Determination 298380

Denial of building damage claims (storm, hail and neighbouring construction)

FirmFinancial Firm (Unknown - Insurer)
Decided2013-11-26
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant claimed under a commercial building policy for structural, water and storm damage linked to neighbouring construction and storms. AFCA found the damage was largely pre-existing, age related, excluded or not shown to be caused by insured events, and ordered nothing.

Pre-existing and gradually operating damage, settlement exclusions and the vibration exclusion, together with the insureds' failure to take reasonable care, defeated the claims.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 298380 Determination Page 1 of 18 Case number: 298380 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim-Exclusion / condition 25 November 2013 Summary Description: This dispute concerns three claims by the Applicant under a business insurance policy for damage to the insured commercial building as a result of a number of events. Basis for Determination: The damage claimed is not covered by the policy or is excluded from cover. Determination: The FSP is entitled to deny the claim. Background 1. The Applicant insured a commercial property with the Financial Services Provider (FSP) under a business policy. 2. The Applicant claimed for damage to the property said to have been caused by the following incidents:  Construction activity at a neighbouring lot;  A hailstorm on 22 March 2010; and  A storm on 12 December 2011. 3. The FSP declined liability, contending that:  The majority of the damage to the insured building had pre-dated the hailstorm as well as the commencement of construction at the neighbouring lot.  The insured building’s structural damage is due to settling and expansion of its foundations and this is excluded on the basis of earth movement, wear and tear.  Any damage arising from the neighbouring construction activity would have been caused by vibration, which the policy specifically excludes. Determination Case No: 298380 Determination Page 2 of 18  The insureds did not take reasonable care to prevent or minimise loss or damage to the insured building although they received advice that substantial remedial work was required to prevent further damage.  The water damage to the building has been occurring over a period of time due to maintenance issues rather than a storm event or the neighbouring construction activity. This damage is not covered in all the circumstances and is excluded as wear and tear damage. 4. The Applicant maintains the insureds are entitled to the damage claimed. Summary of Applicant’s position 5. The insureds were:  Assured that all aggravation of existing faults and subsequent damages would be made good by the builders and their insurers before construction at the neighbouring property commenced.  Advised by their managing agent that they should not undertake any major repairs and to only undertake minor repairs until completion of the construction at the neighbouring property.  Advised by their tenant that there were “accelerated damages” during the construction activity. 6. All necessary repairs were undertaken before the tenants commenced their lease on 1 June 2002. 7. All assessors (DP, RY and DB), other engineers and architects, have acknowledged that the insureds are entitled to compensation for some of the damage to the insured building. This was the broker’s advice too. 8. The report and opinion of the engineer (ATVM) and that of the engineer (R) should be accepted. 9. No one who has assessed the damage can say with certainty that had it not been for the construction next door, that the faults in the building after construction would be as severe as they are. 10. The FSP’s claims specialist and assessor were factually incorrect on a number of matters. The final assessor was unaware that there had been two other claims when he assessed the storm damage claim in December 2012.The assessors’ reports and assessments should not be accepted. 11. The Applicant had a number of complaints about the claims handling of the FSP including that the FSP:  Has not responded to a number of the insureds’ letters;  Has not provided the insureds with DP’s reports; Case No: 298380 Determination Page 3 of 18  Has not provided the insureds with the scope of works and quote prepared by SH;  Has not obtained the building plans for the neighbouring construction for one and half years; and  Closed the claim file although the claim was never properly resolved. Summary of FSP’s position 12. The insured building’s structural damage is excluded because a number of building and engineering experts have expressed consistent views that the damage to the insured building had either:  pre-existed the commencement of construction at the neighbouring property; or  was caused by vibration arising from such construction activity. 13. It is not responsible for any additional damage to the insured building because the insureds failed to take all reasonable care to prevent or minimise further loss or damage.  They failed to act on a report commissioned by their property agent which advised that substantial repair works were required in order to prevent further damage.  They only took action in September 2011. 14. The insured building’s water damage:  has been occurring for a period of time;  is due to maintenance issues rather than a storm event or construction activity at the neighbouring property; and  is excluded because it was caused by a gradually operating cause and/or wear and tear. 15. It does not believe it has unreasonably managed or delayed the claim.  Much of the delay appears to have been caused by attempts to obtain information relevant to the claim.  It had closed the claim file initially because it did not receive a 2007 building report until March 2012.  It decided the claim in accordance with the General Insurance Code of Practice once it had all the necessary information and completed its investigations.  It had kept the Applicant, his broker and property managing agent informed at all relevant times. Case No: 298380 Determination Page 4 of 18  It apologised for any failure on its and its external providers’ part to contact the Applicant in a timely manner or appreciate the history of the insured’s claims. 16. The FSP relies on the following policy provisions:  Construction activity and 22 March 2010 hail damage claims “ Cover We will pay up to the limit of liability in accordance with the basis of settlement for property that is damaged at a premises during the period of insurance. … Exclusions that apply to this Section The following exclusions apply to this Section of the Policy. There are also general exclusions which apply to all Sections of this Policy. … 3. We will not pay for damage caused by or arising from: … (i) erosion, landslide, mudslide, rockslide, subsidence, settling, seepage, shrinkage or expansion of earth, vibration or earth movement provided that this exclusion 3(i) will not apply if damage to property is caused by or arises out of earthquake, subterranean fire or volcanic eruption. … 6. We will not pay for damage caused directly by or arising directly from: … (b) gradually operating causes such as but not limited to wear and tear, mildew, corrosion, disease, oxidisation, fading, tree roots, evaporation, change in flavour, colour, temperature or texture … General conditions These General conditions apply to all Sections of this Policy: 1. Precautions You must take all reasonable care to prevent or minimise loss, damage, injury, illness or liability including your compliance with any law, by-law, ordinance or regulation that concerns the safety of persons or property. ”  12 December 2011 storm claim “ Cover We will pay up to the limit of liability in accordance with the basis of settlement for property that is damaged at a premises during the period of insurance. … Case No: 298380 Determination Page 5 of 18 Accidental Damage Exclusions … 3(d) We will not pay for damage caused by or arising from: (i) erosion, landslide, subsidence, settling, seepage, shrinkage or expansion of earth, vibration or earth movement unless caused by or arising from a direct consequence of an earthquake, subterranean fire, volcanic eruption or water escaping from a water main owned by a water supply authority. … 5 We will not pay for damage caused directly by or arising directly from: (b) gradually operating causes such as, but not limited to wear and tear, mildew, corrosion…” Issues 17. Whether the insureds are entitled to indemnity for the damage to the insured building and if so, to what extent. 18. Whether the insureds are entitled to compensation for the manner in which their claim was handled. Reasons for decision 19. I am satisfied that a full exchange of information has taken place between the parties and that each party has had the opportunity to address any issues raised. 20. I have reviewed the submissions of the parties in relation to the terms and conditions of the policy and will only refer to the relevant submissions and materials raised. 21. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the FOS Terms of Reference. This is due to the nature and complexity of the dispute. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 22. I consider the FOS Terms of Reference relevant to this dispute are: “ 9.3 Other Compensation b) Subject to paragraph 9.3c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for non- financial loss but only where: (i) an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant’s expectation of enjoyment or peace of mind has occurred; or ... The maximum amount of compensation for non-financial loss will be $3,000 per claim made in the Dispute. Case No: 298380 Determination Page 6 of 18 ...” Applicable policy terms for the 12 December 2011 storm claim 23. I have reviewed page 18 of the product disclosure statement (PDS) identified as QM515-0709 and was unable to find the following policy provisions (which were cited in the FSP’s submissions as being applicable to the 12 December 2011 claim): “ Accidental Damage Exclusions … 3(d) We will not pay for damage caused by or arising from: (j) erosion, landslide, subsidence, settling, seepage, shrinkage or expansion of earth, vibration or earth movement unless caused by or arising from a direct consequence of an earthquake, subterranean fire, volcanic eruption or water escaping from a water main owned by a water supply authority. … 5 We will not pay for damage caused directly by or arising directly from: (c) gradually operating causes such as, but not limited to wear and tear, mildew, corrosion…” 24. I assume this was inadvertent. Having reviewed the policy, I am satisfied that the FSP can rely on the following provisions (contained in pages 11 and 12 of the PDS): “ Exclusions … 3. We will not pay for damage caused by or arising from: … (i) erosion, landslide, mudslide, rockslide, subsidence, settling, seepage, shrinkage or expansion of earth, vibration or earth movement unless caused by or arising from a direct consequence of an earthquake, subterranean fire, volcanic eruption or water escaping from a water main owned by a water supply authority. … 5 We will not pay for damage caused directly by or arising directly from: (b) gradually operating causes such as, but not limited to wear and tear, mildew, corrosion…” 25. I also note the same General Condition regarding Precautions applies to this policy too. It is found at page 6 of the PDS. 26. I will rely on these provisions for purposes of the 12 December 2011 claim. Proximate cause of loss 27. According to the available material: Case No: 298380 Determination Page 7 of 18  The insured building consists of a main building and an outbuilding, estimated to be between 50 to 80 years old. For convenience, I will use “insured building” as a reference to both buildings unless otherwise indicated.  It appears that the insureds were covered for damage that occurs during a relevant period of insurance irrespective of which PDS is applicable.  The insureds lodged three claims for building damage under their policy. The FSP treated the first two claims as one claim and the third claim about the storm on 12 December 2011 as the second claim.  The construction activity and hail damage claim purports to relate to the 19 November 2009 to 19 November 2010 policy period.  The 12 December 2011 storm claim purports to relate to the 20 November 2011 to 30 November 2012 policy period.  The Applicant says “all necessary repairs” were undertaken prior to the commencement of the tenant ’s lease on 1 June 2002, but otherwise provided no specific information as to what repairs were actually carried out in that regard. Having regard to “Annexure A” of the offer to lease the insured building, it appears that such works related to the followi ng: - Replacement of the front double timber/glass doors with aluminium frame and glass. - Removal of the front garden and “bitumenise level with car park”. - Sanding and sealing of the timber floors. - Replacement of hand basin next to toilet. - Installation of ceilings to two rear rooms. - Checking for termites and repairing termite damage. - Installation of a monitored security system. - Fitting bars or security screens to windows. - Painting of all concrete floors. - Painting of building’s interior and exterior. - Fixing signage and fitting floodlights to the front and rear of the property. - Fixing floodlights to front and rear.  The insured building was inspected by chartered loss adjusters and surveyors (BS) specifically for the purpose of documenting its condition before commencement of construction activity at the neighbouring lot. The report was called a pre-condition survey and was issued on 30 July 2007. Although this report was supplemented by photographs, they were not made available to me to view. I note the FSP and Applicant have Case No: 298380 Determination Page 8 of 18 viewed the photographs but the Applicant disputes their authenticity. Nonetheless the report describes well the state of the premises at that time. The report relevantly identifies/notes the following: Main building (external) - Structural cracking above window openings and significant mortar disintegration (lower level) on the northern wall. - Miscellaneous super structure fractures to brickwork (through first window rendered finish to first window sill) as well as disintegrated mortar and brickwork above the limestone foundation level on the western wall. - Structural cracking above and below window openings on the eastern wall. Rear outbuilding (external) - Fractured brickwork (upper level) and disintegrated mortar (lower level) on the southern and eastern walls. - Northern wall was generally in poor condition; with some finishing strips (for “hardie board”) missing and disintegrated m ortar (lower level). - The western wall presented with structural cracking towards the front south west corner, disintegrated mortar (lower level) and displaced barge fascia. Front counter/reception area - Staggered fracture on western wall. - Signs of water damage and flaking paint on the ceiling. Display/reception area - Signs of water entry and failure on the ceiling. Room off passage (Office 3) - Ceiling shows signs of water entry on the south west corner and structural failure. Passage leading to toilet - Ceiling shows signs of failure. Toilet - Cover strip failure in front of water heater. - Fracture on floor slab in front of door opening. Front office behind counter area (Office 1) - Ceiling paint flaking. Front office (Office 2) Case No: 298380 Determination Page 9 of 18 - Staggered fracture on south wall, starting adjacent to eastern side of window opening and running up through picture rail to underside of coving and through coving joint. - Diagonal fracture on south west corner and stepped fracture above window. - Separated coving at north-west corner wall junction. - Separation of wall plaster and coving, separation of coving and ceiling joint and vertical fracture below coving line above sliding door opening on north wall. - Damp patches and flaking paint on ceiling. - Cracked paint through finishing strip of feature ceiling. Video recorder room (media room) - Vertical fracture (above sliding door opening below coving line), separation of cornice joint and separation of cornice and ceiling joint on south wall. - Intermittent separation of coving and ceiling joint, sepa ration of return wall at wall junction and diagonal fracture (adjacent to sliding door opening) on north wall. - Separation of coving and ceiling joint at north east and south east corners. - Signs of water entry and flaking paint on ceiling. Large open plan office (office 4) - Diagonal fracture (upper level) at south west corner. - Staining to cornice on west wall. - Separation of wall plaster and coving at the north east corner. - Separation of coving at coving joint, staggered fractures (above and below air vent adjacent to window head) and horizontal fractures (south side of window head and below beam) on the east wall. - Water staining, flaking paint and visible cover strip joints on ceiling. Staff room (kitchen) - Cover strip joints visible. - Fracture/crack on concrete floor (running south to north in front of work bench and east towards the storage area). Rear stores (store 1 and 2) - Separation of all wall plaster and coving on western section. - Fracture running south to north on eastern side of the floor. Rear loading area (store 3) - Separation of wall plaster and coving on all walls. Case No: 298380 Determination Page 10 of 18 - Fracture running east to west on the floor.  Subsequent to the pre-condition report and after complaints from the tenant about the construction works, the managing agent engaged consultant engineers (R) who conducted two inspections of the insured building on 25 and 29 February 2008 to discuss the damage to the building and what steps would be taken to maintain the stability of the building and to stop further damage.  In an email dated 26 February 2008, the agent noted this was done following complaints from the tenant. The builder was told of the concerns and asked to stop all works and arrange a site meeting to discuss the concerns and future works.  The neighbouring block had already been cleared for the new development.  R reviewed the BS report and noted the building’s poor condition. R recommended a number of matters to be done before the builder was to proceed with any further construction at the neighbouring lot commenced. These were: - The foundations of the insured main building and outbuilding should be fully stabilised with either, underpinning or grout injection to a suitable depth. - The fretting mortar in the brickwork of the insured main building and outbuilding should be repaired and the brickwork should be stabilised. - The ceiling linings in the insured building should be checked for stability and generally resecured. - R contended the latter two issues were mostly the responsibility of the builder.  R inspected the property again on 22 March 2010 and was told the internal cracking in the walls and issues with the ceilings had worsened (especially on the side where the new building was) since the February 2008 inspections. R noted new settlement cracks which had appeared at the front of the building which appears to be related to further settlement of the foundations. R noted the work the builder had done including anchors and some patching. R also referred to the BS report and has noted the building was in poor condition at the time of that report in 2007, as the building had internal cracks in the wall and the roof was leaking rain onto the ceilings as a result from long term settlement, roof movement and thermal cyclic loading issues, all age related degeneration normally associated with such old buildings. R said there was little evidence of any maintenance by the Applicant to keep the building in good structural condition before the commencement of the building on the adjacent property. R said most of Case No: 298380 Determination Page 11 of 18 the repairs to the building were due well before the commencement of the adjacent building. In explaining the cause of the existing cracks, R said (in the 30 April 2010 report): “ All the cracking that was present prior to the neighbouring building development was probably age related. Such cracking occurs as building materials deteriorate over time, foundation settlement continues and with the cyclic loading of thermal gradients. The stability and compaction of the ground at and below the building foundations may have originally been poo r, as it was built in the mid 1900’s when construction practices were not as stringent as current local government and Building Code of Australia (BCA) requirements. The ground in the area may have been sensitive to changes in moisture content over time resulting in corresponding foundation movements in varying climatic conditions. Thermal cyclic loading (daily and seasonal temperature variations) also plays a significant part in crack degradation of masonry structures. The timber framed roof structure of the building is subjected to the most temperature variation, while the floors and footings due to their proximity to the ground experience smaller more gradual temperature gradients. It is therefore common particularly in older structures for cracking to appear or be more extensive in the masonry walls at window/door heads and at ceiling to wall cornice junctions. Defects in ceilings such as sagging with age are significantly affected by thermal issues. ”  The Applicant wrote that construction at the neighbouring lot commenced on/about 5 February 2008 and was completed by 15 February 2010.  There appears to be acceptance that construction activity at the neighbouring property had caused some damage to the insured building or at the very least, had exacerbated its existing damage. Original photographs taken by R, recently provided by the Applicant, show damage and cracks. As for the damage: - R said in the 30 April 2010 report that: “ From past experience, vibration/shaking caused by nearby construction activities in such fragile buildings would have easily loosened any poorly mortared brickwork further and hence new cracking and worsening of existing cracking would most likely have occurred. With the concrete tiled roof in such a poor condition, any significant roof movement may also have been expected and may have exacerbated further cracking. The Builder should be liable for such exacerbation damage, however, this cannot be properly defined (except for the new cracking at the main entrance at the front of the building) as most of the damage was already present and needed repair by the Owner anyway. The Builder should be approached… for damages at least for the new cracking to the front of the building…the owner does not have a strong case for any existing damage as stated in the BS report. ” Case No: 298380 Determination Page 12 of 18 - ATVM (in a report prepared after a site inspection on 28 October 2010) said: “…The observed cracking can most likely be attributed to the disturbance which was caused by the building activities on the adjoining land… …The pattern o f cracking indicates mutual settlement of the western section of the old building which can be associated with the adjoining land…” Photographs taken by ATVM are hard to discern. The Applicant has recently advised that the agent does not have the original photographs and that the engineer has since retired. ” - MDA (in a 29 November 2011 report) said: “ 1. It is probable that a significant proportion of the cracking to the structure was caused by the construction work to the adjoining property. We note item 5ii i in the [ATVM report] which states “there was some minor cracking present before the building was constructed”. This would indicate that there were some historic issues with the structure prior to construction of the adjoining building. Given the age of the structure this is not surprising. 2. The cracking to the cornice within the building could be caused by the neighbouring works but could also be due, in some areas, to the age of the property. During our inspection there were large areas of damage to ceilings due to damp ingress. This is more likely due to the poor maintenance of the building. 3. ... 4. There is a significant amount of damage to the structure which could not in any way to attributed to the adjoining construction and is down to a lack of maintenance of the building. Whilst attending site we noted that historically there had been a number of walls removed throughout the property with steel beams installed over the openings. Unless this had been done correctly it could cause some cracking under the point of support to the beams. 5. ... (tests) may also clarify whether the damage is due to poor ground conditions beneath the building rather than the neighbouring works. 6. We note that the ground around the site of the property was damp at the time of our inspection due to water discharge from the roof of the building directly on to the adjoining ground. This water is not being effectively drained from the roof and the high water content can cause fine particles to wash out of sandy soils which reduces the bearing capacity of the soil. … To summarise, we can find no reason to disagree that some of the cracking is due to the works in construction of the building. We do note that there is a significant amount of work required to the structure which is in no way related to the neighbouring construction..... ”  Whilst the Applicant says a hailstorm on 22 March 2010 and a heavy rainstorm on 12 December 2011 caused “further damages” to the insured building, he has not identified these damages in his material. Existing structural/cracking damage Case No: 298380 Determination Page 13 of 18 28. Having carefully reviewed the matter, I am satisfied on the evidence that the FSP has established an entitlement to decline liability for the structural and cracking damages. 29. The material shows the bulk of the structural and cracking damages were identified as existing in 2007. The building was inspected in February 2008 and work was identified to be done to prevent damage or further damage but there is nothing in the material which suggests this work was done by the Applicant or by the builder. 30. With nothing in the material to suggest that they were rectified before 19 November 2009 (ie the commencement of the 2009/2010 policy period), I am accordingly satisfied 2009/2010 policy does not respond to such damages. 31. Whilst it is possible that such damages may have occurred during a period the FSP was still on risk for the insured building (since it had insured the insured building from 2002 and there is nothing in the material exchanged to suggest when such damages first occurred), I am, on the balance of probabilities, more inclined to accept that they would likely be excluded under the policy. 32. In this regard, the evidence establishes that the insured building was at least 50, if not 80 years old. 33. Further, consultant engineers R have provided a plausible and reaso nable explanation for the building’s structural and cracking issues which appear to be unchallenged by contrary expert evidence. According to R, the structural and cracking issues identified in 2007 were age related due to continual deterioration of the in sured building’s construction material, settlement of its foundations and exposure to cyclical temperature changes over the life of the insured building. 34. With nothing to persuasively rebut R’s explanation, I am of the view , that the policy exclusions relating to loss or damage caused by settlement and a gradually operating cause (such as wear and tear) would operate to exclude the existing structural and cracking damages. Exacerbation of existing damage and new damage 35. Whilst there is opinion that the construction activity at the neighbouring property caused new damage to the insured building and exacerbated some of its existing damage, I am also satisfied on the evidence , that the FSP has established an entitlement to decline liability for such damages. 36. It is plain from the evidence that the insured building was old and in poor condition before construction at the neighbouring lot even commenced. 37. The full extent of its state of disrepair was documented in the pre -condition report, prior to the commencement of construction at the neighbouring property. There is nothing in the material exchanged to suggest that the Case No: 298380 Determination Page 14 of 18 existing defects were rectified before construction commenced. I also found nothing to suggest that the works recommended by R to be completed in 2008 before construction commenced and or continued, were ever undertaken. 38. Having regard to the available expert evidence, I am satisfied that the failure to complete the works recommended by R had essentially left the insured building more vulnerable to new and exacerbated damage. Having considered the limited material I have, I am not satisfied that the work done in 2002 was of great substance or related to structural matters and I am not satisfied that this constitutes “all necessary repairs” as is descri bed by the Applicant. 39. The Applicant says that the insureds were advised (by parties unconnected to the FSP) against carrying out significant repair works until after the construction at the neighbouring lot was complete. However, this dispute does not include such parties and I do not have the benefit of their responses to the Applicant’s allegation. Accordingly, I am unable to fairly make a finding as to whether such advice was provided. 40. In any case, to the extent such advice was provided, this would be matter between the insureds and such parties. The insureds are at liberty to pursue such parties if they believe the advice they received was incorrect or inadequate. Their solicitor should be better placed to advise them of their prospects in that regard. 41. Insofar as the contractual relationship between the insureds and the FSP is concerned, the policy plainly imposed an obligation on the insureds to take all reasonable care to prevent or mi nimise loss or damage to the insured building. 42. Based on the material before me, I am not satisfied that the insureds have satisfactorily discharged that obligation. The resulting effect is that the insured building was left exposed to risks of further or exacerbated damage, which in fact eventuated. 43. At law, the insureds were under an obligation to mitigate their loss failing which their entitlement to compensation under the policy (if any) may be reduced or nullified altogether. 44. Also, the available evidence suggests that the new and exacerbated damage to the insured building were predominantly caused by vibration arising from the neighbouring construction activity. In this respect, R reported: “The sheet piling (along the side boundary) was driven in at a d istance of only 1.2 metres away from and along the full length side of the main building. Without any doubt, such vibration to drive the sheet piling in would have caused significant exacerbation of the existing defects in the building.” 45. The policy clearly excludes liability for loss or damage caused by vibration. Case No: 298380 Determination Page 15 of 18 46. Having regard to these matters, I am satisfied on the available evidence that new or exacerbated damage to the insured building arising from the neighbouring construction activity would be excluded from cover and or was pre-existing. 47. The Applicant says that he was informed by a number of persons that they were entitled to compensation for damage caused by the neighbouring construction activity. However, this does not affect the policy response on the available evidence. I am not satisfied that the expert opinion does support the Applicant’s contentions when read in full and with the full knowledge of the condition of the property in 2007 and 2008. Further, if the reports baldly state the cracking was caused by the building work, it was from a cause that was excluded, namely vibration. 48. Whilst the insureds may have an independent cause of action against the owner and/or builder of the neighbouring property for such damage, this does not necessarily mean that the policy with the FSP responds to such damage. Whether the policy responds is based on the terms of the policy and the available evidence; which I have found would have excluded such damage for reasons previously outlined. Hail and rain storm damage 49. Turning to the claims relating to the hail and rain storms that occurred on 22 March 2010 and 12 December 2011 respectively, the Applicant has not provided much detail of the damage caused other than to say these storms had caused “further damages” to the insured building. 50. Based on the material before me, I am satisfied on the balance of probabilities that the insured building was already having significant issues with water entry prior to March 2010 and December 2011 hail and rain storms respectively. 51. This fact has been clearly documented in the pre -condition report and there appears to be nothing in the material exchanged to indicate that such issues were addressed before the March 2010 and December 2011 storm incidents. 52. I also note that there has been no persuasive rebuttal to the assessor’s report of the insured building’s tenant’s advice that:  The insured building has not been subjected to any routine maintenance in the 10 years it occupied the property.  Rainwater regularly enters the property during periods of heavy rain over 10 years, causing staining on the ceilings and cornices and water to drip into the property.  The resultant water damage to the insured building has been ongoing and has not been repaired.  Only patchwork repairs were carried out to the roof whenever it made a report of water entry. Case No: 298380 Determination Page 16 of 18  The insureds have not replaced the roof despite saying that they would do so prior to the commencement of the lease. 53. In the circumstances and on the available evidence, I am satisfied that the FSP is en titled to decline the insureds’ claims for hail and storm damage. Claims handling 54. The Applicant has raised a number of concerns with respect to the manner the insureds’ claims have been handled by the FSP and its representatives. He says that the storm damage claims are the most destructive because of the unacceptable delays by the FSP in settling the claims, over and above the procrastinations, gross mistakes, inaccuracies and factual errors. These included:  Closing the claim file although the insureds’ cl aims were never properly resolved.  Delays in reaching decisions on the claims.  Being unaware that there was more than one claim lodged.  Erroneously stating that there were two claims when there were in fact three claims lodged on the policy.  Erroneously stating that the rain storm occurred in November 2011 when it occurred on 12 December 2011.  Failing to respond to a number of his letters.  Failing to obtain the building plans for the construction next door for one and a half years.  Failing to turn up for a site inspection.  Failing to provide the insureds with a number of documents despite repeated requests.  Advising he would be covered.  The authenticity of the so called pre-construction snaps is questionable. 55. The FSP denies these complaints. I note from the material that;  the first claim was lodged in July 2010 and assessors were appointed straight away. The file was closed but the FSP says this was pending receipt of information about the condition of the property before the construction of the adjoining b uilding from the Applicant’s managing agents. I assume this was the 2007 report from BS. I note it was requested by the assessor as early as 24 August 2010 but the assessor says it was not received. I note the Applicant’s brokers and the managing agent were told the file would be closed if the information was not received. The FSP says the broker was told by letter dated 13 October 2010. Case No: 298380 Determination Page 17 of 18  Some information was received by the FSP from the Applicant on 16 September 2011 (not the 2007 report from BS). The claim reopened and an engineer was appointed to assess the claim.  The FSP required the complete copy of the BS report and photographs but and the report was not provided until March 2012 and the photographs were provided in May 2012.  On 28 May 2012 the Applicant was also asked to provide evidence of work done since 2001.  A report was then prepared by the assessor and a decision was made on 4 July 2012 to deny the claim when the FSP had all necessary information. This letter was not received by the Applicant. The FSP says it resent the letter on 24 July 2012. The FSP therefore says that there was no unnecessary delay and the Applicant and his broker and agent were kept advised at all times.  As for the second claim, which was made 13 December 2011, it was investigated in December 2011 and a report made by the assessor on 3 January 2012. Before a decision was made the FSP waited for the report from BS concerning the state of the premises in 2007. The claim was denied by letters dated 4 July 2012 resent on 24 July 2012 and confirmed in the IDR letter dated 25 September 2012. 56. Having considered the matter, I am satisfied that the FSP was entitled to wait for the 2007 report from BS as the condition of the premises before the work commended on the adjacent building was extremely relevant to the conduct of the claim and its assessment. 57. The FSP asked for that report not long after the claim was first made. The Applicant does not explain why it was not made available by him or his agents until 2012. Nor does the Applicant e xplain why he apparently made no contact with the FSP until September 2011. 58. Once the BS report was made available and the photographs considered, I am of the view, that a decision about the claims were made in a sufficiently timely fashion. 59. As for the closing the file in 2010, I am satisfied that the Applicant and/or his agents were given adequate notice of this and the reason why the file was to be closed. 60. As for the other complaints about the claims handling, I am not satisfied that they are sufficiently egregious to attract the operation of the Terms of Reference and an award of compensation. 61. In conclusion, I am satisfied on the available evidence with the claims management and that the FSP has processed the insureds’ claims with reasonable diligence in all the circumstances of the matter. 62. Accordingly, I propose to make no award of compensation pursuant to clause 9.3(b)(i) of the Terms of Reference. Case No: 298380 Determination Page 18 of 18 Determination 63. On the basis of the available information and for the reasons stated, I determine that the FSP: a. Is entitled to decline liability in response to the insureds’ claims for the damage to the insured building. b. Pay no compensation pursuant to 9.3(b)(i) of the FOS Terms of Reference.