Denial of flood claim and cancellation of home insurance policy

FirmFinancial Firm (Unknown - Insurer)
Decided2013-04-04
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The insurer denied a Fernvale home claim as flood damage and cancelled the policy for 2010-11. AFCA accepted that the flood exclusion was clearly disclosed but found the initial inundation was stormwater runoff, so it ordered cash settlement to 20cm above floor level with interest, voided the cancellation and rejected the bad faith complaint.

The flood exclusion was clearly communicated under section 35(2) of the Insurance Contracts Act, but stormwater damage before floodwaters arrived is not excluded, and the cancellation had no section 60 ground or notice so was void under section 63.

Issues

Subjects and remedies

natural disastercorrect recordspay claimpay interestreinstate policy or contract

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 290660 Determination Page 1 of 13 Case number: 290660 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim (Flood) 18 March 2013 Background 1. The Applicant holds a home insurance policy with the Financial Services Provider (FSP) that covers her residential building and contents in Fernvale. The policy was incepted on 9 November 2006. The relevant period of insurance operated for twelve months beginning from 9 November 2011. During this period, the building was insured for a sum up to $222,834 and contents for $33,075. Claims were subject to a $300 excess. 2. On 15 January 2011, the Applicant lodged a claim due to damage sustained to her property resulting from severe weather events in Queensland. The following description was provided: “House was flooded 608mm rain and live near wivenhoe dam (sic). Wasn’t given any notification to evacuate or anything, has lost all contents. Had attempted to call on Wednesday and spoke to [LR] and was told to gut the house and take photos which has now been done, was advised to call back to lodge the claim.” 3. The FSP denied the claim on the basis it was due to “flood”. The Applicant, through her solicitors, has disputed this decision. For the sake of convenience, reference to the Applicant will include her solicitors. Summary of Applicant ’s position 4. The Applicant has provided a number of submissions on this dispute, which are briefly summarised as follows: a. The cause of the damage was storm, rainwater or runoff. In this regard, the Applicant relies upon her own recollection of events on the day as well as a previous FOS Determination, case number 239580. b. The FSP’s policy failed to clearly inform her that flood was excluded as required under Section 35 of the Insurance Contracts Act 1984 (the Act). c. The FSP, through its loss adjuster, breached its duty of utmost good faith by informing her that her claim would be denied prior to the FSP’s formal claim decision. Determination Case No: 290660 Determination Page 2 of 13 d. The FSP has inappropriately cancelled her policy effective from 12 January 2011. 5. The Applicant therefore seeks indemnity for her losses and compensation for the stress and inconvenience suffered by the loss adjuster’s comments. Summary of FSP’s position 6. The FSP relies on two site specific hydrology reports and the following policy provisions to substantiate its position: “ Words with special meanings … “flood” means the inundation of normally dry land by water that has escaped or been released from the normal confines of any natural watercourse, lake or lagoon whether or not altered or modified or of any reservoir, canal or dam. [Note: This policy does not cover loss, liability, injury or damage caused by or arising from flood to buildings and/or contents] … Insured events we will pay … 9. Storm, rainwater or run-off … We will not pay for loss or damage: a. caused by:  flood, or  flood water combined with run- off and/or rainwater’ “flood” means the inundation of normally dry land by water that has escaped or been released from the normal confines of any natural watercourse, lake or lagoon whether or not altered or modified or of any reservoir, canal or dam. … When we will not pay a claim under your policy … 2. Unless we state differently in your policy, we will not pay for: a. flood as defined on page 12.” 7. In response to the Applicant ’ s arguments, the FSP submits the following: a. The two hydrology reports do not corroborate that the property was inundated by stormwater runoff. b. Evidence from appropriately qualified individuals to corroborate that a policy was sent to the Applicant when she incepted the policy. c. The fact that as the loss adjuster’s comments were consistent with the claim decision, this cannot constitute a breach of the FSP’s duty of utmost good faith. Case No: 290660 Determination Page 3 of 13 Issues 8. Whether the FSP clearly informed the Applicant she was not covered for flood pursuant to Section 35 of the Act. 9. Whether the damage to the Applicant ’ s property was proximately caused by flood as defined in the policy. 10. Whether the FSP, through its loss adjuster, breached its duty of utmost good faith by informing the Applicant that her claim would be denied. 11. Whether the FSP inappropriately cancelled the policy. Reasons for decision 12. Due to the nature of the dispute, the matter has been referred to the Panel for Determination in line with the Operational Gu idelines to the Service’s Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 13. This decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in the insurance industry and a representative with extensive experience in consumer claims. 14. It is appropriate to consider the issues under the various headings. Section 35(2) of the Act 15. Section 35(2) of the Act states that when a claim is made under a “prescribed contract” for a “prescribed event”, an insurer cannot refuse to pay the claim unless it can establish that it clearly informed its insured in writing that it would not cover this event. Section 34 of the Act has defined the terms “prescribed contract” and “prescribed event” by referring to the Insurance Contracts Regulations 1985. 16. There is no dispute that contracts of insurance covering a person’s home and contents are “prescribed contracts” and damage due to flood is a “prescribed event”. 17. The onus is therefore on the FSP to establish that it has clearly informed the Applicant prior to the claim that it would not cover damage caused by “flood”. This is generally done by an insurer providing a copy of its policy to its insured which is meant to set out completely the rights and obligations of both parties under the insurance contract. 18. The Applicant submits she honestly does not remember receiving the policy document. The Panel considers this statement to be fairly equivocal. The FSP in contrast has provided evidence substantiating that a policy was dispatched to her last known address when the contract was originally incepted. Case No: 290660 Determination Page 4 of 13 19. Given this, the Panel accepts it is more probable than not, that the Applicant received this policy. In particular, given this would have been sent to her more than 5 years prior to the event and she has not disputed receiving any of the renewal offers, the Panel accepts that it is probable that she did receive the 2005 policy but has since forgotten. 20. Upon reviewing the policy, the Panel also accepts that a person of average intelligence and education, upon reading the policy, would have readily ascertained that they were not covered for flood given the following: a. It contains an index to relevant sections, such as insured events, general exclusions and “Words with special meanings”. b. In the section titled “Words with special meanings”, flood is a specifically defined term and contains a definition relatively consistent with the current definition in the Act. In addition, the definition states clearly, explicitly and in bold the following: “ [Note: This policy does not cover loss, liability, injury or damage caused by or arising from flood to buildings and/or contents] ” c. Flood is contained in the list of exclusions under the section titled “When we will not pay a claim under your policy”, which is where a person would expect to find limitations and exclusions to their cover. d. The flood exclusion is also prominently placed alongside the insured event of “Storm, rainwater or run -of f” given it is most likely to be associated with this event. 21. In addition, each renewal certificate (which the Applicant has not refuted receiving) contained the following words, alongside important information such as details of the property to be insured and the effective period of insurance: “Please note: Flood is not covered by this policy” 22. Accordingly, after taking all this into consideration, the Panel is satisfied the Applicant was clearly informed that she was not covered for flood in accordance with Section 35(2) of the Act. 23. As such, the FSP is entitled to rely on this exclusion provided it can establish it is applicable to the circumstances. Water Inundation The Evidence 24. The FSP has provided two site specific hydrology reports to substantiate its position. The first report was dated 21 March 2011 and contained the following of relevance:  The property is located on the western side of A Court, approximately 130m from the intersection of A Court and Poole Road. Ferny Gully flows in a north-easterly direction approximately 380m south-east of the Case No: 290660 Determination Page 5 of 13 property and drains to the Brisbane River about 1.6km to the east near Savages Crossing. Ferny Gully has a catchment area of approximately 16 square km to its confluence with the Brisbane River.  The property was inundated to a depth of approximately 1.4m above floor level. The sheds were inundated to a depth of approximately 1.5m. The floor level of the house is approximately 0.1m above the adjoining ground level. The floor levels of the house are similar to that of the shed.  The following information was obtained from the Applicant: - She was at work until approximately 4.00pm on 11 January 2011. - When arriving at the property at around 4.30pm, she observed water lying around from the rain, but no water had entered the house or sheds. - She returned to Fernvale at approximately 5 .00pm. - Her brother returned to the house early the next morning and observed water through the home. - She returned to the property at approximately 11.00am on 12 January. There was no water in the house at that time.  Recorded rainfall data was obtained from Savages Crossing Alert. The peak rainfall intensity of 122.1mm/hr (30.5mm in 15 minutes) occurred at 8.30am on 11 January 2011. Rainfall in the area had effectively ceased at 2.00pm that day.  Based on the observed depth of peak inundation, floodwater from the Brisbane River would have reached the ground level of the property at 8.30pm (11/01/11). 25. Based on the above, the hydrologist concluded as follows: “The house and sheds at the s ubject property were inundated above floor level by floodwater from the Brisbane River that broke out upstream of the property and flowed in a southerly direction past the property towards Ferny Gully. Floodwater from the Brisbane River would have also backed up along Ferny Gully.” 26. The hydrologist provided a supplementary report dated 26 April 2012 (the second site specific report). This was compiled in response to additional submissions and evidence provided by the Applicant. This report contained the following of relevance, which the Panel has broken down into the same sub-headings used by the hydrologist for ease of reference: Topography  Topographical data obtained from the Airborne Laser Survey shows the ground levels of the property range from approximately 41.5m AHD to 42.0m AHD. The easement located at the south-western boundary has a minimum ground level of approximately 41.0m AHD. Case No: 290660 Determination Page 6 of 13  Brisbane River can overflow its banks and drain in a southerly direction towards the property.  The stormwater catchment draining to the property is not large. The majority of stormwater runoff originating from the east is directed away by S Road and A Court. Given the size of the stormwater catchment draining to the property, it is expected stormwater runoff would occur within 1 hour of the peak rainfall intensity. Recorded Rainfall data  The Savages Crossing Alert station is located approximately 1.7km north-east of the property. This shows a very small amount of rainfall falling after 2.00pm on 11 January 2011.  The insured indicated she had to change her clothing due to the rainfall she was exposed to when visiting the property at 4.30pm on 11 January 2011. This could be explained by the fact there was some rainfall recorded after 2.00pm although it was of minimal intensity. Initial Inundation  If stormwater runoff had inundated the property, this would have occurred within an hour of the peak rainfall intensity. As the insured has maintained, the house was not inundated during her visit at 4.30pm, then stormwater runoff inundation could not have occurred.  During other site inspections, the hydrologist company obtained a statement from another resident on A Court. This resident was present at the property until 9.00pm on 11 January 2011. The resident recalled that while water inundated the yard at the property during the morning of 11 January 2011, the depth of water was not sufficient to inundate the residence. This residence has a similar floor level to the Applicant’s property. 27. Based on the above, the hydrologist concluded the following: “We remain of the opinion that the subject property was initially inundated above floor level by floodwater overflowing from the Brisbane River. Brisbane River floodwater would have initially arrived at the subject property by overflowing the river banks to the north of the property and flowing in a southerly direction towards the property. As water levels rose, floodwater would have also arrived at the subject property by backing up along Ferny Gully located to the south of the property. Given the characteristics of the local stormwater catchment and the relative timing of the peak rainfall intensity and initial inundation on 11 January 2011, stormwater runoff could not have inundated the subject property above floor level prior to the arrival of Brisbane River floodwaters. 28. The Applicant provided the following evidence to refute the FSP’s hydrology evidence: a. Rainwater runoff and build up are common occurrences on the property. This is due to the fact the property is located on a flat lying land below the foot of the hill, the area surrounding the property has no drainage and water often flows around the property to an easement. In Case No: 290660 Determination Page 7 of 13 support of this, she has provided photographs of when water accumulated at the property on 10 October 2010 along with rainfall data obtained from the Bureau of Meteorology for that time. b. A statutory declaration from a neighbour at 52 P Road who states that between 18-20 inches of rain fell around the property on 11 January 2011. c. When she attended the property at 4.30pm, she observed that the water had pooled to a depth of approximately ankle height. She could not recall when entering the property whether the carpets were wet or dry. d. She observed heavy rain commencing after 2 .00pm. This is due to the fact that she had to change her clothes when visiting the property because they were wet from precipitation. e. Hydrology reports commissioned by the Insurance Council of Australia (ICA) corroborated the possibility that Fernvale residents could have been inundated by rainwater runoff. f. Previous FOS Determinations (235302 & 239580) accepted there was rainfall that fell after 2.00pm. In particular, Determination 239580 referred to a property located near the Applicant’s residence and at paragraph 43, the Panel made the following conclusions regarding rainfall events observed that day: “The Panel notes the inconsistencies between the FSP’s hydrology and information provided by the Applicants. In particular the Panel notes the inconsistencies in the rainfall data provided. It is apparent from local residents that the rainfall recorded in the area was significant. It is also apparent from the local information that the rainfall did not cease as claimed in the hydrology report but continued. The Applicants maintain that rainfall within the Fernvale area continued throughout the afternoon and early evening. The weight of information provided supports the Applicants’ claim that it rained heavily later that afternoon and on the evening of 11 January 2011. The information provided by residents of the area together with photographs…… support this view.” g. She disagrees with the hydrologist’s evidence that stormwater is directed away from the property, as the surrounding land slopes towards her property and her property is situated on a flat area at the bottom of a hill where there are no gutters to direct the water. h. She disagrees with the hydrologist’s evidence that stormwater runoff would occur within 1 hour of peak rainfall intensity as water flow takes time to feed down the mountain and hills to wards her property. i. In regards to the hydrologist’s reference to a resident’s evidence on A Court, she notes there was only one person who returned or remained after the inundation event. He did not discuss his inundation with the FSP and further, his property is approximately 2 feet higher than the Applicant’s. Case No: 290660 Determination Page 8 of 13 Consideration of the Evidence 29. There are clearly some discrepancies in the evidence. In particular, the Panel considers that one of the substantive issues in dispute is whether there was heavy rain experienced in the area after 2.00pm on 11 January 2011. This is based on the fact that the hydrologist accepted there was minimal rainfall after 2.00pm on 11 January 2011 based on data obtained from Savages Crossing alert. 30. The Applicant’s evidence regardi ng the rainfall after 2.00pm is minimal. In her submission to the FSP dated 29 March 2012, she stated that: “… she observed that heavy rain recommenced at or around 2pm. Our client also advises that at approximately 4:30pm she had changed her clothes becau se they were wet from precipitation.” 31. Despite this, the Panel is aware based on previous site visits to the area that there was heavy rainfall that fell after 2 .00pm. In particular, local residents have provided eyewitness evidence of heavy rainfall occurring after 2.00pm and continuous rainfall occurring throughout the afternoon and early evening. 32. This was corroborated by the finding made in the previous Determination referred to by the Applicant. In addition, the FSP is aware of the Panel’s position in this regard as it was specifically referred to in two previous Determinations involving nearby residents where the FSP was a party to the dispute. 33. Given this, the Panel therefore considers the hydrologist’s evidence to contain a number of gaps. In addition, the hydrologist’s reasoning as to why she concluded the property could not have been initially inundated by stormwater runoff is not persuasive on a number of grounds. 34. A significant basis is due to the fact her evidence in this regard is substantively contingent on concluding that stormwater inundation could only have occurred within one hour of the peak rainfall intensity. She based this on the rainfall recorded at Savages Crossing and her analysis of the local topography and catchment area. 35. However, this conclusion appears inconsistent with the Applicant’s evidence that she observed ankle deep water in the yard at 4.30pm on 11 January 2011. 36. In this regard, the Panel refers to the fact the property’s floor level is approximately 0.1m above the ground level according to the hydrologist. Accordingly, ankle deep water would arguably be at the verge of inundating the property, which would have occurred 8 hours after the most intense period of rainfall. 37. Further, as the hydrologist concluded that floodwaters did not reach the floor level of the property until 8.30pm on 11 January 2011 and the level of the Brisbane River was 5m below at 4.30pm compared to the level measured at Case No: 290660 Determination Page 9 of 13 8.30pm (according to the Savages Crossing Alert), it is reasonable to conclude that the water observed by the Applicant was stormwater runoff that had pooled or accumulated at the property. 38. Given this, the Panel therefore considers there is a material inconsistency between the Applicant’s eyewitness evidence, which is not refuted, and the hyd rologist’s reasoning behind her conclusion that the property was not initially inundated by stormwater runoff. Namely, the Panel cannot reconcile the fact that if the peak level of stormwater inundation would have occurred on or before 9.30am, then it is unclear how the property avoided being inundated at that time yet manage to accumulate sufficient stormwater runoff to almost inundate the home eight hours later. 39. Although the Applicant has now stated that she cannot recall whether the carpets were wet during her visit, her previous evidence made no reference to observing or noticing any water in the property. The Panel considers it unlikely the Applicant would not have noticed water in the property, particularly given the events at that time. Accordingly, given her previous evidence made no reference to this and there is nothing to corroborate the fact the property was inundated prior to her visit, the Panel finds the house was not initially inundated until sometime after her visit. 40. Given this, it therefore appears that the peak level of stormwater runoff occurred at approximately 4.30pm given the property was on the verge of being inundated and the home had not been inundated prior to this. As stipulated previously, this is inconsistent with the hydrologist ’s findings about the drainage characteristics of the catchment affecting the property. 41. Instead, the fact this peak level was evident 8 hours after the peak period of rainfall indicates that the property had a tendency to accumulate and pool stormwater run off. This is consistent with the Applicant’s evidence. In addition, it appears this phenomenon was not properly accounted for by the hydrologist in her assessment of the drainage characteristics, which leaves a significant gap in her evidence on this salient point. 42. Furthermore, it is clear the hydrologist has not accounted for the eyewitness evidence that stated heavy rainfall did occur after 2 .00pm and there was continual rainfall experienced in the area in the afternoon and early evening. Although her supplementary report referred to a statement her company received from a resident on A Court, the report was silent as to whether this witness accepted or refuted the fact there was continual rainfall affecting the area after 2.00pm on 11 January 2011. 43. In pa rticular, the hydrologist’s reference to this witness’s evidence contains a number of gaps and anomalies that were not addressed. For instance:  This witness allegedly remained at his property until 9.00pm and recalled the fact that his home was not inundated until after 6.00pm. As he was at home, it is reasonable to conclude he could have estimated the time of initial inundation with more precision yet the report was silent on this. Case No: 290660 Determination Page 10 of 13  Given this witness referred to the property not being inundated until after 6.00pm, the Panel accepts it is open to infer that the estimated time of inundation was shortly after this. Accordingly, even if the Panel was to accept the inundation occurred up to an hour later, this is still inconsistent with the hydrologist’s conclu sion that floodwater did not reach the floor level of the Applicant’s property until approximately 8.30pm given both properties had allegedly similar floor levels and were proximate to each other. 44. In the Panel’s opinion, when considering all of the availab le evidence, the gaps in the hydrologist’s evidence regarding whether the property was inundated by stormwater runoff are fundamental. Further, the Panel considers there is a reasonable basis to conclude that the property was initially inundated by stormwater runoff prior to the arrival of floodwaters given the following:  The property was on the verge of being inundated when the Applicant visited the property at 4.30pm.  According to the hydrologist, floodwaters did not reach the property until 8.30 pm. The re is nothing to refute this aspect of the hydrologist’s evidence.  There was continual rainfall affecting the area during and after the Applicant’s visit. 45. Accordingly, after carefully reviewing all of the evidence, the Panel accepts that on the balance of probabilities, the property was initially inundated by stormwater runoff. 46. However the Panel accepts that at some stage, floodwater also inundated the property. This latter is substantively based on the fact that the peak level of inundation, being 1.4m above floor level, is difficult to associate solely with stormwater runoff, particularly given this peak level of inundation is consistent with the measured levels of the Brisbane River at Savages Crossing and corroborated by the hydrologist’s findings. 47. There is clear legal principles stating that any damage caused by floodwater or a combination of floodwater and stormwater runoff is not covered. Accordingly, the Applicant’s claimable loss is limited to the damage solely attributable to the initial stormwater runoff inundation. 48. There is minimal evidence in this regard. For instance, the hydrologist’s evidence does not assist and there is no eyewitness evidence to clarify to what extent stormwater runoff inundated the property. In addition, given the nature of this dispute and the timeframe that has elapsed, the Panel considers it is unlikely this information could be obtained. 49. Under paragraph 8.2 of the Terms of Reference, the Panel is empowered to decide disputes based on what is fair in all the circumstances after having regard to legal principles, good insurance practice and prior decisions. Given the fact the Panel has accepted that the property would have been Case No: 290660 Determination Page 11 of 13 inundated solely by stormwater runoff at some stage between 5 .00pm and 8.30pm, there was continual rainfall in the area and floodwater inundation would have been significant when they ultimately reached the property, the Panel estimates the level of inundation, for the purposes of resolving this dispute, to be 0.2m above floor level prior to the arri val of floodwaters. 50. As a result, the Panel directs the FSP to arrange for the Applicant’s property to be assessed and an assessment reached as to the extent of damage caused by stormwater runoff up to a height of 20cms above floor level. This includes the home and the sheds given the floor level of the sheds and the home are similar. The Panel urges the parties to work co -operatively together to reach an agreed settlement figure with respect to this. Breach of utmost good faith 51. The Applicant has substantive ly based this allegation on the FSP’s loss adjuster informing her of the likelihood of the claim being denied on the basis of flood. In particular, the Applicant has submitted this was a breach of the FSP’s duty of utmost good faith based on the following:  It is not professional or compassionate conduct as it cannot be said to be honest and fair for the loss adjuster to pre- empt the FSP’s decision.  It was a clear denial of the Applicant’s right to procedural fairness and natural justice as it deprived her of the opportunity to fully understand the reasons of the rejection.  She suffered significant physical, emotional and psychological damage.  It led her to obtain a private loan in order to fund alternative accommodation and begin repairs. 52. The Panel considers the Applicant’s submissions in this regard to be unfounded. The loss adjuster’s information about the likely claim decision was clearly correct. Accordingly, it is unclear how the Applicant could be said to have suffered further detriment by being armed with the likely outcome of her claim that was forthcoming two months after the claim was lodged. Furthermore, it is unclear how this could be characterised as dishonest, unprofessional or lacking in compassion when the information was based on the loss adjuster’s honest opinion and was ultimately endorsed by the claim decision. 53. In regards to denial of procedural fairness and natural justice, this is also unfounded. There is nothing to indicate that the assessor’s communication was an attempt by the FSP to avoid its obligation to provide a properly expressed claim decision or to make available its internal dispute resolution procedures. Indeed, it is evident that this was readily available to the Applicant and accessed by her through her solicitors. 54. Although the Panel accepts that assessors previewing a likely claim decision can be fraught with perils, particularly given they are not normally vested with such authority and can potentially be incorrect, it is also fairly common Case No: 290660 Determination Page 12 of 13 for this information to be sought by an insured. As a result, although the Panel understands why an assessor would attempt to communicate a likely claim outcome when it is evident, based on their experience, it would be prudent in most circumstances for them to refrain from doing so. 55. However, this does not infer than an assessor who does choose to do so automatically breaches the FSP’s duty of utmost good faith or the General Insurance Code of Practice, particularly in circumstances when their comment is based on an honest opinion and is ultimately correct. 56. Accordingly, the Panel does not accept the loss adjuster’s conduct amount to the FSP breaching its duty of utmost good faith. Given this, the Panel is not prepared to award any compensation for non-financial loss in this regard. Cancellation of the policy 57. The Applicant has raised issue with the fact that her policy was cancelled as at 12 January 2011. In particular, she notes that she did not authorise the FSP to cancel the policy and the FSP had no grounds to do so o n its own motion. Furthermore, there is no evidence of the FSP providing a notice of cancellation. 58. The FSP has not provided a submission addressing this point. 59. Based on the available information, it appears the purported cancellation of the Applicant’s p olicy was void. The reason being is that there is no evidence that the Applicant sought to cancel the policy and there is no evident basis for the FSP being entitled to do so. 60. In relation to the latter, the Panel notes that an insurer only accrues a right of cancellation under a general insurance contract, pursuant to one of the grounds set out in Section 60 of the Act. However, no such grounds are evident in these circumstances. In addition, when exercising a right of cancellation, the insurer must provide notice of cancellation unless the cancellation is due to an insured’s failure to pay an instalment premium and the policy provides the insurer a method of cancellation compliant with Section 62 of the Act. However, according to the Applicant, premiums were still being deducted from her account at the time she discovered this cancellation in September 2011. Accordingly, it appears this ground was not applicable. 61. As such, the Panel accepts the FSP had no right to cancel the policy or if it did have such a right, it did not properly exercise that right given there is no notice of cancellation in compliance with Sections 59 and 77 of the Act. As a result, any purported cancellation of the policy is void pursuant to Section 63 of the Act. In addition, any refere nce to this cancellation on the Applicant’s insurance record should be expunged. Case No: 290660 Determination Page 13 of 13 Determination 62. On the basis of the available information the Panel determines that: a. The FSP is to cash settle the Applicant for agreed damage sustained to the property up to a height of 20cms. In this regard, the Panel refers the parties to paragraph 50 of this Determination. b. The FSP is to pay interest on any sum paid in accordance with the Act from 25 March 2011 (the date it initially denied the claim) to the date when payment is affected. c. The cancellation of the Applicant’s policy for the 2010 -11 period is void and of no effect. d. The FSP is to reverse and/or expunge any reference to the purported cancellation of the Applicant’s policy on both its systems and on any insurance records that can be accessed by other insurers. e. The FSP has not breached its duty of utmost good faith in its handling of this claim.