Home / Financial Firm (Unknown - Credit) / Determination 290757
Determination 290757
Late decline of pre-approved home loan before settlement; alleged misleading preliminary approval letter
Summary
The applicants bought an investment property at auction relying on a preliminary home loan approval. The FSP declined the loan the day before settlement and the applicants settled with another lender. AFCA determined the FSP did not mislead them about final approval and did not delay unreasonably, so no compensation was payable.
The preliminary approval letter clearly stated that further conditions, including trustee approval and lenders mortgage insurance, had to be satisfied, so the applicants' belief that the three conditions were sufficient was not caused by misleading conduct.
Issues
- Misleading conduct primary · not upheld
“I agree with the case manager that the conditions of the pre-approval were not limited to the Three Conditions which the Applicants believed needed to be met.”
- Delay secondary · not upheld
“I accept that the FSP did not delay unreasonably in assessing the application.”
- Failure to disclose secondary · not upheld
“The FSP did not have to inform the Applicants of these reasons. The Trustee was entitled to decline to fund the loan on any grounds that it wished.”
Subjects and remedies
no remedy
Text of the determination
Case No: 290757 Determination Page 1 of 12
Case number: 290757
Credit - Consumer Credit - Home Loans - Disclosure - Misleading
product/service information
11 November 2013
Background
1. On 13 July 2006 the Applicants submitted a Max Lo Doc loan application to
the financial services provider (FSP) for two loans totalling $539,000 (the
Loan Application). The purpose of the loans was to re-finance the existing
home loan for their property at K (the K Property) and also to fund the
purchase of an investment property in G (the G Property)
2. On 14 July 2006, the FSP advised the Applicants in writing that the Loan
Application had received preliminary approval.
3. Based on the 14 July 2006 letter the Applicants entered into a contract of sale
on 29 July 2006 to purchase the G Property for $318,000.
4. On 23 August 2006 the FSP advised the Applicants ’ representative (Mr C)
that the Loan Application had not received final approval.
5. Due to having to imminently settle the G Property purchase on 28 August
2006 the Applicants sold the K Property and also obtained finance from an
alternative financial services provider.
6. The dispute concerns the loss that the Applicants say that they suffered as a
result of the FSP failing to provide final approval for the loan.
Summary of Applicants ’ position
7. On 13 July 2006, Mr C lodged the Loan Application with the FSP. The
facsimile coversheet stated that loan pre-approval was required as they
wished to bid at auction for the G Property on 29 July 2006.
8. By letter dated 14 July 2006, the FSP advised them that preliminary approval
for the Loan Application had been given subject to three conditions which
were to be met being:
a. the K and G Properties must meet valuation (the First Condition);
b. the purchase price at the G Property auction was not to exceed
$350,000 (the Second Condition); and
Determination
Case No: 290757 Determination Page 2 of 12
c. a signed purchase contract from the G Property auction was to be
provided to the FSP (the Third Condition)
(the Three Conditions)
9. The first time that they learnt that the FSP had declined the Loan Application
was through Mr C on 23 August 2006. This did not give them sufficient time to
obtain alternative funding as the settlement date was 28 August 2006. The
reason given was that Mr H was not registered for GST. This requirement had
never previously been communicated by the FSP to them or Mr C.
10. Upon being informed by Mr C that the FSP had declined the Loan Application
they were forced to immediately seek alternative finance. They also placed
the K Property on the market.
11. In early September 2006 the Applicants sold the K Property for $228,000
which they say was $22,000 less than its $250,000 market value. The
Applicants obtained alternative finance and were able to purchase the G
property in October 2006.
12. The FSP misled them by:
a. granting approval for the loan based on the Three Conditions and
subsequently declining the Loan Application despite these conditions
being met; and
b. declining the Loan Application on the basis that Mr H was not
registered for GST purposes when this requirement had not previously
been communicated to them as being a condition of loan approval.
13. They have suffered loss as a result of the FSP’s conduct comprising the
costs they incurred in failing to settle on time, the costs of obtaining a new
loan and other costs associated with the decision to decline shortly before
settlement.
Summary of FSP’s position
The FSP says that:
14. The Applicants ’ Loan Application was received on 14 July 2006 from FW. It
was FW that was the accredited originator and not Mr C. “Accordingly all
formal [FSP] communications and correspondence with regard to the loan
application were with [FW].”
15. The Loan Application contained a number of deficiencies including:
a. the loan annexure form was not provided (the Annexure);
b. an Applicants’ income declaration had not been provided;
c. the loan application was not complete; and
d. all required supporting documentation had not been provided.
Case No: 290757 Determination Page 3 of 12
16. On 14 July 2006, it sent a preliminary approval letter to the Applicants. A
second preliminary approval letter was sent on 20 July 2006. These letters:
a. contained the subject line “YOUR PRELIMINARY APPROVAL –
Application Number: [X]”
b. “...essentially acknowledged receipt of the loan application” ; and
c. state that “The applications do not undergo a full assessment prior to the
preliminary approval being issued, which is why additional requirements and
conditions may arise before formal approval is granted.”
17. The 14 and 20 July 2006 letters set out further conditions to which final loan
approval was subject being:
“satisfactory valuation of the security;
lender’s mortgage insurance (if applicable)
trustee approval;
complete verification of the information you will need to supply as per our
Standard Application Requirements;
full copy of signed purchase contract;
purchase price of [G Property] not to exceed $350,000; and
please note that this is not a letter of offer to make a loan, and a formal loan
agreement wi ll be issued if final approval is granted.”
18. An updated preliminary approval letter was issued on 10 August 2006
adding two specific further conditions being:
“ Applicants to comment on all CRAA enquiries for the past 6 months and also
all enquiries over $5,000 for the past 3 years; and
[the Annexure] to be provided.”
19. All three letters made it clear that final loan approval had not been granted.
20. The FSP did not have the ultimate power to determine the Loan Application.
It operated under a delegated lending authority from another financial
services provider, M. Due to the Loan Application being incomplete an
approval decision was not able to be made by M on the information
provided.
21. It sought further information from the Applicants from 10 August 2006. The
complete Loan Application, including the Annexure, was not provided to it
until 22 August 2006. This was only shortly prior to the G Property settlement
date on 28 August 2006. This left very little time for it to forward the
application to M for “review and determination” .
22. It forwarded the complete Loan Application including the Annexure to M on
22 August and advised that the Applicants required an urgent response.
23. On 23 August 2006 it informed the male Applicant of the need to provide the
PAYG income verification. In so doing, it did not decline the Loan Application
but, rather, requested further information from the Applicants. The Applicants
declined to provide the requested verification. It says that “ Without that
information the loan application could not proceed.”
Case No: 290757 Determination Page 4 of 12
24. The Applicants ’ decision to purchase the G Property at the 29 July 2006
auction was their decision. It did not at any time advise the Applicants that
final loan approval had been obtained. To the contrary, its letters all stated
that only preliminary approval had been given.
25. In assessing the Loan Application it followed its internal procedures
correctly. Ultimately it did not decline the Loan Application but, rather, the
Applicants effectively discontinued by not providing the income verification.
26. It did not mislead the Applicants in relation to final loan approval and did not
delay the approval process. Any delay was caused by the Applicants only
providing the complete Loan Application details on 22 August 2006, 12 days
after the 10 August request to do so.
27. It did not otherwise breach any obligations owed to the Applicants and is not
responsible for any loss that they may have suffered.
Issues
28. On 15 August 2013, my Case Manager issued a Recommendation in which
he concluded that:
a. The FSP did not mislead the Applicants in relation to whether final loan
approval had been given.
b. The FSP did not otherwise breach any obligations owed to the
Applicants relating to any delay in the loan approval process.
c. The Applicants have not substantiated any claim for compensation.
29. The FSP accepted the Recommendation.
30. The Applicants have not provided any new information but rejected the
Recommendation on 24 October 2013 on the basis that:
a. They complied with all the Three Conditions in the preliminary approval
letter of 14 July 2006 and provided all information that had been
requested to the FSP by 15 August 2006.
b. The Applicants did not receive the updated preliminary approval letters
of 20 July 2006 and 10 August 2006.
c. The pre-approval and the conditions were misleading as the Applicants
relied on the FSP’s advice that they could attend and bid at the auction
on 22 July 2013.
d. The loan was declined on the basis that one of the Applicants was not
registered for GST yet this was never raised with the Applicants even
though the FSP had been aware of this issue from 14 July 2006. The
Applicants say that there were internal issues between the FSP and the
trustee, M, that impacted the decision to decline the loan.
Case No: 290757 Determination Page 5 of 12
e. The valuer was aware from 15 July 2013 that the valuation did not
address the zoning of the property and it was valued subsequently with
no such issue.
f. The FSP did not inform the Applicants in a timely manner that the loan
was declined and waited until the day before settlement to tell them
this.
31. I will deal with the issues raised in the Applicants ’ rejection of the
Recommendation dated 24 October 2013 where they may give rise to an
award of compensation, but I do not propose to repeat the information in the
Recommendation on other matters.
32. The issues that I will now consider include:
Whether the Applicants were misled by the letter of 14 July 2006;
Whether the FSP’s conduct in relation to the assessment of the loan
gives rise to a right to compensation; and
Whether the Applicants suffered loss as a result of any misleading
conduct for which the FSP should compensate him
Reasons for decision
33. A timeline of the key events constructed from the information provided by
both parties is as follows:
13 July 2006 Loan Application for pre-approval submitted.
14 July 2006 All parties agree that pre-approval letter was issued
on this day.
19 July 2006 Valuations undertaken.
20 July 2006 Updated preliminary approval letter-receipt disputed
by the Applicants.
24 July 2006 FSP confirms to Mr C that the valuations are
acceptable.
29 July 2006 Auction and purchase of G Property with a 30 day
settlement.
4 August 2006 Contract of Sale provided to FSP.
10 August 2006 Updated preliminary approval letter. Receipt disputed
by the Applicants.
10 August 2006 FSP tells Mr C that file is with LMI for approval and
seeks outstanding information.
10 August 2006 FSP received a query from M about the valuation
which failed to deal with the zoning of the property:
valuation needs to be redone.
Case No: 290757 Determination Page 6 of 12
14 August 2006 Mr C provides CRAA documentation but Lo Doc
Annexure and income declaration remain outstanding.
15 August 2006 Income declaration provided.
18 August 2006 Email from FSP to Mr C requesting Lo Doc Annexure
form.
22 August 2006 FSP receives amended valuation: loan amount
needed to be reduced to remain within 95% LVR.
23 August 2006 Discussion between the FSP and Applicants about the
progress of the loan application: content of discussion
disputed.
28 August 2006 Settlement Due.
1 September 2006 FSP writes to Applicants and says application has
been declined.
16 October 2006 Applicants settled the purchase of G Property through
an alternative lender.
Did the FSP mislead the Applicants that the loan would definitely be
approved?
34. The parties agree that the FSP gave the Applicants a letter on 14 July 2006
in which it set out the basis on which a loan would be made available to the
Applicants. The Applicants deny having received the subsequent preliminary
approval letters of 20 July 2006 and 10 August 2006. I do not consider that
the subsequent letters are determinative of this dispute and base my views
on the content of the letter of 14 July 2006.
35. It is also agreed by both parties that the FSP knew that the Applicants
intended to bid at an auction as Mr C had included this information in the fax
that was sent to the FSP with the loan application in June 2006. The
preliminary loan approval was provided prior to the auction. The FSP does
not dispute that it was aware that the Applicants would bid at the auction and
had set a maximum amount of $320,000 for which the property could be
purchased.
36. The key issue in this dispute for my consideration is whether the terms of the
preliminary approval letter of 14 July 2006 were such that the FSP misled
the Applicants into thinking that the loan would definitely be approved within
the settlement period of 30 days.
37. The Applicants ’ position is tha t they understood that the loan would be
approved if they met the Three Conditions. It is not in dispute that the
Applicants met the Three Conditions. What is in dispute is whether the loan
approval was subject to additional conditions that needed to be satisfied.
Case No: 290757 Determination Page 7 of 12
38. The case manager considered that Mr C and/or the Applicants have
misinterpreted the 14 July 2006 letter by:
a. referring to it as an approval letter when, in fact, it was clearly stated to
be a preliminary approval; and
b. referring to there being “3 Outstanding Items”, being the Three
Conditions. This involved a mistaken belief that the Three Conditions
were the only conditions required to be satisfied in order to obtain final
approval. As discussed earlier, the letter clearly set out that final loan
approval was subject to additional conditions being met.
39. The case manager considered that the letter of 14 July 2010 clearly stated
that only preliminary approval had been provided. The FSP did not at any
stage during the process advise the Applicants that final approval had been
obtained. For reasons of their own the Applicants assumed that they had
done everything necessary to obtain final approval and on that basis entered
into the G Property contract of sale requiring an unconditional, 30 day
settlement. Ultimately, the case manager was not satisfied that the FSP
misled the Applicants in relation to whether final loan approval had been
given.
40. The Applicants have not provided any new information in response to this
aspect of the case manager’s Recommendation but h ave repeated their own
view of the dispute that they had met the Three Conditions that were
required for final approval.
41. I have reviewed the terms of the letter of 14 July 2006. The letter has the
following heading “Re: Your Preliminary Approval”. This shows that the
Three Conditions which the Applicants believed had to be satisfied were not
in fact the only conditions to be satisfied and upon which the loan would be
provided. The first paragraph of the letter of 14 July 2006 says that the loan
would be made available
“subject to payment of all application fees, satisfactory valuation of the
security if required, lender’s mortgage insurance if applicable, trustee
approval, complete verification of information you will need to supply as
per our Standard Application Requirements .” (my emphasis)
42. I agree with the case manager that the conditions of the pre-approval were
not limited to the Three Conditions which the Applicants believed needed to
be met. The conditions upon which the loan would be granted also included:
Lender’s Mortgage Insurance (if applicable)
Trustee Approval
Complete Verification of Information
The letter goes on to indicate that “Lenders mortgage insurance may be
required”.
43. These additional conditions were drafted widely and should in my view have
raised a flag to the Applicants and Mr C that the conditions would not
necessarily be automatically satisfied and there could be any number of
Case No: 290757 Determination Page 8 of 12
issues in relation to all three of these conditions. Whilst the Applicants had
completed a loan application form, there had not been any verification of the
information in the application form by the FSP prior to the auction. If LMI
approval was not given then additional funds would have to be found, and
there were no explicit grounds upon which the trustee may refuse to grant
approval.
44. It does not appear that there was any discussion between Mr C and the FSP
as to the likelihood of M refusing to consent to the loan. Whilst it is arguable
that these conditions should have been more prominent in the letter of 14
July 2006, I am satisfied that the FSP put the Applicants on notice of the
possibility that the trustee may not approve the loan by making the loan offer
conditional on the trustee’s approval. Having regard to the whole of the
letter it is my view that it is not misleading in the manner suggested by the
Applicants. The Applicants say that if the Three Conditions were satisfied,
the loan would be approved. In my view, the letter says that the other
requirements discussed above also need to be satisfied before the loan offer
became unconditional.
Is there any other basis upon which the FSP’s conduct has caused the
Applicants to suffer loss?
The Trust ee’s Approval
45. The Applicants have raised a number of issues about the relationship
between the FSP and M. They consider that there were internal reasons
concerning their relationship as to why M withheld approval.
46. The relationship between the FSP and the trustee is not relevant to the
dispute and is a matter for the FSP.
47. What is important is that the preliminary approval letter clearly stated that
trustee approval had to be obtained. The Applicants say that the FSP did
inform Mr C on 23 August 2006 (which is disputed by the FSP) that the
reasons that M declined the application were because of its concerns about
the GST position of the Applicants and its dissatisfaction with the valuation.
The FSP says it was in fact waiting for more information in relation to one of
the Applicant’s PAYG status. No reasons as to the decline were given in the
letter of 1 September 2006. The FSP did not have to inform the Applicants of
these reasons. The Trustee was entitled to decline to fund the loan on any
grounds that it wished.
Delay
48. The parties disagree as to what information was requested by the FSP and
when it was provided. The Applicants suggests that this issue led to a delay
in assessing the loan which in turn impacted their ability to obtain alternative
funding.
Case No: 290757 Determination Page 9 of 12
49. The Applicants say that:
a. the FSP delayed its request for further income verification from the
male Applicants until 23 August 2006;
b. this delay was unnecessary and inappropriate given that the FSP was
aware that the G Property settlement was to occur on 28 August 2006;
c. the FSP ought to have been aware that this would most likely place
them in breach of the G Property contract of sale due to not having
purchase moneys available; and
d. they supplied all requested information to the FSP in a timely manner.
50. The FSP says that:
a. any delay was caused by the Applicants ’ failure to supply information
on a timely basis;
b. the initial Loan Application was incomplete and that full materials,
including the signed Annexure, were not provided to it until 22 August
2006; and
c. it made several requests of the Applicants to supply the missing
information in order that the application could be progressed to a
decision.
51. The case manager considered at length in the Recommendation whether the
information that was requested was provided in a timely manner.
52. The case manager considered that the materials show that:
a. the FSP’s document entitled “Product Ranges” lists Step 4 of the loan
process as requiring the borrower to complete the Loan Application
Form and Annexure;
b. the FSP made several requests for further information including:
the chronology entry dated 10 August 2006 recording that the
FSP contacted the broker (WG), and left a message as follows:
“For loan to be submitted we still need 1) Max Loan Annexure
Form and 2) Applicants need to comment on all CRAA enquiries
in the past six months and all enquiries greater than $5k in the
last three years for both individuals and business.” ; and
a repeated request for this information in an email dated 14 August
2006 at 8.06am from the FSP’s AC to Mr C. This email also
referred to the loan needing to be submitted to M;
Case No: 290757 Determination Page 10 of 12
c. a facsimile dated 14 August 2006 from Mr C to AC of the FSP encloses
handwritten notations to the various CRAA entries in response to the
FSP’s request for an explanation of each credit entry;
d. a facsimile dated 15 August 2006 from Mr C to AC of the FSP attaches
an Applicants’ income declaration sheet; and
e. a facsimile date stamped 11 August 2006 at 2:28pm appears to show
that a pre filled Annexure was sent by Mr C to the Applicants for their
signatures. The Applicants ’ signature spaces are blank but are pre
dated 11 August 2006.
53. Although the Loan Application was submitted on 13 July 2006 the Applicants
acknowledge that:
a. the signed Annexure was not provided until 11 August 2006; and
b. the female Applicant’s income declaration was not provided until 15
August 2006.
54. The file materials do not contain any letter or email returning the signed
Annexure to the FSP. Whilst the FSP accepts that the completed Annexure
was returned on 22 August 2006, the Applicants say that it was returned on
11 August. Importantly, the materials do not show whether it was returned to
the FSP or only to Mr C.
55. The case manager was unable to determine precisely when the Annexure
was returned to the FSP but concluded that this was done only in the later
stage of the process.
56. No information has been provided in response to the Recommendation which
clarifies this issue any further. Whilst there is a discrepancy in relation to when
all the information was provided, I do not consider this date is determinative
as the FSP was in any event still waiting for the updated valuation during this
period of time.
57. Once it had received the updated valuation on 22 August 2006 and M had
assessed it, there was a further conversation between the FSP and Mr C the
next day on 23 August 2006. The content of this conversation is disputed but
even if the Applicants ’ information was pro vided by 15 August 2013 I consider
that the FSP would have waited for the updated valuation which it received on
22 August 2013 in any event. The date that the Applicants provided their
information was not therefore the sole reason why the FSP could not progress
the application until 22 August 2013. I therefore accept that the FSP did not
delay unreasonably in assessing the application.
58. The content of the conversation on 23 August 2013 is disputed. The
Applicants say that they were informed through Mr C that the loan had been
declined on the basis that one of the Applicants was not registered for GST.
However the FSP says that it had requested further information which was
Case No: 290757 Determination Page 11 of 12
never provided and that this is the reason why the loan did not progress. This
is strongly disputed by the Applicants.
59. Over six years has passed since the conversation of 23 August 2006 took
place and there are no contemporaneous notes of what was said nor any
written request for further information. There is however an entry in the
chronology relied upon by the Applicants dated March 2007 that records that
Mr C received a telephone call telling him that the loan had been declined. Mr
C is very clear in his recollection that they were informed on 23 August 2006
that the loan was declined. The FSP did not decline the loan formally until 1
September 2006 which was three days after the settlement date. Whilst the
FSP says that it only wrote the letter at the Applicants ’ request it should be
treated as a formal letter of decline.
60. If the FSP had not declined the loan on 23 August 2006 but was waiting for
more information it would be expected that it would have followed this up prior
to settlement. In my view, there was confusion between the parties at this late
stage in the process as to what information, if anything further, was required
to progress the application. I consider that this confusion is likely to have
occurred considering the FSP and M were dealing with Mr C, FW and the
Applicants. Even if there was information outstanding it seems that the issues
of the valuation was still to be overcome and I cannot be satisfied that final
approval would have been given in any event. Ultimately no final letter of
approval was issued and the loan was formally declined after the settlement
date of 28 August 2006.
61. The question is whether this confusion at this late stage caused the Applicants
to suffer a loss. By their own acknowledgement, they proceeded from 23
August 2006 on the basis that the loan was declined and they sought an
extension to the settlement date and took other steps to mitigate their loss and
protect their financial position.
62. The FSP was under no obligation to approve the loan where the conditions
had not been met. Trustee Approval had not been granted. Whilst the decision
to decline the loan meant that the Applicants had to obtain alternative funding
from a third party, this was always a possibility under the terms of the
preliminary loan approval which was conditional on a number of factors as
discussed above.
63. I accept that the period between 23 August 2013 and the ultimate date of
settlement on 16 October 2013 would have been a stressful time for the
Applicants. I do not accept that the FSP is liable for the costs that the
Applicants have claimed. Unfortunately for the Applicants, the FSP had stated
in the terms of the preliminary approval that the offer was subject to a number
of conditions that ultimately were not satisfied and a final letter of offer was
never provided. It was up to the Applicants and their advisers to ensure they
understood the terms of the pre-approval. The FSP is not responsible for the
financial decisions that the Applicants made once the loan was ultimately
declined.
Case No: 290757 Determination Page 12 of 12
Conclusion
64. The pre-approval letter of 14 July 2006 stated that there were additional
conditions beyond the Three Conditions relied upon by the Applicants.
These additional conditions were of great significance which should not have
been ignored by the Applicants and should have been taken into account
when deciding whether to bid at the auction and in agreeing to a short
settlement date.
65. The FSP had expressly stated that the loan would be granted subject to the
Trustee ’ s Approval. This was unfortunately not provided.
66. The FSP did not delay unreasonably in assessing the loan.
Determination
67. On the basis of the available information, I determine that the FSP did not
mislead the Applicants that the loan would definitely be approved; and
68. The Applicants are not entitled to receive any compensation.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.