Failure to respond to financial difficulty requests and resulting loss of equity on sale

FirmFinancial Firm (Unknown - Credit)
Decided2014-01-02
ProductCredit · Business lending
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$1,000
Amount claimed$500,000
SourceAFCA PDF

Summary

Applicants in financial difficulty claimed $500,000 for lost equity after a forced sale of their home. AFCA found the FSP did not genuinely consider their requests from 14 May to 28 June 2012, but found no financial loss and awarded $500 each for non-financial loss.

Code of Banking Practice cl 25.2 requires genuine consideration of hardship requests, while financial loss requires causation and non-financial loss awards are limited to unusual cases.

Issues

Subjects and remedies

financial hardshippay non financial loss

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Case No: 289307 Determination Page 1 of 7 Case number: 289307 Credit - Consumer Credit - Home Loans - Financial Difficulty - FSP failure to respond to request for assistance 4 December 2013 Summary Description This dispute concerns a claim by the Applicants that they suffered a loss of equity following the sale of their property as a result of the Financial Services Provider (FSP) failing to meet its obligations to assist them duri ng the time of their financial difficulty. Basis for Determination The FSP did not fully meet its obligations to the Applicants throughout the whole time of their financial difficulty, in particular from 14 May 2012 to 28 June 2012. Determination The FSP should pay the Applicants the sum of $500.00 each as compensation for non financial loss. No further award of compensation is payable . Background 1. As advised to the parties, the Financial Ombudsman Service (FOS) has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This dispute has not been the subject of a Recommendation and has proceeded directly to a Determination. 2. This dispute concerns the financial difficulty the Applicants, Mr & Mrs P, experienced in relation to paying their three loan facilities with the Financial Services Provider (FSP) during 2011 and 2012. These facilities consisted of two home loans, initially approved in February 2009 and March 2009 for $3,953,000 and $350,000, and a line of credit (overdraft) with an initial limit of $50,000. The overdraft limit was increased in March 2011 to $75,000 and again in December 2011 to $210,000. These facilities were secured by mortgage over the Applicants ’ home, for which the title was in M rs P’s name only. 3. The loan facilities were paid out in full when the Applicants sold their home, which sale settled on 30 November 2012. The Applicants seek $500,000 for Determination Case No: 289307 Determination Page 2 of 7 the loss of equity they say they have suffered as a result of the FSP’s failure to assist them. 4. This dispute is about:  Whether the FSP met its obligations to assist the Applicants in relation to their financial difficulty during 2011 and 2012.  Whether the Applicants are entitled to any compensation. Reasons for decision Financial Difficulty 5. I consider that under section 25.2 of the Code of Banking Practice, an FSP has an obligation to genuinely consider a customer’s request for assistance, where the customer is in financial difficulty. 6. I also expect customers to be willing to work with their FSP, and to propose a realistic repayment plan that will result in their repayment of the debt within a reasonable time frame. 7. Most of the contact between the Applicants and the FSP during the period of the Applicants’ financial difficulty was by email. I have reviewed this email correspondence and I have summarised below a history of key events. History of key events 8. From February 2011 to November 2011, Mr P made several requests to the FSP to allow him to draw down funds in excess of the overdraft ’s formal limit. This was to assist him in managing cash flow delays, which mainly related to the timing of salary bonus payments due to him. 9. The FSP responded by approving several temporary draw downs in excess of the overdraft’s limit which Mr P re paid. The FSP also granted an increase of $25,000 to the overdraft’s limit in March 2011 . 10. In November 2011, Mr P requested the FSP further increase the overdraft ’s limit to assist him in managing his cash flows. Mr P said while he expected his bonuses to be reduced, he also expected to receive payments totalling $775,000 from various private business interests, over the next few months. 11. The Applicants completed a Statement of Financial Position and submitted an FSP application form to allow an increase of $135,000 to the overdraft’s formal limit. 12. On 20 December 2011, the FSP emailed Mr P to say that it had approved a short term increase of the overdraft’s limit to $210,000, until 28 February 2012, but this approval was subject to certain conditions. These conditions included: Case No: 289307 Determination Page 3 of 7  No additional funding would be considered.  A $275,000 fee due to Mr P from his private business interests was to be immediately directed to reduce the debt.  If the $275,000 fee was not received by 28 February 2012, the Applicants would place their residential property on the market and set an auction date for no later than mid April 2012. 13. On 21 December 2011, the Applicants signed a n FSP credit contract which provided for the overdraft ’s limit to be increased to $210,000. 14. In early February 2012, the FSP notified Mr P that the new overdraft’s limit had been exceeded by $26,000, and asked Mr P to correct the situation. 15. By the 28 February 2012 due date, Mr P had not cleared the excess and also failed to pay the $275,000 fee to the FSP. 16. On 12 March 2012, Mr P was made redundant from his full time employment position, although he did not notify the FSP of his change of circumstances until 14 May 2012. 17. During late February and March 2012, Mr P sent several emails to the FSP saying the followi ng.  The Applicants had engaged real estate agents to put their property on the market.  Mr P was expecting to receive the $275,000 fee shortly.  Mr P was due to receive approximately $180,000 in deferred equity and bonuses from his employer.  Mr P was still working on other private business interests which would generate significant income.  Mr P’s strategies would take time to implement.  Mr P intended in the meanwhile, to apply for an early release of $200,000 of his personal superannuation funds, for which he requested a letter in support from the FSP. 18. The FSP responded in April 2012 by saying it intended to commence enforcement action for recovery of the amounts relating to all loan facilities. 19. On 20 April 2012, the FSP issued Default notices for the loan facilities. 20. On 14 May 2012, Mr P emailed the FSP notifying it of his change of circumstances. He said he was looking for full time employment, he was pursuing various business interests to generate income, and he wanted the FSP to add his name to the security property’s title so that he could apply for early release of his personal superannuation funds. He also asked the FSP Case No: 289307 Determination Page 4 of 7 to consider granting an extension to the time to pay, or a restructure of repayments. 21. I have not been provided with any information to show that the FSP responded to Mr P’s request, other than providing a letter to the Applicants dated 29 May 2012 which provided loan information necessary for Mr P to be able to apply for a release of his superannuation. However, in the same letter, the FSP also said that it would not agree to a change in the security structure in circumstances where the full amount of the loans was due and payable. This meant that Mr P would not have been successful in applying to access his superannuation to pay down the overdraft. 22. On 28 June 2012, the Applicants lodged their dispute with FOS. 23. During July 2012, the FSP made two offers allowing the Applicants until 30 September 2012 and then 31 October 2012, to sell their residential property. The Applicants declined these offers on the basis that they provided insufficient time to repay or refinance the loans. 24. On 5 November 2012, the Applicants sold their property for $5,335,000, with settlement occurring on 30 November 2012. The sale proceeds were sufficient to pay out all loan facilities in full. 25. The Applicants say that had the FSP allowed them more time to sell their residential property, they would have been able to retain their property, or realise its true market value at sale, which they say is approximately $500,000 higher than the sale price they obtained. Analysis 26. In my view, the FSP did not fully meet its obligations to the Applicants throughout the whole period of their financial difficulty. I am satisfied that the FSP did meet its obligations during 2011 and early 2012, and again from the date the Applicants lodged their dispute onwards. However, it is my view that the FSP failed to meet its obligations to the Applicants during the period 14 May 2012 to 28 June 2012. I will review each of the key time pe riods in detail below. 2011 and early 2012 27. The information contained in emails between Mr P and the FSP shows that for nearly all of 2011, Mr P was experiencing cash flow problems. During this time, Mr P requested assistance from the FSP in the form of being allowed to temporarily draw down funds in excess of the overdraft’s formal limit. He also requested that the overdraft’s limit be increased . 28. Emails between Mr P and the FSP show that Mr P expected his cash flow problems to be short term, and that he would be in a position to repay the excess funds and increased overdraft limits. Case No: 289307 Determination Page 5 of 7 29. In my view, the FSP responded appropriately in the circumstances of this case, to Mr P’s requests during 2011 , by allowing Mr P on several occasions to draw down funds in ex cess of the overdraft’s limit for periods not exceeding 30 days. It also increased the overdraft’s limit on two occasions, in March 2011 to $75,000, and in December 2011 to $210,000. The December 2011 limit increase was also based on an assessment of information provided by the Applicants about their financial position. 30. The Applicants ’ failure to pay $275,000 to the overdraft by 28 February 2012, and their failure also to put their residential property to auction by mid April 2012, breached the conditions of the final limit increase that the Applicants had agreed to in December 2011. In my view, the FSP was accordingly entitled to commence recovery action in March 2012. 14 May 2012 to 28 June 2012 31. Mr P first notified the FSP by email on 14 May 2012 that he had been made redundant from his employment. In that email he informed the FSP of his change of circumstances, his proposed repayment plan, and his intention to access his personal superannuation funds. 32. In my view, Mr P’s notification of his redundancy was a significant new event of financial hardship, which warranted further consideration by the FSP. However, there is no information to show that the FSP sought any further information from the Applicants about their change in circumstances, or gave any consideration to Mr P’s revised proposals. 33. Other than sending a letter to the Applicants on 29 May 2012 providing loan information having to do with Mr P’s request to access his personal superannuation funds, the FSP did not respond directly to Mr P’s requests for assistance until after the Applicants lodged their dispute with FOS on 28 June 2012. For this reason it is my view that the FSP did not meet its obligations to the Applicants during the period of 14 May 2012 until 28 June 2012. 28 June 2012 onwards 34. I am satisfied that the FSP did meet its obligations from 28 June 2012 onwards because it engaged with Mr P, and put forward two further offers to allow the Applicants time to sell the property or refinance the loans, the first being three months, and the second, a further month. When Mr P made a counter offer, the FSP also met its obligations by informing Mr P that it was declining his offer. Conclusion 35. For the reasons detailed above, it is my view that the FSP did not genuinely consider the Applica nts’ change in circumstances and requests for assistance during the period 14 May 2012 to 28 June 2012. Case No: 289307 Determination Page 6 of 7 36. While the Applicants declined the FSP’s offers allowing them time to sell the property post the mid April 2012 date, they did not provide any realistic alternative that would have seen the debts repaid within a reasonable time. Compensation 37. I will now consider what compensation is payable to the Applicants as a result of the FSP’s failure to meet its obligations. Financial Loss 38. The Applicants say that the FSP forced them to sell their property prematurely and in doing so, they had to sell it a price which did not reflect the property’s true value, such that they have suffered a financial loss. 39. It is my view that even if the FSP had genuinely considered the Applicants’ requests for assistance during the period 14 May 2012 to 28 June 2012, the outcome is unlikely to have been any different. 40. During this period, the Applicants were not in a position to make repayments to their loan facilities, and the expected payments due to Mr P from his business interests had failed to eventuate. It appears that Mr P was not entitled to access his superannuation to clear arrears and meet repayments, as the property title was in Mrs P ’s name only. Mr P’s redundancy certainly worsened his circumstances, and made it less likely that the Applicants would be able to repay their debts other than by the sale of their residential property. 41. In July 2012, the FSP offered to allow the Applicants until 31 October 2012 to sell the security property. In my view, this was a reasonable response. As the Applicants were not making payments, the amount of equity in the property was rapidly decreasing. In addition, the Applicants were aware in late 2011, that they would have to sell if they co uld not make repayments. They also had engaged a real estate agent in March 2012 and presumably the property had been on the market since that time. In these circumstances, I would not expect the FSP to provide an indefinite further period of time for the Applicants to sell the property, or for Mr P’s situation to improve. 42. I would also not expect the FSP to wait for repayment of its debt based on a possibility that property market conditions might eventually improve at some unspecified future date. It was equally possible that any delay might have seen a further decline in property market values, potentially worsening the Applicants’ position. 43. It appears that the financial loss the Applicants claim to have suffered is a result of the prevailing conditions of the property market at the time of the sale of their home. The FSP cannot be held responsible for fluctuations in property market conditions. It was open to the Applicants to repay the debt by other means if they were able to do so and retain their home, but it appears in this case that the sale of the security property was unavoidable. Case No: 289307 Determination Page 7 of 7 44. Accordingly the Applicants are not entitled to any award of compensation for financial loss. Non financial loss 45. Claims for non-financial loss include claims for distress, inconvenience, anxiety, and disappointment. 46. It is only in limited circumstances that I will consider compensation for non- financial loss. An award for such damage is unlikely to be substantial. In assessing whether an award may be made for such loss or damage, I expect Applicants:  To be moderately robust in the way in which they deal with a problem  To take responsibility for ensuring that their financial affairs are in order in the ordinary course of the transactions concerned  To bear the ordinary and normal degree of inconvenience associated with correcting an unexpected problem; and  To take reasonable steps to minimise the inconvenience suffered. 47. During the period 14 May 2012 to 28 June 2012, the FSP failed to respond to Mr P’s requests for assistance. Further, it appears that an agent of the FSP visited the Applicants’ home while the Applicants were still awaiting a response to their requests. I accept that these events are likely to have caused the Applicants to suffer undue anxiety and distress, and to have experienced concern that their home was about to be repossessed. 48. In my view, the Applicants are entitled to an award of $500 each, to compensate them for non- financial loss suffered as a result of the FSP’s failure to meet its obligations during this period. Ombudsman’s Determination 49. I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice, and previous FOS decisions. I have taken into account all the material submitted by the parties. I am satisfied that the documentation I have relied on has been provided to both parties. 50. On the basis of the available information I determine that the FSP did not fully meet its obligations to the Applicants in relation to their financial difficulty during the period 14 May 2012 to 28 June 2012. 51. The FSP should pay the Applicants the sum of $500.00 each as compensation for non financial loss. No further award of compensation is payable.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.