Determination 298051

Settlement amount disputed for water damage to bathroom and consequential losses

FirmFinancial Firm (Unknown - Insurer)
Decided2013-11-28
ProductGeneral Insurance · Strata
OutcomeFor the complainant in part
Amount awarded$31,800
Non-financial loss$1,000
Amount claimed$189,480
SourceAFCA PDF

Summary

A beneficiary of a strata policy claimed $189,479.99 after repeated failed bathroom repairs left the home uninhabitable. AFCA accepted the temporary accommodation offer of $28,800, reimbursed $1,000 lot owner fees and $2,000 utilities, awarded $1,000 for delay, and declined the remaining consequential losses.

The policy covers temporary accommodation and specified benefits, but consequential financial losses such as lost savings, mortgage interest and sale costs are excluded and outside the Terms of Reference.

Issues

Subjects and remedies

disabilityfinancial hardshippay claimpay compensationpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 298051 Determination Page 1 of 14 Case number: 298051 General Insurance - Domestic Insurance - Home Building - Service - Delay in Claim Handling - Settlement Amount - Compensation 15 October 2013 Background 1. The Applicant is a beneficiary of a strata insurance policy held in the name of the Owners Corporation (OC) for the residences at the property. 2. In October 2010 the Applicant noted water leaking from the bathroom area. A claim was lodged with the FSP in February 2011 and repairs undertaken. However, the repairs were not effective in stopping the leak and further repairs were authorised by the FSP. The bathroom required rectification on a further three occasions. 3. The Applicant is unhappy with the delays experienced with bringing his claim to a conclusion and the financial impact this has had on him and his partner. He is requiring his financial losses as a result of this incident be covered by the FSP. Summary of Applicant’s position 4. The Applicant says there have been protracted delays in the FSP bringing this matter to a conclusion which has directly impacted him and his partner. The property was uninhabitable due to the non-functional bathroom and they had to move out. They were unable to lease the property as it had no bathroom and when they finally were able to install tenants, the bathroom started leaking again immediately and the tenants had to vacate. 5. The property has been vacant for over two years due to this incident which has caused him significant financial hardship resulting in the forced sale of the property. 6. The Applicant says the original repairer „DJ‟ performed substandard works on the bathroom and was required to re -attend and rectify it on at least three occasions. He feels he was more than reasonable in allowing them access to complete the works but eventually refused them entry to the site after becoming frustrated with the quality of their work. Determination Case No: 298051 Determination Page 2 of 14 7. The Applicant says in addition to the poor repairs, DJ also caused other damage to the home with their untidy habits, such as storing building waste on the carpet and emptying buckets on the garden and driveway. 8. The Applicant says when the FSP finally appointed another builder „AB‟ to complete the bathroom, AB still took another four months to complete repairs, which the Applicant considers is an excessive timeframe. The Applicant denies the FSP‟s inference that he caused or contributed to any of the delays in bringing this matter to a conclusion. 9. The Applicant is seeking the FSP cover loss of rental income of $28,800 as well as temporary accommodation costs of $73,200. He is also seeking payment of the additional benefits of „utilities‟ and „lot owner‟s fees‟ for $12,351.51, as well as the FSP reimburse him his lost savings a nd redundancy payments of approximately $31,500 and the extra costs he incurred on his mortgage of $24,628.48, as a result of this incident. 10. The Applicant has also been forced into the sale of the property and is seeking the agent fees and costs incurred due to the early discharge of the mortgage, estimated to be $19,000. The Applicant‟s claim is in the sum of $189,479.99. 11. The Applicant is also seeking compensation for the manner in which the FSP managed his claim. The Applicant believes the claim was so mishandled that the terms of the policy should no longer apply. Summary of FSP’s position 12. The FSP accepts there were delays in bringing the c laim to a timely conclusion. However, it says there were a number of contributing factors to this including the involvement of their insured‟s representative, the OC, as well as the Applicant himself. 13. The FSP accepts the works undertaken by DJ were not of acceptable standard and it authorised for rectification to be undertaken on three occasions. It also appointed an alternative builder to finally complete the works, at the request of the Applicant. 14. The FSP says it has managed the claim in a timely manner and acted quickly and decisively when made aware of issues regarding the bathroom. It negotiated with DJ to cover some of the Applicant‟s out of pocket expenses such as paying for temporary accommodation for his tenants on an ex gratia basis. It has also provided payments for lost rental income for the periods the tenants were unable to reside in the premises. 15. The FSP says it has requested the Applicant provide documentation in support of his claim for utilities, lot owner‟s fees and temporary accommodation for him and his partner so it can consider these costs under the terms of the policy. However, the Applicant has not supplied the Case No: 298051 Determination Page 3 of 14 documents as requested. The FSP remains willing to consider this aspect on presentation of supporting documentation. 16. The FSP says other costs such as additional interest accrued on the mortgage and the spent savings and redundancy payment are consequential losses which are not covered under the terms of the policy. There is a benefit for discharge of mortgage in the policy, however, this only applies when the property is a total loss. The FSP denies its conduct of the claim has placed the Applicant in financial difficulty, noting the Applicant was involved in a serious accident in April 2011, with his injuries leaving him incapac itated. The FSP considers the Applicant‟s inability to work led to his financial difficulties rather than any action on its behalf. 17. The FSP has reviewed its handling of the claim and maintains it has managed the progression of the claim in a timely manner. It does not agree the Applicant is entitled to compensation. 18. The FSP relies on the following policy provisions: “ What you are covered for Policy 1 – Insured Property This policy is designed to cover you for accidental loss or damage to your insured property (building and common area contents) that occurs during the period of insurance. ... Special Benefits Special benefits are included in addition to Your Sum Insured for Policy 1. 1 Temporary accommodation a Temporary accommodation When You occupy Your Lot/Unit We will pay the reasonable cost of Temporary Accommodation You necessarily incur: i. If Your Lot/Unit is damaged and made unfit to be occupied for its intended purposes by any Event not excluded under Policy 1 or General Exclusions. ... We will pay: ♦ under a i from the time of the Event until the time You reoccupy Your Lot/Unit following completion of rebuilding, repairs or replacement. ... b Rent When You have leased out or can substantiate by means of a signed agreement that You would have leased out Your Lot/Unit or Common Area We will pay the actual Rent You lose or would have lost: Case No: 298051 Determination Page 4 of 14 i. if Your Lot/Unit or Common Area is damaged and made unfit to be occupied for its intended purpose by any Event not excluded under Policy 1 or General Exclusions. ... We will pay: ♦ under b i from the time of the Event until the time Your Lot/Unit or Common Area is relet following completion of rebuilding, repairs or replacement provided You demonstrate You have taken all reasonable actions to obtain a new tenant. ... f Lot owners’ contributions and fees We will pay, up to $1,000 a Lot/Unit, for contributions, levies, maintenance and other fees You are required to pay during the period Your Lot/Unit is made unfit to be occupied for its intended purpose by any Event not excluded by Policy 1 or General Exclusions. ... 6 Excess electricity, gas and similar charges We will pay up to $2,000 for additional electricity, gas, sewerage, water and management charges You are required to pay following loss or damage to Your Insured Property by any Event excluded by Policy 1 or General Exclusions. ... 14 Mortgage Discharge We will pay up to $5,000 to discharge any mortgage over Your Insured Property if it becomes a total loss, is not replaced and We have paid the amount due under Policy 1 . ... Exclusions – what we do not insure ... 2 We will not pay for: ... c consequential loss (other than as specifically provided under an operative Additional Benefit or Special Benefit), loss of use or Depreciation. ” Issues 19. Whether the FSP has fulfilled its obligations under the terms of the policy. 20. Whether the Applicant is entitled to compensation for the manner in which the FSP managed his claim. Case No: 298051 Determination Page 5 of 14 Reasons for decision 21. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the FOS Terms of Reference. This is due to the circumstances of the dispute. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 22. This decision has been made by a Panel consisting of an Ombudsman and two Panel members with extensive experience in the insurance industry and consumer claims. 23. The Panel is satisfied a full exchange of informatio n has taken place between each party and each party has had the opportunity to address any issues raised. 24. The Applicant is not the insured in this matter, but is a beneficiary of the policy held by the Owners Corporation (OC) as a homeowner and member of the OC. This arrangement is recognised by Section 48 of the Act. 25. It is not disputed between the parties the Applicant suffered water damage to his premises, for which a claim was submitted and repairs conducted. However, a dispute has since arisen between the parties regarding the amounts offered in settlement by the FSP. 26. As the Applicant has brought the claim before the FSP, he bears the onus of establishing the claimed loss, that is, the sum of $189,479.99 falls within the terms of the policy. 27. The two parties have provided substantial amounts of material in support of their respective positions. The Panel does not propose to recite this in detail, save for where specifically relevant. However, it is clear this matter is quite complex and protracted in nature and the Panel therefore considers it necessary to consider the matter in an abbreviated chronological order, in order to give proper consideration to the issues raised. The Panel notes the following:  In October 2010 the Applicant noted the carpet in the hallway was damp and notified the strata managers „CS‟ of the issue.  CS appointed a plumber to attend to repair the suspected leak and a tiler to replace the shower tray. CS considered the repairs would be paid for, out of the OC‟s sinking fund rather than by way of an insurance claim.  The Applicant noted the water continued to leak from the bathroom and requested the OC lodge a claim with the FSP. The OC refused to do so and advised the Applicant to proceed with the shower tray replacement.  The Applicant contacted the FSP directly in early January 2011 and was advised he is able to claim on the OC policy directly and a claim was lodged. Case No: 298051 Determination Page 6 of 14  A quotation for repairs was prepared by builder „AN‟ and provided to CS, who sent this onto the FSP on 11 February 2011.  The FSP approved AN to undertake the necessary plumbing repairs on 25 February 2011, with those repairs completed on or around 14 March 2011.  On 14 March 2011 the Applicant asked the FSP to appoint an assessor to inspect the resultant damage. The FSP was unaware of any resultant damage and asked AN to re-attend to inspect same.  AN contacted the Applicant on 12 April 2011 advising that in their opinion, no resultant damage was caused in this incident.  The Applicant corresponded with AN over this issue, however, as he did not receive a satisfactory response, appointed builders „SG‟ on 12 May 2011 to inspect the bathroom. The Applicant supplied a copy of SG‟s report to the FSP on 26 May 2011, which set out the resultant damage to the premises.  The Applicant also vacated the premises in or around May 2011 reportedly due to the mould and odour from the bathroom.  In light of the new information provided, the FSP appointed loss adjuster „MF‟ to inspect the Applicant‟s property. MF attended on or around 30 May 2011 and requested SG and DJ provide quotations for the repairs. MF also requested SG to undertake further leak detection tests.  Upon receipt of the quotations, the FSP offered to cash settle the claim in lieu of repairs, based on the SG quotation.  A release was subsequently prepared which was signed and returned by the Applicant on 12 July 2011.  CS disputed the FSP‟s method of settlement and requested the cash settlement be rescinded and repairs undertaken instead. CS also disputed the amount offered in settlement and requested further quotations be obtained.  The Applicant was informed of this delay by the FSP via a letter dated 18 August 2011, although the Applicant was aware of the delay and had been liaising with CS and the OC over the issue since 27 July 2011. Further discussions were held with the Applicant and CS over CS‟s and the OC‟s objections in proceeding with the claim.  The Applicant also raised concerns with DJ‟s revised quotation to the FSP. The FSP requested MF to re-attend the property with the Applicant and DJ, to discuss the issues raised. This meeting took place on 6 October 2011.  On or around 15 September 2011 the Applicant applied for financial hardship assistance on his mortgage. This was granted for a period of three months, whereby the mortgagee did not require payments to be made during that period. Case No: 298051 Determination Page 7 of 14  After further discussions regarding DJ‟s scope of works (SOW) , DJ was authorised to proceed with repairs on 20 October 2011.  DJ commenced repairs to the bathroom on or around 2 November 2011.  Repairs were halted in December 2011 until late January 2012, although the parties differ as to the reasons why.  The Applicant made a further application on the grounds of financial hardship to his mortgagee to pay interest only on his mortgage for the six months commencing 28 December 2011.  The Applicant had decided to undertake some works outside of the SOW to the bathroom and these parts were received on or around 1 February 2012. Repairs recommenced on or around this date.  The bathroom was near completion on 20 March 2012 when the Applicant raised some concerns regarding the quality of the repairs.  Rectification was approved, with the bathroom being completely refitted. The bathroom was scheduled to be completed by the end of April 2012.  Accordingly, the Applicant arranged a tenant to occupy the premises from 20 April 2012 to 1 May 2012 on a conditional tenancy agreement (due to the pending completion of the bathroom repairs) and from 1 May 2012 on a permanent tenancy agreement for 12 months.  On or around 23 April 2012 it was noted that water was again leaking from the bathroom.  DJ was requested to undertake rectification and the property was deemed uninhabitable whilst the bathroom was re-done. Repairs were completed on or around 1 June 2012.  The FSP agreed to pay loss of rent for the period of 20 April 2012 to 1 June 2012 at the rate of $600 per week.  The Applicant replaced the carpet in the lounge and hall with floating floorboards and during the installation of the flooring it was noticed water again coming from the bathroom. The Applicant advised the FSP of this on 9 August 2012.  The FSP subsequently agreed to cover the cost of the replacement flooring in the amount of $2,694.43.  On 10 August 2012 a site meeting was held between the Applicant, MF and DJ to discuss the claim. Works were agreed on with the bathroom requiring another complete re-fit. DJ agreed to cover the costs of temporary accommodation for the tenant whilst works were undertaken.  Rectification commenced on or around 27 August 2012. On or around 11 September 2012 DJ informed the Applicant the repairs had been unsuccessful and the bathroom would require re-fitting again. Case No: 298051 Determination Page 8 of 14  The Applicant advised the FSP the same day he would no longer allow DJ access to the property and requested another builder be appointed to undertake the works.  On 18 September 2012 a site meeting was held with MF, AB and building consultant „C‟ to discuss the works required to reinstate the bathroom. AB was subsequently authorised by the FSP on or around 25 September 2012 to complete the bathroom works.  The revised SOW also included painting of the premises and cleaning of the carpet in recognition of the damage done by DJ. The FSP also agreed to cover loss of rental income from 24 August 2012 until the property was habitable again.  AB commenced repairs on or around 18 October 2012 and were completed on or around 1 February 2013.  The FSP also agreed to cover loss of rent until 2 March 2013, to allow the Applicant time to source a new tenant.  The FSP requested C complete a post-repair inspection which was undertaken on 6 February 2013. The Applicant raised concerns to the FSP on 22 March 2013, stating the carpet had not been replaced as agreed and he would therefore not sign the release.  C undertook a further inspection on 1 May 2013 and was satisfied all claim related repairs were completed satisfactorily. 28. There are several issues in dispute in this matter and the Panel will consider each item separately below. Temporary Accommodation 29. The Applicant is seeking temporary accommodation costs of $28,800, being for the period 16 April 2011 to 16 April 2012 on the basis the property was not habitable. 30. In his later submission to the Service, the Applicant has provided a statutory declaration from his father saying there was an arrangement between the two for the Applicant to rent his „downstairs residence‟ for the sum of $600 per week. The Applicant‟s fa ther says the Applicant has paid $7,000 to date and owes him another $66,200 for rent. The Panel will therefore assume the Applicant is seeking the higher amount of $73,200 in respect of the temporary accommodation. 31. The FSP in their latest correspondence to the Service have advised that they have now agreed to accept this portion of the Applicant‟s claim in the sum of $28,800. 32. The FSP maintains however, that the Applicant is not entitled to temporary accommodation expenses beyond April 2012 as the property was occupied by a tenant after that time and the Applicant would have been eligible for loss of rent payments. Case No: 298051 Determination Page 9 of 14 33. The Panel notes that the Applicant has not provided any actual proof of any payments made with respect to the temporary accommodation. The Panel notes, however, that the Applicant was involved in a serious accident in April 2011 which left him confined to a wheelchair for an indefinite period of time. This unfortunate change in the Applicant‟s circumstances meant his capacity to live in the premises with a lack of a functional shower facility was severely limited. 34. The Panel accepts that the lack of a functional shower facility at the property meant that the property was no longer safely habitable for the Applicant‟s purposes and therefore it is reasonable to consider the property uninhabitable for the period from 16 April 2011 to 16 April 2012. 35. The only supporting documentation provided by the Applicant has been the recent statutory declaration provided in his last submission to the Service. Whilst the statutory declaration now identifies a sum of $600 per week as being his “rent”. This amount seems vague. 36. In the Panel‟s view, in the absence of any proof of actual payment of the temporary accommodation, the FSP‟s offer to accept the Applicant‟s origi nal claim for temporary accommodation costs of $28,800 is reasonable. Loss of rent 37. The Applicant is seeking lost rental income of $28,800 being for the period 20 April 2012 to 20 April 2013 on the basis the tenants were unable to reside at the premises. 38. The Panel notes that in anticipation of the completed repairs, the property was tenanted by the Applicant effective 20 April 2012 for 12 months. The first ten days rental was $270 due to the bathroom works, with the monthly rent being $2,400pcm thereafter. 39. The FSP has advised that it has already accepted the loss of rent claim for the following periods: 20 April 2012 to 1 June 2012 - $3,600; 24 August 2012 to 19 October 2012 - $4,153.90 20 October 2012 to 24 November 2012 - $2,769.25 25 November 2012 to 26 January 2013 - $4,984.64 27 January 2013 to 2 March 2013 - $2,769.25 40. The Applicant says the tenant refused to pay rent whilst the bathroom works were being completed. Although the Applicant has not detailed what period of time he is referring to, in the Pa nel‟s view , this could only be the period from 1 June 2012 to 24 August 2012. Case No: 298051 Determination Page 10 of 14 41. Again the Panel notes from the FSP‟s latest submission of 4 September 2013, that the repairs were completed by DJ on 1 June 2012. The C report relied upon, confirms the property was occupied by the tenant and some three weeks later, that is three weeks after 1 June 2012, when the bathroom was leaking. According to the submission in light of this, DJ placed the tenants in temporary accommodation. 42. It is likely therefore that the Applicant is claiming that the tenants refused to pay rent from the period they were placed in temporary accommodation at DJ‟s expense on or about 23 June 2012 until 23 August 2012. 43. In the Panel‟s view, the Applicant‟s claim for loss of rent during this peri od is reasonable and the FSP should meet the Applicant‟s claim for loss of rent for the period 23 June 2012 to 23 August 2012. 44. The Applicant has also stated he is seeking lost rent from 2 March 2013 to 20 April 2013. The Applicant says he chose not to source another tenant and instead placed the property on the market. He is seeking the balance of the 12 month lease paid to him. 45. The Panel has carefully considered the policy wording in this regard. The Panel notes the policy does not allow for automatic cover for the period of the lease agreement. Rather, the policy says from the time of the Event until the time Your Lot/Unit or Common Area is relet following completion of rebuilding, repairs or replacement provided You demonstrate You have taken all reasonable actions to obtain a new tenant. 46. Therefore, loss of rent is payable until the property is re-tenanted at the completion of repairs provided it is demonstrated all reasonable actions have been taken to secure a new tenant. 47. However, in this instance, the Applicant appears to have made no endeavours to source a new tenant but chose instead to put the property on the market. Therefore, the question before the Panel is whether the FSP should be liable for the continuing payment of lost rent where the Applicant has chosen not to re-let the property. 48. The Panel has given careful consideration to this matter and notes the period claimed by the Applicant is approximately six weeks, which the Panel does not consider excessive. Although the Applicant had not sourced a new tenant, but for the excessive time taken to restore the bathroom, his original tenant would most likely have still been in residence. Therefore, in the Panel‟s view , after taking into account the claim and the Applicant‟s circumstances, it is fair in all the circumstances that the FSP covers the lost rent until the lease period was due to expire on 20 April 2013. Utilities and lot owner’s fees 49. The Applicant is seeking $12,351.51 in utilities and lot owners fees incurred. The Panel notes the FSP‟s policy has an additional benefit to allow payment of lot owner‟s fees up to a maximum of $1,000 where the property is not fit Case No: 298051 Determination Page 11 of 14 for habitation. The policy also allows up to $2,000 for additional electricity, gas, sewerage, water and management charges incurred as a result of a claimed event. 50. The Applicant has now provided documentation direct to the Service in support of his claim for these additional benefits. 51. The Panel has considered the documentation supplied as well as the policy wording and notes the policy allows up to $1,000 for lot owners fees where the property is not fit for habitation. The Panel accepts the Applicant incurred fees in excess of $1,000 whilst the repairs were being undertaken. 52. The FSP have now advised that they accept liability with respect to the lot owner ‟ s fees incurred in accordance with the terms of the policy and has agreed to indemnify the Applicant the sum of $1,000 being the policy limit. 53. In regard to the claim for utilities, the Panel notes the policy provides for „additional‟ costs incurred as a result of the claimed event. Whilst the Applicant has provided utilities bills for the period whilst he resided there to use in a comparison against the bills for the period whilst the works were undertaken, in order to determine what „additional‟ fees he incurred, the Panel accepts that as the property was largely uninhabited during this timeframe, all but the most minimal of water and electricity usage would be related to the repairs being undertaken. 54. Accordingly, after considering what is fair in all the circumstances, the Panel finds the Applicant has adequately demonstrated he incurred additional costs in excess of $2,000 for utilities whilst the repairs were being undertaken. On this basis, the Panel finds the Applicant is entitled to be reimbursed the sum of $2,000 pursuant to the terms of the policy. Lost savings, redundancy payment, additional interest accrued on loan, discharge of mortgage and real estate agent fees 55. The Applicant is seeki ng the FSP reimburse him for his savings and redundancy payment which he states was depleted as a result of this event. He is further seeking $24,628.48 in additional interest accrued on his mortgage as a result of his periods of hardship as agreed with his financier, including switching to interest only repayments. He is also seeking the costs of the agent fees incurred in selling the property and the early exit fees from his home loan, which the Applicant estimates will be approximately $19,000. 56. The FSP considers such losses are consequential losses and are therefore not covered under the terms of the policy. 57. The Panel has carefully considered this matter and notes the FSP‟s policy is clear in stating consequential losses are specifically excluded from co ver under all sections of the policy. Case No: 298051 Determination Page 12 of 14 58. Since consequential or financial loss is not defined in the policy, the Panel considers that a plain English meaning applies. The TOR defines “Consequential Financial Loss” as “indirect financial loss or damage”. 59. Consequential loss is often defined as the effect or result or as a logical conclusion or inference arising from the damage sustained. 60. Considering these definitions, the Panel understands the loss of savings or a redundancy payout, presumably to cover either the ongoing mortgage repayments, living expenses or the upgrades undertaken to the bathroom as a result of a claimed event refers to a pecuniary loss and in this instance, is an indirect consequence of the repairs to the bathroom or, as seems likely, contributed to by the unfortunate accident suffered by the Applicant. 61. Similarly, the Panel finds the fees incurred for the sale of the property and discharge of the mortgage to be consequential losses. Whilst the policy does provide cover for mortgage discharge fees, this is limited to circumstances where the property is a total loss as a result of a claimed event. As such, the Panel finds this benefit is not triggered in the current dispute. 62. Accordingly, the Panel is satisfied these losses claimed by the Applicant are consequential financial losses. As such type of loss is expressly excluded from cover in the policy, following its TOR, FOS is unable to consider awarding of compensation for such claims. 63. The Applicant has said he believes the FSP‟s handlin g of his claim to be so poor that the terms of the policy should not apply when considering these losses. However, the Panel notes this Service does not have the power to grant entitlements not provided for under the terms of the insurance contact and the TOR specifically excludes the ability to award punitive, exemplary or aggravated damages from the powers of the Service. Is the Applicant entitled to compensation as a result of the FSP’s handling of the claim? 64. However, this does not preclude the Panel from considering whether an award of compensation for non-financial loss is appropriate in the circumstances. The Applicant is seeking compensation for emotional stress that he states has been caused by the FSP‟s handling of the claim. 65. Whilst the Panel accepts that the FSP has, in the main, fulfilled its obligations to the Applicant pursuant to the terms of the policy, this does not preclude the Panel from considering whether the Applicant is entitled to compensation pursuant to the FOS Terms of Reference 9.3b. 66. The Panel accepts that to some degree, all insurance claims a re stressful and inconvenient. In order to invoke an order of compensation under 9.3b, the Panel must be satisfied that some action of the FSP caused the Applicant an unusual degree of inconvenience or time taken to resolve the situation. Case No: 298051 Determination Page 13 of 14 67. The Panel has considered the timeline of events in this matter and in particular, the delays and difficulties encountered from the time of the initial repairs to the ultimate completion of the repairs. 68. The Panel notes the bathroom required rectification on at least three occasions following the initial repairs. This involved not only the Applicant‟s time but led to extreme frustration with the Applicant, ultimately refusing access to the original repairer. 69. It became evident that the original repairer, DJ, was unable to remedy the defects and another contractor had to be engaged. It took time not only to engage the contractor AB, but they then took some three and half months to complete the repairs. 70. In all, the lengthy repairs and rectification required to this property meant the bathroom and residence was not able to be occupied by either the Applicant or his tenant for a period of nearly two years. 71. In the Panel‟s view, the actions of the FSP and their cont ractors have clearly caused an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant‟s expectation of enjoyment or peace of mind. 72. Accordingly, the Panel is satisfied it is appropriate to consider an award of compensation pursuant to Section 9.3b(i) of the TOR. The Panel considers an award of $1,000 to be appropriate in the circumstances. Determination 73. On the basis of the available information, the Panel determines the Applicant is entitled to be reimbursed loss of rent for the period 23 June 2012 to 23 August 2012 and 2 March 2013 to 20 April 2013. 74. The Panel determines the FSP has offered to pay a sum of $28,800 with respect to temporary accommodation costs incurred for the periods 16 April 2011 to 16 April 2012 as reasonable and meets the FSP‟s liability in accordance with the terms of the policy. 75. Further, the Panel determines that the FSP‟s agreement to pay the sum of $1,000 being the policy limit for special benefit 1(f) under the terms of the policy and settlement of the Applicant‟s claim for lot owner‟ s contribution and fees and to meet the FSP‟s liability under the terms of the policy. 76. The Panel determines that the FSP is liable to meet the Applicant‟s claim for electricity, gas, sewerage etc in the sum of $2,000 in accordance with the terms of the policy. Case No: 298051 Determination Page 14 of 14 77. The Panel further determines the Applicant is entitled to an award of compensation in the amount of $1,000 for the delays experienced in bringing this claim to a conclusion. 78. The Panel is satisfied the remainder of losses claimed by the Applicant are consequential losses which are specifically excluded from cover under the terms of the FSP‟s policy. The Panel is satisfied the FSP was entitled to decline that aspect of the Applicant‟s claim. 79. The Panel determines that interest is not applicable in this case, in view of the nature of the issues in dispute.