Text of the determination
Case No: 298051 Determination Page 1 of 14
Case number: 298051
General Insurance - Domestic Insurance - Home Building - Service - Delay in
Claim Handling - Settlement Amount - Compensation
15 October 2013
Background
1. The Applicant is a beneficiary of a strata insurance policy held in the name of
the Owners Corporation (OC) for the residences at the property.
2. In October 2010 the Applicant noted water leaking from the bathroom area.
A claim was lodged with the FSP in February 2011 and repairs undertaken.
However, the repairs were not effective in stopping the leak and further
repairs were authorised by the FSP. The bathroom required rectification on a
further three occasions.
3. The Applicant is unhappy with the delays experienced with bringing his claim
to a conclusion and the financial impact this has had on him and his partner.
He is requiring his financial losses as a result of this incident be covered by
the FSP.
Summary of Applicant’s position
4. The Applicant says there have been protracted delays in the FSP bringing
this matter to a conclusion which has directly impacted him and his partner.
The property was uninhabitable due to the non-functional bathroom and they
had to move out. They were unable to lease the property as it had no
bathroom and when they finally were able to install tenants, the bathroom
started leaking again immediately and the tenants had to vacate.
5. The property has been vacant for over two years due to this incident which
has caused him significant financial hardship resulting in the forced sale of
the property.
6. The Applicant says the original repairer „DJ‟ performed substandard works
on the bathroom and was required to re -attend and rectify it on at least three
occasions. He feels he was more than reasonable in allowing them access
to complete the works but eventually refused them entry to the site after
becoming frustrated with the quality of their work.
Determination
Case No: 298051 Determination Page 2 of 14
7. The Applicant says in addition to the poor repairs, DJ also caused other
damage to the home with their untidy habits, such as storing building waste
on the carpet and emptying buckets on the garden and driveway.
8. The Applicant says when the FSP finally appointed another builder „AB‟ to
complete the bathroom, AB still took another four months to complete
repairs, which the Applicant considers is an excessive timeframe. The
Applicant denies the FSP‟s inference that he caused or contributed to any of
the delays in bringing this matter to a conclusion.
9. The Applicant is seeking the FSP cover loss of rental income of $28,800 as
well as temporary accommodation costs of $73,200. He is also seeking
payment of the additional benefits of „utilities‟ and „lot owner‟s fees‟ for
$12,351.51, as well as the FSP reimburse him his lost savings a nd
redundancy payments of approximately $31,500 and the extra costs he
incurred on his mortgage of $24,628.48, as a result of this incident.
10. The Applicant has also been forced into the sale of the property and is
seeking the agent fees and costs incurred due to the early discharge of the
mortgage, estimated to be $19,000. The Applicant‟s claim is in the sum of
$189,479.99.
11. The Applicant is also seeking compensation for the manner in which the FSP
managed his claim. The Applicant believes the claim was so mishandled that
the terms of the policy should no longer apply.
Summary of FSP’s position
12. The FSP accepts there were delays in bringing the c laim to a timely
conclusion. However, it says there were a number of contributing factors to
this including the involvement of their insured‟s representative, the OC, as
well as the Applicant himself.
13. The FSP accepts the works undertaken by DJ were not of acceptable
standard and it authorised for rectification to be undertaken on three
occasions. It also appointed an alternative builder to finally complete the
works, at the request of the Applicant.
14. The FSP says it has managed the claim in a timely manner and acted
quickly and decisively when made aware of issues regarding the bathroom.
It negotiated with DJ to cover some of the Applicant‟s out of pocket
expenses such as paying for temporary accommodation for his tenants on
an ex gratia basis. It has also provided payments for lost rental income for
the periods the tenants were unable to reside in the premises.
15. The FSP says it has requested the Applicant provide documentation in
support of his claim for utilities, lot owner‟s fees and temporary
accommodation for him and his partner so it can consider these costs under
the terms of the policy. However, the Applicant has not supplied the
Case No: 298051 Determination Page 3 of 14
documents as requested. The FSP remains willing to consider this aspect on
presentation of supporting documentation.
16. The FSP says other costs such as additional interest accrued on the
mortgage and the spent savings and redundancy payment are consequential
losses which are not covered under the terms of the policy. There is a
benefit for discharge of mortgage in the policy, however, this only applies
when the property is a total loss. The FSP denies its conduct of the claim
has placed the Applicant in financial difficulty, noting the Applicant was
involved in a serious accident in April 2011, with his injuries leaving him
incapac itated. The FSP considers the Applicant‟s inability to work led to his
financial difficulties rather than any action on its behalf.
17. The FSP has reviewed its handling of the claim and maintains it has
managed the progression of the claim in a timely manner. It does not agree
the Applicant is entitled to compensation.
18. The FSP relies on the following policy provisions:
“ What you are covered for
Policy 1 – Insured Property
This policy is designed to cover you for accidental loss or damage to your
insured property (building and common area contents) that occurs during the
period of insurance.
...
Special Benefits
Special benefits are included in addition to Your Sum Insured for Policy 1.
1 Temporary accommodation
a Temporary accommodation
When You occupy Your Lot/Unit We will pay the reasonable
cost of Temporary Accommodation You necessarily incur:
i. If Your Lot/Unit is damaged and made unfit to be occupied for
its intended purposes by any Event not excluded under Policy
1 or General Exclusions.
...
We will pay:
♦ under a i from the time of the Event until the time You reoccupy Your
Lot/Unit following completion of rebuilding, repairs or replacement.
...
b Rent
When You have leased out or can substantiate by means of a
signed agreement that You would have leased out Your
Lot/Unit or Common Area We will pay the actual Rent You lose
or would have lost:
Case No: 298051 Determination Page 4 of 14
i. if Your Lot/Unit or Common Area is damaged and made unfit
to be occupied for its intended purpose by any Event not
excluded under Policy 1 or General Exclusions.
...
We will pay:
♦ under b i from the time of the Event until the time Your Lot/Unit or
Common Area is relet following completion of rebuilding, repairs or
replacement provided You demonstrate You have taken all
reasonable actions to obtain a new tenant.
...
f Lot owners’ contributions and fees
We will pay, up to $1,000 a Lot/Unit, for contributions, levies,
maintenance and other fees You are required to pay during the
period Your Lot/Unit is made unfit to be occupied for its
intended purpose by any Event not excluded by Policy 1 or
General Exclusions.
...
6 Excess electricity, gas and similar charges
We will pay up to $2,000 for additional electricity, gas, sewerage,
water and management charges You are required to pay following
loss or damage to Your Insured Property by any Event excluded by
Policy 1 or General Exclusions.
...
14 Mortgage Discharge
We will pay up to $5,000 to discharge any mortgage over Your
Insured Property if it becomes a total loss, is not replaced and We
have paid the amount due under Policy 1 .
...
Exclusions – what we do not insure
...
2 We will not pay for:
...
c consequential loss (other than as specifically provided under
an operative Additional Benefit or Special Benefit), loss of use
or Depreciation. ”
Issues
19. Whether the FSP has fulfilled its obligations under the terms of the policy.
20. Whether the Applicant is entitled to compensation for the manner in which
the FSP managed his claim.
Case No: 298051 Determination Page 5 of 14
Reasons for decision
21. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with the FOS Terms of Reference. This is due to the
circumstances of the dispute. This dispute has not been the subject of a
FOS Recommendation and has proceeded directly to Determination.
22. This decision has been made by a Panel consisting of an Ombudsman and
two Panel members with extensive experience in the insurance industry and
consumer claims.
23. The Panel is satisfied a full exchange of informatio n has taken place
between each party and each party has had the opportunity to address any
issues raised.
24. The Applicant is not the insured in this matter, but is a beneficiary of the
policy held by the Owners Corporation (OC) as a homeowner and member
of the OC. This arrangement is recognised by Section 48 of the Act.
25. It is not disputed between the parties the Applicant suffered water damage to
his premises, for which a claim was submitted and repairs conducted.
However, a dispute has since arisen between the parties regarding the
amounts offered in settlement by the FSP.
26. As the Applicant has brought the claim before the FSP, he bears the onus of
establishing the claimed loss, that is, the sum of $189,479.99 falls within the
terms of the policy.
27. The two parties have provided substantial amounts of material in support of
their respective positions. The Panel does not propose to recite this in detail,
save for where specifically relevant. However, it is clear this matter is quite
complex and protracted in nature and the Panel therefore considers it
necessary to consider the matter in an abbreviated chronological order, in
order to give proper consideration to the issues raised. The Panel notes the
following:
In October 2010 the Applicant noted the carpet in the hallway was
damp and notified the strata managers „CS‟ of the issue.
CS appointed a plumber to attend to repair the suspected leak and a
tiler to replace the shower tray. CS considered the repairs would be
paid for, out of the OC‟s sinking fund rather than by way of an
insurance claim.
The Applicant noted the water continued to leak from the bathroom and
requested the OC lodge a claim with the FSP. The OC refused to do so
and advised the Applicant to proceed with the shower tray replacement.
The Applicant contacted the FSP directly in early January 2011 and
was advised he is able to claim on the OC policy directly and a claim
was lodged.
Case No: 298051 Determination Page 6 of 14
A quotation for repairs was prepared by builder „AN‟ and provided to
CS, who sent this onto the FSP on 11 February 2011.
The FSP approved AN to undertake the necessary plumbing repairs on
25 February 2011, with those repairs completed on or around 14 March
2011.
On 14 March 2011 the Applicant asked the FSP to appoint an assessor
to inspect the resultant damage. The FSP was unaware of any
resultant damage and asked AN to re-attend to inspect same.
AN contacted the Applicant on 12 April 2011 advising that in their
opinion, no resultant damage was caused in this incident.
The Applicant corresponded with AN over this issue, however, as he
did not receive a satisfactory response, appointed builders „SG‟ on 12
May 2011 to inspect the bathroom. The Applicant supplied a copy of
SG‟s report to the FSP on 26 May 2011, which set out the resultant
damage to the premises.
The Applicant also vacated the premises in or around May 2011
reportedly due to the mould and odour from the bathroom.
In light of the new information provided, the FSP appointed loss
adjuster „MF‟ to inspect the Applicant‟s property. MF attended on or
around 30 May 2011 and requested SG and DJ provide quotations for
the repairs. MF also requested SG to undertake further leak detection
tests.
Upon receipt of the quotations, the FSP offered to cash settle the claim
in lieu of repairs, based on the SG quotation.
A release was subsequently prepared which was signed and returned
by the Applicant on 12 July 2011.
CS disputed the FSP‟s method of settlement and requested the cash
settlement be rescinded and repairs undertaken instead. CS also
disputed the amount offered in settlement and requested further
quotations be obtained.
The Applicant was informed of this delay by the FSP via a letter dated
18 August 2011, although the Applicant was aware of the delay and
had been liaising with CS and the OC over the issue since 27 July
2011. Further discussions were held with the Applicant and CS over
CS‟s and the OC‟s objections in proceeding with the claim.
The Applicant also raised concerns with DJ‟s revised quotation to the
FSP. The FSP requested MF to re-attend the property with the
Applicant and DJ, to discuss the issues raised. This meeting took place
on 6 October 2011.
On or around 15 September 2011 the Applicant applied for financial
hardship assistance on his mortgage. This was granted for a period of
three months, whereby the mortgagee did not require payments to be
made during that period.
Case No: 298051 Determination Page 7 of 14
After further discussions regarding DJ‟s scope of works (SOW) , DJ was
authorised to proceed with repairs on 20 October 2011.
DJ commenced repairs to the bathroom on or around 2 November
2011.
Repairs were halted in December 2011 until late January 2012,
although the parties differ as to the reasons why.
The Applicant made a further application on the grounds of financial
hardship to his mortgagee to pay interest only on his mortgage for the
six months commencing 28 December 2011.
The Applicant had decided to undertake some works outside of the
SOW to the bathroom and these parts were received on or around 1
February 2012. Repairs recommenced on or around this date.
The bathroom was near completion on 20 March 2012 when the
Applicant raised some concerns regarding the quality of the repairs.
Rectification was approved, with the bathroom being completely
refitted. The bathroom was scheduled to be completed by the end of
April 2012.
Accordingly, the Applicant arranged a tenant to occupy the premises
from 20 April 2012 to 1 May 2012 on a conditional tenancy agreement
(due to the pending completion of the bathroom repairs) and from 1
May 2012 on a permanent tenancy agreement for 12 months.
On or around 23 April 2012 it was noted that water was again leaking
from the bathroom.
DJ was requested to undertake rectification and the property was
deemed uninhabitable whilst the bathroom was re-done. Repairs were
completed on or around 1 June 2012.
The FSP agreed to pay loss of rent for the period of 20 April 2012 to 1
June 2012 at the rate of $600 per week.
The Applicant replaced the carpet in the lounge and hall with floating
floorboards and during the installation of the flooring it was noticed
water again coming from the bathroom. The Applicant advised the FSP
of this on 9 August 2012.
The FSP subsequently agreed to cover the cost of the replacement
flooring in the amount of $2,694.43.
On 10 August 2012 a site meeting was held between the Applicant, MF
and DJ to discuss the claim. Works were agreed on with the bathroom
requiring another complete re-fit. DJ agreed to cover the costs of
temporary accommodation for the tenant whilst works were undertaken.
Rectification commenced on or around 27 August 2012. On or around
11 September 2012 DJ informed the Applicant the repairs had been
unsuccessful and the bathroom would require re-fitting again.
Case No: 298051 Determination Page 8 of 14
The Applicant advised the FSP the same day he would no longer allow
DJ access to the property and requested another builder be appointed
to undertake the works.
On 18 September 2012 a site meeting was held with MF, AB and
building consultant „C‟ to discuss the works required to reinstate the
bathroom. AB was subsequently authorised by the FSP on or around
25 September 2012 to complete the bathroom works.
The revised SOW also included painting of the premises and cleaning
of the carpet in recognition of the damage done by DJ. The FSP also
agreed to cover loss of rental income from 24 August 2012 until the
property was habitable again.
AB commenced repairs on or around 18 October 2012 and were
completed on or around 1 February 2013.
The FSP also agreed to cover loss of rent until 2 March 2013, to allow
the Applicant time to source a new tenant.
The FSP requested C complete a post-repair inspection which was
undertaken on 6 February 2013. The Applicant raised concerns to the
FSP on 22 March 2013, stating the carpet had not been replaced as
agreed and he would therefore not sign the release.
C undertook a further inspection on 1 May 2013 and was satisfied all
claim related repairs were completed satisfactorily.
28. There are several issues in dispute in this matter and the Panel will consider
each item separately below.
Temporary Accommodation
29. The Applicant is seeking temporary accommodation costs of $28,800, being
for the period 16 April 2011 to 16 April 2012 on the basis the property was
not habitable.
30. In his later submission to the Service, the Applicant has provided a statutory
declaration from his father saying there was an arrangement between the
two for the Applicant to rent his „downstairs residence‟ for the sum of $600
per week. The Applicant‟s fa ther says the Applicant has paid $7,000 to date
and owes him another $66,200 for rent. The Panel will therefore assume the
Applicant is seeking the higher amount of $73,200 in respect of the
temporary accommodation.
31. The FSP in their latest correspondence to the Service have advised that they
have now agreed to accept this portion of the Applicant‟s claim in the sum of
$28,800.
32. The FSP maintains however, that the Applicant is not entitled to temporary
accommodation expenses beyond April 2012 as the property was occupied
by a tenant after that time and the Applicant would have been eligible for
loss of rent payments.
Case No: 298051 Determination Page 9 of 14
33. The Panel notes that the Applicant has not provided any actual proof of any
payments made with respect to the temporary accommodation. The Panel
notes, however, that the Applicant was involved in a serious accident in April
2011 which left him confined to a wheelchair for an indefinite period of time.
This unfortunate change in the Applicant‟s circumstances meant his capacity
to live in the premises with a lack of a functional shower facility was severely
limited.
34. The Panel accepts that the lack of a functional shower facility at the property
meant that the property was no longer safely habitable for the Applicant‟s
purposes and therefore it is reasonable to consider the property
uninhabitable for the period from 16 April 2011 to 16 April 2012.
35. The only supporting documentation provided by the Applicant has been the
recent statutory declaration provided in his last submission to the Service.
Whilst the statutory declaration now identifies a sum of $600 per week as
being his “rent”. This amount seems vague.
36. In the Panel‟s view, in the absence of any proof of actual payment of the
temporary accommodation, the FSP‟s offer to accept the Applicant‟s origi nal
claim for temporary accommodation costs of $28,800 is reasonable.
Loss of rent
37. The Applicant is seeking lost rental income of $28,800 being for the period
20 April 2012 to 20 April 2013 on the basis the tenants were unable to reside
at the premises.
38. The Panel notes that in anticipation of the completed repairs, the property
was tenanted by the Applicant effective 20 April 2012 for 12 months. The
first ten days rental was $270 due to the bathroom works, with the monthly
rent being $2,400pcm thereafter.
39. The FSP has advised that it has already accepted the loss of rent claim for
the following periods:
20 April 2012 to 1 June 2012 - $3,600;
24 August 2012 to 19 October 2012 - $4,153.90
20 October 2012 to 24 November 2012 - $2,769.25
25 November 2012 to 26 January 2013 - $4,984.64
27 January 2013 to 2 March 2013 - $2,769.25
40. The Applicant says the tenant refused to pay rent whilst the bathroom works
were being completed. Although the Applicant has not detailed what period
of time he is referring to, in the Pa nel‟s view , this could only be the period
from 1 June 2012 to 24 August 2012.
Case No: 298051 Determination Page 10 of 14
41. Again the Panel notes from the FSP‟s latest submission of 4 September
2013, that the repairs were completed by DJ on 1 June 2012. The C report
relied upon, confirms the property was occupied by the tenant and some
three weeks later, that is three weeks after 1 June 2012, when the bathroom
was leaking. According to the submission in light of this, DJ placed the
tenants in temporary accommodation.
42. It is likely therefore that the Applicant is claiming that the tenants refused to
pay rent from the period they were placed in temporary accommodation at
DJ‟s expense on or about 23 June 2012 until 23 August 2012.
43. In the Panel‟s view, the Applicant‟s claim for loss of rent during this peri od is
reasonable and the FSP should meet the Applicant‟s claim for loss of rent for
the period 23 June 2012 to 23 August 2012.
44. The Applicant has also stated he is seeking lost rent from 2 March 2013 to
20 April 2013. The Applicant says he chose not to source another tenant and
instead placed the property on the market. He is seeking the balance of the
12 month lease paid to him.
45. The Panel has carefully considered the policy wording in this regard. The
Panel notes the policy does not allow for automatic cover for the period of
the lease agreement. Rather, the policy says from the time of the Event until
the time Your Lot/Unit or Common Area is relet following completion of
rebuilding, repairs or replacement provided You demonstrate You have
taken all reasonable actions to obtain a new tenant.
46. Therefore, loss of rent is payable until the property is re-tenanted at the
completion of repairs provided it is demonstrated all reasonable actions have
been taken to secure a new tenant.
47. However, in this instance, the Applicant appears to have made no
endeavours to source a new tenant but chose instead to put the property on
the market. Therefore, the question before the Panel is whether the FSP
should be liable for the continuing payment of lost rent where the Applicant
has chosen not to re-let the property.
48. The Panel has given careful consideration to this matter and notes the
period claimed by the Applicant is approximately six weeks, which the Panel
does not consider excessive. Although the Applicant had not sourced a new
tenant, but for the excessive time taken to restore the bathroom, his original
tenant would most likely have still been in residence. Therefore, in the
Panel‟s view , after taking into account the claim and the Applicant‟s
circumstances, it is fair in all the circumstances that the FSP covers the lost
rent until the lease period was due to expire on 20 April 2013.
Utilities and lot owner’s fees
49. The Applicant is seeking $12,351.51 in utilities and lot owners fees incurred.
The Panel notes the FSP‟s policy has an additional benefit to allow payment
of lot owner‟s fees up to a maximum of $1,000 where the property is not fit
Case No: 298051 Determination Page 11 of 14
for habitation. The policy also allows up to $2,000 for additional electricity,
gas, sewerage, water and management charges incurred as a result of a
claimed event.
50. The Applicant has now provided documentation direct to the Service in
support of his claim for these additional benefits.
51. The Panel has considered the documentation supplied as well as the policy
wording and notes the policy allows up to $1,000 for lot owners fees where
the property is not fit for habitation. The Panel accepts the Applicant incurred
fees in excess of $1,000 whilst the repairs were being undertaken.
52. The FSP have now advised that they accept liability with respect to the lot
owner ‟ s fees incurred in accordance with the terms of the policy and has
agreed to indemnify the Applicant the sum of $1,000 being the policy limit.
53. In regard to the claim for utilities, the Panel notes the policy provides for
„additional‟ costs incurred as a result of the claimed event. Whilst the
Applicant has provided utilities bills for the period whilst he resided there to
use in a comparison against the bills for the period whilst the works were
undertaken, in order to determine what „additional‟ fees he incurred, the
Panel accepts that as the property was largely uninhabited during this
timeframe, all but the most minimal of water and electricity usage would be
related to the repairs being undertaken.
54. Accordingly, after considering what is fair in all the circumstances, the Panel
finds the Applicant has adequately demonstrated he incurred additional
costs in excess of $2,000 for utilities whilst the repairs were being
undertaken. On this basis, the Panel finds the Applicant is entitled to be
reimbursed the sum of $2,000 pursuant to the terms of the policy.
Lost savings, redundancy payment, additional interest accrued on loan,
discharge of mortgage and real estate agent fees
55. The Applicant is seeki ng the FSP reimburse him for his savings and
redundancy payment which he states was depleted as a result of this event.
He is further seeking $24,628.48 in additional interest accrued on his
mortgage as a result of his periods of hardship as agreed with his financier,
including switching to interest only repayments. He is also seeking the costs
of the agent fees incurred in selling the property and the early exit fees from
his home loan, which the Applicant estimates will be approximately $19,000.
56. The FSP considers such losses are consequential losses and are therefore
not covered under the terms of the policy.
57. The Panel has carefully considered this matter and notes the FSP‟s policy is
clear in stating consequential losses are specifically excluded from co ver
under all sections of the policy.
Case No: 298051 Determination Page 12 of 14
58. Since consequential or financial loss is not defined in the policy, the Panel
considers that a plain English meaning applies. The TOR defines
“Consequential Financial Loss” as “indirect financial loss or damage”.
59. Consequential loss is often defined as the effect or result or as a logical
conclusion or inference arising from the damage sustained.
60. Considering these definitions, the Panel understands the loss of savings or a
redundancy payout, presumably to cover either the ongoing mortgage
repayments, living expenses or the upgrades undertaken to the bathroom as
a result of a claimed event refers to a pecuniary loss and in this instance, is
an indirect consequence of the repairs to the bathroom or, as seems likely,
contributed to by the unfortunate accident suffered by the Applicant.
61. Similarly, the Panel finds the fees incurred for the sale of the property and
discharge of the mortgage to be consequential losses. Whilst the policy does
provide cover for mortgage discharge fees, this is limited to circumstances
where the property is a total loss as a result of a claimed event. As such, the
Panel finds this benefit is not triggered in the current dispute.
62. Accordingly, the Panel is satisfied these losses claimed by the Applicant are
consequential financial losses. As such type of loss is expressly excluded
from cover in the policy, following its TOR, FOS is unable to consider
awarding of compensation for such claims.
63. The Applicant has said he believes the FSP‟s handlin g of his claim to be so
poor that the terms of the policy should not apply when considering these
losses. However, the Panel notes this Service does not have the power to
grant entitlements not provided for under the terms of the insurance contact
and the TOR specifically excludes the ability to award punitive, exemplary or
aggravated damages from the powers of the Service.
Is the Applicant entitled to compensation as a result of the FSP’s handling of
the claim?
64. However, this does not preclude the Panel from considering whether an
award of compensation for non-financial loss is appropriate in the
circumstances. The Applicant is seeking compensation for emotional stress
that he states has been caused by the FSP‟s handling of the claim.
65. Whilst the Panel accepts that the FSP has, in the main, fulfilled its
obligations to the Applicant pursuant to the terms of the policy, this does not
preclude the Panel from considering whether the Applicant is entitled to
compensation pursuant to the FOS Terms of Reference 9.3b.
66. The Panel accepts that to some degree, all insurance claims a re stressful
and inconvenient. In order to invoke an order of compensation under 9.3b,
the Panel must be satisfied that some action of the FSP caused the
Applicant an unusual degree of inconvenience or time taken to resolve the
situation.
Case No: 298051 Determination Page 13 of 14
67. The Panel has considered the timeline of events in this matter and in
particular, the delays and difficulties encountered from the time of the initial
repairs to the ultimate completion of the repairs.
68. The Panel notes the bathroom required rectification on at least three
occasions following the initial repairs. This involved not only the Applicant‟s
time but led to extreme frustration with the Applicant, ultimately refusing
access to the original repairer.
69. It became evident that the original repairer, DJ, was unable to remedy the
defects and another contractor had to be engaged. It took time not only to
engage the contractor AB, but they then took some three and half months to
complete the repairs.
70. In all, the lengthy repairs and rectification required to this property meant the
bathroom and residence was not able to be occupied by either the Applicant
or his tenant for a period of nearly two years.
71. In the Panel‟s view, the actions of the FSP and their cont ractors have clearly
caused an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the Applicant‟s expectation of
enjoyment or peace of mind.
72. Accordingly, the Panel is satisfied it is appropriate to consider an award of
compensation pursuant to Section 9.3b(i) of the TOR. The Panel considers
an award of $1,000 to be appropriate in the circumstances.
Determination
73. On the basis of the available information, the Panel determines the Applicant
is entitled to be reimbursed loss of rent for the period 23 June 2012 to 23
August 2012 and 2 March 2013 to 20 April 2013.
74. The Panel determines the FSP has offered to pay a sum of $28,800 with
respect to temporary accommodation costs incurred for the periods 16 April
2011 to 16 April 2012 as reasonable and meets the FSP‟s liability in
accordance with the terms of the policy.
75. Further, the Panel determines that the FSP‟s agreement to pay the sum of
$1,000 being the policy limit for special benefit 1(f) under the terms of the
policy and settlement of the Applicant‟s claim for lot owner‟ s contribution and
fees and to meet the FSP‟s liability under the terms of the policy.
76. The Panel determines that the FSP is liable to meet the Applicant‟s claim for
electricity, gas, sewerage etc in the sum of $2,000 in accordance with the
terms of the policy.
Case No: 298051 Determination Page 14 of 14
77. The Panel further determines the Applicant is entitled to an award of
compensation in the amount of $1,000 for the delays experienced in bringing
this claim to a conclusion.
78. The Panel is satisfied the remainder of losses claimed by the Applicant are
consequential losses which are specifically excluded from cover under the
terms of the FSP‟s policy. The Panel is satisfied the FSP was entitled to
decline that aspect of the Applicant‟s claim.
79. The Panel determines that interest is not applicable in this case, in view of
the nature of the issues in dispute.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.