Text of the determination
Case No: 290630 Determination Page 1 of 12
Case number: 290630
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
29 July 2013
Background
1. The Applicant held a home building and contents policy with the Financial
Services Provider (FSP) which was current at the time of the loss.
2. The Applicant‟s home was damaged by a hail storm on 25 December 2011,
forcing the Applicant and his family to move into temporary accommodation.
The Applicant‟s house caught fire while it was vacant and sustained
significant further damage.
3. The Applicant lodged a claim for damage to the house and contents. The
FSP accepted liability and cash settled the contents portion of the claim. The
FSP arranged for a Scope of Works to be prepared and quotes obtained for
the repair of the building.
4. The Applicant complained that the Scope of Works obtained by the FSP was
inadequate. Following an internal review, the FSP agreed to accept a more
extensive Scope of Works prepared by the Applicant‟s architect . The FSP
sought updated quotes from its builders based on this Scope of Works
accepted the lowest quote (for $276,969). As the Applicant had advised the
FSP that he preferred to use his own builder, the FSP offered to cash settle
the Applicant for this amount.
5. The Applicant advised the FSP that he had obtained a quote from his own
builder (“R”) for $349,800 and therefore considered the FSP‟s offer
inadequate. The Applicant noted that both his builder (R) and his architect
(“AB”) had advised that mould had developed in the timber framework of the
house due to it being without a roof for a lengthy period of time, and
accordingly it would be necessary to completely demolish the house (other
than the concrete slab).
6. The FSP engaged a building consultant (“S”) who inspected the house and
reported that, in his opinion, the existing framework could be repaired and
therefore demolition was not required. S also provided a revised Scope of
Works , following review of which the FSP‟s builder (“BB”) increased its quote
for the repairs to $314,441.60.
Determination
Case No: 290630 Determination Page 2 of 12
7. The Applicant remains dissatisfied with the FSP‟s offer, as he considers that
the amount offered is not sufficient to restore the house to its pre -loss
condition.
8. The Applicant is also dissatisfied with the amount offered by the FSP for
temporary accommodation expenses. In addition, he seeks reimbursement
for certain other expenses incurred in connection with his claim.
Summary of Applicant’s position
9. The Applicant has been assisted by his architect in relation to this dispute.
For clarity and brevity, submissions made by the Applicant‟s architect will be
treated as having been made by the Applicant for the purposes of this
Determination.
10. The Applicant says that the initial Scope of Works provided by the FSP‟s
assessor was too vague to allow an accurate quotation to be obtained.
Accordingly, he had to engage his own architect and spend significant time
and effort negotiating with the FSP to arrive at an appropriate Scope of
Works.
11. The Applicant seeks an appropriate cash settlement so that he can restore
the house to the condition it was in prior to the insured events. The
Applicant‟s architec t has estimated the cost of repairs to be $362,177.77,
and has provided an itemised breakdown showing the differences between
his estimate and the quote prepared by the FSP‟s builder.
12. The Applicant says that the house has been exposed to the elements for a
long time as a result of the FSP‟s delays and failure to prepare an adequate
Scope of Works. He says that this has resulted in further deterioration of the
house, including the growth of mould and the further decay of the timber
framework. The Applicant says that both his builder and his architect have
confirmed that this represents a potential health issue and therefore the
house (other than the concrete slab) should be demolished and rebuilt.
13. The Applicant seeks an additional amount of $31,100 in total for the costs of
temporary accommodation while the repairs are carried out, plus the costs of
hiring removalists and reconnecting essential services once the repairs are
completed.
14. The Applicant also seeks $2,750 in professional fees for the work carried out
by his architect to help him progress this dispute.
15. The Applicant says that the FSP‟s delay in finalising his claim has placed a
great deal of stress on his marriage and family.
Case No: 290630 Determination Page 3 of 12
Summary of FSP’s position
16. The FSP says that it has accepted liability for the claim and has offered the
Applicant a cash settlement for the cost of repairs to the house, given that he
prefers to use his own builder.
17. The FSP says that the quote prepared by its builder differs from the quotes
supplied by the Applicant, becaus e the Applicant‟s quotes are based on the
assumption that the property (other than the concrete slab) needs to be
demolished and rebuilt. However, the building consultant (S) engaged by the
FSP has confirmed that the damage to the timber framework can be repaired
and is not sufficiently extensive to warrant demolition. The FSP says that,
given S ‟s experience in dealing with claims for fire and water damage, his
opinion should be accepted.
18. In relation to the specific items which the Applicant has identified as being
excluded from the quote provided by the FSP‟s builder (BB), the FSP says
that:
the Applicant‟s quote includes an allowance for carpet, blinds and
curtains. However, these are classified as contents items under the
policy and are therefore covered by the cash settlement already paid to
the Applicant for the contents portion of the claim. Accordingly, these
items are not included in BB‟s quote; and
the “Supervision” section of BB‟s quote includes an amount for the cost
of plans and permits.
19. The FSP says that its settlement offer satisfies its obligations under the
policy. Further, as the FSP‟s builder has agreed to undertake the repair
works directly for the Applicant if required, the Applicant can be certain that
he will be able to have the repairs completed for the quoted amount.
20. The FSP says that the policy does not allow for temporary accommodation
for a period longer than 52 weeks. However, it acknowledges that the final
quotation from its builder (BB) was not received until 20 November 2012,
and that it will take approximately eight months to complete the work.
Accordingly, the FSP has offered to cover the Applicant‟s costs of temporary
accommodation for nine months from 20 November 2012 (including an
additional month to allow for weather delays).
21. The FSP relies on the following policy provisions:
“ What we cover as your contents
Your contents means your furniture, furnishings, unfixed electrical
goods, valuables, portable personal possessions, clothing and unfixed
household goods that you own.
Contents also includes:
carpet and rugs (fixed and unfixed)
internal blinds and curtains
Case No: 290630 Determination Page 4 of 12
…
How we settle your claim
We choose how your claim is settled
If we agree to pay a claim for loss, theft or damage to your home, contents or
landlord‟s fixtures and fittings, we will decide if we will:
repair damage new for old or
replace home or contents new for old or
pay you what it would cost us to repair or replace your home or
contents new for old.
The meaning of new for old is defined below.
We will not:
pay extra to replace your home, contents or landlord‟s fixtures and
fittings to a better standard, specification or quality than it was before
the loss or damage occurred except as stated in „new for old‟ below
fix a fault that existed before the loss or damage occurred.
New for old means:
new materials, new items
we replace or repair with new items or new materials that are available
at the time of replacement or repair from Australian suppliers.
new for old, regardless of age
we replace or repair new for old regardless of age, with no allowance for
depreciation ...
same type, standard and specification as when new
we replace or repair to the same type, standard and specification as
when new. If the same is not available, it means of a similar type,
standard and specification when new. It can be a different brand.
New for old does not:
include paying the extra cost of replacing or purchasing an extended
warranty on any home or contents item or
mean of a better standard, specification or quality than when new.
…
Home claims
How we settle home claims
If we agree to pay a claim for loss, theft or damage to your home, we will
decide if we will:
repair damage new for old or
rebuild your home new for old or
pay you what it would cost us to repair or rebuild your home new for old.
Case No: 290630 Determination Page 5 of 12
When we repair or rebuild your home
We will do our best to obtain new materials that are the same type, standard
and specification as when new. If the same is not available, we will use new
materials of a similar type, standard and specification that are commercially
available and compliant with the latest building regulations. ”
Issue
22. Whether the FSP‟s offer to cash settle the Applicant for $314,441.60
represents an appropriate settlement of the Applicant‟s claim for damage to
his house.
23. Whether the Applicant is entitled to compensation for his architect‟s fees for
assistance provided in pursuing this dispute.
24. Whether the Applicant is entitled to compensation for non-financial loss due
to the manner in which the FSP has handled his claim.
Reasons for decision
25. As advised to the parties, this matter has been expedited in accordance with
the Operational Guidelines to the Service‟s Terms of Reference due to the
complex nature of the issues to be considered. Accordingly, this dispute has
not been the subject of a Recommendation but has proceeded directly to
Determination.
26. I am satisfied that there has been an exchange of material between the
parties and that each party has had the opportunity to respond to the issues
raised therein.
Settlement offer
27. After extended negotiations between the parties during the claim process,
the FSP has made a final settlement offer, which has been rejected by the
Applicant. Having reviewed the materials, I consider the issues in dispute
between the parties in relation to the settlement offer are as follows:
the overall difference of approximately $47,000 between the cost of
repairs as quoted by the FSP‟s repairer (BB) and the Applicant‟s
architect (AB);
the treatment of the following specific items: carpet, curtains and blinds;
plans and permits; supply authority connection costs; removalist costs;
and
the date from which payment of temporary accommodation costs
should be made.
28. I will consider each of these issues in turn.
Case No: 290630 Determination Page 6 of 12
Repair costs
29. Under the terms of the policy, the FSP is entitled to decide whether to repair
the Applicant‟s house, rebuild the house or pay the Applicant the amount it
would cost the FSP to repair or rebuild the Applicant‟s house. As the
Applicant has expressed a preference to use his own builder, the FSP has
agreed to cash settle the Applicant for the repair costs.
30. The Applicant has disputed the FSP‟s proposed settlement amount on the
basis that it is not sufficient to restore his house to its pre-existing condition.
In particular, the Applicant argues that the house (other than the concrete
slab) requires complete demolition, due to the damage it has suffered in the
fire, which has been exacerbated by exposure to the elements over the
intervening 17 months, resulting in mould and decay of the timber
framework.
31. The Applicant has provided the following two estimates of the cost of
repairing the house:
a quotation for $349,800 prepared by his builder (R) on 16 September
2012; and
an estimate of $362,177.77 provided by his architect (AB) in May 2013.
32. Based on the available evidence, it appears that both estimates have been
prepared on the assumption that the house will require demolition (noting
that R‟s estimate was prepared at the same time the presence of mould was
initially reported). However, the reason for the difference of approximately
$12,000 between the two estimates is not apparent.
33. The FSP‟s estimate of $314,441.60 is based on a quotation provided by its
builder (BB) on 20 November 2012. In its Additional Response to the Service
dated 6 June 2013, the FSP agreed to increase this amount by an additional
$3,900 to include two items which the Applicant‟s architect had identified as
having been wrongly excluded from BB‟s quote. I note that the revised figure
of $315,156.60 referred to in the FSP‟s Additional Response appears
incorrect, as adding $3,900 to BB‟s quote of $314,331.60 would produce an
updated total of $318,341.60.
34. The FSP‟s estimate is based on a Scope of Works provided by its building
consultant (S) who inspected the property in October 2012. While S
observed evidence of mould and partial decay to the bottom plates of the
walls in the master and second bedroom, he considered that the house had
not been sufficiently damaged to warrant demolition of the entire building , as
the majority of the wall frames were still intact and struc turally sound or
repairable.
35. From the material provided to the Service, it is clear that arriving at an
agreed Scope of Works and obtaining quotes has been a lengthy and
tortuous process. In particular, I note that:
the initial Scope of Works prepared by the FSP excluded certain parts
of the house, based on the view of the FSP‟s assessor that these
Case No: 290630 Determination Page 7 of 12
sections had been constructed without the necessary planning
approvals. It was not until the FSP‟s inte rnal dispute resolution
department (“IDR”) reviewed the handling of the claim in July 2012 that
the FSP accepted that these parts of the house should be included in
the Scope of Works;
following the IDR decision, the FSP accepted the alternative Scope of
Works which had been prepared by the Applicant‟s architect (which in
turn was later superseded by the Scope of Works prepared by the
FSP‟s building consultant (S)); and
over the course of the claims process, the FSP‟s builder ( BB) has
provided a number of quotations for increasingly higher amounts, as
summarised below:
i. a quote for $187,603.62 in May 2012 (based on the initial,
restricted Scope of Works);
ii. a quote for $276,969 in August 2012 (based on the Scope of
Works prepared by t he Applicant‟s architect); and
iii. a quote for $314,441.60 in November 2012 (based on S‟s Scope
of Works), which has now effectively increased to $318,341,60
given the FSP‟s Additional Response dated 6 June 2013.
36. In my view, the available evidence casts some doubt on the ability of the
FSP‟s contractors to accurately estimate the cost of repairs to the Applicant‟s
house. I also consider that the credibility of the comments made by the
Applicant‟s architect (AB) is enhanced by the FSP‟s willingness to adopt the
Scope of Works he prepared in mid-2012, and to modify its estimates to
reflect various views expressed by him throughout the claims process.
37. However, I also note that under the terms of the policy, the FSP is not
required to cash settle the Applicant for a ny more than it would cost the FSP
to repair the house, even if this is less than the amount it would cost the
Applicant to complete the repairs. This reflects the fact that the FSP has
offered a cash settlement in lieu of undertaking the repairs itself, which it
could reasonably expect to be able to do on a discounted basis having
regard to its existing relationships with contractors.
38. The FSP has provided a copy of an email from BB confirming that it is
prepared to undertake the repair works for the Applicant directly if required,
which the FSP says ensures that the Applicant can have the house repaired
for the amount quoted. However, in the circumstances, I consider that it is
not unreasonable for the Applicant to prefer his own builder, given the
amount of time and effort he has expended to date in seeking to have the
FSP and its contractors agree on an acceptable Scope of Works and
seeking increases in the estimated cost of repairs.
39. The Applicant has provided documents prepared by his architect (AB) which
compare:
the Scope of Works prepared by S in November 2012 with the Scope of
Works previously prepare by AB; and
Case No: 290630 Determination Page 8 of 12
the itemised q uotation provided by BB with AB‟s own estimate for each
trade component of the repairs.
40. AB‟s comparison indicates that, in general, the difference between the total
overall estimates arises from the cumulative effect of minor differences in the
amounts for each line item, rather than the inclusion or exclusion of
particular items (other than those specifically considered later in this
Determination).
41. In relation to the need to demolish the building (other than the concrete
slab) , I acknowledge that the FSP‟s building contractor (S), who is
experienced in matters of this nature, has concluded that this is not required.
On the other hand, I note that:
in their initial reports prepared in June 2012, t he Applicant‟s builder and
architect did not indicate that demolition was required. It was only when
they reinspected the house in September 2012 (after it had been
without a roof for seven months) that they determined demolition was
necessary, due to ongoing mould and decay. In my view, this lends
support to their opinion;
the photographs taken by S in October 2012 confirm that the timber
framework of the house was beginning to mould and decay at that time;
an additional nine months have now passed since S‟s inspection in
October 2012, during which the house has continued to be exposed to
the elements;
in an email dated 17 December 2012, the FSP‟s builder ( BB) has noted
that, due to continued exposure, the property may continue to
deteriorate resulting in unforseen damage which would require a
variation of their estimate; and
to a significant degree, the delay in finalising the claim has arisen as a
result of the numerous revisions required to the Scope of Works and
the quotations prepared by the FSP‟s contractors, and the ti me taken to
effect these.
42. In light of the above, I consider that it is appropriate for the Applicant‟s house
(other than the concrete slab) to be demolished and rebuilt.
43. I note that the quotation of $349,8 00 prepared by the Applicant‟s builder (R)
in September 2012 was based on demolishing the house (other than the
concrete slab) prior to rebuilding . Further, the FSP‟s file notes indicate that,
when the Applicant‟s arc hitect (AB) challenged the BB quote of $314,441 .60
in November 2011, he did so on the basis that “a successful repair cannot be
completed for less than $350,000”.
44. While the Applicant has subsequently provided AB‟s higher estimate of
$362,177.70, no evidence has been provided to support the i ncrease over
R‟s quote of $349,8 00. Accordingly, I c onsider that R‟s quote of $349,8 00
should be used as the basis for the cash settlement amount.
Case No: 290630 Determination Page 9 of 12
45. I will now consider whether this amount should be adjusted in the light of the
issues raised by the parties in relation to specific items.
Carpet, curtains and blinds
46. The Applicant‟s architect (AB) queried the fact that amounts for carpet,
curtains and blinds were not included in S‟s Scope of Works (and therefore
BB‟s quote).
47. The policy clearly sets out that carpet, blinds and curtains are contents items
and therefore do not fall within the scope of the building cover. As the cash
settlement for the contents portion of the claim has been paid, the FSP
should not have any further liability for these amounts.
48. The works provided for in R‟s quote includ e carpet, blinds and curtains.
Accordingly, I consider that R‟s quote should be reduced by the amount
allowed for carpets, blinds and curtains, which R should be asked to confirm.
Plans
49. The comparison documents prepared by the Applicant‟s architect (AB)
indicate that his estimate included an amount of $7,500 for plans and
permits, in addition to an amount of $13,880 for “Supervision” (materials and
labour). AB has not provided any further detail as to how he arrived at the
estimate of $7,500.
50. AB commented that the quote prepared by the FSP‟s builder (BB) did not
include an amount for plans and permits. However, the FSP has
subsequently confirmed that the a mount of $14,330 for “Supervision”
(materials and labour) in BB‟s quote includes an allowance of $3,530 for
plans and permits.
51. It appears that R‟s quote for $349,800 does not include any allowance for
plans and permits. In the circumstances, I consider that it is appropriate to
adjust R‟s quote so as to include an amount of $5,000 for plans and permits.
Removalists
52. The scope of cover under the policy does not extend to costs incurred in
moving back into the repaired property. Accordingly, I consider that the FSP
is entitled to deny liability for these costs.
Supply connection costs
53. The reconnection of essential services was included in S‟s Scope of Works
and BB has confirmed that these were also included in its quote. However, it
is not clear whether such costs were in cluded in R‟s estimate of $349,8 00,
which I have determined should form the basis of the settlement amount.
Case No: 290630 Determination Page 10 of 12
54. If R‟s estimate does not include an amount for the costs of connecting
essential services, the cash settlement amount should be increased to
reflect this. The detailed cost estimate prepared by S includes a total of
$1,280 for these items, which I consider is appropriate.
Interest
55. I consider that the FSP should be required to pay interest on the total cash
settlement for repairs, in accordance with section 57 of the Insurance
Contracts Act 1984 (Cth). Interest should be calculated from 20 November
2012, being the date the FSP received BB‟s final quotation .
Temporary accommodation expenses
56. Under the policy, the payment of temporary accommodation expenses is
limited to 52 weeks and 10% of the sum insured. However, the FSP has
agreed to extend this in the circumstances, to pay for temporary
accommodation while the dispute is resolved.
57. The FSP says it will also provide cover for tempora ry accommodation costs
of $21,600 for the nine month period required to complete the repairs, but
argues that this should be backdated to 20 November 2012, when BB
provided its updated quotation for $314,441.60.
58. Given my finding that R‟s estimate (and not BB‟s estimate) should be used
as the basis for the settlement amount, it follows that the Applicant was
justified in disputing the FSP‟s settlement offer. Additionally, a significant
portion of the delay in processing his claim was attributable to the actions of
the FSP and its contractors. Accordingly, I consider that the Applicant should
be entitled to the benefit of temporary accommodation for the period during
which the repairs are carried out.
Compensation for non-financial loss
59. Under paragraph 9.3(b) of the Service‟s Terms of Reference, compensation
for non-financial loss may be awarded where there has been an unusual
degree or extent of physical inconvenience, time taken to resolve the
situation or interference with an insured‟s expectation of enjoym ent or peace
of mind.
60. As set out above, there have been significant delays in the processing of the
Applicant‟s claim and it is now over 18 months since the fire which severely
damaged his house. The Applicant says that this has had a significant effect
on his marriage and his family, to the extent that his children have required
counselling to cope with the ordeal.
61. I accept that not all of the delays in processing the Applicant‟s claim were
solely attributable to the actions of the FSP. However, having reviewed the
FSP‟s file notes setting out the chronology of the claim, I consider that the
FSP and its contractors were responsible for a significant portion of the
Case No: 290630 Determination Page 11 of 12
delays because of, among other things, the need to review the Scope of
Works and obtain updated quotations on a number of occasions. These
delays could have been avoided if the Scope of Works had been prepared
properly in the beginning. Even after the Applicant‟s initial claim regarding
the Scope of Works was upheld following IDR review, there were further
delays in obtaining updated quotations.
62. Given the extensive nature of the damage and the fact that the Applicant and
his family were forced out of their home for an extended period of time, it
was incumbent on the FSP to process their claim within a reasonable
timeframe. Having regard to all of the available evidence, I do not believe
that the FSP has done so. Further, the Applicant has been required to spend
a significant amount of time and effort, and engage his own consultants, in
an attempt to resolve the claim.
63. For the reasons outlined above, I consider that the FSP should be required
to pay the Applicant $2,000 as compensation for non-financial loss.
Costs in pursuing the matter
64. Under section 9.4 of the Service‟s Terms of Reference, a Financial Services
Provider can be required to contribute to professional costs incurred by an
Applicant in the course of progressing their dispute.
65. The Applicant has provided a copy of an invoice from his architect (AB) for
fees of $2,750 relating to attending the site inspection carried out by S,
reviewing S‟s Scope of Works and BB‟s quotes and discussing the
Applicant‟s dispute with the Service . While I am satisfied that the work
undertaken by AB in reviewing and commenting on the quotation prepared
by BB was necessary for the purpose of the dispute, I do not accept that the
Applicant required the services of AB to communicate with the Service on his
behalf. Accordingly, I consider that it is reasonable to require the FSP to pay
the Applicant an amount equal to 80 % of AB‟s invoice, being $ 2,200.
Determination
66. On the basis of the available information, I determine that the FSP is
required to pay to the Applicant:
in addition to the amount of $314,441.60 quoted by BB, an additional
amount of $35,048.40, adjusted as follows:
i. reduced by the amount (if any) allowed in R‟s qu otation for
$349,800 for carpets, curtains and blinds (to be confirmed by R);
ii. increased by $5,000 for the cost of plans and permits; and
iii. increased by $1,280 if R‟s quotation for $349,8 00 did not include
an allowance for the cost of connecting essential services (to be
confirmed by R);
Case No: 290630 Determination Page 12 of 12
interest on the total cash settlement for repairs calculated from 20
November 2012 (being the date the FSP received BB‟s final quotation)
to the date of settlement, in accordance with section 57 of the
Insurance Contracts Act 1984 (Cth);
the amount of $21,600 for temporary accommodation costs;
the amount of $2,000 as compensation for non-financial loss; and
the amount of $2,200 as partial contribution towards the fees payable
to the Applicant‟s architect for services provided in the course of this
dispute.