Home / Financial Firm (Unknown - Insurer) / Determination 292134
Determination 292134
Dispute over extent of inundation repairs and cash settlement
Summary
After storm and flood inundation, the FSP offered to cash settle the balance of repairs for two buildings, but disputed the timber framework and the applicants' asbestos removal and the need to rebuild. AFCA ordered the FSP to pay $4,950 for asbestos removal, appointed a new repairer to determine whether the buildings can be repaired or must be rebuilt, and ordered interest.
Asbestos removal was required by law for exposed material caused by the insured event, while the framework damage was not shown to be caused by inundation and the repair versus rebuild question needed an independent scope of works.
Issues
- Claim amount dispute primary · upheld
“I am satisfied that the removal of same undertaken by MA should be covered by the FSP. Based on the provided quote for this work from MA, the cost of this removal was $4,950.”
- Claim denial secondary · not upheld
“I accept that the framework will need to be redone and that there is nothing to suggest that the observed damage to this framework was caused by the inundation.”
Subjects and remedies
home or building damagenatural disasterpay claimpay interestreassess claim
Text of the determination
Case No: 292134 Determination Page 1 of 7
Case number: 292134
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim Amount - Inundation Damage - Dispute Over Extent of Repairs
18 March 2013
Background
1. The Applicants held a home and contents policy with the Financial Services
Provider (FSP) from 1 September 2010.
2. On 14 January 2011, the Applicants ’ home, comprised of two buildings and a
separate laundry, was subjected to storm and flooding events and they
subsequently lodged a claim for inundation damage.
3. The FSP accepted the claim and agreed to attend to repairs. Upon stripping
part of the damaged second building, the FSP found a problem with the
existing timber framework and informed the Applicants that it would not
indemnify them for this damage, unless the Applicants repaired it or covered
the replacement cost. It later offered to cash settle the Applicants for the
balance of the work it considers needs to be done, being $78,030.69.
4. The Applicants consider that the FSP abandoned the repair attempt upon
the discovery of asbestos and note that they have received advice from a
builder that the home cannot be legally rebuilt at the same location. They
further seek indemnity for asbestos cleaning incurred through the stripping of
the property.
Summary of Applicants ’ Position
5. The Applicants say that their builder has suggested the property cannot be
rebuilt on the same area of land as it is no longer within the relevant safety
regulations. The buildings on the property should be moved at the expense
of the FSP to comply with these regulations.
6. They incurred an account for asbestos removal from the external cladding of
the building from “ MA ” and contend that this should be covered under the
policy. They deny that they instructed the agent to remove all of the asbestos
from this area at their expense.
Determination
Case No: 292134 Determination Page 2 of 7
Summary of FSP’s Position
7. The FSP says that it agrees to cover the Applicants for their loss but is
unable to repair the second building as there are wear and tear issues with
the framework that are not relevant to the insured event. The Applicants
need to repair this damage prior to any work being done.
8. To assist the Applicants, the FSP offered to pay a cash settlement for the
balance of the damage based on its scope of works at the premises. This will
enable the Applicants to complete the work as they see fit.
9. The FSP disagrees that the building should be moved and/or rebuilt as it
was not constructed to Australian standards in the first place and appears to
be a converted outhouse or chicken coop.
10. The total amount of estimated repairs for the two buildings was $111,237.18
of which the FSP has already committed $33,206.49 to repairs. It is satisfied
that the balance should be paid in a cash settlement.
11. The FSP relies on the following policy provisions:
Page 15 of the Product Disclosure Statement (PDS)
“ WHAT YOU ARE COVERED FOR
Storm
If your home or contents suffer loss or damage caused by
a violent wind ...
thunderstorm or hail which may be accompanied by rain ... or
a sudden, excessive run-off of water as a direct result of a
storm ...
...
we will ...
rebuild or repair that part of your home that was damaged”
Page 24 of the PDS
“ Buildings – what we will cover under buildings insurance
We cover domestic residential buildings for replacement or
repairs up to the buildings sum insured
we will under buildings insurance
rebuild or repair that part of your home that was damaged as a result of
an incident described...”
Page 35 of the PDS
“ What you are not covered for – general exclusions
we will NOT cover
loss, damage, injury or death that occurs as a result of
...
Case No: 292134 Determination Page 3 of 7
wear, tear, rust, corrosion, deterioration or erosion”
Page 62 of the PDS
“ Settling claims – under buildings
If we agree to cover the claim under buildings insurance
we will
repair or rebuild that part of your home which sustained loss or damage,
or
pay you the cost to repair or rebuild it, whichever is smaller
...
however
...
we may cash-settle your claim if
...
we choose to pay you the cost to repair or rebuild your home...”
Issues
12. Whether the FSP is entitled to cash settle the Applicants for the amount of
damage caused by the insured event.
13. Whether the amount offered in settlement is sufficient for the FSP to
discharge its responsibilities for the claim.
Reasons for Decision
14. I am satisfied that a full exchange of the relevant information has taken place
between the respective parties and that each party has had the opportunity
of addressing any issues raised.
15. There were three buildings identified on the Applicants’ property, being the
main property (building one), a secondary unit (building two) and a laundry.
For the purposes of this Determination, only the damage relating to building
two is in dispute.
16. Th e FSP has categorised building two as a converted “outhouse/chicken
coop” which was later converted into a dwelling and (in its opinion) well short
of Australian Design Standards. This is disputed by the Applicants, who note
that when they purchased the property, building two was advertised as a
“two bedroom flat”.
17. No evidence has been submitted as to the exact age of the buildings or what
standards (if any) they were subject to at the time of construction. It is fair to
say that the bluestone buildings had stood for some time. They were not
recent constructions. I am of the view that they served the purpose of two
Case No: 292134 Determination Page 4 of 7
separate buildings with living areas, were of sound-enough construction to
have been standing and functional at the time of the loss and therefore
should be considered as being of an acceptable standard.
18. It is not in dispute that the Applicants’ loss was covered under the policy and
that the laundry was demolished and will not be rebuilt with the consent of
the Applicants. The dispute relates to the damage caused and payable for
the reconstruction of building two.
19. From the Certificate of Insurance provided by the Applicants (which relates
to the next period of insurance and not the relevant period for this claim), it is
apparent that the FSP’s policy provides “replacement cover for your
buildings”. There is no suggestion that this was not the case with the cover
at the time of the loss.
20. The provision of “replacement cover” implies that the policy will provide
indemnity for the replacement of a buildi ng should it require it, up to the limit
of the policy. At the time of the contract, the FSP suggests that the policy
was limited to $400,000.
21. After the report of the loss, the FSP engaged “ BB ” to assess and report on
the scope of the damage. The relevant representative noted that building two
had been inundated to about 1,500mm at the back of the building and that
extensive work would be required to repair it:
“The kitchen cupboards have been damaged and will require full replacement.
All timber skirtings, doors, walls, door jambs and architraves will require
sanding and painting. All concrete flooring will require painting also...”
22. Additional costs were incurred after asbestos was found in the building. The
FSP was prepared to repair the damaged second building until it discovered
that the existing timber framework was not in an acceptable state. Based on
the provided photographs and absence of evidence to the contrary, I accept
that the framework will need to be redone and that there is nothing to
suggest that the observed damage to this framework was caused by the
inundation.
23. It is common ground that there was asbestos inside the walls of the building,
which was removed by the FSP inside the home. The FSP accepted no
responsibility for the asbestos located in the external wall cladding as it
suggests that this was removed at the request of the Applicants. To this end,
a statement was provided by the asbestos remover, MA:
“After taking samples & measurements from the inside of the building, I was
standing with the owner explaining the job when I noticed a piece of asbestos
protruding above the sliding door, behind the cladding. On seeing this I said to
the owner, “that could be asbestos as well”. In reply the owner said “take a
sample and if it is please have it removed”
We send the samples off and it came back Positive to Asbestos, so the
Removalists did what the owner said and removed it.
After speaking to the Site Supervisor, he has also said that the owners did tell
him to remove it as well.”
Case No: 292134 Determination Page 5 of 7
24. The FSP suggests that such a representation from the Applicants was
tantamount to contracting MA for separate work and that this work was not
related to the claim. As such, the FSP suggests that this constitutes an
agreement outside of the policy and an issue that the Service is unable to
determine.
25. I am not convinced that the representation made in the relayed conversation
amounts to an agreement to contract MA. Even if I accept that such a
conversation may have taken place, it probably reflects nothing more than a
desire of the Applicants for the asbestos to be removed from the property in
the knowledge that repairs are to be done and understanding that they would
or should be covered under the policy.
26. The FSP retained BB to quote and attend to work at the property to repair
the buildings. BB noted in her report of 2 April 2012 that she had located
asbestos on the property and that BB would be “required to remove all
affected areas of asbestos”.
27. Such a statement implies that all asbestos was to be removed from the
property regardless and may have alluded to any misunderstanding that
occurred about whether such removal was covered under the policy or not.
28. In a further report, dated 18 May 2012, BB noted:
“Whilst conducting the removal [of the asbestos] it became obvious to our site
supervisor that to remove all the asbestos wall sheets, the cornices would
need to be removed. The cornices had been glued and nailed to both the wall
and ceiling sheets. After a thorough inspection it was obvious there was no
way to avoid damaging the ceiling sheets and under Worksafe Legislation, all
exposed or damaged asbestos sheeting or fibres must be removed...”
29. The above passage illustrates the difficulty for the contractor and her
knowledge that all “exposed or damaged asbestos” had to b e removed in
accordance with the relevant law. The earlier statement from MA highlighted
that the asbestos he identified was “protruding” from the building and
therefore exposed.
30. On this basis, I am satisfied that the removal of same undertaken by MA
should be covered by the FSP. Based on the provided quote for this work
from MA, the cost of this removal was $4,950.
31. The remaining issue is therefore that of the repair of the second building. It is
apparent that BB saw it as a repairable proposition and was prepared to
attend to same until the discovery of the poorly constructed original timber
work. The FSP formed the view that the framework would need to be
replaced but that this was not within the scope of the claim as it was not
damaged by the insured event.
32. The Applicants retained a builder, “ AU ” , to inspect and quote for the repair of
the property. AU’s eventual quote was for the replacement of both buildings
at a cost of $156,817 although the quote itself was not detailed as to how
this amount was calculated. Relevantly, AU noted in his report that:
Case No: 292134 Determination Page 6 of 7
“Due to the location of this unit on the block and its close proximity to deep
creek, new council and water authority regulations will not allow this building
to be rebuilt in its current location or at its current floor level.
To render the building[s] compliant with the current building code the lowest
floor level needs to be elevated approximately 1600mm and the structure
positioned further away from the boundary it shares with the Deep Creek
Reserve.
All existing concrete and footings will need to be removed to make way for
new footings.”
33. The FSP has not addressed the issues regarding building compliance raised
by this report, which imply that the home cannot be rebuilt to a standard
which will enable it to comply with the relevant codes and regulations. This
might be an issue dependent on whether the home can be safely repaired
(as was the aim of BB) or if it needs to be rebuilt.
34. It is clear that the damage with the second building was extensive. This
raises the prospect that an entire rebuild of the property was appropriate and
necessary. In my view, such a judgement cannot be made on the available
evidence.
35. The FSP’s policy provides indemnity for “replacement or repairs” for the
buildings, as necessary. The question in this instance is whether the work
undertaken by BB amounted to a replacement or repair of the property and
the categorisation of the remaining work.
36. I am of the view that the buildings should be repaired if it is safe to do so and
is compliant with the relevant standards required of the building industry,
relevant Council and other regulations.
37. I am reluctant to rely upon the quotes prepared by BB as these were
prepared some time ago and inclusive of work which has already been done.
If the Applicants are required to retain another builder, it is conceivable that
the cost for any repairs will increase due to the reduced amount of work
involved and the need to work within the constraints of what has already
been done.
38. To this end, I consider that the FSP must appoint a new independent builder
to consider the scope of works for what needs to be done in view of the
relevant codes and regulations and to prepare a scope of works for the
repair of the property (if it is permitted). Assuming that the repair may
proceed, the builder should provide a scope of works, inclusive of all relevant
costs.
39. If the buildings are considered repairable, the FSP may either cash settle the
Applicants for the nominated amount, less the value of the framework or
arrange to attend to the work on the basis that the Applicants contribute the
amount for this framework to be completed satisfactorily.
40. If the buildings cannot be safely repaired, the builder must prepare a scope
of works to demolish and relocate the buildings as required under any
Case No: 292134 Determination Page 7 of 7
relevant codes. This means that the FSP will be liable for the entire
replacement of both structures (if it has been concluded that the buildings
cannot be safely and/or legally repaired).
Determination
41. I determine that the FSP is liable for the costs of removing the asbestos from
the site and should indemnify the Applicants for the relevant costs.
42. I further determine that the FSP should retain a new repairer to complete a
full inspection of the site and to determine whether the b uildings can be
legally and safely repaired at their existing locations or whether it is not safe
or legal to do so and they must be demolished and moved. The parties
should be guided by the findings of this repairer as to the repair or rebuilding
of the home, as appropriate.
43. I otherwise determine that the parties should adopt my considerations from
paragraphs 34-40 of this Determination, inclusive.
44. Insofar as the FSP is to provide any payment to the Applicants with respect
to the claim, I determine that it must include interest at the statutory rate,
calculated from 8 April 2011 until the date of payment.