Home / Financial Firm (Unknown - Insurer) / Determination 291005

Determination 291005

Insurer limited liability for water leak damage to bathroom and hallway

FirmFinancial Firm (Unknown - Insurer)
Decided2013-05-10
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A leaking shower pipe damaged the applicant's home, and the FSP accepted the claim but limited its liability to the damage it considered covered. AFCA found the FSP had not established its reduced liability, ordered indemnity subject to policy terms and excess with a fresh assessment and interest, but excluded damage caused by earlier plumbing repairs.

Once the applicant establishes a prima facie claim, the insurer bears the onus to prove an exclusion applies, and it did not on the balance of probabilities.

Issues

Subjects and remedies

home or building damagepay claimpay interestreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 291005 Determination Page 1 of 10 Case number: 291005 General Insurance - Domestic Insurance - Home Building - FSP Decision – Insured Event – Policy Limitation- Claim Settlement 1 May 2013 Background 1. The Applicant held a Home Building and Contents Insurance Policy (the policy) with the Financial Services Provider (FSP). 2. A claim was lodged under the policy for water damage to the insured property due to a leaking shower water pipe (pipe). 3. The FSP accepted the claim however limited its liability to costs it believes are covered under the policy and which are significantly lower than what the Applicant is seeking as indemnity under the claim. 4. The Applicant remains dissatisfied with the FSP‟s assessment and subsequent offer of settlement offer put to him under the claim. Summary of Applicant’s position 5. The Applicant discovered damage to his home due to a leaking pipe which was inside a wall cavity and only became evident once significant damage had been done. 6. It is important to note that prior to purchasing the property (close to a year before the date of loss subject to the claim) he arranged for a pre-purchase building inspection report. The appointed builder confirmed that there was no evidence of water damage and/or leaks in the home; this has been further supported b y a statement from the builder “DK” made available for consideration. 7. It is also of relevance, that before the damage became apparent the home went from having two adults and one child (around 3-4 showers a day) to four adults and one child (6-9 showers a day) prior to the damage being discovered. He maintains that this is a large increase in water usage through the leaking pipe. 8. The wall between the bathroom and hallway where the leak was discovered was solid and did not have a bow until such time the leak occurred. At no Determination Case No: 291005 Determination Page 2 of 10 time did the Applicant advise the FSP that the leak occurred over a period of a few days. 9. The Applicant strongly refutes the FSP‟s position that there was no evidence of damage beneath the leak. He maintains the evidence he has made available establishes that there is significant staining of the particle floorboard directly below the leak. Further, considering gravity it is only reasonable to accept that the water leaking from the pipe would not have pooled half way up the wall rather would leak down to the bottom of the wall cavity and therefore floor. 10. There is a slight fall in the floorboards (from the directly beneath the location of the leak) towards the area of the bathroom floor and which is why there existed continuous staining from the underneath the leak to point of exit i.e. hole in the floor near bathroom door. 11. The Applicant remains dissatisfied with the FSP‟s appointed assessor‟s efforts in respect to assessment of the cause and extent of damage subject to the claim. He maintains the first assessor “MP” did not even turn a tap on during his visit nor was he interested in listening to the Applicant in respect to how the leak was discovered. He did not consider inspecting the sub-floor area necessary and was only at the home for aro und 15 minutes. 12. The Applicant fails to understand how the FSP continues to ignore the evidence made available by multiple consultants commissioned by him. Further, he notes that all of these consultants were appropriately qualified and licensed builders however questions whether the same applies to the FSP‟s assessors PM and “DH”. 13. He maintains that DH verbally advised him (when continuously questioned) that he could not guarantee that DH‟s conclusion regarding the circumstances resulting in the loss was exactly what happened, rather it was only his professional opinion. Further, DH acknowledged the Applicant‟s position and that of the other consultants‟ was possible however this was not his opinion. 14. The Applicant is seeking for the FSP to authorise repairs to the bathroom and reduce hazards in the home i.e. the hole in the floor. The FSP‟s management of the claim has caused a lot of disruption and undue stress for the Applicant and his family. Summary of FSP’s position 15. It is a general principle of insurance that the onus rests with the Applicant to establish the loss claimed falls within the scope of cover available under the policy. The policy does not provide indemnity for all risks and is subject to specific exclusions. 16. The Applicant and his appointed consultants maintain the damage is due to the leaking shower breach. However, they provide no explanation as to why Case No: 291005 Determination Page 3 of 10 there is an absence of any damage to the area surrounding the location of the leak. 17. It has never been the FSP‟s position that water had flowed up the tiled surface. Simply, the damage is attributed to escape of water from the shower base over a considerable period of time, due to a leaking shower membrane which is not covered under the policy. 18. Following the FSP‟s investigation it was clear that the water from the leaking pipe had not travelled through the confines of the wall cavity as there was minimal damage and not consistent with the rotting to the floor that was present only a few meters away. 19. The FSP questions as to why water continued to leak and cause damage following the repair of the leaking pipe. It is not for the FSP to establish how a particular incident occurred rather the onus rests with the Applicant to establish the damage claimed is covered under the policy. 20. The total extent of damage requiring repairs was not all the result of the insured event. In this instance the extent of cover available under the policy is limited to damage to the hallway wall lining as well as the damaged carpet. The shower tiles and shower wall were damaged as a result of the repairs and not the event and the FSP notes the repairs could have been undertaken from the hallway side of the wall which had already been damaged. 21. The FSP acknowledges the Applicant‟s reference to the bow in the villa board on the bathroom walls however it maintains that this was found to be due to an application of the incorrect glue and inadequate fixing. Therefore, this aspect of the claim is not covered under the policy in line with the relevant policy limitations. 22. In line with the opinions made available by its assessors, the FSP maintains the leak discovered was only a recent event and was separate to the damage located in the vicinity of the bathroom floor which had been occurring over an extended period of time. 23. The pre-purchase building report identified the presence of cracked tiles however failed to indicate where these were in the bathroom. Also, at the assessment DH noted evidence of water still leaking under the aluminium strip across the bathroom doorway where the rotten flooring was, this being subsequent to the leaking pipe being repaired. 24. Simply, the FSP maintains that the leaking pipe did not cause or contribute to the damage in the vicinity of the bathroom door. If the leaking pipe was the cause there would have been evidence of water damage between the location of the leaking pipe and the area around the door. Rather, it maintains the damage was due to a failed shower membrane and occurred over a period of time, therefore excluded from cover. 25. The FSP relies on the following policy provisions: Case No: 291005 Determination Page 4 of 10 “ Page 20 of the Classic Home & Contents Insurance policy provides: Damage from leaking, overflowing or bursting pipes and water containers at the home including: …  Water beds, baths, sinks, toilets and basins … We do not cover …  the repair of a leaking shower floor or base, shower cubicle walls, shower glass screening or shower doors, or any damage caused by the leak …  fixing normal wear and tear (e.g. replacing worn out tile grouting) … • Page 49 of the Classic Home & Contents Insurance policy provides: We do not cover: Wear, tear, rust or mould Loss or damage caused by wear, tear, rust, fading, gradual deterioration, mould, rising damp, mildew, action of light, atmospheric or climatic conditions corrosion or rot unless this is covered under:  insured event 1 (storm and flood)  insured event 2 (burst pipes, leaks and overflows) ” Issues 26. Whether the Applicant has established an entitlement for the full extent of the loss claimed under the policy. 27. Whether the FSP was entitled to limit its liability under the claim to the Applicant in line with the policy. Reasons for decision 28. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This is due to the circumstances of the dispute. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 29. I have reviewed the submissions of the parties in relation to the terms and conditions of the policy and will only refer to the relevant submissions and materials raised. 30. I am satisfied the following is not in dispute between the parties: Case No: 291005 Determination Page 5 of 10  The Applicant held an active home building and contents insurance policy with the FSP at the time of loss.  The FSP provided and the Applicant received the relevant policy documentation including the Product Disclosure Statement (PDS) prior to the loss.  A leak in the shower plumbing was located by the Applicant and which had caused damage to the insured home.  The policy provides cover for loss or damage arising from leaking pipes however the extent of damage covered under the policy remains in contention between the parties.  Both parties have obtained and rely upon the opinions submitted by their preferred consultants. 31. I have been provided with several consultants‟ reports commissioned to the claim by the parties in respect to the cause and extent of damage to the insured property. I am satisfied that this information has been exchanged between the parties each having had the opportunity to comment. In the interest of brevity I will only reiterate information from these reports I find relevant in providing this Determination. MP’s (Assessor) Report  Date of assessment 6 December 2011.  The Applicant purchased the home in February and had a pre- purchase building inspection in December 2010, which reported no moisture/related issues for the bathroom and sub-floor area.  The leaking water pipe to the shower rose does appear to have been leaking prior to the building report judging by the extent of water damage to the flooring and rotted hardwood joist.  The plumber appointed by the Applicant removed the tiles in the shower recess and cut a hole through the villa board instead of completing repairs through the hallway wall plasterboard which had already been cut. Therefore, the damage to the tiles and villa board were the result of repairs as opposed to the insured event.  The bow in the villa board was noted to be due to incorrect glue and inadequate fixings, very few nails were used and so not due to the insured event. TL’s Builders Report dated 9 December 2012  An inspection revealed a leaking copper pipe in the hallway wall which had caused substantial damage to the wall structure, hallway flooring and bathroom flooring.  It appeared the join in the copper pipe soldering had fatigued over a substantial time. Case No: 291005 Determination Page 6 of 10  The repairs would require stripping of the room back to the floor joists and wall framing etc. HC’s Report dated 12 December 2011  Inspected water damage to main bathroom and adjoining hallway.  Prior to inspection plumbing repairs had been completed to the shower area. The repairs indicated that the junction of copper pipes in the wall cavity behind the shower recess had leaked.  The slow leak had likely been unnoticeable for some time, causing wet rot to the wall and floor structure.  To achieve full repair, it would be necessary to strip the current bathroom back to wall linings to allow sufficient waterproof to all wet areas. Removal of damaged wall alone will not be sufficient.  Wet rot timber is known to attract termite activity, so HC recommended that that full replacement of wet rot timber. DH Assessor’s Report  Date of Assessment 30 March 2012.  Inspected the areas of concern and confirmed presence of water damage to structural sheet flooring to the hallway, wall lining damage (due to location works), wall tiles and shower wall (due to repair works), detached wall lining from the timber frame on shower wall.  He also noted badly water damaged vanity unit, rotte n bathroom door architraves and some minor rot to hardwood door joist.  DH noted no evidence of any water damage to the timber wall framing around the leaking pipe location and there was no water staining to the rear of the villa board.  There was no rotten or water damaged structural sheeting flooring below the location of the leaking pipe. The rotten flooring, door architrave and floor joist are located at the bathroom door, approximately one metre away from the leaking pipe.  Lack of water damages to the softwood wall framing and water resistant sheet flooring below the leak point indicates the leak had been occurring over a short time only.  The level of damage in the vicinity of bathroom door indicated that a leak had been present for some time. Further, he noted aged clear silicone had been applied to the base of the rotten door architrave, indicating that the rotten architrave had been present for an extended period of time.  There were no restrictions for any water leaking into the wall cavity to prevent it from flowing directly out in the hallway. So, if the leaking pipe had been ongoing for a while, that would have caused rotting of the Case No: 291005 Determination Page 7 of 10 water resistant sheet flooring, carpet to the hallway directly below the leak and would have been wet and rotten a long time ago.  DH noted the shower was in use (after the leaking pipe had been repaired) and there continued to be water leaking out of the bathroom floor area. It could only be coming from the shower recess when in use, indicating a failed shower recess.  Sub-floor inspection showed no water damage to floor/floor joists under leaking pipe area, only damage noted was at the doorway region. Inspection under vanity not undertaken.  The sighted evidence showed that the stud adhesive glue at points of failure left remnants of the adhesive on both the wall sheeting and studs, both these being honey combed. DH formed the opinion that they separated whilst the glue was still wet. DB Builders Report  Attended the property on 24 April 2012  He noted there had been a water leak from a blown copper pipe fitting between the taps and shower nose. It was not evident until the shower was in constant and excessive use.  Two studs and walls directly within the vicinity of the leaking pipe were affected.  Seems to have caused significant cracking and movement to the all tiles due to expansion and contraction of the wall sheet in the process of saturation and drying out.  He noted a pre-purchase building inspection report had been undertaken on 3 December 2010, at which time the tiles were noted to be in general good condition. There was one cracked tile noted in the shower recess wall which was cosmetic only.  There was no moisture penetration readings detected when the shower was tested, a „Tramex Moisture Encounter Plus Meter‟ w as used at the time of the pre-purchase inspection. 32. In addition to the above discussed consultants‟ opinions I have also been provided with photographic evidence in respect to the damage by the parties. In addition to this, a video recording made available by the Applicant has also been provided which details the extent of damage subject to the dispute and also his response to certain issues raised by the FSP in its submission to the Service. 33. I have carefully considered the available evidence and am satisfied that the Applicant has established a prima facie claim under the policy. Accordingly, the onus rests with the FSP to establish, on the balance of probabilities, that the extent of damage claimed is not the result of the insured event and therefore its entitlement to limit liability under the claim. Case No: 291005 Determination Page 8 of 10 34. It is not in dispute that a pre-purchase building inspection report was arranged by the Applicant prior to purchasing the property around 12 months before the date of loss subject to the claim. I am satisfied that it is not in dispute that the report confirmed there were no moisture issues with the home at the time. It would not be unreasonable to accept that the leak in the shower plumbing occurred at some stage after the home was purchased. 35. I note the consultants‟ appointed by the Applicant are for the most part consistent in their view that the leaking pipe was responsible for the full extent of damage subject to the claim as well as the scope of works required to repair the damage. I have also carefully considered the FSP‟s assessors‟ main concerns in respect to the damage and based upon which they are seeking to partially decline the claim. 36. The FSP maintains the fact that there is minimal damage around the location of the leak (inside the wall cavity) and the absence of damage to the floorboard directly under the leak are inconsistent with the significant damage and deterioration noted to the property in and around the bathroom doorway being the result of the leaking pipe. The FSP acknowledges some minor damage has occurred due to the insured event however maintains it is not liable for the cost to repair :  the damage in the vicinity of the bathroom doorway as it has occurred over an extended period of time due to failure of the shower recess and not the insured event.  the damage to the shower wall tiles and shower recess (bathroom side) wall due to repairs undertaken to fix the leaking pipe and which could have been completed through the leak location damage on the hallway side of the wall.  Bowing of the villa board in the vicinity of the leak as this is due to use of the wrong/inadequate glue and a lack of fixing. 37. The Applicant maintains that he has made available sufficient evidence to establish, on the balance of probabilities the damage subject to the claim is all related to the insured event. Further, that he acknowledges certain costs involved in the repair process are his responsibility and he is prepared to accept these as his to bear. The damage became apparent arising from the fact that the shower was in use much more than normal due to guests residing with him prior to the date of loss. 38. I have carefully considered all the available evidence and am not satisfied that the FSP has established an entitlement to reduce its liability under the claim to the extent it maintains is reasonable. The available information, in my opinion and on the balance of probabilities, clearly establishes that:  At the time of purchasing the home there were no issues relating to water damage and/or moisture penetration related issues discovered at the insured property. Case No: 291005 Determination Page 9 of 10  There is clear evidence of water damage/staining at the foot of the hallway wall where it meets the floorboards directly below the leaking pipe.  The available photographic evidence made available by the Applicant in his undated document (sent to the FSP‟s dispu te resolution representative) clearly shows how much water would leak into and pool in the bottom of the wall cavity (photo 2 and 4).  Further, the water damage/staining continues in an unbroken flow from directly beneath the location of the pipe towards the bathroom doorway both inside the wall cavity as well as along the particle floorboards.  I am satisfied that this supports the Applicant‟s position (and which has not been rebutted) that there exists a slope in the floorboards from the location of the leak towards the bathroom doorway.  Therefore, it is not unreasonable to accept that the water would flow towards the bathroom doorway and has then pooled in area just outside doorway. Due this being the point where the water has pooled I accept this explains why there is significantly more damage and rotting of the particle floorboard.  DH‟s opinion that the damage to the area in front of the bathroom doorway is due to water escaping under the bathroom floor tiles from a leaking shower recess over an extended period of time is not supported. I would expect if this was the case (consistent with damage occurring over an extended period of time and of which there is no evidence made available) there would exist evidence of this alleged ongoing damage in the form of:  significant staining and swelling of the floorboards from the shower recess to the doorway;  drummy and lifting of the floor tiles all the way from the shower recess to the doorway.  Considering the bowing of the villa boards had not occurred for close to thirty years (age of the home), was not evident at the time of the pre- purchase inspection and did not become evident until the insured event, I do not accept the assessor‟s opinion that it was due to inadequate glue and fixings is a reasonable conclusion in this regard.  Also, in respect to his comments relating to the lack of or minimal damage around the area of the leak I note that the villa board(s) installed there are used because of their quality for being moisture resistant in comparison the significantly damaged particle board flooring. It is therefore not unreasonable to accept that the moisture resistant villa board(s) installed at the height of the leak would be less susceptible to moisture damage from the leak. 39. On the basis of the evidence of the parties and their commissioned / appointed consultants I am satisfied that the Applicant‟s understanding of the circumstances leading up to and causing the damage is the more likely and consistent with the resultant damage subject to the claim. I am not satisfied Case No: 291005 Determination Page 10 of 10 that the FSP has fulfilled its onus to establish that the damage claimed, on the balance of probabilities, is due to circumstances excluded under the policy. 40. Accordingly, I am satisfied the FSP is obliged under the policy to provide indemnity to the Applicant for the damage claimed in line with the relevant provisions of the policy. Determination 41. On the basis of the available information I determine:  The FSP is obliged to provide indemnity to the Applicant for the damage claimed subject to the relevant policy provisions and subject to the applicable policy excess.  The FSP is to arrange for the appointment of an adequately qualified consultant acceptable to both parties to undertake a fresh assessment and provide a quote for the required scope of works in line with this Determination.  In the instance the FSP seeks to settle any aspect of the claim by way of cash settlement it is to pay interest upon this amount in line with the Insurance Contracts Act (1984) from 14 June 2012 (date of final decision) till such payment is issued.  In the instance the Applicant has incurred any costs in an effort to mitigate any further loss and which would normally form part of the scope of works under the claim for which he is to reimbursed, the FSP is pay interest upon such payment in line with the Act from 14 June 2012 (date of final decision) till such payment is issued.  The FSP is not responsible for the damage caused by the plumbing repairs previously attempted.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.