Text of the determination
Case No: 294707 Determination Page 1 of 9
Case number: 294707
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
19 July 2013
Background
1. This Determination follows the review of a Recommendation issued on
behalf of the Service on 30 May 2013. The Applicant has disputed the
Recommendation.
2. The Applicant held a home building and contents policy with the Financial
Services Provider (FSP) which was current at the time of the loss.
3. On 4 October 2011, the Applicant lodged a claim for damage to her first floor
balcony and the ceiling of the porch underneath, which she said was caused
by a storm on 1 October 2011.
4. The FSP engaged a builder (“F”) to assess the damage. Following receipt of
F’s report, the FSP denied the Applicant’s claim for damag e to the balcony,
on the basis that the damage was not caused by a storm or other insured
event, but was due to factors such as wear and tear, deterioration,
atmospheric conditions and/or the Applicant’s failure to maintain her home in
good repair and condition. However, the FSP agreed to indemnify the
Applicant for the damage to the ceiling under the balcony.
5. The Applicant subsequently lodged a separate claim for damage to various
parts of her home caused by a severe hailstorm on 25 December 2011. The
claimed damage included further damage to the balcony, which the
Applicant said was caused by the FSP’s builder failing to put back a tile
removed during the investigation of the original claim.
6. The FSP disputes that its builder removed a tile from the Appl icant’s
balcony. The FSP says that the additional damage to the balcony (other than
hail damage to one tile) was caused by the same issues as the initial
damage, and is therefore excluded under the policy.
7. The Applicant seeks indemnity under the policy fo r the damage to her
balcony.
Determination
Case No: 294707 Determination Page 2 of 9
Summary of Applicant’s position
8. The Applicant says that the initial damage to her balcony was caused by a
severe storm in October 2011. She engaged a builder (“J”), who advised that
the balcony timber had contracted due to dry weather resulting in the
grouting becoming loose. The condition of the grouting had been worsened
by the wind and rain, allowing water to get in and damage the balcony floor
and the ceiling below.
9. The Applicant says that the damage to the balcony has subsequently
worsened as a result of the FSP’s failure to fix it following her initial claim.
10. The Applicant says that the FSP’s builder cut out a balcony tile during the
course of inspecting the initial damage, which was not properly replaced.
This meant that the severe hailstorm on 25 December 2011 caused
extensive further damage to the balcony resulting in it rotting right through
and becoming unsafe.
11. The Applicant denies that the balcony was poorly constructed. She says that
the balcony was properly waterproofed and has provided a quotation from
another contractor (“C”) in support of this.
12. The Applicant seeks indemnity under the policy for the damage to her
balcony.
Summary of FSP’s position
13. The FSP says that the damage to the Applicant’s balcony was not caused by
a storm or by any other event within the scope of cover under the policy. The
FSP disputes that a “storm” (as defined in the policy) occurred on 1 October
2011.
14. The FSP relies on the report of its builder, F, in support of its conclusion that
the damage claimed in October 2011 was caused by factors such as poor
construction, wear and tear and a lack of maintenance, and therefore falls
within specific exclusions under the policy.
15. The FSP says that it engaged a different builder (“U”) to assess the damage
to the balcony following the hail storm on 25 December 2011. U identified
one balcony tile as having been damaged by the hailstorm, but concluded
that the remainder of the damage was caused by the issues identified by F.
16. The FSP says that the Applicant has not provided any evidence which
establishes that the damage was caused by an event for which the policy
provides cover.
17. The FSP disputes that F cut out a tile when inspecting the initial damage to
the balcony, as alleged by the Applicant. The FSP has provided copies of
correspondence from F and U confirming that this did not occur.
Case No: 294707 Determination Page 3 of 9
18. Accordingly, the FSP says it is entitled to rely on the terms of the policy to
deny the Applicant’s claim for the damage to her balcony.
19. The FSP relies on the following policy provisions:
“ What You Are Covered For
Storm
If your home or contents suffer loss or damage caused by
a violent wind, cyclone or tornado
a thunderstorm or hail which may be accompanied by rain or snow
a sudden, excessive run-off of water as a direct result of a storm in
your local area
…
What you are not covered for - general exclusions
we will NOT cover
► loss, damage, injury or death that occurs as a result of
…
wear, tear, rust, corrosion, deterioration or erosion
...
atmospheric conditions or extreme temperature
…
faulty design or workmanship
…
Things that may put your claim or cover at risk
You may put your insurance claim or cover at risk if you do not meet your
obligations to us. We may refuse a claim, cancel your Policy, or do both
if you …
► do not maintain your home in good repair and condition. This means your
home must be watertight, structurally sound, secure and well maintained”
Issue
20. Whether the FSP is entitled to deny the Applicant’s claim for the initial and/or
subsequent damage to her balcony.
Reasons for decision
21. I am satisfied that there has been a full exchange of material between the
parties and that each party has had an opportunity to address the issues
raised therein.
Case No: 294707 Determination Page 4 of 9
22. There is an onus on an insured to establish on the balance of probabilities
that a claim fits the definition of an insured event. This is known as a prima
facie claim. Should this onus be discharged, it is then the responsibility of the
insurer to establish, on the balance of probabilities, that an exclusion applies.
23. The issue in dispute between the parties, concerns the cause of the initial
and s ubsequent damage to the Applicant’s balcony.
Cause of initial damage
24. Following lodgement of the Applicant’s initial c laim, the FSP engaged a
builder, F, to inspect the damage to the Applicant’s property and report on
the cause of the damage. F inspected th e property on 7 October 2011. F’s
report dated 12 December 2011 states that:
“…Upon inspection of the claimed areas of damage in our professional
opinion, we believe the claimed damage to be attributable to faulty design /
workmanship and the use of incorrect materials at the time of construction of
the balcony.
Upon inspection of the 1st floor balcony, we noted that the grout has cracked
in several places and the subfloor has sustained long term water damage
causing it to become springy when walked on. We also believe that there is a
lack of / failure of the underneath waterproofing membrane.
We found there to be no damage to the 1 st floor balcony attributable to a
single storm event, and note the damage has been occurring over a long
period of time (12 to 24 months); however we do note the insured believes the
damage is consistent with storm. ” [sic]
25. I have reviewed photographs of the damage to the balcony taken during F’s
inspection of the property on 7 October 2011. These photographs show
deterioration of the grout between the tiles as well as some degree of vertical
misalignment between neighbouring tiles.
26. On 21 November 2011, the Applicant’s builder , J, inspected the damage to
the balcony and provided a quotation for the repair of the damage. In his
quotation, J noted that the damage appeared to have been caused by water
penetration which may have resulted from water finding its way under the top
layer of tiles and weakening the substrate, causing the tiles to dislodge and
break away, as witnessed during the site inspection.
27. J did not express an opinion in his quotation as to the underlying cause of
the water penetration he had observed. However, in the Dispute Form which
the Applicant lodged with the Service, she says that J told her that the
balcony timber had contracted due to dry weather resulting in the grouting
becoming loose, which in turn was worsened by wind and rain, allowing
water to get in.
28. I consider that the FSP is entitled to rely on F’s professional opinion
regarding the cause of the dama ge to the Applicant’s balcony, in the
absence of evidence to the contrary. J’s quotation describes the process by
which the water damage occurred, but does not identify the underlying cause
Case No: 294707 Determination Page 5 of 9
of the water penetrating the surface. Accordingly, J’s quotation i s not
inconsistent with, and does not contradict, the findings of F’s report.
29. The oral advice provided by J (as reported by the Applicant in her Dispute
Form) does provide an alternative explanation as to the underlying cause of
the damage. However, even if this explanation is accepted, at best it
attributes the cause of the damage to a combination of “dry weather” and
“wind and rain”.
30. The Applicant’s policy expressly excludes damage caused by “ atmospheric
conditions or extreme temperature ”. Accordingly, even if J’s oral explanation
as to the cause of the damage were accepted, the FSP would be entitled to
deny the Applicant’s claim in reliance on the Wayne Tank principle (which
provides that where any one of multiple effective causes of damage is
excluded under a policy, the exclusion operates to defeat the claim).
31. Accordingly, in the absence of conflicting evidence, I consider that the FSP
is entitled to rely on F’s report as to the cause of the damage to the
Applicant’s balcony. I consider that the photog raphs taken by F support the
conclusion that the damage has occurred over a long period of time due to
the operation of factors excluded under the policy, rather than being
attributable to a single storm event.
32. I will now consider the available evidence relating to the cause of the
subsequent damage to the Applicant’s balcony, including whether this alters
in any way my findings as to the cause of the initial damage.
Cause of subsequent damage
33. The Applicant says that the further damage to the balcony identified
following the hail storm on 25 December 2011 was caused and/or
exacerbated by the fact that the FSP’s builder cut out a tile and failed to
replace it.
34. In her written submissions, the Applicant says that it was F who cut out the
tile during the initial inspection in October 2011. However, in a later
discussion with the Service’s Case Manager, the Applicant indicated that she
was not sure whether it was F or U who removed the tile and whether this
occurred before or after the hailstorm in December 2011.
Evidence regarding cause of damage
35. Following the Applicant’s claim for damage arising out of the hail storm, the
FSP engaged U to inspect the property on 20 January 2012 and report on
the cause of the damage. U’s report states that:
the Applicant had advised U that the damage to her balcony was present
before the hail storm but became worse as a result; and
Case No: 294707 Determination Page 6 of 9
U’s inspection of the balcony and porch ceiling fou nd that extensive
deterioration and building defects had caused the damage, which was
considered to be completely unrelated to the storm.
36. After the Applicant identified additional damage from the hail storm, U
conducted a second inspection on 12 April 2012 . U’s report dated 19 April
2012 states that at the time of this inspection:
the balcony floor was in poor condition due to general wear and tear,
along with lack of maintenance over an extended period of time;
the tile grout throughout the balcony had cracked, thereby creating
numerous openings through which rainwater had entered the floor
cavity. As a result, the cement sheet tile substrate had been adversely
affected and softened by constant water ingress, allowing the floor to
give way and causing several floor tiles to lift; and
other than one tile which had been damaged by hail impact, the
damage to the balcony floor was “clearly the result of general wear and
tear over an extended period of time” and not related to the hail storm
or otherwise covered by the policy.
37. I have reviewed photographs of the damage to the balcony taken when U
inspected the property on 12 April 2012. These photographs are of a high
quality and show extensive deterioration of the grout between the tiles, as
well as significant vertical misalignment of neighbouring tiles. The
photographs include a close-up of one tile in particular which appears to be
almost entirely detached from the surrounding grout and has started to tilt in
a downwards direction below the surface of the tiled floor. It is this tile
(identifiable by its distance from the balcony rail and side pillar) which the
Applicant claims was cut out by the FSP’s builder.
38. The Applicant arranged for a further inspection by her builder J, on 15 April
2013. J’s report dated 1 7 April 2012, states that several more tiles have lifted
and dislodged from the substrate of the balcony since his first inspection in
November 2011. J’s report goes on to state that:
“the cause of the deterioration to the balcony floor tiles and porch ce iling
appear to be in our opinion further water ingress caused by penetration
through the floor tile and substrate protrusion that was lifted up to obtain an
intrusive inspection of the substrate composition by an [FSP] representative
as claimed by [Applicant]
The action and inaction to replace the tile that was removed from the intrusive
inspection has allowed subsequent storm and wet weather events to easily
penetrate the balcony floor and cause further consequential damage that
could have been prevented. ”
39. Following the Applicant’s submission that a tile had been removed by the
FSP’s contractor, the FSP sought further information from F and U to confirm
whether this had occurred.
40. In an email dated 10 May 2013, F advised that:
Case No: 294707 Determination Page 7 of 9
its employee had confirmed that he did not cut out or remove the balcony
tile and F had not engaged any tradesman to do so;
the balcony tiles had already begun to sink at the time of the initial
inspection in October 2011, and the tile shown in U’s photos would have
dropped as a result of the further deterioration;
it was likely that water had continued to enter through the deteriorated
grout during rain events; and
the extent of water damage under the ceiling in October 2011 supported
the conclusion that either there was no waterproofi ng membrane or the
membrane was faulty.
41. A further inspection was conducted by U on 10 May 2013. U reported that:
the balcony flooring substrate had completely rotted through as no
waterproof membrane had been installed over the substrate before the
balcony floor was lined;
there was no evidence of any power tool cut lines or chisel impact marks
in the floor tile grout or other evidence of a tile being lifted out of position
before the more recent collapse of the rotted flooring substrate;
U’s inspection of the photos taken by F in October 2011 found no evidence
of a tile being removed from its pre-inspection position;
the fact that no definitive finding in relation to the presence or absence of a
waterproofing membrane was made in F’s initial report , indicates that F did
not conduct an intrusive investigation, as any such investigation would
have confirmed that no waterproofing membrane had been installed; and
in U’s opinion, the underlying cause of the damage to the balcony floor
was faulty design and workmanship when the balcony was constructed, in
that no waterproofing membrane was installed between the flooring
substrate and the tiles.
42. U’s report included photographs which showed significant deterioration of
the grout and several tiles lifting.
43. Following the issues of the Recommendation, the Applicant provided several
photographs, which showed the tile which she says was cut out by the FSP’s
builder. In the photographs, this tile appears to have detached entirely from
the surrounding tiles and partly sunk beneath the surface of the tiled floor. It
appears from the metadata that these photographs were taken on 21
November 2012.
Analysis
44. I consider that the further evidence outlined above supports the conclusion
that the initial damage to the Applicant’s balc ony arose due to causes which
are excluded under the policy. In particular, U’s inspection on 10 May 2013
confirms that a waterproof membrane was not installed when the balcony
Case No: 294707 Determination Page 8 of 9
was constructed, meaning that, water soaking through cracks in the grout
caused the floor substrate to rot.
45. The Applicant has not provided any evidence to contradict U’s findings in
relation to the lack of a waterproof membrane. While the Applicant has
provided copies of quotations from J and another builder, C, which refer to
the need to install a waterproof membrane as part of the process of repairing
the damage to the balcony, these quotations do not establish that a
waterproof membrane was installed when the balcony was originally
constructed.
46. I consider that U’s report of 10 May 2013 is consistent with F’s earlier
findings and supports my earlier conclusion that the FSP is entitled to deny
the Applicant’s claim for the initial damage to the balcony. In the absence of
conflicting evidence, U’s report establishes that the penet ration of water into
the balcony substrate was caused by the failure to install a waterproof
membrane when the balcony was constructed, and therefore falls within the
exclusion under the policy for damage caused by “faulty design or
workmanship”.
47. In relation to the subsequent damage identified following the hailstorm in
December 2011, I do not consider the Applicant has established, on the
balance of probabilities, that this was caused by the FSP’s builder cutting
out, and failing to properly replace, one of the balcony tiles. In particular, I
note that:
the progression of damage to the balcony shown in the photographs taken
during F’s initial inspection in October 2011, U’s second inspection in April
2012 and U’s final inspection in May 2013 show a continu ed deterioration
in the condition of the balcony, as may be expected given that repairs
were not undertaken to address underlying issues and therefore, the
balcony continued to be adversely affected by subsequent rain events;
in particular, the photographs demonstrate the gradual detaching and
sinking of the specific tile identified by the Applicant as having been cut out
by the FSP’s builder. The change in the position of this tile over time
appears consistent with the ongoing deterioration of the balcony and does
not necessarily result from intrusive action taken by a third party;
F has expressly denied removing a tile and U has confirmed that there is
no physical evidence that a tile has been cut out with a power tool or
chisel;
J’s report following his initial inspection (which was conducted after F’s
inspection) does not refer to a tile having been removed by another
contractor;
while J’s subsequent report dated 17 April 2012 refers to the removal of a
tile by the FSP’s builder, J’s comments are based solely on information
provided by the Applicant and J does not refer to any physical evidence
that this has occurred; and
as noted by U, F would have been able to express a definitive opinion
about the absence of a waterproofing membrane if an intrusive
Case No: 294707 Determination Page 9 of 9
investigation had been carried out in October 2011. However, F did not do
so.
48. For the reasons outlined above, I find that the initial and subsequent damage
to the Applicant’s balcony was caused by events which are excluded under
the policy, and therefore, the FSP is entitled to deny liability for the
Applicant’s claim (other than in respect of the hail damage to one tile, which
the FSP has accepted).
Determination
49. On the basis of the available information I determine that the FSP is entitled
to deny the App licant’s claim for damage to her balcony (other than the hail
damage to one tile which the FSP has already accepted).
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.