Determination 287133

Flood damage claim: quantum of cash settlement and temporary accommodation

FirmFinancial Firm (Unknown - Insurer)
Decided2013-03-25
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$279,552
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Applicants' flood-damaged home claim: the FSP offered a cash settlement based on a builder's quotation, which the Applicants disputed. AFCA required settlement of $279,552.37, temporary accommodation costs as consequential loss, and statutory interest, but no further non-financial loss payment.

Delay and disputed scope were consequential loss outside the policy's temporary accommodation limit, and the panel adopted the Applicants' quantity surveyor estimate as the reasonable cost of repair.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 287133 Determination Page 1 of 14 Case number: 287133 General Insurance - Domestic Insurance - Home Building - Service - Delay in claim handling – Emergency Accommodation – Quantum of settlement 22 February 2013 Background 1. The Applicants held a home building insurance policy with the Financial Services Provider (FSP). 2. After their home in Indooroopilly, Queensland was damaged by flood in January 2011, the Applicants lodged a claim and the FSP accepted liability for the damage. 3. The FSP offered to cash settle th e claim on the basis of a builder’s quotation it obtained for the repairs to the Applicants’ home. 4. The Applicants dispute the settlement offer made by the FSP, saying the FSP’s builder’s quotation does not adequately represent the reasonable costs associated with repairing their home. 5. In addition, they also want the FSP to pay their rental accommodation up until the time they are able to move back into their repaired home. Summary of Applicants ’ position 6. The Applicants say that they have obtained several builders’ quotations for the required repair work, all of which are far higher than the quotation provided by the FSP’s builder (“JB”). 7. They say that the JB’s quotation is based on an obsolete version of the Scope of Works (SoW) for the repairs. 8. The Applic ants have also obtained a report by a quantity surveyor (“WW”) which reviewed the quotations they obtained and the quotation provided by the FSP. The report by WW concludes that the FSP’s quotation does not represent the reasonable costs associated with repairing their home. 9. As the FSP has unreasonably delayed the handling of their claim, they want it to pay the costs they have incurred for temporary rental accommodation from the time their home was damaged by flood to the time they are able to move back into their home once the repairs are completed. Determination Case No: 287133 Determination Page 2 of 14 10. They also want to be compensated for the stress and ill-health they have suffered as a result of the FSP’s poor handling of their claim. Summary of FSP’s position 11. The FSP says that it obtained a quotation for the repair work to the Applicants’ home from JB, which was based on the SoW which was developed by building consultant “S” and which the Applicants signed off. 12. It engaged quantity surveyor “NB” to review and c omment on the validity the quotations produced by JB and by “DC”, a builder engaged by the Applicants. The report by NB establishes that the quotation provided by DC is excessive and does not accurately represent the reasonable cost of repair. 13. Further, it rejects the Applicants’ position that the report by WW should be held in higher regard than the report by its own expert, NB. 14. It says that the Applicants have not provided any evidence to support their opinion that its numerous experts should not be relied upon and should not form the basis for determining their claim. 15. With regard to the issue of temporary accommodation, the FSP acknowledges that there have been several delays to the claim due to a number of errors and necessary amendments required to the SoW, but does not accept that all the delays were due to its own actions and management of the claim. 16. Although the Applicants have already received the maximum entitlement for temporary accommodation under the policy, it is prepared to provide — on an ex-gratia basis — further temporary accommodation benefit to them, covering the period from the time provided to the Applicants with the initial SoW until the time it was finalised. 17. The FSP relies on the following policy provisions: “ 3.4 Residential Home and Contents Insurance insured events ... Flood Quality Care We will cover Loss or damage caused by any form of flood, including action of the sea, highwater or tsunami.  We will not cover loss or damage cause by: - Landslide, subsidence, erosion or any earth movement (other than earthquake)  Case No: 287133 Determination Page 3 of 14 - ... loss or damage to retaining walls, paths, driveways or landscaping. ... 3.6 Additional benefits for Building cover Additional benefits Quality Care Demolition and removal of debris We will cover the costs of necessary demolition of the home or parts of it, and removal from the home and the site of all the resulting debris. ...  Up to 10% of the sum insured Emergency accommodation We will cover the cost s of similar alternative accommodation for you and any persons currently permanently living in your home, provided your home is unliveable . This expense will only be paid if you actually pay for emergency accommodation and only while your home remains unliveable.  Up to 10% of the current building sum insured or the cost of accommodation for up to 12 months from the date of the event, whichever is the smaller. ... 8.4 How we settle your claim. ... Repairing or replacing: When we agree to pay your claim for loss or damage: We may choose to pay the reasonable cost of repair; or ... a cash amount. If we agree to pay cash, we will pay the amount it would reasonably cost to repair or replace the property. Where buildings are not being replaced, the amount we will pay will be less a reasonable deduction for depreci ation due to wear and tear and age or the property. We will pay The reasonably additional cost of repairing or rebuilding caused by changes in building codes, by - laws or ordinances ... Only those costs that directly apply to the part of your property that has suffered the loss or damage. ... ” Case No: 287133 Determination Page 4 of 14 Issues 18. Whether the offer of settlement made by the FSP represents the reasonable cost of repairing the Applicants’ home. 19. Whether the FSP is required to pay the Applicants’ costs of temporary accommodation up until the time the repairs on their home are completed. Reasons for decision 20. Due to the nature of the dispute, FOS has considered it appropriate to refer the dispute to a Panel in accordance with the Operational Guidelines to the FOS Terms of Reference. Thus, this dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. The parties have been previously advised that a Determination will be issued in this case. 21. This decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in insurance industry matters and a representative with extensive experience in consumer claims. 22. There has been an exchange of information between the parties and the Panel is satisfied that each party has had an opportunity to address the issues raised. 23. There is no dispute that the Applicants’ home was damaged by flood which is an insured event under the policy and that the FSP is liable for that damage. 24. The parties are also in agreement that the document produced by S, dated 24 January 2012 and titled “Flood Specification and Scope of Works ”, appropriately and accurately represents the extent of the repairs to be carried out on the Applicants’ home. 25. The FSP has agreed to pay, under the terms of the policy, professional fees incurred by the Applicants. The Panel notes that payments have already been made to reimburse the Applicants for costs associated with their engagement of the services of a quantity surveyor WW ($2,200) and engineer “E” ($1,320) based on invoices presented by the Applicants. 26. The Panel anticipates that should the Applicants present further invoices relating to the services provided by engineers and/or lawyers, the FSP will reimburse them accordingly. 27. The Applicants have asked for consideration of an award of compensation for non-financial loss, due to the inconvenience and impact on their peace of mind caused by the delay in resolving their claim. The Panel notes that the FSP acknowledges that the Service will consider the Applicants’ claim in this regard but it has in good faith made a payment to the Applicants of $3,000 Case No: 287133 Determination Page 5 of 14 being the maximum compensation that can be awarded by the Service under Section 9.3b) of its Terms of Reference. Does the FSP’s offer of settlement represent the reasonabl e costs of repair? Basis for JB quotation 28. The FSP says that the quotation by builder JB is based on the 24 January 2012 SoW document produced by S, which was agreed to by the Applicants. 29. It says that the report by quantity surveyor NB dated 5 June 2012 confirms that the Applicants’ property can be repaired to its pre -event condition in accordance with the agreed 24 January 2012 SoW and the JB quotation. 30. The FSP rejects the Applicants’ assertion that the quotation by JB is based on a 19 January 2012 SoW. It refers to its account of the history of the claim administration in which it explains that the 19 January 2012 SoW was issued with an amended date. 31. The Panel notes that the JB quotation dated 3 February 2012 states the following: “As per the [S] Scope of Works for the above job dated the 19 th January 2012 please find listed below our price to do the flood repair work.” 32. The Applicants agreed to and signed-off on the 19 January 2012 SoW but subsequently notified the FSP of further changes which were required to this document. The FSP agreed to the Applicants’ changes and arranged for an updated version of the SoW to be produced on 24 January 2012. 33. The change to the 19 January 2012 SoW which the Applicants requested related to item 1.19 of the document. The earlier version of the SoW included the checking (and if necessary, replacement) of the stumps but limited this to the weatherboard and asbestos clad sections of the home and noted the floor area involved was 60 square metres. The Applicants asked for this to be changed so that the stumps of the entire house were to be checked (and replaced if necessary) with a floor area of 134 square metres. 34. The Panel notes that on 4 April 2012, the FSP provided to the Applicants a spreadsheet which detailed the breakdown of costs of its 3 February 2012 quotation. In this spreadsheet, item 1.19 specifies that all the stumps of the house were to be checked and replaced if necessary and also specifies the floor area of 134 square metres. In this respect, the Panel accepts that the JB quotation is reflective of the updated 24 January 2012 SoW, albeit that the quotation states that it is based on the earlier version of the SoW. 35. However, the Panel notes that on a quotation provided by the Applicants from “RMH”, a restumping of th e house would cost $36,300 and the report by WW estimates a cost of $26,400 for this work, should it be required. Case No: 287133 Determination Page 6 of 14 36. Against this background, the Panel considers that the allowance of $2,500 in the JB quotation to be inadequate, and it is likely to be reflective of the costs of the inspection of the stumps, rather than inclusive of any consideration of replacement of any stumps. 37. The Panel also notes that the JB quotation dated 3 February 2012 was provided to the Applicants accompanied by a high-level, handwritten breakdown of the composition of the cost estimate on the quotation. 38. A more detailed breakdown of the costs of the JB quotations was produced on a spreadsheet on 4 April 2012, some two months after the date of the quotation. 39. The Panel has concerns about the time taken for JB to provide this detailed breakdown, particularly since the Applicants had already waited more than a year for the SoW to be finalised. 40. Also of concern is the fact that the cost estimate contained in the detailed breakdown did not match the original quotation amount, with the variation being more than $5,000. Report by FSP’s Quantity Surveyor 41. After the Applicants presented the FSP with a quotation from DC for the repair work and it was clear that there was a significant difference between the cost estimates on the quotations from JB and DC, the FSP engaged quantity surveyor NB to review both of these quotations and report on their respective validity. 42. The report from NB states the following with respect to the JB quotation: “... The rates appear to be generally sound but a little inconsistent in places. There is a schedule of Prime Cost sums which are stated as ‘supply only’. It is not imm ediately apparent where the labour allowances for some of these items have been included in the final cost. There is minimal allowance for preliminary costs such as contract works insurance, liability insurance, waste bins, sheds, storage and toilets. There is no allowance for costs other than construction such as Q Leave, design or engineering fees and council costs. Taking the above into account, the quote is a little lower than might be expected.” 43. With respect to the quotation by DC, the NB report states the following: “... The rates generally appear a little high, some noticeably so, such as house stumps and plasterboard. The preliminary costs, whilst Case No: 287133 Determination Page 7 of 14 detailed, are considered on the high side as they include non- construction costs such as Council fees, Q Leave and perimeter scaffolding. A number of items appear to have higher rates than expected possibly due to the items specified such as some joinery items, shower screen, external doors and kitchen appliances. A number of items priced do not appear to be part of the Scope such as roof framing, ceiling insulation, wall insulation and roof sheeting. An allowance of 3% or $5,909 has been made for contingency which should not form part of the base estimate. Separate allowances have been made for overheads, project manager and profit. These total approximately 30% of construction cost which is extremely high. Taking account of the above the quote is considerably higher than what might be expected.” 44. The report by NB includes an alternative estimate of costs which is $13,102 (including GST) higher than the quotation by JB. 45. The NB estimate is based on “the provided Scope” (although it is not entirely clear which version of the SoW was provided to NB by the FSP) and in the opinion of the report’s authors represents the cost to bring the Applicants’ house back to its condition prior to the inundation. 46. The Panel notes that NB was critical of the inclusion by DC in its quotation of non-construction costs (Council fees, Q Leave and perimeter scaffolding). However, in the opinion of the Panel, it was appropriate to include such items in a quotation for repair work to be performed if it could be reasonably expected that these costs would be incurred during the repairs. 47. In addition, the Panel notes that NB was critical of the rates provided by DC for house stumps ($23,200) and in its own cost estimate included an allowance of $2,500 for this work, the same amount that appeared in the JB quotation. However, as noted in paragraphs 35 and 36 , the Panel considers the JB allowance for stumping to be inadequate. 48. Notwithstanding the issues the Panel might have with the NB report, the Panel notes that although NB stated that the quotation by JB is a little lower than might be expected, the FSP did not amend its offer of settlement to the Applicants to take into account the marginal increase in the cost estimate proposed by NB, the quantity surveyor it engaged. 49. The Panel finds the FSP’s actions in this regard to be disingenuous and somewhat disturbing, given it took more than a year from the flood event to finalise the SoW for the repairs. Case No: 287133 Determination Page 8 of 14 Quotations provided by Applicants 50. The Applicants arranged for five quotations for the repair work to their home. The cost estimates in these quotations ranges from $215,200 through to $295,000, with an average cost across the five quotations being $275,585. 51. The Panel notes that one of the quotations by “DB” did not include any amount for the required underpinning work and if this was added in, the DB quotation would increase to $335,250 and the average across the five quotations would increase to $279,569. 52. The various quotations provided by the Applicants are specified in different levels of detail and the Panel is cautious about putting forward any of these documents as definitive. 53. Nevertheless, the Panel notes that the average of the five cost estimates is reasonably close to the amount provided in the DC quotation and considers it to be a useful “ballpark guide” of the costs that might be associated with the repairs to the Applicants’ home. Report by Applicants’ quantity surveyor 54. The Applicants’ quantity surveyor WW prepared a report which examined: The quotation by the FSP’s builder JB; The report by the FSP’s quantity surveyor NB, including its cost estimate; The cost estimate provided by S (the building consultant which produced the SoW); and The five quotations produced by the builders put forward by the Applicants. 55. WW included an analysis of the various reports and quotations examined, and also provided a detailed cost estimate of what its author considered to be the reasonable cost of repair to the Applicants’ ho me, based on the 24 January 2012 SoW. 56. After considering the WW report, the Panel is satisfied that it contains by far the most detailed and comprehensive of all the cost estimates provided. It takes into account various non- construction costs such as “Q Leave”, insurances and scaffolding (which as outlined earlier, the Panel considers to be necessary inclusions in any cost estimate for the reasonable cost of repairs). 57. It also provides an estimate of “Construction Contingency”. The report states that every construction project requires the inclusion of a construction contingency which are not included in the construction costs due to the uncertainty in scope and to make appropriate allowance for unexpected or unknown errors which will occur. Case No: 287133 Determination Page 9 of 14 58. In arriving at the amount of its construction contingency, WW estimated the cost of various items which were not included in the construction costs and that it considered “risk items” (ie: full restumping of the house; full cost of replacing the drainage; replacement of damaged wall frames, ceiling insulation; gas line repairs; and replacement of light fittings), then calculated the total amount that would be required if it eventuated that these items were required in their entirety. WW then applied a weighting to the total cost of these items (35% - 40%) to arrive at a total of $18,910. 59. In the view of the Panel, the estimate of construction contingency is a reasonable approximation of real costs that are likely to be faced when repairs to the Applicants’ home are undertaken . 60. The cost estimate for the repair of the Applicants’ home as detailed in the WW report is $279,552.37 which the Panel notes is consistent with the average of the five quotations provided by the Applicants. 61. The Panel has considered the fact that the differ ence between the FSP’s settlement offer and the cost estimate by WW is greater than $100,000; however on balance, the Panel accepts that the WW cost estimate is a better representation of the reasonable costs of repairs to the Applicants’ home. 62. Accordingly, the Panel finds that the FSP is required to pay the Applicants $279,552.37 as settlement of the claim. Temporary Accommodation 63. The Applicants say that because of the delays to the handling of their claim, the FSP should pay the costs of their temporary accommodation from the time of the flood until the time they are able to move back into their home after the repairs are completed. 64. The FSP says that the Applicants have already received the maximum entitlement under the policy benefit of emergency accommodation, being 12 months from the date of the flood event. 65. It concedes that there were several delays inadvertently caused due to a number of errors and necessary amendments to the SoW and that in addition to the Applicants’ maximum entitlement, it has paid the Applicants for temporary accommodation costs from 4 April 2011 (when it presented the initial SoW to them) until 19 February 2012 (when they agreed to the final SoW.) 66. The FSP maintains that it is not prepared to accept all responsibility for the time that has lapsed since the lodgement of the claim and submits upon review of the claim history section of its submission, it was clearly in a position to commence the necessary repairs on or around January/February 2012 when it obtained the necessary scopes and quotations. 67. The Panel has reviewed the submissions from both parties in this respect. Case No: 287133 Determination Page 10 of 14 68. In April 2011, more than two and a half months after the flood event, the FSP’s building consultant “S” reported that it was clear that substantial damage was present at the property as a result of flood, but there were also aspects that were pre-existing and present prior to that event. 69. After the Applicants disputed the findings of S, the FSP engaged a consulting engineer “F” to perform an inspection of the Applicants’ property and on 1 July 2011 a report was provided which noted that: Cracks to the brickwork around the built up patio appear to have been in place for a considerable time and not caused or exacerbated by the flood. No formed vertical articulation joints were found to be included which would have allowed for some, if not all the apparent movement to occur without unsightly cracking. Poor plumbing practice has caused the roof water drainage to discharge to the ground adjacent to the rear footings, and poor owner maintenance has allowed total failure of the rear guttering system to occur. F stated that it believed that this would have had some contribution to the movement and damage to the property. Limited movement between some concrete stumps and the floor framing members was observed (up to 15 mm) and although the reason for the movement was unclear, it did not pose a structural risk to the building and did not require rectification. There was evidence of long term wood decay and previous termite activity to the exposed bearer and joists in two corners of the home and this was not flood related. 70. On 11 August 2011, S completed a revised SoW and cost estimate after a review by the Applicants of the existing SoW and consideration of the report by F. 71. The Ap plicants engaged engineer “E” to inspect the property and review the existing SoW and reports. On 25 October 2011, the Applicants provided a report by E which concluded that all the works omitted by the FSP’s previous SoW were the result of flood and should be included as part of the SoW. 72. On 18 November 2011 the FSP wrote to the Applicants saying it had reinspected the property following receipt of the report by E and that with the exception of three items, it agreed with most of the report recommendations. It provided the Applicants with a revised SoW on 23 November 2011. 73. On 8 December 2011 the FSP’s assessor wrote to the Applicants indicating that the cost estimate of the repair was $207,661.92, and that the FSP intended to offer a cash settlement of this amount to them. 74. Over the following two months, the Applicants identified various errors and omissions to the SoW and requested amendments be made. The final SoW was agreed by both parties on 24 January 2012. Case No: 287133 Determination Page 11 of 14 75. The FSP then obtained from JB a quotation dated 3 February 2012 for the repairs in the amount of $174,488.01, which was more than $33,000 less that the cost estimate its assessor advised to them approximately two months earlier and despite the Applicants identifying various errors and omissions from the SoW. 76. The Applicants disputed the cost estimate of the JB quotation, and proceeded to obtain their own quotations for the repairs and a quotation by DC was provided on 24 May 2012 (it is worthy of note that the detailed cost breakdown of the JB cost estimate was only provided to the Applicants on 4 April 2012). 77. The FSP arranged for a review of the quotations by DC and JB by quantity surveyor NB. On 5 June 2012, NB provided its report to the FSP. 78. In the meantime, the Applicants lodged a dispute with the FSP over the quantum of the settlement offer. The FSP produced its final decision letter (FDL) on 31 May 2012 after — according to the FSP’s submission — considering the report by NB dated 5 June 2012. 79. The Panel has examined the claim history section included in the FSP’s submission and finds little evidence of the Applicants contributing to the significant delays to the claim, except to the extent that they disagreed with the findings of the FSP’s various experts. 80. A review of the Applicants’ account of the hi story of the claim reveals that on many occasions, they would attempt contact with the FSP or its agents, then have to follow up again and again in order to obtain simple information about the claim and its status. 81. The Panel is perplexed as to how the FSP could produce a FDL with respect to the Applicants’ dispute on a date prior to the date of the report from NB, which it purports to have considered as part of arriving at its final decision. 82. Interestingly, the FSP appears to have sent the FDL using an incorrect postcode for the Applicants, which resulted in a further two week delay before the Applicants received the FDL on 14 June 2012. 83. The Panel notes that although the Applicants indicated that properties in their area drew rentals of $450 per week, th e FSP’s assessor advised them to limit any temporary rental accommodation they obtained to $380 per week. The reasoning for the assessor’s rental recommendation is unclear. 84. The policy provides for emergency accommodation of up to 12 months or 10% of the building sum insured, whichever is less. As the building sum insured was $337,100, the 10% limit would have to provide 12 months accommodation at a rate of $648 per week without exhausting the benefits under the policy. 85. The Panel notes that due to the lack of availability of suitable accommodation close to their property address at the price advised by the Case No: 287133 Determination Page 12 of 14 FSP’s assessor at the time of the flood, the Applicant s had to settle for accommodation several suburbs away. Because of this, the FSP agreed to pay an al lowance of $30 per week as ‘travel allowance’ on top of the $330 per week for the rental accommodation secured by the Applicants. 86. The policy limits the payment of temporary accommodation to 12 months from the date of the event, and the Panel notes that the FSP has agreed to pay the costs of temporary accommodation above this limit. This includes coverage of the period between the delivery of the initial and final (agreed) SoW, as well as an allowance for the period during which the Applicants’ dispute had been lodged and was under consideration by the FSP. 87. Based on information provided by the FSP, a total of $26,748 in temporary accommodation and ‘travel allowance’ has been paid to the Applicants. At a rate of $360 per week ($330 accommodation and $30 travel allowance), this equates to approximately 74 weeks. 88. Having paid 74 weeks accommodation expenses the FSP has already exceeded the allowance provided for temporary accommodation for up to 12 months under the terms of the policy. The FSP has already elected to waive its strict reliance upon that policy provision. 89. Nevertheless, the Panel is of the view that the FSP and its agents have been almost entirely responsible for extensive delays in the claim settlement process, and at the time of this Determination being drafted the claim had been open (not finalised) for approximately two years. 90. The ongoing accommodation expenses incurred by the Applicants are a consequential loss of the FSP’s delays in the proper processing of the claim. In the Panel’s view, delays and dispute over the Scope of Works can be correctly classified as being consequential loss which is anything beyond the normal measures, such as loss of profits etc. Such a view is consistent with the comments contained in “ Environmental Systems Proprietary Limited v Peerless Holdings 2008 VSCA 26 ” and more recent appellate court decisions in NSW and in South Australia, as to the concept of consequential loss. 91. The FSP’s policy does not exclude payment for consequential loss. If it did, in the circumstances of the current dispute, arguably to allow it to rely on such a provision would be fundamentally unfair. Arguably the delays occasioned in this dispute could bring into consideration the application of Section 14 of the Insurance Contracts Act 1984 (the Act ), although the Panel has determined not to proceed down that path. 92. In the Panel’s view, it would be unreasonable and unfair for the FSP to be able to rely upon the limitations contained within the policy relating to temporary accommodation expenses as the additional expenses incurred are not related to the Applicants’ delays but in fact incurred due to delays in the processing of the claim that the Panel considers to be largely the responsibility of the FSP. Case No: 287133 Determination Page 13 of 14 93. In the circumstances, the Panel believes that the additional accommodation expenses amount to consequential loss and it is fair in all the circumstances that the FSP extend the policy benefit relating to temporary accommodation to cover those costs. 94. The Panel acknowledges that uncertainty exists with respect to the time required for the rebuilding of the Applicants’ home. Given the question of the Scope of Works and costs has been resolved, the Panel believes that a further period of six months after payment of the claim for the building damage in accordance with the terms of the policy would be an adequate provision for payment of temporary accommodation costs. 95. Accordingly, the Panel finds that the FSP is required to pay the Applicants for their temporary accommodation costs at the rate of $360 per week for the period from 12 January 2011 up until the date equivalent to six months after the date upon which the next payment for the building damage to the Applicants ’ home after taking into account payments already made for temporary accommodation. Compensation 96. The Applicants have asked for the Service to consider the payment of compensation for non-financial loss due to the stress caused by the delay to their claim. 97. Under Section 9.3b) of the Terms of Reference, the Service may decide that the FSP is required to compensate an Applicant for non-financial loss in circumstances where they have experienced an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind has occurred. The limit of such an award is $3,000. 98. In the view of the Panel, the circumstances of this dispute meet the criteria for an award of compensation for non-financial loss. 99. However, the Panel acknowledges that the FSP has already made an ex- gratia payment to the Applicants of $3,000, and accepts that this is an appropriate level of compensation for their non-financial loss. 100. Accordingly, the Panel finds that the FSP is not required to make any further payment to the Applicants for non-financial loss. Determination 101. On the basis of the available information the Panel determines that: The FSP is required to pay the Applicants $279,552.37 as settlement of the component of the claim which relates to the repair of their home building, subject to any restrictions or conditions which may be present Case No: 287133 Determination Page 14 of 14 because of the presence of any bank mortgage, encumbrance or other financial interest over their property. The FSP is required to pay the Applicants for temporary accommodation (and its concomitant travel requirements), at the rate of $360 per week for the period from the date of the flood event (12 January 2011) until a date the equivalent of six months after the date upon which payment is made for the building damage. 102. Pursuant to Section 57 of the Act, the FSP is required to pay the Applicants statutory interest on $279,552.37, calculated from 31 May 2012, being the date of its FDL with respect to the Applicants’ dispute about the settlement offer made. 103. Payment of these amounts will fulfil the FSP’s obl igations under the policy for this loss. 104. The FSP is not required to make any further payments to the Applicants as compensation for any non-financial they may have suffered.