Text of the determination
Case No: 297363 Determination Page 1 of 14
Case number: 297363
General Insurance - Domestic Insurance - Home Building - Service - Delay in
claim handling
24 January 2014
Summary
Description
This dispute concerns issues raised by the Applicants about the scope of
works prepared by the FSP to repair damage to their home following a
hailstorm. The Applicants also dispute the FSP’s proposed cash
settlement in respect of their damaged carpet and are generally
dissatisfied with the manner in which the FSP has handled their claim.
Basis of Determination
The FSP’s proposed cash settlement for the carpet is appropriate, having
regard to its obligations and good industry practice.
The FSP has accepted liability for the additional items of damage identified
by the Applicants’ architect, and has also agreed to provide the Applicants
with information about the contractors it will engage to carry out the
repairs.
The FSP is entitled to arrange for the repairs to be carried out. While the
Applicants are to be provided with certain information in relation to the
repairs, the level of control over the repairs which they are seeking is not
reasonable in the circumstances.
Determination
The FSP is to prepare and cost a revised scope of works incorporating the
additional items of damage identified by the Applicants’ architect. The FSP
is to arrange for the works to be completed subject to certain specified
conditions, including the provision of certain information to the Applicants.
The FSP is to provide the Applicants with temporary accommodation
benefits in accordance with the terms of the policy, if required based on
the revised scope of works.
If the Applicants are not satisfied with, or do not authorise, the revised
scope of works, then either party may elect that the claim be cash settled
Determination
Case No: 297363 Determination Page 2 of 14
for an amount which reflects the cost (to the FSP) of completing the
repairs.
The Applicants are entitled to the amount of $500 as compensation for
non- financial loss, together with reimbursement of their architect’s fees.
Background
1. The Applicants held a home building and contents insurance policy with the
FSP. The policy was current at the time of the loss.
2. On 26 December 2011, the Applicants lodged a claim under the policy for
significant damage to their property following a hailstorm the previous day.
3. The FSP accepted the Applicants’ claim and authorised repairs to the
property in accordance with a scope o f works prepared by the FSP’s builder
(S). The FSP offered to cash settle the Applicants for damage to the upstairs
carpet, when it was unable to source a suitable replacement.
4. The Applicants disputed the scope of works prepared by the FSP’s builder,
following which the FSP authorised variations to the scope of works to cover
additional items of damage. However, the FSP and the Applicants have
been unable to agree the scope of works so that the repairs can proceed.
5. The Applicants say that the revised scope of works approved by the FSP
does not include all works required to restore their property to its pre-loss
condition. The Applicants also dispute the FSP’s offer of a cash s ettlement of
$4,446.53 in respect of the damage to their carpet.
6. Further, the Applicants seek compensation for the manner in which the FSP
has handled their claim.
Summary of Applicants ’ position
7. The Applicants dispute that they were provided with a copy of the Product
Disclosure Statement (PDS) in relation to their policy. They say that the
FSP’s claim records show that they requested a copy of the PDS on 13
August 2012. They were previously unaware of the FSP’s policy in relation to
the replacement of damaged carpet.
8. The Applicants are dissatisfied with the FSP’s decision to offer them a cash
settlement to replace the carpet in the upstairs hallway and connected
stairwell. The Applicants say that the FSP should also indemnify them for the
cost of replacing the carpet in the four bedrooms leading off the hallway.
9. The Applicants’ preference is for the FSP to arrange and authorise the
necessary repairs to their property, as they travel frequently for work.
However, they are concerned about the quality of the repairs undertaken to
Case No: 297363 Determination Page 3 of 14
date, and are anxious to ensure that any further repairs are carried out by
appropriately skilled and qualified tradespeople.
10. Accordingly, the Applicants want the FSP to appoint an architect to oversee
the works, and provide them with detailed information about the contractors
who will undertake the repairs. The Applicants also want the FSP to provide
them with a detailed scope of works, workmanship and materials
specifications and a schedule for carrying out the repairs.
11. The Applicants say that the FSP has failed to deal with their claim in a timely
manner and has breached section 3.2.4 of the Code of Practice (the “Code”).
Further, by delaying the progress of their claim and approving an incomplete
scope of works, the FSP has been negligent and has demonstrated bad
faith.
12. The Applicants say that the FSP should be required to:
complete the necessary repairs in the manner requested or
alternatively cash settle them for a total amount of $150,000;
fund the costs of temporary accommodation (of an appropriate
standard) while repairs to their property are carried out, or cash settle
them for an equivalent amount (which they estimate to be $24,000);
reimburse them for professional fees incurred during the course of their
claim; and
pay them $10,000 as compensation for financial and non-financial loss
incurred as a result of the FSP’s handling of their claim.
Summary of FSP’s position
13. The FSP says that a copy of the PDS setting out the terms of cover was
enclosed with the certificate of insurance sent to the Applicants.
14. The FSP says that it accepted the Applicants’ claim, arranged make safe
repairs, assessed the damage and obtained quotations for the required
repairs in accordance with a scope of works prepared by its builder (S)
(which was subsequently varied to address further items of damage advised
by the Applicants).
15. The FSP says that, as it was unable to source a suitable match for the
original carpet, it offered the Applicants a cash settlement based on a quote
provided by its carpet supplier (“C”) for the cost of replacing the carpet in the
upstairs hallway and connected stairwell. The FSP disputes that it is required
to replace undamaged sections of the carpet in the bedrooms leading off the
hallway.
16. The FSP says that it is willing to provide the information requested by the
Applicants in relation to the contractors appointed to carry out the repairs,
and will make arrangements for the repairs to be appropriately supervised
and inspected following completion.
Case No: 297363 Determination Page 4 of 14
17. The FSP says that it will provide temporary accommodation benefits for the
Applicants in accordance with the terms and conditions of the policy, should
this be necessary having regard to the repairs required under the approved
scope of works.
18. The FSP acknowledges that delays occurred in the handling of the
Applicants’ claim and that the Applicants are dissatisfied with the level of
service provided. However, the FSP says that it has formally apologised to
the Applicants and, in any event, the delays were not such as should entitle
the Applicants to compensation. The FSP says that, at the time of the
Applicants’ claim, it was dealing with a number of natural disasters which
significantly impacted its resources.
Issues
19. Whether the FSP’s cash settlement offer is sufficient to satisfy its liability in
relation to the damaged carpet.
20. Whether the FSP is obliged to carry out the repairs to the property in the
manner requested by the Applicants.
21. Whether the Applicants are entitled to temporary accommodation benefits
while the repairs are completed.
22. Whether the Applicants are entitled to compensation due to the manner in
which the FSP has handled their claim.
Reasons for decision
23. As advised to the parties, FOS has considered it appropriate to expedite this
dispute in accordance with the Operational Guidelines to the FOS Terms of
Reference, due to the nature of the dispute. Accordingly, this dispute has not
been the subject of a Recommendation and has proceeded directly to
Determination.
24. I am satisfied that a full exchange of material information has taken place
between the parties and that each party has had the opportunity to address
any issues raised therein.
25. The parties do not dispute that the Applicants’ home was damaged by a hail
storm on 25 December 2011. However, the Applicants dispute the basis on
which the FSP has proposed to settle their claim, and are dissatisfied with
the manner in which the FSP has handled their claim.
Provision of PDS
26. In determining the extent of its obligations in relation to the Applicants’ claim,
the FSP has sought to rely on the terms of the Applicants’ policy, as set out
Case No: 297363 Determination Page 5 of 14
in the PDS. The FSP says that a copy of the PDS was sent to the Applicants
together with their certificate of insurance.
27. The Applicants say that the FSP is not entitled to rely on the terms of the
policy as set out in the PDS, because they were not provided with a copy of
the PDS prior to the insured event (and therefore had to request one during
the course of the claim).
28. The FSP has provided general information in relation to its system for
generating, printing and despatching policy documentation. However, the
FSP has advised that it is unable to provide any specific information to
establish that it provided a copy of the PDS to the Applicants prior to 23
September 2011 (being the date they renewed their policy for the period
during which the hailstorm occurred).
29. In these circumstances, I am not satisfied the FSP has established that, on
the balance of probabilities, it provided the Applicants with a copy of the PDS
before they renewed their policy of insurance.
30. Accordingly, the FSP is unable to rely on the policy provisions as set out in
the PDS, and is required to provide the Applicants with the minimum level of
cover specified under the Insurance Contracts Act 1984 (the “Act”) and the
Insurance Contracts Regulations 1985 (the “Regulations”), which is known
as “standard cover”.
Replacement of carpet
31. The Applicants are dissatisfied with the cash settlement of $4,446.53 offered
by the FSP in relation to the carpeted area in the upper level of the
Applicants’ house, which was damaged in the hailstorm.
32. The information provided by the parties establishes that:
the FSP accepted liability for water damage to the upstairs hallway
carpet and attempted to source a replacement carpet for this area, as
well as the connected stairwell;
despite contacting two carpet suppliers, the FSP was unable to obtain
an exact match for the carpet (which it was informed by one of the
suppliers was approximately 14 years old); and
as it was unable to obtain an exact match, and because the same
carpet was used in the four bedrooms adjoining the hallway, the FSP
offered the Applicants a cash settlement of $4,446.53, being the
estimated cost of replacing the carpet in the hallway and stairwell,
based on a quotation provided by one of the FSP’s suppliers.
33. The Applicants say that the FSP should be required to cash settle them for
the cost of replacing the carpet in the four bedrooms leading off the hallway,
as well as the carpet in the hallway and the connected stairwell.
Case No: 297363 Determination Page 6 of 14
34. Under the “standard cover” provisions of the Act and Regulations, the
minimum level of cover provided for a claim for storm damage under a policy
of insurance which provides cover for home contents (including fixed floor
coverings) is “the amount sufficient to indemnify the person who made the
claim”. In considering a dispute which is governed by the standard cover
provisions, FOS will also have regard to what is reasonable and fair in all the
circumstances.
35. During the course of this dispute, the Applicants engaged an architect (“SK”)
to inspect the damage to their property. In his report dated 26 June 2013, SK
considered a number of items of storm damage claimed by the Applicants,
including damage to the upstairs carpet. In this regard, SK stated that:
the carpet in the hallway was water stained;
there was a water stain on the carpet next to the bed in the master
bedroom, which the Applicants claimed was caused by the hailstorm.
However, SK was not able to determine the timing and cause of this
stain and therefore it could not be directly attributed to the storm; and
the Applicants claimed that the carpet in the south west, so uth east and
north west bedrooms was damaged by the hailstorm. However, SK
could not see any water stains on the carpet in any of these rooms.
36. Based on SK’s report, I am satisfied that the only water damage to the
upstairs carpet which was directly attributable to the hailstorm was the
damage to the carpet in the hallway (which the FSP has agreed to cover).
37. Given the extent of the FSP’s obligations under “standard cover”, and having
regard to usual industry practice, I am satisfied that the FSP’s offer to cash
settle the Applicants for the cost of replacing the carpet in the hallway and
connected stairwell was appropriate. I consider that, in these circumstances,
the “amount sufficient to indemnify the insured” is the amount required to
replace the damaged area of carpet, and the carpet in the immediate
surrounds. In my view, the FSP’s obligations do not extend to replacing the
carpet in the adjoining bedrooms which was not damaged by the insured
event. I note that I would have reached the same conclusion, had the FSP
been able to establish that it was entitled to rely on the relevant policy
provisions.
38. Accordingly, I consider that the cash settlement of $4,446.53 offered by the
FSP in respect of the damaged carpet is reasonable and complies with its
obligations.
Scope of works
39. The Applicants say that the scope of works prepared by the FSP’s builder
(S) is incomplete and does not address all of the storm damage to their
property.
40. The scope of works was originally prepared by S in January 2012 and was
subsequently varied on several occasions to incorporate additional items of
Case No: 297363 Determination Page 7 of 14
storm damage notified by the Applicants and authorised by the FSP. Other
items of damage notified by the Applicants were rejected by the FSP based
on advice from its contractors that they were not caused by the storm.
41. As noted above, during the course of this dispute, the Applicants engaged
an architect (SK) to carry out a comprehensive assessment of the storm
damage to their property. In his report dated 26 June 2013, SK considered
49 separate items of damage claimed by the Applicants, of which 22 had not
been accepted by the FSP. SK reviewed each of the disputed items and
concluded that the following items had been damaged by the storm and
therefore should be accepted by the FSP:
eave overhang on front balcony – one panel;
sisalation paper in roof;
internal garage door;
repainting of timber bead on front balcony (although I note that this
appears to have been included in the FSP’s current scope of works) ;
formal lounge front window sills (partial contribution only);
formal dining room wall and window sills (partial contribution only);
TV room wall and windows sills (partial contribution only);
master bedroom window sills (partial contribution only);
south west bedroom window sills (partial contribution only);
south east bedroom window sill;
north west bedroom window sills (partial contribution only); and
front and back balcony door sills (partial contribution only).
42. In his report, SK set out the works required to address each of the above
issues, and provided an estimate of the costs involved. These additional
costs amount to $23,635.90, of which approximately 80% is attributable to
the replacement of the damaged sisalation paper in the roof (which also
requires the removal and replacement of the roof tiles and battens).
43. In its submissions to FOS, the FSP acknowledged that SK’s report identified
some items which were not included in its approved scope of works. The
FSP has since agreed to include the additional items of storm damage
identif ied in SK’s report in its approved scope of works, and has confirmed
that it will obtain quotes for repairing this damage.
44. I have reviewed SK’s report, which includes a number of photographs of the
relevant items of damage. I consider that SK is appropriately qualified to
determine the cause of the damage to these items, and that his report
provides a reasonable and logical explanation for each of his findings.
45. Accordingly, I consider that it is appropriate that the FSP accept liability for
each of the items referred to in paragraph 41 above, on the basis and to the
extent set out in SK’s report.
Case No: 297363 Determination Page 8 of 14
46. In order to ensure that there is no misunderstanding between the parties as
to the approved scope of works, the FSP should prepare a revised,
comprehensive scope of works which includes the additional items identified
in SK’s report, and provide a copy to the Applicants.
Completion of works
47. The Applicants say tha t they have lost confidence in the ability of the FSP’s
contractors to carry out the repair works to an appropriate standard. It
appears that this has occurred mainly as a result of the Applicants’
dissatisfaction with repairs to a downpipe carried out by a builder engaged
by the FSP to undertake make safe repairs soon after the claim was lodged.
It does not appear that the FSP has not suggested that this builder will be
engaged to carry out any of the further repairs, and the Applicants do not
seem to have raised any other specific concerns about work performed by
the FSP’s contractors to date.
48. When the Applicants expressed these concerns during the course of the
claim process, the FSP offered to cash settle them for the cost of the repairs,
so that they could appoint their own contractors. However, the Applicants
rejected this offer and have subsequently confirmed that their preference is
for the FSP to arrange the repairs.
49. However, the Applicants say that, in order to ensure that any further repairs
are carried out to an appropriate standard, they require the FSP to provide
them with:
details of two independent qualified architects, so that they can choose
one architect to supervise and manage the repairs;
for each component of the repairs, details of at least two qualified
contractors (including their registration details, references and
qualifications) capable of carrying out that component of the work, so
that they can choose which contractors carry out the repairs;
a detailed scope of works, applicable workmanship and materials
specifications and an execution schedule that reflects a firm start date,
firm milestones and a firm completion date; and
a lifetime guarantee of the repairs.
50. It is clear from the measures requested by the Applicants that they are
seeking a high level of approval and control over the works, as well as
detailed information as to how the works will be carried out.
51. In the circumstances, I do not consider that the level of control sought by the
Applicants is justified. In particular, I note that:
as the party liable for the cost of the works, the FSP is entitled to select
and appoint the contractors who will undertake the works (although it is
expected to act reasonably in doing so);
Case No: 297363 Determination Page 9 of 14
the Applicants have not provided any information which establishes that
the contractors who the FSP proposes to engage are not suitably
qualified and capable of undertaking the works;
the FSP has confirmed that the Applicants will have the benefit of a
lifetime guarantee of the works. Accordingly, to the extent that there are
any issues with the quality of the works, the Applicants will be able to
seek rectification; and
it is not apparent from the nature of the works that supervision by an
architect is either necessary or appropriate. The FSP has previously
offered to arrange for its builder to appoint a supervisor to co-ordinate
the repairs and to have an assessor complete quality inspections of the
works. It is also open to the Applicants to have the works inspected by
an independent expert (at their own expense) once they are completed,
if they have any concerns at that stage .
52. In relation to the additional information sought by the Applicants about the
FSP’s contractors to carry out the repairs, I note that:
the FSP has offered to provide the Applicants with details about the
qualifications of its contractors and their proposed start dates. It
appears that the FSP has previously provided the Applicants with some
of this information, in the interests of progressing the claim; and
the FSP has noted that it may not be possible for all of the requested
information to be provided upfront before the repairs commence, as
additional sub-contractors may be engaged during the repair process.
However, the FSP has agreed to provide details of any further
contractors as and when they are appropriate.
53. As noted above, I consider that the FSP should be required to prepare a
revised scope of works and provide a copy to the Applicants. In the
circumstances, I consider that the revised scope of works:
should include a proposed start date and estimated completion date for
each aspect of the works (to the extent reasonably practicable); and
should describe the works in sufficient detail to enable a clear
understanding of the nature and extent of repairs which will be carried
out. In this respect, I consider that the previous scopes of work
prepared by the FSP’s builder (S) contain a sufficient level of detail. I
do not consider that the FSP is required to provide the Applicants with
information about the applicable workmanship and materials
specifications (on the basis that the works will be carried out by suitably
qualified contractors and are subject to a lifetime guarantee).
54. I consider that, if the Applicants are dissatisfied with the revised scope of
works, it should be open to them at any time before the repairs commence to
request that the FSP cash settle them for the cost (to the FSP) of carrying
out the repairs. Given that the FSP has previously put forward a cash
settlement as an appropriate way to finalise th e Applicants’ claim, I consider
that it is fair in all the circumstances that this option remain available to them.
Case No: 297363 Determination Page 10 of 14
Equally, if the Applicants do not agree to authorise the works, I consider that
the FSP may elect to cash settle their claim.
Temporary accommodation
55. The Applicants say that, as the roof of their property needs to be repaired,
the property will not be habitable while the repairs are carried out.
Accordingly, they say that the FSP should fund the costs of temporary
accommodation.
56. The available information establishes that the FSP’s contractors have
previously replaced eight roof tiles. The report prepared by the Applicant’s
architect (SK) concluded that the remainder of the damage to the roof tiles
was not attributable to the hailstorm, but found that the sisalation paper in
the roof needed to be replaced (which required the removal and replacement
of the timber battens and roof tiles).
57. It is not clear from the information available to me whether there will be a
need for temporary accommodation while the repairs are carried out.
However, I note that the FSP has agreed to provide the Applicants with
temporary accommodation benefits in accordance with the terms and
conditions of the policy, subject to the builder confirming that temporary
accommodation is necessary.
58. Given the above, I consider that:
the revised scope of works to be prepared by the FSP should include
confirmation of whether temporary accommodation will be required
while any aspect of the repairs are carried out and, if so, how long such
repairs are likely to take; and
the FSP should provide the Applicants with temporary accommodation
benefits in accordance with the terms of their policy, for the time it takes
to complete such repairs.
Compensation
59. The Applicants are dissatisfied with the FSP’s management of their claim
and say that it took an unreasonable amount of time for their claim to be
processed. The Applicants say this has caused them “undue stress” and
“immeasurable and immense damages”. However, the Applicants h ave not
provided details of any specific financial losses which they have incurred as
a result of the FSP’s claim handling (other than professional fees as referred
to below).
60. The FSP acknowledges that delays occurred during the course of the
Applicants’ claim and has apologised to the Applicants. However, the FSP
says that the extent of these delays were not such as would justify the award
of compensation. The FSP also notes that, at the time of the Applicants’
claim it was dealing with a number of claims arising from the same event
(the Melbourne Christmas Day 2011 hailstorm) and that its resources (and
Case No: 297363 Determination Page 11 of 14
those of its contractors) were also significantly stretched by significant floods
which occurred in New South Wales, Victoria and Queensland at around the
same time.
61. Under paragraph 9.3(b) of FOS’s Terms of Reference, compensation for
non-financial loss (capped at $3,000) may be awarded where an insured has
suffered an unusual degree or extent of physical inconvenience, time taken
to resolve the situation or interference with the insured’s expectation of
enjoyment or peace of mind.
62. However, FOS generally adopts a conservative approach to the award of
compensation for non-financial loss. FOS expects an insured to be
moderately robust, bear the normal inconve nience experienced when a
problem occurs and take reasonable steps to reduce such inconvenience.
63. The FSP has provided copies of its systems records, a review of which
provides a detailed chronology of the Applicants’ claim. The Applicants have
also provided copies of correspondence with the FSP during the course of
their claim.
64. My review of the information provided by the parties indicates that:
extended delays occurred at various stages during the claim handling
process. Some of these delays where due to the actions of the FSP or
its contractors – in particular, on several occasions, the FSP’s
contractors failed to promptly provide the quotations requested by the
FSP in order for the claim to be appropriately progressed;
the repair of the roof sisalation paper which has been confirmed as
necessary by the Applicants’ architect (SK) (and subsequently
accepted by the FSP) was identified in the initial scope of works
prepared by the FSP’s builder (S). However, it appears that the FSP’s
roof repairer (“J”) lat er advised that this was not required;
the FSP initially applied the incorrect excess to the Applicants’ claim;
and
the FSP did not on all occasions provide the Applicants with updates on
their claim within the timeframes agreed. The FSP’s systems records
indicate that the Applicants followed up the FSP on a number of
occasions seeking updates and further information in relation to their
claim.
65. However, I consider that the FSP and its contractors were not responsible
for all of the delays which occurred during the claim handling process. In this
regard, I note that:
in part, the length of time taken to assess the damage to the Applicants’
property and prepare a scope of works was due to the need for the
FSP’s contractors to re - attend the Applicants’ prope rty to assess
additional items of damage raised during the claims process. In some
cases, the FSP accepted these items, while in other cases, the FSP
Case No: 297363 Determination Page 12 of 14
(and later the Applicants’ architect ) considered that the claimed
damage was not attributable to the hailstorm;
it is clear that there was a breakdown in trust and communication
between the Applicants and the FSP at a relatively early stage in the
claim handling process, which resulted in misunderstandings and made
it more difficult that it might otherwise ha ve been to resolve any
subsequent issues which arose; and
the FSP appears to have made genuine efforts to resolve the
Applicants’ concerns at various stages during the course of the claim –
for example, by providing detailed information about its contracto rs,
providing the Applicants a further opportunity to meet with its builder to
review the scope of works, and offering the Applicants a cash
settlement if they no longer wanted the FSP to arrange the repairs.
66. Given the above, in the circumstances, I consider that the FSP should be
required to pay the Applicants the amount of $500 as compensation for non-
financial loss incurred as a result of the claim handling process.
67. Under paragraph 9.4 of the Terms of Reference, FOS may require a
financial services provider to reimburse an applicant for professional costs
incurred during the course of their dispute.
68. As outlined above, the FSP has agreed to amend its scope of work to
incorporate the additional items of damage confirmed in SK’s report as
attributable to t he hail storm. Accordingly, I consider that SK’s report has
been of assistance in progressing this dispute, and therefore the FSP should
be required to reimburse the Applicants for SK’s professional fees, subject to
the Applicants providing an appropriate invoice.
Code of Practice
69. The Applicants say that the FSP has breached section 3.2.4 of the Code of
Practice (the “Code”) , which requires the FSP to respond to routine requests
for information within 10 business days.
70. For the reasons outlined above, I have awarded the Applicants the amount
of $500 as compensation for non-financial loss as a result of the manner in
which the FSP has handled their claim, including the delays which occurred
at various times.
71. Further, I note that section 4.3 of the Code provides that the FSP may not be
able to meet all standards of the Code following a catastrophe or disaster,
due to the large number of claims received during such time.
72. I recognise that, at the time the Applicants lodged their claim, the FSP was
dealing with a significant increase in claim volume, arising from the number
of adverse weather events which occurred during this period. Accordingly, I
consider that it would be unreasonable to hold the FSP to the timeframe set
out in section 3.2.4 in these circumsta nces.
Case No: 297363 Determination Page 13 of 14
73. For the reasons outlined above, I consider that the FSP should not be
required to pay the Applicants additional compensation as a result of its
failure to comply with the timeframe set out in section 3.2.4 of the Code.
Determination
74. On the basis of the available information I determine that:
the cash settlement of $4,446.53 offered by the FSP in respect of the
carpet is reasonable and complies with its obligations;
within 21 days of the Applicants accepting this Determination, the FSP
is to appoint a suitably qualified and experienced builder to:
a. prepare a revised scope of works for the repair of the storm
damage to the Applicants’ house, which incorporates the
additional items of damage identified in SK’ s report and describes
the works in sufficient detail to enable a clear understanding of the
nature and extent of repairs which will be carried out;
b. provide a costing for the scope of works;
c. provide a proposed start date and estimated completion date for
each aspect of the works (to the extent reasonably practicable);
and
d. confirm whether temporary accommodation will be required while
any aspect of the repairs are carried out;
the FSP is to provide a copy of the above information to the
Applicants, together with details about the qualifications of its
contractors and their proposed start dates prior to repairs commencing
and as additional contractors are appointed from time to time;
subject to the Applicants authorising the scope of works, the FSP is to
complete the works and make arrangements for its assessor to assess
the works on completion. The FSP is to provide the Applicants with a
lifetime guarantee of the works, in accordance with the terms of their
policy;
if the FSP’s builder confirms that temporary accommodation will be
required while any aspect of the repairs are carried out, then the FSP is
to provide the Applicants with the benefit of temporary accommodation
in accordance with the terms of their policy which such repairs are
carried out;
if the Applicants are dissatisfied with the revised scope of works, they
may at any time before the repairs commence request that the FSP
cash settle them for the estimated cost (to the FSP) of carrying out the
repairs. Equally, if the Applicants do not authorise the repairs in
accordance with the revised scope of works prepared by the FSP in the
manner set out above, then the FSP may elect to cash settle them for
the cost of the repairs;
Case No: 297363 Determination Page 14 of 14
the FSP is to pay the Applicants the amount of $500 as compensation
for non-financial loss incurred as a result of the FSP ’s claims handling;
and
the FSP is to reimburse the Applicants for the amount of RK’s fees,
subject to the Applicants providing an appropriate invoice.