Home / Financial Firm (Unknown - Insurer) / Determination 293664

Determination 293664

Cash settlement offer for burst pipe damage disputed

FirmFinancial Firm (Unknown - Insurer)
Decided2013-04-30
ProductGeneral Insurance · Business / commercial
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$129,895
SourceAFCA PDF

Summary

The applicant rejected the FSP's $80,000 cash settlement offer for leak damage to a tenanted rear extension and sought $129,895 based on a builder's quote. The Panel found the offer fair because much of the damage predated the leak or stemmed from other defects outside the leak scope.

The settlement must be consistent with policy obligations, and expert evidence showed the covered damage was limited to the scope of works rather than full replacement of the extension.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 293664 Determination Page 1 of 9 Case number: 293664 General Insurance - Small Business/Farm Insurance - Commercial Property - FSP Decision - Claim amount 24 April 2013 Background 1. The Applicant is an insured under a farm insurance policy underwritten by the Financial Services Provider (FSP). The relevant period of insurance operated for twelve months beginning from 22 December 2007 and covered various risks, including farm and domestic buildings and contents as well as agricultural and other vehicles. 2. On 5 November 2008, a claim was lodged for damage sustained to one of the properties owned by the Applicant which was tenanted. The FSP was advised that a domestic water pipe underneath the concrete slab had developed a leak and the Applicant’s son, who is a plumber, had disconnected the leaking pipe and installed a copper pipe in its place. However, the Applicant advised that the leak caused movement in the concrete slab with fairly significant resultant damage being sustained. 3. This damage is localised to the rear extension of the property. 4. The FSP, after the engagement of various engineers and builders to review the damage, found that a substantive part of the loss was caused by other factors excluded under the policy. 5. Following additional investigations and assessments into the extent of loss, the FSP has now offered to cash settle the Applicant’s claim by way of payment in the sum of $80,000. The Applicant has rejected this offer as he is seeking payment in the sum of $129,895 pursuant to a quotation he has received. Summary of Applicant ’s position 6. The Applicant has submitted the following in disputing the FSP’s position:  Although the FSP has highlighted various other issues, such as leakages to the roof, he reiterates his claim is solely limited to the damages he maintains were sustained by the leaking pipe.  Despite the FSP’s submissions to the contrary, the damages he is seeking indemnity for all occurred after the leakage occurred. That is, there was no damage to the building prior to the leaking pipe. Determination Case No: 293664 Determination Page 2 of 9 7. The Applicant has also specifically commented on various aspects of the FSP’s reports in his latest submission to substantiate his position. 8. Based on the above, the Applicant is therefore seeking reimbursement of the quotation (RW) has provided which sets out his estimate to repair all of the resultant damage. This totals $129,895. Summary of FSP’s position 9. The FSP is relying on two reports from engineer S, a report from another engineer (B) as well as its loss adjuster reports to substantiate its position that not all of the damage was due to the leaking pipe. 10. Further, the FSP engaged S to provide a scope of works that sets out the resultant damage caused by the leaking pipe. It has then based its settlement offer on this scope of works. In particular, it has based its offer on RW’s quotation but only after deducting the works included in RW’s quotation that were not part of S’s scope of works. 11. The FSP therefore relies on the above and the following policy provisions to maintain its position that the amount offered is fair and reasonable: “ WHAT YOU ARE COVERED FOR … We will cover You for Accidental Loss to Your House unless the Loss is excluded. … WHAT THIS INSURANCE DOES NOT COVER Your House is not covered for Loss by: … 2. normal maintenance, wear and tear, erosion, corrosion, slowly developing deformation and distortion, marring or scratching; 3. mildew, rot, rust or gradual deterioration … Your House is not covered for: 12. the cost of repairing or replacing faulty materials; 13. the cost of putting right faulty workmanship.” Issue 12. Whether the FSP’s offer of settlement is consistent with its policy obligat ions and fair in all the circumstances. Case No: 293664 Determination Page 3 of 9 Reasons for decision 13. As advised to the parties, due to the nature of the dispute, the matter has been referred to the Panel for Determination in line with the Operational Guidelines to the Service’s Terms of Referenc e. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 14. This decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in the insurance industry and a representative with extensive experience in consumer claims. Expert Evidence 15. B provided a report on 8 December 2008, which was approximately two months after the leaking pipe event. This report described the damage in detail which, for the sake of brevity, the Panel does not propose to recount in detail. 16. However, the Panel does note that the report contained the following of relevance:  The rear extension consisted of an office, sunroom and open dining room entry. The construction type is hardiplank and brick s upported on a concrete slab with external footings. A side main bedroom plus ensuite extension of brick veneer was added at the same time as the rear extension.  The broken pipe was located between the ensuite and the hardiplank section of the extension.  The carpet and timber strip at the rear of the ensuite has rotted due to water leaking from the shower recess, which appears to have now been sealed.  The extension roofing, particularly where it abuts the higher section of roof and the original section of the roof, has the general appearance of not being effectively done. 17. B also provided the following relevant comments: “A fair percentage of the cracks in the original residence and the external wall of the extension appear to date back much further that when the water pipe leaked … We believe that up to 50% of the movement and cracking may have occurred before the broken pipe. This movement could be related to the water from the leaking shower recess in the ensuite, this was has been leaking out of the shower for a long time as the carpet and timber anchoring strips were badly rotted (doesn’t happen in 9 weeks). This water would have been running under the footings every time the shower was used. Other contributing factors to the cracking in the original residence would be normal movement associated to an older house with limited footings built on highly reactive black soil, with water ponding around the residence due to poor grading and poor roof drainage away from the residence.” Case No: 293664 Determination Page 4 of 9 18. The loss adjuster provided a report dated 28 February 2009 that set out issues identified by a building contractor and that of the engineer, presumably B. This contained the following of relevance:  The insured advised that his son, a plumber, fitted a copper water pipe as a bypass to the leaking polythene pipe. Upon inspecting the copper pipe though, it appears to predate the discovery of the leaking pipe.  A number of cracks in the property precede the leaking pipe event.  The shower recess has been leaking for a long period of time. The rotting of the carpet and the carpet timber smooth edge, as well as the staining of the concrete, were caused by this. It is also possible that the leaking shower recess was the catalyst for the present building damage.  The building is constructed upon very reactive black soil.  Water ponds around the building as a result of poor grading. Roof drainage is also a contributing factor for the building movement given the highly reactive black soils.  Water is entering the building past the extension roofing. This has resulted in mould damage to the plasterboard cornice. This is possibly due to movement in the building causing openings to the roof cladding, which is contributing to the damage.  The condition of the guttering, down pipe and drainage are also factors. For instance, there is an insufficient number of downpipes. They are also undersized as in one case, there is a 60mm PVC down pipe used when a 90mm pipe should have been used. 19. The report then provided the following comments: “First and foremost we c onsider that the long term water leak from the shower recess has been a major contributor in the development of building movement associated with the rear extension section of the building. The saturation of the black soil from the escape of water from the shower recess has then in turn caused swelling of the black soil placing strain upon the polythene pipe which has then fractured and contributed to further movement. Also contributing to the loss has been the inadequate and poor drainage and the dubious c onstruction of the building and roof.” 20. It is unclear why a report direct from the building contractor was not provided to corroborate the findings. 21. JH of S, who is a building consultant and licensed builder, provided a report dated 3 July 2009. The report described the damage in detail which, again for the sake of brevity, the Panel does not propose to recount in detail. However, the Panel does note the following contained in this report:  Water damage was observed to the plasterboard lined northern wall elevation and 90mm cornice. Paintwork was blistering and peeling down the internal wall corner. Case No: 293664 Determination Page 5 of 9  The southern wall elevation had water seeping between the bottom row of bricks and the concrete slab. The ensuite is on the other side of this water leak. In his opinion, this appears to have been leaking for a long period of time with green algae and mould attached to the concrete slab. The underside of the carpet was also covered in mould.  In the ensuite, the wall tiles on the eastern elevation have dislodged, exposing the junction between the asbestos wall sheeting and the tiled floor. There was no waterproofing membrane to this area.  In the shower recess, there were large amounts of silicon which had been applied. There were approximately 3-5 loose tiles in this shower recess area. Between the shower recess and the WC on the northern wall elevation, he observed moisture at the junction of the tiled wall and tiled floor. This indicates that the shower recess is leaking.  He observed on the eastern wall elevation water leaking between the bottom course of bricks and the concrete slab. This corroborates leaking from outside the ensuite.  On accessing the roof surface, the roof pitch ranged from 2.5 and 6.5 degrees. The minimum pitch should be 5 degrees so the part of the roof installed below this would constitute a building defect. He also observed heavy foot traffic damage on the northern end of the roof area.  In his opinion, the foot traffic damage, combined with the low pitch of the roof sheeting has caused water damage to the plasterboard lined ceiling and walls in the computer room, as well as to the 90mm cornice.  He observed guttering now being propped up with a steel post to maintain the height. He also observed the roll top ridge capping to the main pitched roof over the hallway has gaps between the lap joints. These gaps are up to 10mm wide. In his opinion, water has been entering the ridge capping area of the pitched roof causing water damage to the plasterboard lined ceiling to the hallway area.  On the western wall elevation, he observed a 50mm stormwater pipe, which is less than the required 90mm size. This means the pipe would not cope with large volumes of rain and the guttering would over flow on the reactive soil below.  The 25mm rural poly pipe to the underside of the concrete slab has not been installed to Australian Standards. Namely, it did not allow a 75mm gap between the slab and the pipe. 22. Following this, JH provided these specific comments: “It is my opinion that the movement and cracking to the rear northern elevations of the residence is the result of the failed waterproofing membrane in the ensuite causing the reactive soils of the area to swell which has resulted in the 25mm rural poly pipe to the underside of the concrete slab to fail. When the 25mm rural poly pipe has failed this has then caused more damage to the rear northern elevations of the residence. Case No: 293664 Determination Page 6 of 9 SUMMARY The use of a rural poly pipe for residential in my opinion is adequate. I am unable to put and (sic) age the copper pipe that has been used to re-plumb the ensuite and main bathroom. It is my opinion the water damage to the plasterboard lined ceiling to the hallway is a result of the gaps between the roll top ridge capping. This has allowed water to penetrate the roof surface during times of strong rain. It is my opinion that the water damage to the plasterboard lined ceiling, 90mm cornice and plasterboard lined walls of the office is a result of the corrugated roof sheeting being installed below the minimum pitch of 5 degrees, combined with foot traffic damage. It is my opinion that the ensuite has not had the waterproofing installed to Australian Standards and this has caused water to leak out of the ensuite area causing the subsurface soils below the residence to swell which has resulted in the 25mm rural poly pipe to the underside of the concrete slab to fail. It is also my opinion that the shower recess to the ensuite has been leaking over an extended period of time, resulting in water penetrating the reactive subsurface soils. I therefore consider this a building defect …” 23. Following this report, S was engaged to provide a scope of works associated with the resultant damage caused by the leaking pipe. This was conducted by an other licensed builder (LD). During the course of LD’s inspection, he notified the loss adjuster of further faults and defects. LD was advised to provide a further report in this regard. 24. LD did so and provided a report dated 27 August 2009. Some of the con tents of the report reflected JH’s comments. LD also provided the following observations of relevance:  Upon gaining access to the roof, he noted damage to the corrugated roof sheeting as a result of foot traffic. The damage was over 70% of the roof surface with 85% of the roof sheets damaged. This has created gaps of up to 10mm in the side laps of the roof sheets. Gaps between the side laps of the roof sheets allowed wind driven rain to penetrate the roof.  The water damage to the plasterboard lined ceiling, 90mm cornice and walls of the office is as a result of foot traffic damage.  Gaining access to the roof void, he observed water stains of 100- 150mm in diameter extending along the centre of the hallway area. He noticed the valleys at the top of the corruga ted roof sheets have not been turned up in accordance with the manufacturer’s installation recommendations. This is defective building work. 25. Following this, LD provided these specific comments: “I am of the opinion that the water damage to the plasterboard lined ceiling, 90mm cornice and walls of the office, is a result of the corrugated roof sheeting being damaged as a result of foot traffic. I am also of the opinion that the water stains on the hallway plasterboard lined ceilings is a result of gaps between the roll top ridge capping and the top of Case No: 293664 Determination Page 7 of 9 the roof sheets not been turned up allowing water to penetrate the roof surface during times of wind driven rain. I am of the opinion that the cracked plasterboard and cornice at the eastern end of the hallway is a result of the strutting beam being in direct contact with the plasterboard ceiling lining. Therefore I consider this to be defective building work.” 26. In RW’s quotation, which the Applicant is relying upon, he stated the following regarding the extent of repairs necessary: “The extension from the existing building has pulled away, caused by a burst water pipe under the slab. As a complication of [BB] Engineering Scope of Works and my recent assessment, it is recommended that the entire extension be removed and replaced, including foundations. There are minor gyprock repairs required to the hallway, bedroom and bathroom.” Consideration of the evidence 27. As stipulated previously, the FSP has attempted to settle the Applicant’s claim based on RW’s quote but aft er deducting the additional work RW has allowed for which is not covered by S’s scope of works. In particular, RW quoted for the complete removal and replacement of the extension, which is significantly greater than S’s scope of works. 28. The Applicant maint ains he is entitled to the full amount of RW’s quote. 29. In the Panel’s view, such an amount would appear excessive when you consider the overall state of the extension. Although there is no dispute that a significant amount of damage has been sustained as a result of the leaking pipe, there are also substantive issues with the extension’s condition prior to the event. 30. For instance, the shower recess appears to be an ongoing problem. Although the Applicant has stated this has been rectified and is not relevant, both S and B identified that this has been leaking for an extended period of time with S stating it may still be leaking. 31. The photographs would appear to support S’s position as there is evidence of discolouration, missing tiles and significant amounts of silicone. The latter would be indicative of numerous attempts to address an ongoing leaking issue. 32. Both S and B agreed that there was movement in the soils under the extension that pre- existed the burst pipe. For instance, S’s first report stated that the leak from the shower recess in the ensuite area has been leaking over an extended period of time, resulting in water penetrating the reactive subsurface soils. WJB corroborated such a theory. 33. In addition, both S and B identified that the extension did not have the correct sized downpipe to deal with high amounts of stormwater. S stated this would result in overflow to the reactive soil below. Case No: 293664 Determination Page 8 of 9 34. Although the Applicant has attempted to rebut this by stating these pipes drain to water tanks, this does not account for the fact that given the downpipes are less than the required size (50mm as opposed to required size of 90mm), rainwater would not be able to reach the tanks if the downpipe’s capacity i s exceeded. Instead, it is reasonable to accept that overflow would occur from the gutters as the downpipe is of insufficient size to handle high volumes of rainwater, resulting in this water reaching the reactive soils in the ground. 35. Furthermore, B opined that a number of cracks pre-existed the leaking pipe. The Applicant has refuted this based on the fact he regularly inspected the property. However, he has not articulated how often he inspected the property and if so, how thorough his inspection was. 36. In particular, there were clearly ongoing issues with the property that did not appear to have been addressed by the Applicant for a long period of time and predated the leaking pipe. This is corroborated by the following photographs contained in S’s report d ated 3 July 2009:  Water damage to the plasterboard lined ceiling and walls in the computer room that were discoloured and indicative of ongoing issues likely to have pre-existed the leaking pipe (photograph 9).  Mould to the underside of the carpet in the sitting room from the leaking ensuite (photograph 12). This is consistent with the leaking shower recess and is evident of a longstanding issue.  Water penetrating the adjoining wall of the ensuite (photographs 10 and 11), again consistent with the leaking shower recess which is an ongoing issue.  Brown water marks to the plasterboard lined ceiling (photograph 13). This is indicative of issues with the roof’s pitch and condition and not associated with the leaking pipe at all.  Lack of waterproofing membrane i n the ensuite (photograph 15). This clearly predated the leaking pipe.  Extensive foot traffic damage to the roof (photographs 19) that is clearly not associated with the leaking pipe. 37. Despite this evidence, the Applicant continues to maintain that due to the leaking pipe, the whole extension (including the foundation) requires replacement. However, this is not supported by the majority of the expert evidence. 38. Although RW does support the Applicant’s position, his report is minimal and does not address what contribution (if any) was provided by the leaking shower recess and the inappropriate design of the roof. Accordingly, the Panel finds it difficult to place much weight on his opinion. 39. Accordingly, the Panel accepts the expert evidence establishing that there were clearly instances of ongoing water penetration to the highly reactive soils that pre-existed the bursting pipe, namely from the leaking shower Case No: 293664 Determination Page 9 of 9 recess and the lack of appropriate downpipes. In particular, both S and B opine there would have been swelling in the soils caused by the leaking shower recess. Further, B specifically stated that approximately 50% of the cracking predated the leaking pipe and was likely to have been caused by these factors. 40. Although S does not specifically support B’s fin ding regarding the pre- existing cracking, the Panel notes the builder from S (JH) inspected the property on 25 & 30 June 2009, approximately 9 months after the event. In contrast, B inspected the property only two months after the event. It is therefore re asonable to accept that JH’s ability to conclusively determine this issue would be substantively compromised as compared to WJB whose inspection was fairly contemporaneous to the event. 41. Given all of this, the Panel therefore accepts that S’s scope of work s dated 27 August 2009 likely reflects the extent of damage sustained from the leaking pipe. 42. The FSP, in attempting to settle the Applicant’s claim, has offered to pay a proportion of RW’s quote that discounts the additional works RW allowed beyond the scope of works. Based on this, and in an effort to resolve the dispute, the FSP offered to pay $80,000. 43. Having given due consideration to all of the available evidence the Panel considers that the FSP’s offer of $80,000 is fair in all the circumstances and consistent with its policy obligations. Determination 44. The Panel determines the FSP’s offer of settlement is consistent with its policy obligations and fair in all the circumstances.