Home / Financial Firm (Unknown - Insurer) / Determination 287448
Determination 287448
Denial of structural flood damage: uneven ground slab, driveway cracking and render cracking; subsidence exclusion
Summary
The Applicant claimed for structural damage after a January 2011 flood, which the FSP declined as subsidence not occurring within 72 hours. AFCA found the flood was a proximate cause and ordered the FSP to bear 50% of the cost of the affected slab, driveway and render damage.
The flood was a proximate cause of the damage, but the matter was finely balanced on expert evidence, so AFCA apportioned the cost 50/50 under its fairness criteria.
Subjects and remedies
home or building damagenatural disasterpay claim
Text of the determination
Case No: 287448 Determination Page 1 of 9
Case number: 287448
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
17 January 2013
Background
1. The Applicant incepted a home building and contents insurance policy with
the Financial Services Provider (FSP) on 18 September 2004. The policy
was renewed annually.
2. On 17 January 2011 the Applicant contacted the FSP to report insured
property had suffered damage as a result of a storm/flood event that
occurred on 14 January 2011.
3. The FSP accepted the claim for contents and cash settled the Applicant in
the amount of $26,500.
4. The FSP accepted internal damage to the lower level of the home building
and damage to a shed. The FSP cash settled the Applicant in the amount of
$69,083.60 following his acceptance of this on 20 June 2011. The settlement
amount is based on a scope of works following expert engineering and
building opinion.
5. The Applicant is concerned with the building structure due to the
unevenness of the ground floor slab as well as cracking damage to the
driveway. The Applicant is also concerned with cracking to rendering
following commencement of repairs.
6. The FSP does not accept the above mentioned damage has been caused by
the claimed flood event but has resulted from soil movement and settlement
which are excluded causes in the policy.
Summary of Applicant’s position
7. The Applicant says his property suffered severe damage from the flood
event.
Determination
Case No: 287448 Determination Page 2 of 9
8. The FSP has accepted some of the claim but disputes liability in relation to
the building structure and driveway caused by subsidence as a result of the
flood.
9. The Applicant says the FSP won’t accept the damage as he has not
sufficiently proven it was caused by the flood.
10. He says three of the four obtained reports support the damage was caused
by the flood. However, the FSP has chosen to accept the dissenting report.
11. The Applicant asks that the FSP accept the builder’s report (RPC) and
undertake the repairs as recommended.
Summary of FSP’s position
12. The FSP says the property has been carefully assessed and the decision to
decline damage to the driveway slab, ground floor slab and render was
based on the findings and relevant expert opinion of its appointed Consulting
engineer (MCE).
13. It says the onus rest with the Applicant to establish property has been
damaged by one of the insured events covered under the policy, having
regard to the relevant exclusions contained in the policy.
14. The FSP says there is no evidence to support the damage in dispute
resulted from an insured event as defined in the policy.
15. It says the policy excludes loss or damage caused by or as a res ult of
subsidence, shrinkage or any other earth movement not occurring within 72
hours of an insured event happening. There is no evidence of any such
activity occurring within the relevant period.
16. The FSP relies on the following policy provisions:
“ What you are covered for
Insured events 1 to 12
When covered under this policy, your home and contents are insured for loss
or damage at the insured address by any of the 12 insured events, if they
happen in the period of insurance.
1. Storm and flood
We cover
Loss and damage caused by storm and flood e.g. rain, wind, hail,
storm and damage caused by flooding from rivers, streets and
canals.
...
What you are not covered for
This section details what is not covered under any part of your policy.
We do not cover loss or damage:
Case No: 287448 Determination Page 3 of 9
...
Erosion or subsidence
Caused by or as a result of erosion, vibration, subsidence, landslip, landslide,
mudslide, collapse, shrinkage or any other earth movement, but we will
cover subsidence damage to your home if it is caused by:
- insured event 2 (burst pipes, leak and overflows)
- contents items insured by portable cover
- these insured events if the damage occurs within 72 hours of the event
happening:
insured event 1 (storm and flood)
...
How we settle your claim
...
We will not
- ....
- fix a f ault that existed before the loss or damage occurred.”
Issues
17. Whether the FSP has settled the claim for flood damage in accordance with
the terms and conditions of the policy.
Reasons for decision
18. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with the Operational Guidelines to the FOS Terms of
Reference. This is because of the issues to be considered. This dispute has
not been the subject of a FOS Recommendation and has proceeded directly
to Determination.
19. There has been an exchange of information between the parties. It is not
intended to recite information in this determination unless deemed
necessary.
20. There is an onus on an insured to establish on the balance of probabilities
that a claim fits the definition of an insured event. Should this onus be
discharged, it is then the responsibility of the insurer to establish the
application of any exclusion on which it relies to deny the claim.
21. To be entitled to cover from the FSP, the onus therefore rests with the
Applicant to establish that his loss fits within the scope of what is covered by
the FSP’s policy.
Case No: 287448 Determination Page 4 of 9
22. The policy provides cover for a series of defined events as outlined in the
PDS. It does not provide blanket cover for all types of loss.
23. Amongst the defined events included in the cover outlined in the PDS is
cover for storm and flood. The FSP accepted a claim for damaged contents
as well as internal damage caused to the building that was identified as
having resulted from the insured event.
24. However a dispute has arisen. The Applicant is seeking indemnity under the
policy in respect of the structural integrity of the building due to the ground
floor slab being uneven, cracking to the driveway and cracking caused to
new render.
25. The Applicant says the weight of evidence by obtained reports supports that
the FSP is liable to indemnify him for this damage.
26. In response the FSP says the terms and conditions of the policy are clear
that subsidence is not covered under any part of the policy unless the
subsidence damage occurs within 72 hours of the insured event.
27. I have given consideration to the reports submitted. Nevertheless I do not
consider them to be exhaustive. Although the Applicant places weight on the
bu ilder’s report s, I place more weight on the reports provided by the
engineers in determining this matter.
28. I note MCE first attended the property on 21 April 2011 on the FSP’s behalf
to specifically address the issue of cracking to the driveway and shed slab.
The FSP accepted the damage to the shed but not the driveway.
29. In the conclusion of his report dated 3 May 2011 MCE advised:
“The pattern and style of cracking to the driveway is consistent with normal
long terms shrinkage of the concrete and is considered to be pre-existing the
flood event. It is considered that the cleaning process does not affect the
structural adequacy of the slab in any way.”
30. In response to the Applicant’s concerns regarding cracking to the lower level
external walls the FSP arranged for building consultant (RPC) to attend the
property and provide a report.
31. In his report dated 20 October 2011 the inspection was carried out to
determine whether internal and external walls have suffered excessive
moisture to the slab ground area due to the January flood event.
32. RPC advised he took floor level reading to determine if the dwelling had
subsided in any direction. He noted the front area of the dwelling was
approximately 35mm lower than the rear of the dwelling.
33. He advised the footing system has experienced moderate to significant
downward and upward movement, and in some cases rotational movement.
As a result of the rotational movement this has caused eventual settlement
and cracking along various parts of external walls.
Case No: 287448 Determination Page 5 of 9
34. RPC was of the opinion the resultant damage sustained to the property was
a direct result of the flood event, causing the sub-soil foundation to react
and become unstable, and in return causing the dwelling to subside, which
has caused minor cracking walls and uneven internal doors.
35. RPC recommended:
The dwelling foundations system to settle and dry out approximately 12
months after the flood event, allowing the structure to settle;
Re-visit the dwelling to revaluate floor levels
Re-align the dwelling to its original position.
36. RPC re-inspected the property which is detailed in a report dated 23 January
2012. He says he was requested by the FSP to report on:
Whether the house/site has stabilised and dried out enough for works
to be done.
Whether any of the damage observed had worsened or changed in any
way (eg. Doors more out of plumb, more or worse cracking in walls etc)
Whether there are any new issues occurring.
Re-evaluate the floor levels.
The driveway as the Applicant thinks the driveway has gotten worse
and that this damage may be from the house movement/sinking.
37. His inspection revealed:
The dwelling had stabilised and therefore repairs can be undertaken.
No signs of damage that had become worse since the first inspection.
No new issues occurring since the first inspection.
Took floor levels for both ground level and upper level in the same
position and found that the levels compared to the first time are of
minimal difference; between 2mm – 5mm in some areas. He believed
this to be general building movement over time.
Reviewed MCE report and can confirm the driveway did have some
minor cracking and appeared to have moved since MCE’s inspection.
Believed driveway will need to be replacement to return it its original
condition prior to the flood event.
38. MCE did not re-attend the property until 8 February 2012 and was requested
to inspect the cracking render, unlevel ground floor slab and unlevel upper
timber floor.
39. MCE noted:
there were a small number of hairlines cracks in the render,
The rendering occurred after the first inspection; around September
2011,
Case No: 287448 Determination Page 6 of 9
Internal repairs had been completed and no defects observed,
The upper floor was constructed of VJ lined timbers walls and ceilings,
There were many wide gaps between the VJ boards however these
had been painted over
The paintwork predated the claimed event.
40. MCE noted the two building reports by RPC which concluded:
That the residence may have been10mm out of level before the flood.
That the movement has resulted from the flood waters saturating the
soil beneath the residence causing it to subside.
41. However, MCE was of the opinion the evidence outlined in the building
reports were incorrect.
42. MCE advised that whilst the ground floor slab does have a fall of 42mm
across its length there is no evidence this settlement occurred as a result of
the flood.
43. Also he advised that whilst the upper floor shows movement has occurred
within the structure, the paintwork across the gaps indicate this movement
occurred prior to the last time the house was painted which was before the
claimed event.
44. MCE stood by his initial report regarding cracking to the driveway.
45. Based on MCE’s evidence, the FSP advised the Applicant it was not
accepting the further claimed damage as it occurred from subsidence but not
within 72hours of the claimed event as required by the policy.
46. The Applicant does not dispute the policy excludes subsidence damage but
will covers such damage if caused within 72 hours of the flood event.
47. The Applicant has evidence from his own engineer (OL). OL’s report dated 2
April 2012 noted the lower level of the house was flooded to about a one
metre in January 2011.
48. I noted OL advised the building is situated on a flat flood plain and that
accordingly one would expect the presence of reactive clay soil at the site.
Although a soil test was not undertaken, the presence of reactive soil is
confirmed by the cracking in the brick since it was rendered since it was
rendered some months ago.
49. OL reported downstairs wall linings and floor coverings and been replaced,
downstairs brickwork rendered, jammed and sticking doors and windows
freed, additional areas of the yard concrete and fence re-built.
50. OL noted the house was out of level by 42mm. He indicated this was
probably caused by the flood. He reported there was no evidence this
Case No: 287448 Determination Page 7 of 9
movement occurred before the flood and that flooding of clay sites is known
to cause ground movement like this.
51. OL says on the balance of probabilities the out of level house was caused by
the flood.
52. In regards to the driveway OL reported that looking at the cracks there is no
way of knowing if the they were as bad before the flood or not. He indicated
the Applicant had asserted that the cracking in the driveway was not like this
before the flood. OL advised floods are known to disturb and stress slabs on
the ground.
53. The Applicant says when he contacted the FSP on 19 January 2011 he says
he had concerns about the building structure. The FSP claim records note
the Applicant having contacting that day as he was worried about structural
damage.
54. There is no indication as to what structural damage the Applicant was
concerned about but he was advised that if damage had been caused by
flood he would be covered.
55. The Applicant says that had the FSP drawn his attention to subsidence
damage within 72 hours at an earlier stage he may have been in a position
to gather conclusive evidence.
56. The Applicant asked OL to comment on whether the damage occurred at the
property more or less 72 hours after the house was flooded.
57. In a response dated 17 May 2012 OL advised:
“The process by which the house was damaged was that the flood water
saturated the foundations, causing the clay in the foundation to swell. This
moved the house and slab out of its original position. When the flood waters
receded, the moisture content of the foundation gradually reduced, and the
house moved back to something like its original position. Due to the random
variability of natural processes, the house did not end up in exact the original
position, and some damage was done to brittle elements during the
movement.
The question of how long this took does seem relevant to its being caused by
the flood. For the record, movement would have stated immediately the flood
waters struck, and the swelling and shrinking would have continued well past
72 hours afterwards. However, I cannot see how this is relevant to the cause
of damage.”
58. However, I noted in his initial report OL stated “the out -of-level house was
probably caused by the flood. Whereas now he appears to be more
definitive. Nevertheless, he says the house has moved back to something
like its original position but due to random variability the house did not end
up in exact original position. OL has not explained what this random
variability could be.
Case No: 287448 Determination Page 8 of 9
59. Nonetheless, the policy does not cover loss or damage caused by or as
result of .... subsidence,.... shrinkage or ... any earth movement but the
FSP will cover subsidence damage to the home if it is caused by flood if the
damage occurs within 72 hours of the event happening.
60. It would appear that cracking existed in the driveway prior to the claimed
event as it is indicated the cracking was no longer the same.
61. MCE reported that cracking to the driveway slab pre-existed the claimed
event and was the result of long term shrinkage.
62. New rendering which was applied to the lower level brickwork some 10
months after the claimed event. I don’t know why the Applicant undertook
such repairs when the house was still being affected by settlement.
63. Even so, the render sustained cracking. MCE indicated the width of the
cracks show slight movement which can happe n due to thermal expansion
or normal changes in soil moisture content.
64. In regards to the structure it is not disputed the ground floor slab is not level.
OL reported the house has moved back to something like its original position
but due to random variability the house did not end up in exact original
position. No explanation has been given as to why. It is possible the slab
should have returned to its position, following drying of the ground, to that
prior to the claimed event. However other factors maybe at play.
65. I am satisfied the evidence establishes that the flood event was a proximate
cause of the unevenness of the floor, cracking to driveway and render.
66. There are differences between the Applicant’s experts and the FSPs builder
on the one hand and t he FSP’s engineer’s report on the other. Furthermore
the FSP carries the burden of proving that the exclusion clause applies in
this case. I believe it appropriate in this case to invoke clause 8.2 of the
Terms of Reference which states:
8.2 Dispute resolution criteria
Subject to paragraph 8.1, when deciding a Dispute and whether a remedy
should be provided in accordance with paragraph 9, FOS will do what in its
opinion is fair in all the circumstances, having regard to each of the following:
a) legal principles;
b) applicable industry codes or guidance as to practice;
c) good industry practice; and
d) previous relevant decisions of FOS or a Predecessor Scheme (although
FOS will not be bound by these).
67. The matter being somewhat finely balanced I believe it is appropriate to
apportion the cost of the damage causing unevenness of the floor, cracking
to the driveway and rendering on a 50/50 basis.
Case No: 287448 Determination Page 9 of 9
Determination
68. The FSP is required to bear 50% of the cost of rendering, the damage to the
driveway and the damage caused by the uneven ground slab.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.