Fire reinstatement under scope of works, fuse box relocation and delayed rectification
Text of the determination
Case No: 292026 Determination Page 1 of 18
Case number: 292026
General Insurance - Domestic Insurance - Home Building - Service - Delay in
Claim Handling - Rectification and Scope of Works
20 January 2014
Summary
Description:
This dispute concerns a claim by the Applicant under a strata building
insurance policy regarding several issues which arose out of the
reinstatement of the property after a fire.
Basis for Determination:
The facts of the matter as applied to the policy terms and the Terms of
Reference resulted in some findings in favour of the Applicant, the basis for
which are too specific to the dispute to summarise in this instance but which
are set out herein.
Determination:
The FSP was entitled to deny some aspects of the claim but not others.
Background
1. I have reviewed all the material submitted by the parties and save where I
make note specifically, I am satisfied the Background as set out in the
Recommendation is accurate and is as follows.
2. The Applicant holds a strata building insurance policy with the Financial
Services Provider (FSP) covering her home building. The policy was current
at the time of the loss.
3. On 13 March 2012 the Applicant‟s home was severely damaged by fire. The
Applicant lodged a claim with the FSP which was subsequently accepted.
4. A scope of works (SOW) was prepared for the reinstatement of the
premises, which was supplied to the builder „BBS‟ to undertake the works
required.
Determination
Case No: 292026 Determination Page 2 of 18
5. The Applicant says that the SOW has not been followed and several items
have not been replaced or completed in line with the SOW.
6. The dispute was the subject of a Recommendation. The Recommendation
was mostly in favour of the FSP and was not accepted by the Applicant. The
FSP accepted the Recommendation. In the circumstances, the matter has
been referred to me for Determination.
Summary of Applicant’s p osition
7. I have reviewed all the material submitted by the parties and save where I
make note specifically, I am satisfied the Applicant‟s position as set out in
the Recommendation is accurate and is as follows.
8. The Applicant says that BBS did not have enough time to prepare a quote
and so its quote was under prepared and BBS did not quote adequately to
reinstate her property. She believes that as they underquoted, corners have
been cut in the quality of materials used to ensure that the project falls within
the budget allowed. She is unhappy with the tender process used by the
FSP.
9. The Applicant says BBS did not reinstate the house using the agreed SOW
and that the FSP did not require BBS to keep to the SOW. There have been
many disagreements and compromises with BBS. The FSP has not
responded to complaints.
10. The Applicant says she agreed with the building consultant „JM‟ who
prepared the SOW, to change a number of items in the home to better suit
her needs. She had requested that the original ducted heating not be
replaced but a cheaper single space heater be installed, with the difference
in price contributing to the costs to relocate the fuse box outside. The fuse
box has been relocated from the hallway to the entry just inside the front
door but is still inside. She wants it relocated to the front veranda. She has a
quote to do this for $1,950 plus two truck appointments which would cost
about $200.
11. She says she discussed this at length with JM and said she did not want to
live in a house with a fuse box in the house as she blamed the fuse box for
the fire. She also was wary now of the ducted heating as the fire had come
through it so quickly. She says there is no reason to merely switch the fuse
box from one side of the bedroom door to the other.
12. The quote for the Brivis ducted heating for $4,356 was in line with the
market. The quote by the builder for the Rinnai heater is too high. She
estimated it would cost $2,500. BBS allowed for ducted heating at $2,500 on
the tender.
13. She also requested and agreed with JM that the wall between the kitchen
and laundry be removed to make one large room and was going to alter the
two doorways into one larger doorway with a sliding door at her expense.
Case No: 292026 Determination Page 3 of 18
This was discussed with JM and the kitchen sliding door was not included in
the SOW. The laundry walls were removed instead, without contacting her
and even though it wasn‟t in the SOW, the builder replaced the door and
window, similar to what had been in the house originally. Now the Applicant
is left with two doors right next to each other and of differing materials and
sizes which looks unaesthetically pleasing and will be prohibitively expensive
to install. She says to get what she wants will cost $3,900. If the builder had
have done what was asked, the Applicant would only have had to pay for the
door and the builder‟s costs if the door was installed during the
reinstatement. She has a quote for the door. It is $2,095.50. She always
expected to pay for this.
14. The Applicant says that an inferior quality laminate product was used in the
kitchen bench tops instead of the Laminex product she requested and which
was specified in the SOW. She provides a letter from the Laminex Group
which she used in making up the SOW.
15. The finished home has many defects in the workmanship which are yet to be
remedied. She has provided a copy of the defect report she submitted to the
FSP but they have not taken any action as a result of the report. She does
not wish to deal with BBS again.
16. The Applicant is seeking $2,000 compensation for the strain of dealing with
the mismanagement of the reinstatement, the delays in finishing her home,
the extended time living in temporary accommodation and the stress she
experienced from BBS‟s refusal to adhere to the SOW. She also claims the
FSP did not require the builder to keep to the SOW.
17. The Applicant rejected the Recommendation although she accepted part of
the Recommendation about the kitchen and laundry doors. She was advised
that she cannot accept part of the Recommendation and that the whole of
the dispute will now be reviewed.
18. The Applicant provided several letters and further documentary information
in support of her position. The material is exchanged and so I won‟t repeat it
in detail. The Applicant has essentially reiterated her position. I note also the
following:
The contract was for reinstatement on the basis of equivalent to what
was damaged.
She says it appears that the real reinstatement appears to be an
unwritten agreement to reinstate as cheaply as possible.
The Fuse Box
JM did not go through the SOW in significant detail. She met him twice
and then the communication with JM about the SOW was by telephone
and email. JM did not go through the SOW with her when it was
finished.
At the meeting on 10 July 2012, she was under the impression that
independent quotes were to be obtained.
Case No: 292026 Determination Page 4 of 18
The quotes from BBS should be queried.
Adjacent means next to and contiguous means near and so the fuse
box was meant to be located next to the power board outside the
premises.
The fuse box was installed inside to avoid the expense of obtaining
temporary power.
Moving the fuse box outside is not an upgrade.
She disputes the statement by BBS that it would be considerably more
expensive to put the fuse box outside. She notes his scope of works
included the cost to “brick around new meter box to accommodate
smaller size”.
Kitchen and Laundry doors
The doors are now replaced with one sliding door. A cash settlement of
$500 is acceptable. BBS can have the old doors now stored in the
garage.
Kitchen carpentry, tender process and adherence to SOW
There were many items not agreed to but the Applicant agreed to it
because the tradesman would not adhere to the SOW. The Applicant
says she agreed as she was talked out of it or agreed to a compromise
as she had no choice.
She explains and justifies the items in the BBS variation letter.
The accepted quote from BBS was 24% under the estimate by JM of
$121,000 and “surely that alone would ring alarm bells.” She queries
the tender process.
Rectification List
Many items need to be rectified and she has listed them. Her requests
to remedy defects were ignored. She has been reluctant to allow BBS
back because of their shoddy workmanship.
She asked an architect A to report on the property.
In her email dated 20 October 2013 she says rectification work begun
but in her email dated 7 November 2013, she said the work was not
completed and she asks the Service to order the Certificate of Final
Inspection and that the work be completed.
Compensation
She should not have been asked to do the SOW. She was put under
pressure and had no time to recover from the event. Then the FSP was
disinterested when she lodged complaints. She felt it was normal
practice to ignore the SOW which was upsetting in view of her input.
BBS was argumentative and voices were raised. BBS‟s work was
shoddy. The reinstatement was to take three months and it took six
months. Defects listed by A have not been rectified. She does not have
peace of mind and she says the house does not meet the same
Case No: 292026 Determination Page 5 of 18
standard that it was in prior to the fire. The reinstatement has been
mismanaged and it is a continued strain. She now wants $3,000
compensation.
Premium
She wants a review of the increase in premium and excess since the
fire.
Summary of FSP’ s position
19. I have reviewed all the material submitted by the parties and save where I
make note specifically, I am satisfied the FSP‟s position as set out in the
Recommendation is accurate and is as follows.
20. The FSP accepts that BBS provided a tender for the job late in the process
but says it is satisfied that BBS had adequate time to prepare and cost the
job properly. It rejects the Applicant‟s suggestion that BBS cut corners in
order to ensure the costs stayed within budget or that the tender process
was flawed.
21. The FSP agrees the fuse box was moved at the Applicant‟s request ,
however, both JM and BBS believed that the Applicant simply wanted it
moved closer to the front door. The FSP says its re -positioning was allowed
for in the SOW and works have been completed in line with the SOW. The
FSP states there is nothing in the SOW that suggests the fuse box be
located outside. Moving the fuse box outside would be an extra expense and
it is not liable to complete upgrades to the property.
22. The FSP says the SOW does not refer to the replacement of the rear kitchen
door with one large door. BBS was not advised of this. The Applicant did not
make it known to BBS that she wanted to alter the kitchen/laundry doors until
after the doors had been replaced and she was unhappy with the result. The
FSP says the Applicant then requested a quote to alter this area but found it
prohibitively expensive to do so. The FSP says altering the doorways would
have required additional carpentry, brick works, plumbing etc which is not
covered under the policy. The installation of a larger door is also an extra
expense and it is not liable to complete upgrades to the property.
23. The FSP states the Duropal used in the Applicant‟s kitchen bench tops is an
equivalent product to Laminex. It denies using inferior quality materials in the
rebuild of the Applicant‟s kitchen. Fu rther, the FSP notes the Applicant
arranged a compromise with the kitchen joiners to accept the bench tops in
lieu of some additional cabinetry to upgrade the kitchen. This compromise
work was done and it is not liable further.
24. The FSP denies the SOW was not followed by BBS. Whilst it admits to some
errors in product supplied during the rebuilding process, these have since
been remedied in the Applicant‟s favour. The FSP submits the Applicant‟s
claim was a difficult one to bring to a resolution but there is no evidence to
Case No: 292026 Determination Page 6 of 18
suggest it mishandled or unreasonably delayed either the repairs or the
claim itself.
25. The FSP relies on the following policy provisions:
“ Claims – how we will settle your claim
1 Replacement
If your Insured Property is damaged, We may choose to either rebuild,
replace, repair or pay the amount it would cost to rebuild, replace or repair.
...
We will not pay the cost to:
i rebuild or replace Your undamaged Insured Property;
ii rebuild, replace or repair illegal installations.
...
Indemnity Value
Means the cost to rebuild, replace or repair property to a condition which is
equivalent to or substantially the same as but not better nor more extensive
than its condition at the time of the loss taking into consideration age,
condition and remaining useful life.
...
Replacement
means:
a the reasonable cost of rebuilding, replacing or repairing to a condition
which is equivalent to or substantially the same as but not better nor
more extensive when it was new.”
26. The FSP accepted the Recommendation. After the Applicant rejected the
Recommendation, it rebutted the Applicant‟s further submissions in various
letters. The material is exchanged and so I won‟t repeat it in detail. The FSP
has essentially reiterated its position. I note also the following :
The fuse box
JM went through the SOW in considerable detail with the Applicant.
The Applicant signed off on it.
JM set out what work he did do in regard to the SOW in his lengthy
letter dated 25 September 2013.
Moving the fuse box would be an upgrade.
The cost of the relocation from M does not include the brickwork
adjustments and penetration through the front walls as allowed by BBS.
The fact that the new meter box is smaller does not mean that a large
penetration does not have to be made in the front wall.
BBS has advised the FSP that the quotes are sourced from external
contractors.
Kitchen and laundry doors
Case No: 292026 Determination Page 7 of 18
The FSP accepts this part of the Recommendation.
Kitchen carpentry, tender process and adherence to SOW
There were many compromises to the SOW in accordance with the
requests of the Applicant. The FSP relies on a letter from BBS dated 29
November 2012 which has been exchanged.
All quotes were reviewed and the mere fact that BB‟s independent
quote was less does not prove the tender process was flawed or that
BBS was cutting costs.
Rectification works
Initially BBS tried to remedy but the Applicant refused access.
BBS received the report from A and attended the property on
10 September 2013 to rectify.
The email dated 11 November 2013 indicates BBS was currently in
attendance at the property to rectify and will provide a Certificate of
Final Inspection when the works are completed.
Compensation
The FSP relies on previous submissions and says the FSP has
handled the claim with due dispatch and made its best efforts to
accommodate the Applicant.
Premium
The FSP says the increase is an underwriting decision based on
multiple factors. The Service has no jurisdiction to deal with the matter
as per Terms of Reference 5.1(b).
Issues
27. Whether the FSP has fulfilled its policy obligations to the Applicant.
28. Whether the Applicant is entitled to compensation.
Reasons for Decision
29. There has been an exchange of material between each party and I am
satisfied each party has had an opportunity to reply to the issues raised.
30. Each FOS case is decided on its merits, taking into account the facts of the
case. I have reviewed all the material submitted by the parties both before
and after the Recommendation was issued, in order to reach my decision. I
will only refer to the relevant submissions and materials raised.
Case No: 292026 Determination Page 8 of 18
31. In reaching a decision, it is appropriate to consider the Terms of Reference
under which FOS operate. The Terms of Reference require that I consider
what is fair in all the circumstance having regard to the relevant legal
principles, the terms of the relevant policy and good industry practice.
Regard should also be had to prior Determinations, although such
Determinations are not binding or precedents.
The evidence and contentions of the parties
Photographs
32. JM took photographs of the fire damage to the property. The switchboard at
the entrance is noted as are the sliding doors and door at the back of the
house. The remains of the fuse box can be seen in photograph #10.
33. The Applicant has provided photographs showing where the fuse box was
and where it was moved to. The fuse box was on the wall between the two
bedroom doors and relocated to the other side of the main bedroom door
closer to the front door and the switchboard.
34. The Applicant‟s photographs also show the two doors at the back of the
house which she says are different heights, styles and materials.
The Building Contract
35. The contract was sent to the Applicant by BBS on 30 April 2012. It was
entered into by the Applicant and BBS for fire damage reinstatement. Time
for completion was 90 days. The contract price was $91,938 including GST.
The contract price was not fixed and may be altered by variation.
The Scope of Works
36. The SOW was provided by JM on 26 April 2012. It was sent by BBS to the
Applicant with the contract. I note the following relevant material from the
SOW:
“ Suggested Reinstatement Approach
Location/Item Trade EST $ Comments
Demolition
Kitchen/Meals Area:
Remove sliding door Labour On south wall. Dump.
& windows
General:
Rewire unit: Electrician Locate fuse box adjacent main
switchboard. Supply & install new
switchboard. Allow for 2 No direct
wired smoke detectors.
Heating Rinnai Energy saver gas heater
Model 556 ... (in lieu of Brivis
ducted heating)
Case No: 292026 Determination Page 9 of 18
...”
List of Fixtures and Fittings prepared for JM by the Applicant
37. The List was very detailed. I note the following relevant material from the
List:
“ Kitchen and Laundry
Cabinetry
Bench top Laminex 180fx Carera Marble Diamond gloss
Lounge room
Heating Rinnai in lieu of Brivis ducted heating $2,000.00
...”
Report from the adjuster RA 20 July 2012
38. The parties met on 20 July 2012 to discuss the work done and the SOW.
The main issue was said to be the location of the fuse box. Other issues
were discussed too and resolved. RA identifies the problem stemming from
the interpretation of the SOW. A solution was identified and the builder was
asked to get quotes to relocate the fuse box and offset that against the
savings with the heating system.
JM‟s email 29 June 2012
39. JM was asked to comment about the dispute with the fuse box. He writes:
“ A discussion did take place regarding relocating the fuse box closer to /
adjacent the meter box but still inside the Unit as per the current one – ie.
nearer the front door. Obviously to locate it externally would be considerably
more expensive and involve brickwork adjustments as well as well as a larger
penetration through the front wall. On reflection, there may have been a
misunderstanding by (the Applicant) in this regard. Should she wish to locate
the fuse box this she still has the option of arranging it with the builder at her
cost.
Under General in the Scope of Works it reads “Locate the fuse box adjacent
the main switchboard. Supply and install a new S witchboard.” I understood
from (the Applicant) that she merely wanted the fuse box closer to the front
door – adjacent the switchboard noting the proximity of the board to the front
door.
I also explained to the Insured at the outset that the basis of my assessment
and consequently reflected in the documentation was a “like with like
reinstatement” and that I had no authority to authorise enhancements.
Additionally, the development of the scope and very detailed specifications
with every appliance, tiling, joinery etc fully specified was a painstaking
process involving much liaison and input from the (Applicant) who was most
particular before she eventually fully signed off. There was not one PC item
called up. The issue regarding the precise location of the fuse box was never
raised. The scope reflects a very considerable enhancement to this property
Case No: 292026 Determination Page 10 of 18
over what previously existed and at all stages maximum benefit of the doubt
in the Insured‟s favour was exercised during the SOW preparation process.”
The Applicants‟ email 3 July 2012
40. The Applicant says she is complaining because the SOW is part of the
contract to reinstate the house and is being ignored. Specifically, she says
about the fuse box:
“ In regards to the fuse box,
“Locate fuse box adjacent main switchboard. Supply & install new
switchboard.” This was included in the scope of works. I can‟t see the
relevance of (JM‟s) statement. If the item is on the scope of works it needs to
be carried out/installed . You can‟t choose to ignore it .”
Quotes
41. I have noted the quotes from the Applicant which show the costs as set out
in the summary above. I note in particular the quote from „ M ‟ dated
16 August 2012 which says:
“ Details of work quoted :
Relocate switchboard from inside house to meter box at front door. Price
includes new DRAV meter box with metering at bottom and (not clear) nil - for
circuit breakers.
Existing switchboard hole to be patched by others.
Includes electrical inspection costs and prescribed certificate of electrical
safety.
Doesn‟t include 2x truck appointment fees these will be added to your
electricity account – option 1: $1,950 GST incl.
Option 2: Relocate switchboard to garage - $1,450 GST incl.
Quote Incl: GST $1,950 ”
Defects report after inspection on 14 September 2012
42. A number of defects were noted.
A‟s report August 2013
43. A attended the site on 28 August 2013. He listed items including roofing and
roofing construction and internal finishing. A concluded that the many works
described in the report have been carried out to an unacceptable standard of
workmanship and require rectification as soon as possible.
Analysis
44. The dispute deals with a number of matters arising out of damage to the
Applicant‟s property as a res ult of a fire. The FSP accepted the claim and
proceeded to arrange to rebuild, repair and replace the damage to the
Case No: 292026 Determination Page 11 of 18
property. The policy provides that the amount the FSP will pay, will be the
cost of replacement as defined and set out above.
45. A number of it ems are in dispute and are set out separately. The parties‟
positions and supporting documentation is set out above and I will not repeat
that material in my analysis save when necessary and in the context of my
decision.
The tender process
46. I am not satisfied that the tender process itself was flawed. Three builders
were asked to tender and although the time for BBS to bid was short and the
bid was less than the others and less than the estimate by JM, I do not
accept that this indicates that BBS underquoted and then cut corners to
ensure the job was within the quote.
47. The SOW was thorough and detailed. BBS was aware of the work which had
to be done and that the reinstatement was to be a condition which was
equivalent or substantially the same as what was damaged. I accept that
BBS are experienced builders and could prepare a quote in the short time
allowed.
48. I accept the BBS quote was the cheapest. But I do not accept that the
acceptance of it was improper or done otherwise than by an independent
review of the three quotes.
Positioning of electrical fuse box
49. The SOW provides that the property was to be rewired. A new switchboard
was to be installed. The old switchboard was outside the house on the front
veranda. The SOW says the work to be done was to “locate the fuse box
adjacent to the main switchboard.”
50. The Applicant says she says she spoke at length about this to JM and her
reasons for the move. She says here was no reason to merely switch the
fuse box from one side of the bedroom door to the other. She has obtained
quotes to do this and says the move is not an upgrade and queries the
quotes obtained by BBS.
51. JM agrees that they talked about relocating the fuse box closer to the meter
box but he thought this meant near the front door. He agrees there may have
been a misunderstanding about what the SOW meant but says he had no
authority to authorise enhancements and considered that the move outside
was an enhancement because of the cost of brickwork adjustments and a
large penetration through the front wall.
52. The issue of the fuse box was discussed at length at a meeting on 10 July
2012 and an agreement was reached on how to go forward , but the quotes
received by the FSP were such that they did not bring about a solution to the
dispute. The Applicant disputes the quotes obtained.
Case No: 292026 Determination Page 12 of 18
53. I note the following about the costs involved;
Initially BBS quoted $2,500 to put in ducted heating .
After the meeting, BBS quoted $4,356 to put in the ducted heating.
The Applicant says the quote for the ducted heating is in line with the
market.
A Rinnai heater was on the SOW in lieu of the Brivis ducted heating.
The Rinnai heater quoted by BBS after the meeting was $3,900.60.
The Applicant challenges this amount and says the cost is too high.
She notes the heater retails for $2,000 and on average the heater costs
$500 to install.
BBS quoted on 25 July 2012 for $7,920 to move the switchboard
outside and that quote included 2 truck appointment fees and the repair
of plaster damage and brickwork unlike the quote from M.
M‟s quote wa s in the amount of $1,950 to relocate the fuse box and the
Applicant says the 2 truck appointments cost $200.
54. If I were to accept the analysis of the FSP relying on the quotes from BBS,
then the cost of the relocation of the fuse box would have exceeded the
savings made by replacing the Brivis ducted heating with Rinnai heating and
would be an upgrade.
55. On the other hand, if I were to accept the analysis of the Applicant relying on
her quotes, then the saving on the heating is $1,856 compared with the
estimate she made to relocate the fuse box and pay the truck appointments
in the amount of $2,150. I am satisfied that this amount is such that to do this
work is not an upgrade if these figures were accepted.
56. I accept that:
The policy only allows for an equivalent work to be done.
The parties talked about the relocation of the fuse box when preparing
the SOW and prima facie moving it outside would not have been
equivalent to what was there before the fire.
Nonetheless, the Applicant has a clear recall of why s he wanted the
fuse box to be relocated and in all the circumstances of the trauma of
the fire I accept that clear recall.
The photographs show the fuse box had been in the house before the
fire and it was moved up the wall a short distance only to be closer to
the door after the fire and I see no real benefit in that relocation.
The SOW was meant to deal with this issue.
There was a misunderstanding about what the Applicant meant when
she said she wanted to relocate the fuse box.
The words in the SOW are not conclusive of what was agreed. The
words could substantiate both parties‟ view of what was agreed.
Case No: 292026 Determination Page 13 of 18
If the fuse box was moved outside, it would not be the equivalent of
what had been before the fire and it is unlikely that JM would have
agreed to do it at the FSP‟s expense if he had appreciated what the
Applicant meant by relocation of the fuse box.
The cost of the relocation varies.
57. Having taking into account all of what both parties say on this subject, I am
satisfied that it is fair in all the circumstances for the FSP to make a payment
to the Applicant for this item in dispute. I accept what both parties say on the
matter but I also accept there was a misunderstanding.
58. From the Applicant‟s figures , I am also satisfied that the relocation is not a
significant upgrade and I determine that the FSP pay to the Applicant the
amount of $2,150 for her to arrange and pay to relocate the fuse box.
Kitchen and Laundry Doors
59. I accept that the SOW is such that the Applicant‟s contentions about this
aspect of the dispute have credence as I am satisfied that the SOW
suggests that something else was to be done once the existing doors and
windows were removed.
60. JM has not refuted the Applicant‟s assertions on the subject.
61. BBS would not have been a party to the discussions between JM and the
Applicant until it was too late.
62. The work has been done by the Applicant and the Applicant has paid for it.
She always was going to accept the cost of the new door. She said that to
undo the work done by BBS and put in the new door will cost in the amount
of $3,900. I do not know what component of the cost is referrable to BBS‟s
mistake.
63. Both parties indicated after the Recommendation that the amount of $500
was acceptable to them for this part of the dispute. I do not propose
therefore to determine another amount.
64. I note the Applicant says that BBS can have the old doors stored in the
garage. I accept that the FSP is entitled to the salvage of the old door and
window in the garage.
Kitchen cabinetry
65. The Applicant says the kitchen bench tops were not covered in Laminex as
specified in the SOW but a product called Duropal which the Applicant says
she did not select and which is inferior.
66. Under the policy, the FSP has an obligation to replace the kitchen benches
to a condition which is equivalent to or substantially the same as what was
there before the fire.
Case No: 292026 Determination Page 14 of 18
67. I accept that the SOW set out that Laminex was to be used but I am not
satisfied that the Duroapl is inferior. The FSP say that it is an equivalent
product and the Applicant has adduced no evidence to persuade me to the
contrary.
68. I am not satisfied therefore that the FSP must pay to replace the kitchen
benches with Laminex.
Adherence to SOW
69. The Applicant says there were many items not adhered to and the Applicant
agreed to them because the tradesman would not adhere to the SOW. The
Applicant says she agreed as she was talked out of it or agreed to a
compromise as she had no choice.
70. The FSP denies the SOW was not followed by BBS. Whilst it admits to some
errors in product supplied during the rebuilding process, it says these have
since been remedied in the Applicant‟s favour. It also says the compromises
to the SOW were in accordance with the requests of the Applicant. The FSP
relies on a letter from BBS dated 29 November 2012 which has been
exchanged. The Applicant explains and justifies the items in the BBS
variation in her letter to the Service dated 3 September 2013.
71. While I accept that there were variations for a variety of reasons I am not
satisfied on the information that I have, that the result was that the
replacement was not done to a condition that was equivalent to or
substantially the same as what was there before the fire.
72. Furthermore, the Applicant has compiled a list of complaints which the FSP
has agreed to rectify. In order to do so she consulted with an architect, A. I
accept the report from A assisted in the agreement that BBS rectify the
complaints.
73. I assume A has invoiced the Applicant for the work done in this regard. I am
satisfied that it is fair in all the circumstances and appropriate pursuant to the
Terms of Reference that the FSP pay for the professional cost incurred by
the Applicant in obtaining the report from A, upon production of the invoice
from A and providing the cost of A‟s report does not exceed $3, 000.
74. In this regard, the FOS Terms of Reference state:
“ 9.4 Applicant’s costs in pursuing the matter
FOS may decide that the Financial Services Provider contribute to the legal or
other professional costs or travel costs incurred by the Applicant in the course
of the Dispute. Unless exceptional circumstances apply, FOS will not require
the Financial Services Provider to contribute more than $3,000 to these
costs.”
Rectification works
75. The Applicant provided a defect report in September 2012 which detailed a
number of issues with BBS‟s work. The FSP responded and BBS undertook
Case No: 292026 Determination Page 15 of 18
to remedy the work but the Applicant refused to allow BBS access to the
premises.
76. In August 2013, the Applicant asked an architect, A, to report on the property
and the FSP responded to this report too. BBS received the report from A
and attended the property on 10 September 2013 to rectify.
77. The FSP‟s email dated 11 November 2013 indicates BBS was currently in
attendance at the property to rectify and will provide a Certificate of Final
Inspection when the works are completed.
78. In her email dated 20 October 2013 the Applicant said the rectification work
had begun but in her email dated 7 November 2013, she said the work was
not completed and she asks the Service to order the Certificate of Final
Inspection and that the work be completed.
79. I have nothing from either party since that date and as such I assume the
rectification work has continued and or is completed.
80. If not, the Applicant should continue to make contact with BBS and continue
to make her property available for BBS to complete the rectification works if
these are not complete, to ensure the provision of the Certificate of Final
Inspection. The completion of the works and the provision of the Certificate
of Final Inspection is the responsibility of BBS. The FSP has complied with
its obligations under the policy by ensuring the attendance of BBS to rectify
and should continue to do so.
81. On the evidence to hand I can make no other comment about the standard
of or the completion of the rectification works.
Compensation
82. The FOS Terms of Reference provide:
“ 9.3 Other compensation
a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that
the Financial Services Provider compensate the Applicant for
consequential financial loss or damage up to a maximum amount of
$3,000 per claim made in the Dispute.
b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that
the Financial Services Provider compensate the Applicant for non-
financial loss but only where:
(i) an unusual degree or extent of physical inconvenience, time
taken to resolve the situation or interference with the
Applicant‟s expectation of enjoyment or peace of mind has
occurred; or
(ii) in the case of a Dispute pertaining to an individual‟s privacy
rights - injury has occurred to the Applicant‟s feelings or
humiliation has been suffered by the Applicant.
Case No: 292026 Determination Page 16 of 18
The maximum amount of compensation for non-financial loss will be
$3,000 per claim made in the Dispute.
c) Notwithstanding paragraphs 9.3 a) and b), FOS will not provide
compensation for:
(i) consequential financial loss; or
(ii) non-financial loss,
in a Dispute arising as a result of a claim on a General Insurance
Policy that expressly excludes such liability.
d) The cap on liability in paragraph 9.3 a) does not in any way restrict
FOS‟s ability to make an interest award under paragraph 9.5.”
83. The Applicant is seeking $3,000 compensation for:
the strain of dealing with the mismanagement of the reinstatement;
the delays in finishing her home - the reinstatement was to take three
months and it took six months;
the extended time living in temporary accommodation;
the stress she experienced from BBS‟s refusal to adhere to the SOW
and that the FSP did not require the builder to keep to the SOW;
the fact she had to do the SOW, put her under pressure with no time to
recover from the event;
the disinterest of the FSP when she lodged complaints;
the dissatisfaction when the SOW was not adhered to in view of her
input;
BBS‟s argumentativeness and raised voices;
BBS‟s shoddy work;
The defects listed by A which have not been rectified;
Her lack of peace of mind; and
The fact the house does not meet the same standard that it was prior to
the fire.
84. The FSP says it has handled the claim with due dispatch and made its best
efforts to accommodate the Applicant.
85. I accept that the rectification of a home after a fire would be stressful as well
as living away from that home for an extended period. I also accept from the
material presented to me that the FSP has not been unresponsive to the
many issues that arose with this rectification.
86. However, I do not accept the rectification and the remedy of defects have
been handled in a timely fashion. The Applicant‟s home was damaged by fi re
in March 2012 and yet as late as November 2013 the parties were still
dealing with the remedy of the defects.
Case No: 292026 Determination Page 17 of 18
87. The rectification work was to a small unit, the initial quote to do the
rectification was under $100,000 and the contract provided the work would
take 90 days. Even with the disputes raised, the various complications
outlined herein and variations to the contract, I am not satisfied that the time
taken to resolve the situation is acceptable and that this time taken would
interfere with the Applic ant‟s peace of mind.
88. While I accept that BBS may be responsible for some of the delay, the FSP
has ultimate responsibility to ensure its agents do good work in a timely
fashion and I am not satisfied that it has been proactive enough in this
regard in all the circumstances of the matter.
89. Taking all matters into account, I accept the Applicant is entitled to
compensation under the Terms of Reference and I propose the FSP pay the
Applicant $1,500.
Increase in Premium
90. The Applicant wants a review of the increase in premium and excess since
the fire.
91. The FSP says this is an underwriting decision based on multiple factors and
that the Service has no jurisdiction to deal with the matter as per Terms of
Reference 5.1(b).
92. The FOS Terms of Reference provide:
“ 5.1 Exclusions from FOS’s jurisdiction
The Service may not consider a Dispute:
...
b) about the level of a fee, premium, charge or interest rate – unless:
(i) the Dispute concerns non-disclosure, misrepresentation or incorrect
application of the fee, premium, charge or interest rate by the
Financial Services Provider having regard to any scale or practices
generally applied by that Financial Services Provider or agreed with
that Applicant;
(ii) the Dispute concerns a breach of any legal obligation or duty on the
part of the Financial Services Provider; or
(iii) the Applicant‟s Dispute is with a medical indemnity insurer and
pertains to the level of medical indemnity insurance premium or the
application of a risk surcharge (as defined in the Services Contract
between the Health Insurance Commission, and the Commonwealth
of Australia represented by the Department of Health and Ageing,
and medical indemnity insurer);
...”
93. I may consider a dispute about the level of premium in certain circumstances
but I am not satisfied that those circumstances apply in this matter on the
material before me. I do accept that an increase in premium is an
Case No: 292026 Determination Page 18 of 18
underwriting decision based on many factors, one of which is the insured‟s
claims history.
Determination
94. On the information to hand and for the reasons stated I determine:
The tender process was not flawed;
The FSP is to pay to the Applicant the amount of $2,150 so she can
relocate the fuse box outside;
The FSP is to pay the Applicant $500 for the removal of the kitchen
doors, with the doors and windows then becoming the property of the
FSP;
The FSP does not have to pay to replace the kitchen benches with
Laminex;
Pursuant to paragraph 9.4 of the Terms of Reference , the FSP pay for
the professional cost incurred by the Applicant in obtaining the report
from A, upon production of the invoice from A and providing the cost of
A‟s report does not exceed $3,000;
Pursuant to paragraph 9.3 of the Terms of Reference , the FSP pay the
Applicant $1,500 for compensation for non- financial loss; and
Pursuant to paragraph 5.1b) of the Terms of Reference, I make no
determination regarding the level of premium.
95. The FSP is to make the payments within seven days from the date the
Applicant ‟s acceptance of the Determination and seven days after receipt of
the invoice from A.
96. As for the amounts already paid by the Applicant, the FSP is to pay statutory
interest on the amounts from the date they were paid by the Applicant until
the date of reimbursement to the Applicant by the FSP.