Determination 291308
Claim amount - cyclone repair cost
Summary
The applicants claimed the cost of storm repairs from cyclone damage based on their representative's quote of $183,464.05. The FSP had already cash settled $78,575.39 based on its expert's scope of works.
The burden lies with the applicants to show all claimed loss was caused by the insured event, and the FSP's expert evidence was preferred over the representative's quote.
Issues
- Claim amount dispute primary · not upheld“I am persuaded by the FSP's experts' evidence as to the extent of cyclone damage and the cost of repairing the property.”
Subjects and remedies
home or building damagenatural disasterno remedy
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Case No: 291308 Determination Page 1 of 5
Case number: 291308
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim Amount
9 April 2013
Background
1. The Applicants held a farm insurance policy with the Financial Services
Provider (FSP) which was current at the time of the loss.
2. The Applicants lodged a claim with the FSP after their property was
extensively damaged during Cyclone Yasi.
3. The FSP accepts an insured event has occurred and has cash settled the
Applicants the cost of repairs in the sum o f $78,575.39, this being the higher
of two quotes obtained to complete repairs.
4. The Applicants seek a total cash settlement of $183,464.05, based upon
their chosen repairer‟s quotation, BNI, who is representing them in this
dispute.
Summary of Applicants ’ position
5. BNI says its quotation is complete and accurately reflects the cost of
repairing the cyclone damaged property.
6. As such, it submits the Applicants should be paid by the FSP based upon its
quotation.
Summary of FSP’s position
7. The FSP says it has cash settled the cost to it for repairing the cyclone
damaged property.
8. The FSP further says BNI has quoted for damaged property which was not
damaged during the cyclone.
9. The FSP suggests BNI has a vested interest in this matter and should step
aside as the Applicants‟ representative.
Determination
Case No: 291308 Determination Page 2 of 5
10. The FSP relies on the following policy provisions contained within the
Product Disclosure Statement (PDS), which the Applicants do not dispute
receiving:
““Indemnity Value” means the market value of a Building, Contents,
personal valuables or Farm Property at the time of loss or damage, taking into
consideration the age, condition and state of repair.
...
What you are insured for
We will pay for loss or damage caused by the Occurrences listed under
Defined Events Cover or Accidental Damage Cover to your Building or
Contents depending on the cover type you have selected.”
Issue
11. Whether the FSP is required to cash settle the Applicants in accordance with
BNI‟s quotation.
Reasons for decision
12. I am satisfied there has been a full exchange of information between the
parties with each being afforded the opportunity of addressing any issues
raised therein.
13. Due to the nature of this dispute, FOS has considered it appropriate to
expedite the dispute in accordance with the Operational Guidelines to the
FOS Terms of Reference. This dispute has not been the subject of a FOS
Recommendation and has proceeded directly to Determination.
14. When lodging a claim for consideration, the burden of proof lies with the
Applicants to demonstrate on the balance of probabilities that all of the loss
claimed is as a result of an insured event.
15. There is no dispute an insured event occurred. What is in dispute is whether
all of the damage claimed by the Applicants and the cost to repair the
damage is as a result of Cyclone Yasi.
16. Following lodgement of the claim, the FSP appointed a loss assessor, C, to
attend the Applicants ‟ property and report on the extent and cause of the
damage. After C‟s attendance, the Applicants provided a list of damaged
contents, buildings and property with quotations for either repair or
replacement. With the exception of the quotation from BNI, all other
quotations were accepted and cash settlements issued to the Applicants.
17. C arranged for a building consultant, IC, to attend the Applicant s‟ property to
provide a report on the extent of the damage caused by the cyclone and to
produce a scope of works for repairing the damage. BH reported, in
particular to the roof:
Case No: 291308 Determination Page 3 of 5
“Roof Sheeting – Debris damage has occurred to the northern roof face above
the vicinity of the garage. The factory Colorbond finish is heavily weathered.
Replacement sheeting will therefore be vastly different in appearance. We
believe the weathered finish of the exiting roof is consistent with the age of the
roof. The cyclone Yasi event would definitely accelerated the deterioration of
the finish.
...
Roof Frame – We did not identify any damage sustained to the roof frame at
the time of the inspection. Insulation batts installed reduced ability to fully
inspect all roof/ceiling areas.
...
The dwelling has sustained debris damage to various roof sheets and other
non-structural roof components. As such there is no requirement to obtain
building approval for repair of this roof. We believe replacement only of the
damaged components are required.
...
The northern face of the roof is the side that has sustained most damage and
is the side that will be most obvious once repaired. Approximately 50% of the
northern face of the roof will be required to be replaced.”
18. IC reviewed and considered the quotation from BNI, which included the
replacement of the entire roof, to ascertain if it was reasonable and restricted
to the cyclone damage only. BH reported:
“The subject dwelling has sustained debris damage only to the roof sheeting
and some associated flashings. Regardless of this amount equating to more
or less than 20%, there is no structural damage sustained to the roof as such.
The Queensland State Government Roof Repair Guideline is industry
accepted guide for rectification of Cyclone damaged dwellings.
This document does not describe that roof sheeting damaged by debris to an
area of more than 20% necessitates total roof sheeting replacement.
We believe there is no structural damage to the roof. The roof sheeting itself
has not failed and has sustained cosmetic damage only. On that basis we
believe the roof sheeting can be repaired “like for like”.
...
We reviewed the BNI scope of works against the items described in the IC
scope of works and our Preliminary Report. The following items extracted
from the BNI scope of works are items we have deemed not cyclone damage.
...
From our assessment and review of this claim we believe the monetary value
of works deemed “not cyclone damage” should be subtracted from the total
quoted amount provided by BNI.
From our calculation this equates to $183 464.05- $104 888.66 = $78 575.39”
19. The FSP opted to obtain a second opinion from P as to the reasonable cost
of repairing the cyclone damage at the Applicants‟ property. P considered
there was additional damage which had not been identified by IC. P quoted
$26,893.75 for the cost of repairing the additional damage and $43,208.60 to
Case No: 291308 Determination Page 4 of 5
repair the already identified damage. Therefore the total quoted for repairs
was $70,102.35. In regards to the Applicants‟ roof, P r eported:
“The insured has insisted that more then 20% of the roof has been damaged
and will now require full replacement. The roof is of some age and that we
could only find cosmetic damage and there no signs of impact other then
some parts of the ridge ca pping.”
20. Upon receipt of this report, the FSP offered to cash settle the Applicants in
the sum of $70,102.35. As this offer was rejected by the Applicants and upon
further review, the FSP offered a cash settlement of $78,575.39, this being
the figure originally quoted by IC.
21. This again was rejected by the Applicants. BNI argues the FSP‟s expert, IC,
cannot be relied upon as there was an error in the calculation of the roof
size. This was put to IC who responded:
“The comment should read ‘Replacement of the e ntire northern roof face to
the house’ . We have calculated this amount at 60 square metres, however we
concede that our intention was for this entire northern face to be replaced
which is to override the 60 square metres allotted should this figure be proven
inaccurate.
...
We have indicated in this photograph (number 8) to show the extent of
damage has not been sustained across the entire northern roof elevation,
however we believed it was „fair and reasonable‟ to increase the area of
roofing to be replaced to include the remainder of this roof face. This was
done on the basis of what we considered a more acceptable cosmetic finish
as opposed to the roof, to the northern elevation, appearing „patched‟.”
22. BNI has provided no detailed explanation as to why he considers the entire
roof of the Applicants‟ property requires replacing nor why he considers
other items require repair as a result of cyclone damage, when two experts
are of the opinion the roof can be successfully repaired and BNI has quoted
for non cyclone related damage.
23. Having considered the various reports, I am satisfied that given his position
as the Applicants‟ representative, BNI cannot be considered as completely
independent of the dispute. Further, I prefer the analysis, logic and
conclusions of the reports provided by the FSP.
24. As previously detailed, the onus, first and foremost, lies with the Applicants
to demonstrate that all of the loss claimed is as a result of Cyclone Yasi. I
am not satisfied that they have been able to demonstrate this. Therefore, I
am persuaded by the FSP‟s experts‟ evidence as to the extent of cyclone
damage and the cost of repairing the property.
25. On this occasion, the FSP has opted to cash settle the Applicants at the
higher quotation of $78,575.39, which I consider to be fair in all the
circumstances.
Case No: 291308 Determination Page 5 of 5
Determination
26. On the basis of the available information, I determine the FSP is not required
to cash settle the Applicants based upon the quotation supplied by BNI.