Home / Financial Firm (Unknown - Insurer) / Determination 297363

Determination 297363

Hailstorm claim scope of works, carpet cash settlement and claim handling delays

FirmFinancial Firm (Unknown - Insurer)
Decided2014-02-25
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$500
Amount claimed$184,000
SourceAFCA PDF

Summary

The Applicants disputed the FSP's hailstorm scope of works, its $4,446.53 carpet cash settlement and its claim handling, and sought about $184,000 in repairs, accommodation and compensation. AFCA found the carpet offer reasonable, ordered a revised scope including additional storm items, temporary accommodation, reimbursement of the architect's fees and $500 compensation.

The FSP could not rely on PDS terms it did not prove were provided, so standard cover applies; the insured is indemnified for storm damage, and the carpet offer was reasonable under that standard.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay non financial lossreassess claimrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 297363 Determination Page 1 of 14 Case number: 297363 General Insurance - Domestic Insurance - Home Building - Service - Delay in claim handling 24 January 2014 Summary Description  This dispute concerns issues raised by the Applicants about the scope of works prepared by the FSP to repair damage to their home following a hailstorm. The Applicants also dispute the FSP’s proposed cash settlement in respect of their damaged carpet and are generally dissatisfied with the manner in which the FSP has handled their claim. Basis of Determination  The FSP’s proposed cash settlement for the carpet is appropriate, having regard to its obligations and good industry practice.  The FSP has accepted liability for the additional items of damage identified by the Applicants’ architect, and has also agreed to provide the Applicants with information about the contractors it will engage to carry out the repairs.  The FSP is entitled to arrange for the repairs to be carried out. While the Applicants are to be provided with certain information in relation to the repairs, the level of control over the repairs which they are seeking is not reasonable in the circumstances. Determination  The FSP is to prepare and cost a revised scope of works incorporating the additional items of damage identified by the Applicants’ architect. The FSP is to arrange for the works to be completed subject to certain specified conditions, including the provision of certain information to the Applicants.  The FSP is to provide the Applicants with temporary accommodation benefits in accordance with the terms of the policy, if required based on the revised scope of works.  If the Applicants are not satisfied with, or do not authorise, the revised scope of works, then either party may elect that the claim be cash settled Determination Case No: 297363 Determination Page 2 of 14 for an amount which reflects the cost (to the FSP) of completing the repairs.  The Applicants are entitled to the amount of $500 as compensation for non- financial loss, together with reimbursement of their architect’s fees. Background 1. The Applicants held a home building and contents insurance policy with the FSP. The policy was current at the time of the loss. 2. On 26 December 2011, the Applicants lodged a claim under the policy for significant damage to their property following a hailstorm the previous day. 3. The FSP accepted the Applicants’ claim and authorised repairs to the property in accordance with a scope o f works prepared by the FSP’s builder (S). The FSP offered to cash settle the Applicants for damage to the upstairs carpet, when it was unable to source a suitable replacement. 4. The Applicants disputed the scope of works prepared by the FSP’s builder, following which the FSP authorised variations to the scope of works to cover additional items of damage. However, the FSP and the Applicants have been unable to agree the scope of works so that the repairs can proceed. 5. The Applicants say that the revised scope of works approved by the FSP does not include all works required to restore their property to its pre-loss condition. The Applicants also dispute the FSP’s offer of a cash s ettlement of $4,446.53 in respect of the damage to their carpet. 6. Further, the Applicants seek compensation for the manner in which the FSP has handled their claim. Summary of Applicants ’ position 7. The Applicants dispute that they were provided with a copy of the Product Disclosure Statement (PDS) in relation to their policy. They say that the FSP’s claim records show that they requested a copy of the PDS on 13 August 2012. They were previously unaware of the FSP’s policy in relation to the replacement of damaged carpet. 8. The Applicants are dissatisfied with the FSP’s decision to offer them a cash settlement to replace the carpet in the upstairs hallway and connected stairwell. The Applicants say that the FSP should also indemnify them for the cost of replacing the carpet in the four bedrooms leading off the hallway. 9. The Applicants’ preference is for the FSP to arrange and authorise the necessary repairs to their property, as they travel frequently for work. However, they are concerned about the quality of the repairs undertaken to Case No: 297363 Determination Page 3 of 14 date, and are anxious to ensure that any further repairs are carried out by appropriately skilled and qualified tradespeople. 10. Accordingly, the Applicants want the FSP to appoint an architect to oversee the works, and provide them with detailed information about the contractors who will undertake the repairs. The Applicants also want the FSP to provide them with a detailed scope of works, workmanship and materials specifications and a schedule for carrying out the repairs. 11. The Applicants say that the FSP has failed to deal with their claim in a timely manner and has breached section 3.2.4 of the Code of Practice (the “Code”). Further, by delaying the progress of their claim and approving an incomplete scope of works, the FSP has been negligent and has demonstrated bad faith. 12. The Applicants say that the FSP should be required to:  complete the necessary repairs in the manner requested or alternatively cash settle them for a total amount of $150,000;  fund the costs of temporary accommodation (of an appropriate standard) while repairs to their property are carried out, or cash settle them for an equivalent amount (which they estimate to be $24,000);  reimburse them for professional fees incurred during the course of their claim; and  pay them $10,000 as compensation for financial and non-financial loss incurred as a result of the FSP’s handling of their claim. Summary of FSP’s position 13. The FSP says that a copy of the PDS setting out the terms of cover was enclosed with the certificate of insurance sent to the Applicants. 14. The FSP says that it accepted the Applicants’ claim, arranged make safe repairs, assessed the damage and obtained quotations for the required repairs in accordance with a scope of works prepared by its builder (S) (which was subsequently varied to address further items of damage advised by the Applicants). 15. The FSP says that, as it was unable to source a suitable match for the original carpet, it offered the Applicants a cash settlement based on a quote provided by its carpet supplier (“C”) for the cost of replacing the carpet in the upstairs hallway and connected stairwell. The FSP disputes that it is required to replace undamaged sections of the carpet in the bedrooms leading off the hallway. 16. The FSP says that it is willing to provide the information requested by the Applicants in relation to the contractors appointed to carry out the repairs, and will make arrangements for the repairs to be appropriately supervised and inspected following completion. Case No: 297363 Determination Page 4 of 14 17. The FSP says that it will provide temporary accommodation benefits for the Applicants in accordance with the terms and conditions of the policy, should this be necessary having regard to the repairs required under the approved scope of works. 18. The FSP acknowledges that delays occurred in the handling of the Applicants’ claim and that the Applicants are dissatisfied with the level of service provided. However, the FSP says that it has formally apologised to the Applicants and, in any event, the delays were not such as should entitle the Applicants to compensation. The FSP says that, at the time of the Applicants’ claim, it was dealing with a number of natural disasters which significantly impacted its resources. Issues 19. Whether the FSP’s cash settlement offer is sufficient to satisfy its liability in relation to the damaged carpet. 20. Whether the FSP is obliged to carry out the repairs to the property in the manner requested by the Applicants. 21. Whether the Applicants are entitled to temporary accommodation benefits while the repairs are completed. 22. Whether the Applicants are entitled to compensation due to the manner in which the FSP has handled their claim. Reasons for decision 23. As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a Recommendation and has proceeded directly to Determination. 24. I am satisfied that a full exchange of material information has taken place between the parties and that each party has had the opportunity to address any issues raised therein. 25. The parties do not dispute that the Applicants’ home was damaged by a hail storm on 25 December 2011. However, the Applicants dispute the basis on which the FSP has proposed to settle their claim, and are dissatisfied with the manner in which the FSP has handled their claim. Provision of PDS 26. In determining the extent of its obligations in relation to the Applicants’ claim, the FSP has sought to rely on the terms of the Applicants’ policy, as set out Case No: 297363 Determination Page 5 of 14 in the PDS. The FSP says that a copy of the PDS was sent to the Applicants together with their certificate of insurance. 27. The Applicants say that the FSP is not entitled to rely on the terms of the policy as set out in the PDS, because they were not provided with a copy of the PDS prior to the insured event (and therefore had to request one during the course of the claim). 28. The FSP has provided general information in relation to its system for generating, printing and despatching policy documentation. However, the FSP has advised that it is unable to provide any specific information to establish that it provided a copy of the PDS to the Applicants prior to 23 September 2011 (being the date they renewed their policy for the period during which the hailstorm occurred). 29. In these circumstances, I am not satisfied the FSP has established that, on the balance of probabilities, it provided the Applicants with a copy of the PDS before they renewed their policy of insurance. 30. Accordingly, the FSP is unable to rely on the policy provisions as set out in the PDS, and is required to provide the Applicants with the minimum level of cover specified under the Insurance Contracts Act 1984 (the “Act”) and the Insurance Contracts Regulations 1985 (the “Regulations”), which is known as “standard cover”. Replacement of carpet 31. The Applicants are dissatisfied with the cash settlement of $4,446.53 offered by the FSP in relation to the carpeted area in the upper level of the Applicants’ house, which was damaged in the hailstorm. 32. The information provided by the parties establishes that:  the FSP accepted liability for water damage to the upstairs hallway carpet and attempted to source a replacement carpet for this area, as well as the connected stairwell;  despite contacting two carpet suppliers, the FSP was unable to obtain an exact match for the carpet (which it was informed by one of the suppliers was approximately 14 years old); and  as it was unable to obtain an exact match, and because the same carpet was used in the four bedrooms adjoining the hallway, the FSP offered the Applicants a cash settlement of $4,446.53, being the estimated cost of replacing the carpet in the hallway and stairwell, based on a quotation provided by one of the FSP’s suppliers. 33. The Applicants say that the FSP should be required to cash settle them for the cost of replacing the carpet in the four bedrooms leading off the hallway, as well as the carpet in the hallway and the connected stairwell. Case No: 297363 Determination Page 6 of 14 34. Under the “standard cover” provisions of the Act and Regulations, the minimum level of cover provided for a claim for storm damage under a policy of insurance which provides cover for home contents (including fixed floor coverings) is “the amount sufficient to indemnify the person who made the claim”. In considering a dispute which is governed by the standard cover provisions, FOS will also have regard to what is reasonable and fair in all the circumstances. 35. During the course of this dispute, the Applicants engaged an architect (“SK”) to inspect the damage to their property. In his report dated 26 June 2013, SK considered a number of items of storm damage claimed by the Applicants, including damage to the upstairs carpet. In this regard, SK stated that:  the carpet in the hallway was water stained;  there was a water stain on the carpet next to the bed in the master bedroom, which the Applicants claimed was caused by the hailstorm. However, SK was not able to determine the timing and cause of this stain and therefore it could not be directly attributed to the storm; and  the Applicants claimed that the carpet in the south west, so uth east and north west bedrooms was damaged by the hailstorm. However, SK could not see any water stains on the carpet in any of these rooms. 36. Based on SK’s report, I am satisfied that the only water damage to the upstairs carpet which was directly attributable to the hailstorm was the damage to the carpet in the hallway (which the FSP has agreed to cover). 37. Given the extent of the FSP’s obligations under “standard cover”, and having regard to usual industry practice, I am satisfied that the FSP’s offer to cash settle the Applicants for the cost of replacing the carpet in the hallway and connected stairwell was appropriate. I consider that, in these circumstances, the “amount sufficient to indemnify the insured” is the amount required to replace the damaged area of carpet, and the carpet in the immediate surrounds. In my view, the FSP’s obligations do not extend to replacing the carpet in the adjoining bedrooms which was not damaged by the insured event. I note that I would have reached the same conclusion, had the FSP been able to establish that it was entitled to rely on the relevant policy provisions. 38. Accordingly, I consider that the cash settlement of $4,446.53 offered by the FSP in respect of the damaged carpet is reasonable and complies with its obligations. Scope of works 39. The Applicants say that the scope of works prepared by the FSP’s builder (S) is incomplete and does not address all of the storm damage to their property. 40. The scope of works was originally prepared by S in January 2012 and was subsequently varied on several occasions to incorporate additional items of Case No: 297363 Determination Page 7 of 14 storm damage notified by the Applicants and authorised by the FSP. Other items of damage notified by the Applicants were rejected by the FSP based on advice from its contractors that they were not caused by the storm. 41. As noted above, during the course of this dispute, the Applicants engaged an architect (SK) to carry out a comprehensive assessment of the storm damage to their property. In his report dated 26 June 2013, SK considered 49 separate items of damage claimed by the Applicants, of which 22 had not been accepted by the FSP. SK reviewed each of the disputed items and concluded that the following items had been damaged by the storm and therefore should be accepted by the FSP:  eave overhang on front balcony – one panel;  sisalation paper in roof;  internal garage door;  repainting of timber bead on front balcony (although I note that this appears to have been included in the FSP’s current scope of works) ;  formal lounge front window sills (partial contribution only);  formal dining room wall and window sills (partial contribution only);  TV room wall and windows sills (partial contribution only);  master bedroom window sills (partial contribution only);  south west bedroom window sills (partial contribution only);  south east bedroom window sill;  north west bedroom window sills (partial contribution only); and  front and back balcony door sills (partial contribution only). 42. In his report, SK set out the works required to address each of the above issues, and provided an estimate of the costs involved. These additional costs amount to $23,635.90, of which approximately 80% is attributable to the replacement of the damaged sisalation paper in the roof (which also requires the removal and replacement of the roof tiles and battens). 43. In its submissions to FOS, the FSP acknowledged that SK’s report identified some items which were not included in its approved scope of works. The FSP has since agreed to include the additional items of storm damage identif ied in SK’s report in its approved scope of works, and has confirmed that it will obtain quotes for repairing this damage. 44. I have reviewed SK’s report, which includes a number of photographs of the relevant items of damage. I consider that SK is appropriately qualified to determine the cause of the damage to these items, and that his report provides a reasonable and logical explanation for each of his findings. 45. Accordingly, I consider that it is appropriate that the FSP accept liability for each of the items referred to in paragraph 41 above, on the basis and to the extent set out in SK’s report. Case No: 297363 Determination Page 8 of 14 46. In order to ensure that there is no misunderstanding between the parties as to the approved scope of works, the FSP should prepare a revised, comprehensive scope of works which includes the additional items identified in SK’s report, and provide a copy to the Applicants. Completion of works 47. The Applicants say tha t they have lost confidence in the ability of the FSP’s contractors to carry out the repair works to an appropriate standard. It appears that this has occurred mainly as a result of the Applicants’ dissatisfaction with repairs to a downpipe carried out by a builder engaged by the FSP to undertake make safe repairs soon after the claim was lodged. It does not appear that the FSP has not suggested that this builder will be engaged to carry out any of the further repairs, and the Applicants do not seem to have raised any other specific concerns about work performed by the FSP’s contractors to date. 48. When the Applicants expressed these concerns during the course of the claim process, the FSP offered to cash settle them for the cost of the repairs, so that they could appoint their own contractors. However, the Applicants rejected this offer and have subsequently confirmed that their preference is for the FSP to arrange the repairs. 49. However, the Applicants say that, in order to ensure that any further repairs are carried out to an appropriate standard, they require the FSP to provide them with:  details of two independent qualified architects, so that they can choose one architect to supervise and manage the repairs;  for each component of the repairs, details of at least two qualified contractors (including their registration details, references and qualifications) capable of carrying out that component of the work, so that they can choose which contractors carry out the repairs;  a detailed scope of works, applicable workmanship and materials specifications and an execution schedule that reflects a firm start date, firm milestones and a firm completion date; and  a lifetime guarantee of the repairs. 50. It is clear from the measures requested by the Applicants that they are seeking a high level of approval and control over the works, as well as detailed information as to how the works will be carried out. 51. In the circumstances, I do not consider that the level of control sought by the Applicants is justified. In particular, I note that:  as the party liable for the cost of the works, the FSP is entitled to select and appoint the contractors who will undertake the works (although it is expected to act reasonably in doing so); Case No: 297363 Determination Page 9 of 14  the Applicants have not provided any information which establishes that the contractors who the FSP proposes to engage are not suitably qualified and capable of undertaking the works;  the FSP has confirmed that the Applicants will have the benefit of a lifetime guarantee of the works. Accordingly, to the extent that there are any issues with the quality of the works, the Applicants will be able to seek rectification; and  it is not apparent from the nature of the works that supervision by an architect is either necessary or appropriate. The FSP has previously offered to arrange for its builder to appoint a supervisor to co-ordinate the repairs and to have an assessor complete quality inspections of the works. It is also open to the Applicants to have the works inspected by an independent expert (at their own expense) once they are completed, if they have any concerns at that stage . 52. In relation to the additional information sought by the Applicants about the FSP’s contractors to carry out the repairs, I note that:  the FSP has offered to provide the Applicants with details about the qualifications of its contractors and their proposed start dates. It appears that the FSP has previously provided the Applicants with some of this information, in the interests of progressing the claim; and  the FSP has noted that it may not be possible for all of the requested information to be provided upfront before the repairs commence, as additional sub-contractors may be engaged during the repair process. However, the FSP has agreed to provide details of any further contractors as and when they are appropriate. 53. As noted above, I consider that the FSP should be required to prepare a revised scope of works and provide a copy to the Applicants. In the circumstances, I consider that the revised scope of works:  should include a proposed start date and estimated completion date for each aspect of the works (to the extent reasonably practicable); and  should describe the works in sufficient detail to enable a clear understanding of the nature and extent of repairs which will be carried out. In this respect, I consider that the previous scopes of work prepared by the FSP’s builder (S) contain a sufficient level of detail. I do not consider that the FSP is required to provide the Applicants with information about the applicable workmanship and materials specifications (on the basis that the works will be carried out by suitably qualified contractors and are subject to a lifetime guarantee). 54. I consider that, if the Applicants are dissatisfied with the revised scope of works, it should be open to them at any time before the repairs commence to request that the FSP cash settle them for the cost (to the FSP) of carrying out the repairs. Given that the FSP has previously put forward a cash settlement as an appropriate way to finalise th e Applicants’ claim, I consider that it is fair in all the circumstances that this option remain available to them. Case No: 297363 Determination Page 10 of 14 Equally, if the Applicants do not agree to authorise the works, I consider that the FSP may elect to cash settle their claim. Temporary accommodation 55. The Applicants say that, as the roof of their property needs to be repaired, the property will not be habitable while the repairs are carried out. Accordingly, they say that the FSP should fund the costs of temporary accommodation. 56. The available information establishes that the FSP’s contractors have previously replaced eight roof tiles. The report prepared by the Applicant’s architect (SK) concluded that the remainder of the damage to the roof tiles was not attributable to the hailstorm, but found that the sisalation paper in the roof needed to be replaced (which required the removal and replacement of the timber battens and roof tiles). 57. It is not clear from the information available to me whether there will be a need for temporary accommodation while the repairs are carried out. However, I note that the FSP has agreed to provide the Applicants with temporary accommodation benefits in accordance with the terms and conditions of the policy, subject to the builder confirming that temporary accommodation is necessary. 58. Given the above, I consider that:  the revised scope of works to be prepared by the FSP should include confirmation of whether temporary accommodation will be required while any aspect of the repairs are carried out and, if so, how long such repairs are likely to take; and  the FSP should provide the Applicants with temporary accommodation benefits in accordance with the terms of their policy, for the time it takes to complete such repairs. Compensation 59. The Applicants are dissatisfied with the FSP’s management of their claim and say that it took an unreasonable amount of time for their claim to be processed. The Applicants say this has caused them “undue stress” and “immeasurable and immense damages”. However, the Applicants h ave not provided details of any specific financial losses which they have incurred as a result of the FSP’s claim handling (other than professional fees as referred to below). 60. The FSP acknowledges that delays occurred during the course of the Applicants’ claim and has apologised to the Applicants. However, the FSP says that the extent of these delays were not such as would justify the award of compensation. The FSP also notes that, at the time of the Applicants’ claim it was dealing with a number of claims arising from the same event (the Melbourne Christmas Day 2011 hailstorm) and that its resources (and Case No: 297363 Determination Page 11 of 14 those of its contractors) were also significantly stretched by significant floods which occurred in New South Wales, Victoria and Queensland at around the same time. 61. Under paragraph 9.3(b) of FOS’s Terms of Reference, compensation for non-financial loss (capped at $3,000) may be awarded where an insured has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the insured’s expectation of enjoyment or peace of mind. 62. However, FOS generally adopts a conservative approach to the award of compensation for non-financial loss. FOS expects an insured to be moderately robust, bear the normal inconve nience experienced when a problem occurs and take reasonable steps to reduce such inconvenience. 63. The FSP has provided copies of its systems records, a review of which provides a detailed chronology of the Applicants’ claim. The Applicants have also provided copies of correspondence with the FSP during the course of their claim. 64. My review of the information provided by the parties indicates that:  extended delays occurred at various stages during the claim handling process. Some of these delays where due to the actions of the FSP or its contractors – in particular, on several occasions, the FSP’s contractors failed to promptly provide the quotations requested by the FSP in order for the claim to be appropriately progressed;  the repair of the roof sisalation paper which has been confirmed as necessary by the Applicants’ architect (SK) (and subsequently accepted by the FSP) was identified in the initial scope of works prepared by the FSP’s builder (S). However, it appears that the FSP’s roof repairer (“J”) lat er advised that this was not required;  the FSP initially applied the incorrect excess to the Applicants’ claim; and  the FSP did not on all occasions provide the Applicants with updates on their claim within the timeframes agreed. The FSP’s systems records indicate that the Applicants followed up the FSP on a number of occasions seeking updates and further information in relation to their claim. 65. However, I consider that the FSP and its contractors were not responsible for all of the delays which occurred during the claim handling process. In this regard, I note that:  in part, the length of time taken to assess the damage to the Applicants’ property and prepare a scope of works was due to the need for the FSP’s contractors to re - attend the Applicants’ prope rty to assess additional items of damage raised during the claims process. In some cases, the FSP accepted these items, while in other cases, the FSP Case No: 297363 Determination Page 12 of 14 (and later the Applicants’ architect ) considered that the claimed damage was not attributable to the hailstorm;  it is clear that there was a breakdown in trust and communication between the Applicants and the FSP at a relatively early stage in the claim handling process, which resulted in misunderstandings and made it more difficult that it might otherwise ha ve been to resolve any subsequent issues which arose; and  the FSP appears to have made genuine efforts to resolve the Applicants’ concerns at various stages during the course of the claim – for example, by providing detailed information about its contracto rs, providing the Applicants a further opportunity to meet with its builder to review the scope of works, and offering the Applicants a cash settlement if they no longer wanted the FSP to arrange the repairs. 66. Given the above, in the circumstances, I consider that the FSP should be required to pay the Applicants the amount of $500 as compensation for non- financial loss incurred as a result of the claim handling process. 67. Under paragraph 9.4 of the Terms of Reference, FOS may require a financial services provider to reimburse an applicant for professional costs incurred during the course of their dispute. 68. As outlined above, the FSP has agreed to amend its scope of work to incorporate the additional items of damage confirmed in SK’s report as attributable to t he hail storm. Accordingly, I consider that SK’s report has been of assistance in progressing this dispute, and therefore the FSP should be required to reimburse the Applicants for SK’s professional fees, subject to the Applicants providing an appropriate invoice. Code of Practice 69. The Applicants say that the FSP has breached section 3.2.4 of the Code of Practice (the “Code”) , which requires the FSP to respond to routine requests for information within 10 business days. 70. For the reasons outlined above, I have awarded the Applicants the amount of $500 as compensation for non-financial loss as a result of the manner in which the FSP has handled their claim, including the delays which occurred at various times. 71. Further, I note that section 4.3 of the Code provides that the FSP may not be able to meet all standards of the Code following a catastrophe or disaster, due to the large number of claims received during such time. 72. I recognise that, at the time the Applicants lodged their claim, the FSP was dealing with a significant increase in claim volume, arising from the number of adverse weather events which occurred during this period. Accordingly, I consider that it would be unreasonable to hold the FSP to the timeframe set out in section 3.2.4 in these circumsta nces. Case No: 297363 Determination Page 13 of 14 73. For the reasons outlined above, I consider that the FSP should not be required to pay the Applicants additional compensation as a result of its failure to comply with the timeframe set out in section 3.2.4 of the Code. Determination 74. On the basis of the available information I determine that:  the cash settlement of $4,446.53 offered by the FSP in respect of the carpet is reasonable and complies with its obligations;  within 21 days of the Applicants accepting this Determination, the FSP is to appoint a suitably qualified and experienced builder to: a. prepare a revised scope of works for the repair of the storm damage to the Applicants’ house, which incorporates the additional items of damage identified in SK’ s report and describes the works in sufficient detail to enable a clear understanding of the nature and extent of repairs which will be carried out; b. provide a costing for the scope of works; c. provide a proposed start date and estimated completion date for each aspect of the works (to the extent reasonably practicable); and d. confirm whether temporary accommodation will be required while any aspect of the repairs are carried out;  the FSP is to provide a copy of the above information to the Applicants, together with details about the qualifications of its contractors and their proposed start dates prior to repairs commencing and as additional contractors are appointed from time to time;  subject to the Applicants authorising the scope of works, the FSP is to complete the works and make arrangements for its assessor to assess the works on completion. The FSP is to provide the Applicants with a lifetime guarantee of the works, in accordance with the terms of their policy;  if the FSP’s builder confirms that temporary accommodation will be required while any aspect of the repairs are carried out, then the FSP is to provide the Applicants with the benefit of temporary accommodation in accordance with the terms of their policy which such repairs are carried out;  if the Applicants are dissatisfied with the revised scope of works, they may at any time before the repairs commence request that the FSP cash settle them for the estimated cost (to the FSP) of carrying out the repairs. Equally, if the Applicants do not authorise the repairs in accordance with the revised scope of works prepared by the FSP in the manner set out above, then the FSP may elect to cash settle them for the cost of the repairs; Case No: 297363 Determination Page 14 of 14  the FSP is to pay the Applicants the amount of $500 as compensation for non-financial loss incurred as a result of the FSP ’s claims handling; and  the FSP is to reimburse the Applicants for the amount of RK’s fees, subject to the Applicants providing an appropriate invoice.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.