy to avoid
liability in this case.
52. The Applicant has stated that she left her property at approximately 4.30pm on
11 January 2011 at which time water was lapping a shed adjacent to her home.
Sometime later she received a telephone call from a neighbour at
approximately 6.30pm informing her that water was flowing through the
windows of her home towards the Bremer River
53. The Applicant submits that her neighbours who witnessed the event reported
that water was running to the Bremer River from properties above her property.
After a time, the water stopped moving and started to backup.
54. The Applicant refers to the ICA Hydrology Panel report „Flooding in the
Brisbane River Catchment, January 2011 – Ipswich City LGA‟ in which it was
reported:
‘There were four generally distinct rainfall periods across Ipswich City LGA during the
period Sunday 9 January to Thursday 13 January 2011. The first rainfall event
occurred from around 1000 hours to 1200 hours on Sunday 9 January; the second
event from around 1500 hours to 2100 hours on Sunday 9 January; the third event,
from 0700 hours to around 1100 hours on Monday 10 January; and the fourth event,
from 0600 hours to 1500 hours on Tuesday 11 January. Rainfalls were notably
significant only during the fourth event. The final three rainfall events generated small
floods in the Bremer River and its tributaries, the final flood being the largest.’
Case No: 299097 Determination Page 8 of 12
55. The Applicant has submitted that as she left her property shortly after 4.30pm
on 11 January 2011, it is reasonable to suggest that the water which affected
her property at that time was runoff from storms and rain affecting the area up
until 3.00pm as it was running towards Bremer River.
56. The FSP e ngaged a hydrologist, „WRM‟, to carry out a site inspection and
report on the cause of the inundation of the Applicant‟s property.
57. In WRM‟s report dated 10 October 2012, it stated:
the Applicant‟s property is constructed on steeply sloping land that falls
away to the south; ( to wards the Bremer River (Panel’s comment) )
the property backs onto a large grassed low-lying area;
the house is raised approximately 3.2m above the surrounding ground
level;
a garage is located to the west of the house with a floor level similar to
the surrounding ground level;
the house and garage were completely inundated to a maximum of 4.7m
above the habitable floor level;
an unnamed watercourse originates approximately 0.75 km north west
of the Applicant‟s property;
another branch of the unnamed watercourse originates about 0.9km
north east of the Applicant‟s property;
the two branches of the unnamed watercourse merge to the immediate
east of the Applicant‟s property before joining the Bremer River some
0.35 km to the south-east.
58. WRM reported that no significant rainfall was recorded at the Bundamba
(Hanlon Street) Alert 540249 located 3.4 km south-west of the subject property
after about 1400 hours on 11 January 2011. The peak hourly rainfall intensity of
16.3mm/hour was recorded at the Bundamba (Hanlon Street) Alert in the hour
to 1400 hours on 11 January. The peak stormwater runoff at the subject
property would have occurred within about 15 minutes of the peak intensity
rainfall.
59. WRM stated that the Applicant‟s property is locat ed approximately halfway
between the Bundamba (Hanlon Street) Alert upstream and the Moggill Alert
540200 downstream.
60. The extrapolated peak water levels of the Bremer River by WRM, in the vicinity
of the Applicant‟s property, indicate that the peak water l evel was approximately
18.5 m AHD at approximately 1600 hours on 12 January 2011.
Case No: 299097 Determination Page 9 of 12
61. WRM submits that the ground level in the vicinity of the Applicant‟s property is
approximately 9.8 m AHD and the habitable floor level of the house is
estimated at approximately 13.8 m AHD.
62. WRM calculates that the estimated time of initial above floor inundation of the
Applicant‟s house by floodwa ters from the Bremer River was approximately
2000 hours on 11 January 2011.
63. WRM was not able to interview the Applicant but a neighbour, Ms F, two
properties up from the Applicant‟s house, informed WRM that the Applicant‟s
next door neighbour‟s property (which is situated between Ms F‟s property and
the Applicant‟s) had told her that the water had begun to lap at the rear door of
her house at approximately 0200 hours on Wednesday 12 January 2011. At
about 0700 hours on Wednesday 12 January this house had become
inundated above floor level.
64. The Applicant submits that this was over seven hours after her property had
already been signific antly affected by water. Ms F‟s property is at least 3 -4
metres higher than the Applicant‟s property. The Applicant asserts that „ all of
the neighbours witnessed the event. The water was running down to the river
from the properties above me then, after a time, the water stopped moving and
started backing up’ .
65. FOS accessed the Bureau of Meteorology records to ascertain the recorded
rainfall at Karalee, the Applicant‟s suburb. The record of rainfall from 0900
hours on 11 January to 0900 hours on 12 January 2011 was approximately
68.2mm. The approximate total rainfall at the Bundamba (Hanlon Street) Alert
from 0900 hours on the 11 January was 44.3mm with rainfall ceasing at
approximately 1800 hours on 11 January 2011.
66. The Applicant left her property at approximately 4.30pm on 11 January 2011
when water was lapping a shed adjacent to her home. The Applicant stated that
at about 6.30pm on 11 January a neighbour „M‟ telephoned her and reported
that water was flowing through the windows of her house and running down hill
south east towards the Bremer River. WRM estimates that initial above floor
level inundation of the house occurred at approximately 8.00pm on 11 January
2011. The FSP has not attempted to reconcile this significant timing disparity of
initial water inundation above floor level of the house, as between the
Applicant‟s neighbour „M‟ and the WRM hydrology report‟s estimation.
67. In view of the uncertainty involved and the lack of clarity in the hydrology report
given its inconsistency with the witness‟ st atements, the Panel Chair
Ombudsman conducted a site inspection of the Applicant‟s property on 2 April
2013. Also present were the Applicant and a representative from the FSP.
68. The Applicant‟s property is as described in the hydrology report situated on a
steeply sloping block that leads down to a stormwater drainage area which has
been described as a grass lined swale. The water from this area would
eventually runoff through to the Bremer River. The property itself sits on about
four acres composed of a number of paddocks.
Case No: 299097 Determination Page 10 of 12
69. Neighbouring properties sit significantly higher than the Applicant‟s property on
land sloping down towards the Applicant‟s home.
70. There is no doubt that during any period of heavy rain, there would be
significant stormwater runoff going t hrough the Applicant‟s property down
towards the lower paddocks of the property and the unnamed water course.
71. The Applicant‟s home is built on stilts. The lowest section of the Applicant‟s
home is well above ground level. Whilst the WRM report identifies the house as
being 3.2 metres above ground level, based on the Panel Chair Ombudsman‟s
observation, the rear of the property was approximately 1.6 metres above
ground level with the front of the property closer to 3.2 metres above ground
level. There is a general open storage area underneath of the property. At a
lower level of the property is an open garage area. The floor of the garage area
is at the same level as the ground at that point. There is also a second garage
level that is built just off the road.
72. The Applicant described how the water flowed down across the property from
the higher ground. The Panel does not doubt that during and shortly after
heavy rainfall, the runoff would be properly classified as stormwater runoff.
Given the intensity of the rain on 11 January 2011, it is likely any items stored
in the open storage area underneath the house or in either garage would suffer
damage as a result of such stormwater runoff.
73. Given the topography stormwater runoff would continue to flow through the
property and although it would have pooled in some sections of the property,
would have continued to flow until such time as the water in the lower paddocks
built up.
74. Based on the hydrology, the water level in the lower paddocks increased as the
backflow from the Bremer River increased and combined with the stormwater
runoff. This would have continued as the Bremer River continued to rise until it
ultimately reached its peak.
75. The Panel has no reason to dispute the FSP‟s hydrologist calculation that the
Bremer River would have peaked at approximately 18.5 metres at
approximately 1600 hours on 12 January 2011. At that level the Applicant‟s
property would have been submerged to the height of the eaves of the home.
76. Given the topography of the area, the Panel accepts that it is unlikely the
Applicant‟s home could have been inundated by stormwater runoff alone above
floor level. In the Panel‟s view most likely, the initial inundation of the
Applicant‟s home above floor level would have been due to flood waters fr om
the Bremer River backflowing up through the unnamed watercourse and
combining with continued stormwater runoff. Such a combination of stormwater
and flood is correctly described as flood.
77. In the circumstances the Panel accepts that the inundation of the Applicant‟s
home above floor level would be due to flood and therefore excluded under the
terms of the policy.
Case No: 299097 Determination Page 11 of 12
78. The Panel however considers the items stored in the open storage area below
the Applicant‟s home and in both garages would have been impacted by
stormwater runoff. This would have occurred throughout the time of the heavy
rainfall and shortly afterwards. The FSP has not provided any evidence with
respect to this aspect of the claim that enables the Panel to determine the
height that such stormwater runoff would have reached.
79. Having had the opportunity of the site inspection, the Panel believes it is fair
and reasonable to accept there would have been some stormwater runoff
pooling in both garages and that this would have impacted on items that were
stored at a low level and on electrical or mechanical items stored within the
garages.
80. Insofar as the items stored in the open storage area, the Panel accepts that
these would have been impacted by the stormwater runoff and again items of a
mechanical or electrical nature would have been impacted. The information
available to the Panel does not allow it to assess the extent of this damage.
The Panel accepts this area would have been extremely damp although the
height of the stormwater runoff itself is unlikely to be greater than 100mm
above ground level even at the peak of the rainfall.
81. In order to adequately assess the extent of such damage, the Panel determines
that the FSP arrange for an appropriate assessment of damage to be
conducted as to those items stored in the open storage area and in both
garages to determine the extent of the loss sustained.
82. The parties are asked to work co-operatively to determine the extent of such
loss and once agreed, the FSP is to cash settle the Applicant for the loss
sustained to that area.
Determination
83. Accordingly, the Panel determines the FSP is to meet the Applicant‟s claim w ith
respect to loss and damage sustained as a result of stormwater runoff to a
height of 100mm impacting on the items stored in the open storage area below
the Applicant‟s home and in the two garages on the property.
84. As for the damage to the Applicant‟s ho me above floor level, the Panel
determines that such damage was sustained as a result of flood and
accordingly the FSP is entitled to deny liability for that aspect of the claim in
accordance with the flood exclusion contained within the policy.
Case No: 299097 Determination Page 12 of 12
85. The FSP is to cash settle the claim and pay interest in accordance with section
57 of the Insurance Contracts Act 1984 from 21 March 2011 being the date of
the FSP‟s denial of the claim to date of payment of the claim.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.