Determination 298888

Storm water floorboard replacement scope

FirmFinancial Firm (Unknown - Insurer)
Decided2013-05-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed replacement of the whole floor after storm water damage, and the FSP limited its liability to certain areas. AFCA ordered the FSP to meet liability for the hallway and study floorboards, to settle by a new quotation, and to pay statutory interest, but not the bedrooms.

Under the policy the matching repair is limited to the functional area where damage occurred, so the bedrooms, separated by a door, fall outside the cover.

Issues

Subjects and remedies

home or building damagepay claimpay interestreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 298888 Determination Page 1 of 5 Case number: 298888 General Insurance - Domestic Insurance - Home Building - FSP Decision – Policy provision - Claim amount 29 April 2013 Background 1. The Applicant held a Home Building and Contents Insurance Policy (the policy) with the Financial Services Provider (FSP). 2. A claim was lodged under the policy for water damage to floorboards at the insured property due to a severe storm which occurred on 25 December 2011. 3. The FSP accepted the claim but limited its obligations to the areas of the home it assessed to be affected by the stormwater. 4. The Applicant remains dissatisfied with the FSP’s offer and is seeking settlement in a higher amount. 5. The dispute was considered by a Case Manager of the Service who issued a Recommendation. In that Recommendation, the Case Manager determined that the FSP was to meet the cost to replace the damaged floorboards in the hallway but not the cost to replace the floorboards in the two bedrooms and study. Further, the Recommendation required the FSP to obtain a fresh quote to determine the FSP’s liability under the claim. 6. The Recommendation was not accepted by the Applicant. Pursuant to clause 8.5(c) of the Terms of Reference of the Service, the Applicant requested that the dispute proceed to Determination. Summary of Applicant’s p osition 7. I am satisfied that the Case Manager’s Recommendation satisfactorily and accurately details the Applicant’s position and as such for the sake of brevity I do not propose to repeat the Applicant’s submissions , save to say that the Applicant maintains that the floor of the home is the same throughout the home and the policy provisions provide for the replacement of the whole floor of the home, in order to achieve a match, as contemplated by the terms of the policy. Determination Case No: 298888 Determination Page 2 of 5 Summary of FSP’ s position 8. I am satisfied that the Case Manager’s Recommendation satisfactorily and accurately details the FSP’s submissions in respect to this matter and thus for the sake of brevity, I do not propose to repeat those submissions here. 9. The FSP relies on the following policy provisions: “ What we will pay – new for old … Repairing your building When we establish that your home building can be properly repaired, we will decide to: repair it, or pay the cost of repairing it. When we repair your building, we will use new materials. We will make reasonable endeavours to match materials. Where this does not achieve an exact match, materials that in our opinion match the damaged or lost materials as near as reasonably practicable will be used. We will not pay to replace undamaged materials or any undamaged part of them to achieve a match. … Damage to fixed wall or floor coverings When we repair or replace damage to fixed wall, ceiling or floor coverings: we also repair or replace undamaged coverings if this is reasonably required to achieve a match with the repair or replacement of the damaged area, the repair or replacement is limited to the room, passageway, stairwell or functional area where the damage occurred. Fixed wall and floor coverings are items such as tiles, floating floors, fixed cupboards and shelving . … Damage to fixed wall or floor coverings When we repair or replace damage to fixed wall, ceiling or floor coverings: - we also repair or replace undamaged coverings if this is reasonably required to achieve a match with the repair or replacement of the damaged area, - the repair or replacement is limited to the room, passageway, stairwell or functional area where the damage occurred. - Fixed wall and floor coverings are items such as tiles, floating floors, fixed cupboards and shelving . ” 10. The FSP maintains that the policy provisions entitle the FSP to deny the claim in respect to the hallway, the two bedrooms and study. Case No: 298888 Determination Page 3 of 5 Issue 11. Whether the FSP is required to indemnify the Applicant for the cost of replacing the floorboards in the hallway, the two bedrooms and study. Reasons for Decision 12. I have reviewed all of the material provided by the parties and included within their respective submissions. 13. The Recommendation of the Case Manager has not been accepted by the Applicant and as such, this matter will proceed to determination in accordance with the Terms of Reference of the Service. “8.5 Dispute is resolved on the basis of the Recommendation. c) If, within 30 days of receiving the Recommendation, either: (i) The Financial Services Provider does not accept the Recommendation in relation to the Dispute; or (ii) Either party requests FOS to proceed from a Recommendation to a Determination FOS will proceed to a Determination by either an Ombudsman or by a FOS Panel (as the Chief Ombudsman or his or her delegate decides is appropriate). Before the Determination is made, the parties will be given a reasonable opportunity to make submissions, and provide any further information, in response to the Recommendation.” 14. Subsequent to the Case Manager’s Recommendation, the Applicant has lodged a further submission by way of an email dated 10 March 2013. The FSP has not provided any further submissions and seeks to rely upon the material previously provided. 15. I have considered all of the material as part of this Determination. 16. As part of the original dispute, the FSP declined to meet the cost of replacing the floorboards within the hallway. The Case Manager considered this issue and recommended that the FSP meet the cost of replacing the floorboards within the hallway. 17. I agree with the Case Manager’s Recommendation in respect to this aspect of the claim and I am satisfied that the floorboards installed in the lounge room clearly extend into the adjoining hallway and that the cutting of the floorboards at the doorway adjoining the lounge room would leave the floorboards in the hallway in a damaged condition. Case No: 298888 Determination Page 4 of 5 18. I note of significance that the FSP has not sought to challenge the Case Manager’s Recommendation i n respect to the replacement of the floorboards in the hallway. 19. Given the evidence presented, the analysis of the Case Manager and the fact that the FSP does not seek to challenge the Recommendation in this regard, I agree it is appropriate that the FSP meet the cost of replacing the floorboards in the hallway. 20. The FSP has already agreed to meet the cost of replacing the floorboards in the kitchen, meals / dining area and lounge and thus the balance of this Determination will be confined to the dispute as it regards the two bedrooms and study. 21. In this regard, I have considered the submissions of both parties and the conclusions of the Case Manager in his Recommendation. 22. I am satisfied that the repairs required as they involve the area where the lounge room meets the hallway and study are quite different from the repairs required in the area where the hallway meets the two bedrooms . 23. The Applicant within her further submissions says that the floorboards in the two bedrooms and study will also need to be cut, however, she has not produced any evidence to support this submission. 24. I note that the floorboards run in a lengthways direction along the hallway and thus the replacement of those boards would involve the inclusion of new floorboards which would attach to the floorboards of the two bedrooms which are in the same direction. 25. However the room at the opposite end of the hallway to the lounge room, that is, the study, has the floorboards running in the same direction as the lounge room and the hallway and thus to cut across the end of the hallway between the hallway and the study, would result in damage to the floorboards in the study, by the same logic as applied to the floorboards between the hallway and the lounge room. 26. As such, I am satisfied that the FSP in addition to meeting the cost of replacement of the floorboards within the hallway should also meet the cost of the replacements to the floorboards within the study at the end of the hallway. 27. I agree with the Case Manager’s Recommendation that given the exch anges between the parties and the fact that the quote from J was only valid until 12 October 2012 and did not include the cost to replace the floorboards in the hallway and/or the study, liability of the FSP should be resolved by way of a further quotation in respect to the loss arising from the replacement of the floorboards in the kitchen, meals / dining area, lounge, hallway and the study. Case No: 298888 Determination Page 5 of 5 28. In this regard, I ask that the parties work together in a cooperative fashion to select a repairer from whom the quotation is to be obtained, in line with the matters discussed above. 29. Insofar as the Applicant’s claim involves the two bedrooms, whilst I accept that it is not possible to match the hall floorboards with the original bedrooms, I am not satisfied, given the terms of the policy, that the FSP is required to replace the floorboards within the two bedrooms. 30. The terms of the policy require replacement limited to a functional area where the damage occurred. Given my findings that there is effectively no damage within the two bedrooms, I do not regard those two bedrooms as being part of the same functional area as the hallway, as they are separated by a door. 31. In those circumstances, I am not satisfied that the FSP is liable to replace the floorboards within the two bedrooms. 32. I do not accept the Applicant’s interpretation of the policy definitions in that the Applicant says that the matching is not limited to a functional area. In my view, the policy is clear in that the repair or replacement of any undamaged floorboards, required to achieve a match with the repair or replacement of the damaged area, is limited to the same functional area where the damage occurred. Determination 33. I determine that the FSP is to meet its liability under the terms of the policy in respect to the replacement of the floorboards in the area of the kitchen, meals / dining area, lounge, hallway and study. 34. I determine that the extent of the liability is to be based upon a quotation obtained in respect to those areas and in accordance with the matters raised above. 35. The FSP is to pay interest at the statutory rate in line with the Insurance Contracts Act 1984 upon the final settlement of the amount, from 11 October 2012 (date of its final decision), until the date of final settlement of the claim.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.