Home / Financial Firm (Unknown - Insurer) / Determination 286857
Determination 286857
Claim handling and advice (vessel)
Summary
The applicant, a vessel owner, sought $660,180.15 from the FSP, his broker, after the vessel was damaged in cyclones and later sank. AFCA found no breach by the FSP and ordered no remedy.
The applicant's own delays and repeated assurances that he would move the vessel for repair meant the FSP's conduct did not breach its duties.
Issues
- Poor claim handling primary · not upheld“the Panel cannot accept the FSP breached its duty in its conduct surrounding the claim.”
- Conflicted advice secondary · not upheld“he has provided no evidence of these [steering and contingent remuneration].”
- Failure to disclose secondary · not upheld“the Panel does not accept the FSP breached its duty in omitting to inform the Applicant of this benefit.”
- Inappropriate advice secondary · not upheld“The Panel does not consider there is any foundation to this argument given the following: the policy was an accidental damage policy.”
- Poor communication secondary · not upheld“the Panel does not accept the Applicant's allegations that the FSP failed to properly advise and assist him with respect to Q's decision to not offer renewal.”
Subjects and remedies
broker or intermediarynatural disasterno remedy
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Case No: 286857 Determination Page 1 of 17
Case number: 286857
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
25 March 2013
Background
1. The Applicant engaged the Financial Services Provider (FSP) as his general
insurance broker to arrange an insurance policy for a vessel he purchased
on 2 August 2008. The vessel is a pleasure craft.
2. The FSP arranged an insurance policy with insurer Q. The initial policy of
insurance operated for twelve months beginning from 27 July 2008 and the
vessel was insured for an agreed value of $175,000. This policy was
renewed upon similar terms in 2009 but with an agreed value of $178,500.
However, in 2010, Q refused to offer renewal and as the Applicant was
unable to secure insurance elsewhere, the vessel has remained uninsured
since.
3. In late January and early February 2009, there were 3 mini cyclones and/or
tropical storms which resulted in some damage to the vessel (“Event One”).
4. On 6 March 2009, the Applicant further advised the broker that he was
securing the boat from Cyclone Hamish (“Event Two”) and reference was
also made to possible additional damage.
5. Following this, the vessel sustained further damage by Cyclone Yasi on 2
February 2011 (“Event Three”) and on 16 February 2012, it completely sunk
(“Event Four”).
6. The vessel is now considered a constructive total loss following its sinking
and the Applicant has sought to recover its replacement cost from both the
FSP and the broker.
Summary of Applicant ’s position
7. The Applicant notified the FSP of Event One by way of email dated 12
February 2009. The Applicant‟s email described the damage as follows:
“It appears that the high winds & heavy rain has forced a considerable amount
of salt laden water under a number of deck hatches/windows (the seals/locks
appear in good condition) causing observed water damage, but not limited to;
timber, cushions, bedding etc
Determination
Case No: 286857 Determination Page 2 of 17
and more importantly‟
into the electrics under the cabin seats (there was 10mm of water under the
seats)
& then into main electrical panel
& finally made its way down into the bilge
This water immersion has caused the failure of all electrics on board, (i.e. not
everything is ruined, just no current is now flowing) most importantly the auto
bilge pumps are now not operational (we manually hot-wired the bilge pumps
& pumped out the normally dry bilges … the water level was just over the
cabin floors). I would have estimated 300-350lt of water inside the boat.
We have sponged dried up the salt laden water under the seats and left this
area uncovered to dry out it would appear that damage may have occurred in
many areas
A) where the wires are joined in banks of joiners would now be subject to
corrosion & failure in the future, as corrosion progresses
B) possibility some sensitive equipment has shorted out
C) damage to timber swelling etc
D) as the water made its way into the bilge where the wires are joined in
banks of joiners would now be subject to corrosion & failure in the future
as corrosion progresses”.
8. The FSP responded later that same day enclosing a claim form for the
Applicant to complete and asking that the Applicant obtain an estimate for
repairs.
9. On 6 March 2009, the Applicant sent an email to the FSP advising about his
efforts to secure the boat from Cyclone Hamish (“Event Two”). It is unclear if
the vessel sustained further damage but according to the claim form he
completed on 10 November 2010, he made reference to additional damage
when next visiting the boat. The comments in his email on 6 March 2009
stated:
“On our next visit to check the vessel after h eavy rain we subsequently
discovered it was again flooded a detailed inspection revealed the
broken/shattered seals around the large side windows allowing even more
salt laden water to leak continually into the cabin again flooding all the
electrics a second time.
Upon this new discovery:
we again sponged dried up the salt laden water under the seats and left
his area uncovered to dry out
we again manually hot wired the bilge pumps & pumped out the normally
dry bilges (the water level was just over the cabin floors)
temporarily resealed the broken/shattered the seals around the large
windows with sikaflex (the windows will require removal and resealing to
properly fix the damage)
Subsequently most of the positive copper wires have failed as predicted some
corrosively burning out at joins and connections or randomly along their
length. We have temporarily fixed some of the failed circuits to enable the
Case No: 286857 Determination Page 3 of 17
vessel to be made „operational‟ motors, navigation etc. We then found out
that the wind direction instrumentation is damaged and now reads 90 deg to
the true wind direction.” (sic)
10. The FSP advised Q‟s underwriting agent of the potential damage on 6 March
2009 but no further action was taken as the FSP had yet to receive the
completed claim form.
11. A discussion was entered into between the Applicant and the FSP on 10
August 2009. In this conversation, the Applicant explained some of the
logistical issues he was experiencing in obtaining a quotation. The FSP
recommended that Q become involved and to this end, it again sent a claim
form for the Applicant to complete.
12. The Applicant sent an email to the FSP on 15 November 2010 seeking to
pursue the claim. The FSP responded in an email dated 23 November 2010
asking the Applicant to complete Q‟s claim form, which he did. Th is was
forwarded to Q on 30 November 2010.
13. On 9 December 2010, Q had a discussion with the Applicant regarding the
claim. According to Q, the Applicant agreed to sail the vessel to the nearest
repairer to obtain a quote.
14. For various reasons, this did not occur and a quotation was never provided.
15. The vessel sustained further damage by Cyclone Yasi on 2 February 2011
(“Event Three”) and on 16 February 2012, it completely sunk (“Event Four”).
During this time, the FSP had yet to assess or pay the claim as it had not
received a quotation for the damage sustained.
16. The vessel is considered a constructive total loss following its sinking and
the Applicant has sought to recover its replacement cost from both the FSP
and Q. As neither party have agreed to pay this, he has pursued this loss
with the Service and extended his claim to include the following:
Type of Loss Amount
Loss of Vessel claim $178,500.00
General Damages loss of use (Interest) $80,473.15
Other claimable damage $7,500.00
Salvage fees $25,500.00
Interest $2,707.00
Preparation of submissions to the Service $17,000.00
Special Consequential Damages $123,500.00
Compensation for loss of pleasure, relaxation or
peace of mind
$25,000.00
Aggravated and Exemplary Damages $200,000.00
Total Damage $660 , 180.15
Case No: 286857 Determination Page 4 of 17
17. The Applicant has provided substantial and lengthy submissions. His initial
submission to the Service was 79 pages (which also included a summarised
26 page version) and this was followed up by a 329 page submission. His
second submission contains reference to several pages worth of case law
and legislation and also includes reference to numerous legal principles and
judgments.
18. His substantive arguments are:
a. He clearly advised the FSP that the vessel was unseaworthy.
Accordingly, the FSP had a duty to assist him in transporting the vessel
to a safe location.
b. The FSP failed to provide appropriate assistance with respect to his
claim.
c. The policy arranged was inappropriate to his needs. In particular, the
FSP steered him towards this policy due to the remuneration
arrangements it had in place.
d. The FSP failed to properly inform him of the policy benefits, particularly
the fact Q would have paid the costs of transporting the vessel to a safe
harbour. In furtherance of this, the Applicant has stated the FSP never
provided him with a copy of Q‟s policy.
e. The FSP failed to properly advise and assist him in ensuring the vessel
remained insured after Q refused to invite renewal in June 2010.
19. Based on this, the Applicant maintains he is entitled to compensation and
damages as detailed.
Summary of FSP’s position
20. The FSP has submitted the following in response to the Applicant‟s position:
It took all reasonable steps to assist the Applicant in re taining insurance
for the vessel when Q decided not to invite renewal. Further, the
Applicant allowed the policy to lapse and undertook no steps to ensure
it became insured for the following 19 months.
It always acted reasonably when assisting the Applicant in his claim.
However, the Applicant failed to take reasonable steps to comply with
Q‟s requests for information.
The Applicant never informed it that the vessel was unseaworthy as a
result of Events One and Two. Instead, it appeared the vessel was
seaworthy as the Applicant intended to transport the vessel from
Mission Beach to Cardwell after the 2009 event.
A copy of the policy was provided to the Applicant when the insurance
was arranged. Accordingly, the Applicant was aware of the relevant
policy provision with respect to the emergency transporting costs of the
vessel. Further and in the alternative, as the vessel remained moored
Case No: 286857 Determination Page 5 of 17
at Mission Beach for over 3 years before it sank, it is doubtful the
Applicant‟s circumstances would fall within this benefi t.
The policy arranged was appropriate. Further, there was no contingent
remuneration arrangement for this policy. In furtherance of this, it
provided the Applicant with a copy of the Financial Services Guide
(FSG) disclosing relevant information in this regard .
Even if there is a finding of negligence (which it denies) there should be
a finding of complete contributory negligence against the Applicant due
to his actions or inactions .
21. The FSP therefore maintains it is not liable to pay any amount to the
Applicant.
Issue
22. Whether the Applicant is entitled to the remedies he is seeking.
Reasons for decision
23. As advised by the parties, due to the nature of the dispute, the matter has
been referred to the Panel for Determination in line with the Operational
Guide lines to the Service‟s Terms of Reference. This dispute has not been
the subject of a FOS Recommendation and has proceeded directly to
Determination
24. This decision has been made by a Panel consisting of an Ombudsman, a
representative with extensive experience in the insurance industry and a
representative with extensive experience in consumer claims.
25. The Applicant‟s dispute against Q will be dealt with in a separate
Determination. Accordingly, any issues and allegations involving Q will not
be dealt in this Determination.
26. For the sake of brevity and conciseness, and in recognition of the fact the
Applicant‟s dispute was prioritised over other disputes because of his
claimed financial hardship, the Panel does not propose to consider all of the
points raised in the Applicant‟s submissions in detail.
27. Instead, the Panel will consider the facts and principles that it considers are
relevant to the Applicant‟s dispute. Following this same reasoning, the Panel
will only briefly summarise the substantive and relevant arguments raised by
the Applicant as opposed to setting all of them out in detail.
Inappropriate policy
28. The Panel does not consider there is any foundation to this argument given
the following:
Case No: 286857 Determination Page 6 of 17
The policy was an accidental damage policy and the exclusions and
conditions contained therein do not appear harsh or onerous.
There is no evidence to support a view that there were other insurer‟s
policies available to him that contained wider benefits suitable to his
needs.
29. In addition, the Applicant‟s main issues with respect to his insurance claim
have been with the management of the claim itself rather than the policy
terms and conditions. These issues are substantively contingent on the
circumstances surrounding the four events and the parties involved rather
than the terms of the cover itself.
30. Although the Applicant has referred to issues such as „ steering ‟ and
„ contingent remuneration ‟ , he has provided no evidence of these. In any
event, even if the Panel was to accept such practices were in play, in
themselves they do not lead to an automatic conclusion that the policy was
inappropriate to his needs, particularly given the reasons articulated above.
31. As a result, the Panel does not accept the FSP breached any duty with
respect to the arrangement of this policy.
Assisting with the claim
32. The Applicant has raised numerous allegations and provides voluminous
submissions arguing the fact the FSP has breached its duties with respect to
assisting him with the claim. This appears to be the substantive basis of his
arguments, in particular the following:
The FSP‟s failure to inform him about the policy benefits by either
providing a copy of the policy or drawing his attention to the fact the
policy pays the following:
“If your boa t gets into difficulties or is damaged accidentally, we will pay the
reasonable cost of taking action to … remove the boat to safety (including
emergency towing) …”
The continued unreasonable requests for a completed claim form and a
repair quotation.
The FSP being on notice that the vessel was unseaworthy yet failing to
assist him in transporting the vessel to Cardwell.
33. As previewed previously, the Panel does not propose to consider all of the
Applicant‟s arguments in detail. Instead, given the substantial experience it
has in dealing with general insurance disputes, the Panel will consider and
apply the relevant legal principles applicable to the facts surrounding this
dispute.
34. In particular, the Panel considers it is appropriate to consider the events
between Event One and Event Four in detail. The reason being that much of
the Applicant‟s submissions have centred on inaction or omissions allegedly
made by the FSP and Q during this timeframe.
Case No: 286857 Determination Page 7 of 17
Events
35. In regards to Event One, this was notified to the FSP by way of both emails
and telephone on 12 February 2009. In the email, the damage was mainly
associated with the „ electrics ‟ . In particular, the Applicant noted the following:
“I need to get a qualified tradesperson ASAP to have the electrics made
operatio nal … and so to the boat can be moved for repairs.”
36. As is evident, the Applicant clearly took it upon himself to arrange for the
repairs. This was corroborated by the file note recorded by the FSP.
Although the Applicant‟s email subsequently sought the FSP‟s advice about
how to progress the insurance claim, the issue of repairs were clearly being
addressed by the Applicant himself.
37. In regards to the Applicant‟s request for assistance, the FSP responded in
an email sent that same day stating the following:
“ [P] has asked me to forward the attached claim for to you. I would be obliged
if you could complete and return this to me together with an estimate of
repairs.”
38. In the Panel‟s view this is reasonable in the context of the communications
between the parties . That is, there was no indication in the Applicant‟s email
that the provision of a repair quotation or completion of a claim form would
be onerous or difficult. In addition, these are standard requests associated
with most insurance claims. In particular, the completion of a claim form was
a policy requirement.
39. Nothing further was forthcoming from the Applicant until he sent the FSP
another email dated 6 March 2009 advising of his concerns regarding
Cyclone Hamish and the efforts undertaken to secure the vessel. The email
contained the following of relevance:
“We have spent all day on the boat a week prior cleaned up & effected some
temporary repairs to the electrics & we were able to get one of the outboard
motors & some instruments working (we managed to complete repairs & get
the second out board operational en route around 9am today) (a lot of the
caballing has shorted & burnt out) unfortunately the auto bilge pumps are still
not operational.”
40. As is evident, the Applicant was still undertaking some of the repairs.
Further, the Applicant did not seek anything specific from the FSP but rather
appeared to be informing the FSP of potential issues with the vessel. In
particular, this email did not state the vessel had sustained any damage but
rather indicated the likelihood of it doing so in the advent of Cyclone Hamish.
41. The FSP forwarded this information as well as the Applicant‟s email dated 12
February 2009 to Q‟s underwriting agent.
42. Q‟s underwriting agent acknowledged the email. Although nothing further
was forthcoming from either Q or the FSP, the Panel does not consider this
was unreasonable given the following:
Case No: 286857 Determination Page 8 of 17
The Applicant was still undertaking some of the repairs and had made
progress in this regard.
There was no reference whatsoever that the vessel was unseaworthy.
The Applicant had already been instructed to complete a claim form
and provide a repair quotation. Further, the Applicant had not indicated
this was a task beyond his capacity or ability to complete.
The FSP was still waiting for this information to enable it to lodge a
claim with Q.
There was nothing to indicate the Applicant did not agree to provide a
claim form and repair quotation.
43. In light of this, it was reasonable for the FSP to await the provision of the
claim form and repair quote before lodging any claim with Q.
44. The next communication the FSP had with the Applicant was a telephone
conversation on 10 August 2009, being approximately 6 months after Event
One. This was due to the FSP following up the Applicant as nothing further
had been forthcoming. The FSP‟s file note recorded the following:
“Has not yet got quotes for electrical damage, due to logistics & time frame.
Would like it fixed though.
Recommend insurer appoint assessor to get repairs underway, and assist
client getting claim finalised & quote organised.
Will send cheque for payment has been away.”
45. This appears to be the first time the Applicant brought to the FSP‟s at tention
the logistical issues he was experiencing in obtaining a quotation. Further,
he only did so upon being followed up by the FSP. The FSP sent the
Applicant an email the following day asking that he complete a claim form to
ensure a claim was lodged with the insurer.
46. The Panel notes there was no reference in the Applicant‟s communication
that the vessel was unseaworthy.
47. Despite the FSP‟s follow up conversation and email, nothing further was
forthcoming from the Applicant until the FSP received an email from him
dated 13 July 2010. This email was in response to the FSP‟s attempts to
contact him regarding Q‟s decision to not invite renewal.
48. The Panel notes this is 11 months after the FSP‟s previous contact. Although
the Applicant has stated he was extremely busy, this delay is substantial and
unreasonable given he now states the vessel was unseaworthy and required
emergency transport at the time.
49. In the Applicant‟s email, he informed the FSP that he was travelling
extensively and not due to return to Australia until 10 August 2010 (the policy
was due to lapse on 27 July 2010). With respect to the claim, the Applicant
stated the following:
Case No: 286857 Determination Page 9 of 17
“Also the current insurance claim against the current policy (current Insurer ...)
and the repair works on the vessel would need to be completed some time
after 10 August 2010 (we are still waiting to be contacted by a assessor /
officer from the insurer) for it to be passed 100% seaworthy by a qualified
Marine Surveyor (however an out of water survey report is a condition of the
placement.)
The vessel is presently moored in the mangroves creek at South Mission
Beach and accessible to an assessor. We were going to take the boat to
Cardwell Marina upon our return (40km closest dry doc, lifting crane,
shipwrights) and have the insurance claim assessed and quoted on and then
have the insurance repairs and maintainance carried out at the shipwrights in
Cardwell.” (sic)
50. After undertaking enquiries with two other insurers as well as Q in attempting
to arrange alternative cover, the FSP emailed the Applicant on 15 July 2010.
In regards to the claim and the Applicant‟s comments above, the FSP
responded as follows:
“The delay in proceeding with your claim is noted by [Q] but they will honour a
claim from the incident in 2009. However, it must be noted that if the delay in
effecting repairs has exacerbated the damage an Assessor will certainly take
this into account.
…
If there is some way you can organise the boat to be taken to Cardwell, prior
to 27/7/2010, for (a) an out of water Survey + (b) an assessment of claim by
an Assessor, we might then be able to negotiate coverage with other Insurers
& progress the claim.
In saying this, [Q] is still to receive a completed Claim Form from you (via
[FSP]) & it is necessary for this to be attended immediately. I understand you
have this required documentation.”
51. The Applicant responded the next day stating the following:
“The boat simply cannot be taken to Cardwell till I get back.
I will send a more detailed reply later.” (sic)
52. After reviewing this communication, the Panel is satisfied with the following:
a. The FSP did provide direction to the Applicant about dealing with the
claim. In particular, the FSP informed the Applicant that a claim form
was required to be filled in urgently to enable it to be progressed.
b. The Applicant stated in clear and unambiguous terms that he intended
to transport the vessel to Cardwell. This was a statement of intent
which the FSP relied upon when advising him as to the next course of
action with respect to both the claim and the upcoming policy expiry.
c. The Applicant, in his email dated 16 July 2010, further corroborated his
previous email by stating his intent of transporting the vessel to
Cardwell. This again was an unqualified statement.
53. Given this, the Panel is satisfied that the FSP was entitled to await the
Applicant‟s next contact given his clear communication. However, this was
Case No: 286857 Determination Page 10 of 17
not forthcoming until 15 November 2010, being almost 4 months later and
after the FSP sent him an email dated 27 July 2010 informing him that the
policy had now lapsed.
54. The Applicant has not explained in any manner why he delayed actioning the
matter for so long, particularly given he was clearly informed that the vessel
would be uninsured after 27 July 2010 and that in orde r to progress the
claim, a claim form was required to be completed.
55. In this context, the Panel cannot accept that this delay was attributable in
any way to the FSP. Despite the fact the FSP was aware at this time that the
vessel may have been unseaworthy, the FSP was entitled to rely on the
Applicant‟s clear representation that he will arrange the transportation of the
vessel to Cardwell and was therefore taking responsibility for its safety.
56. In the Applicant‟s email dated 15 November 2010, he sought to progress the
claim. The FSP responded in an email dated 23 November 2010 enclosing
the claim form for completion. The Applicant completed this and sent it to the
FSP, who then forwarded it to Q on 30 November 2010.
57. There was nothing to indicate that the Applicant was experiencing any
difficulty in completing the claim form. Given his extensive submissions and
details to date, it would appear the completion of the claim form was well
within his capacity and ability so the substantial delay in completing same is
unexplained and unsubstantiated.
Events following completion of claim form
58. Following receipt of a claim form, a telephone discussion was conducted
between Q and the Applicant on 9 December 2010. This was only 9 days
after Q received the claim form.
59. According to an email sent by Q to the FSP dated 27 December 2010, the
following was discussed:
“I discussed the state of play with the Insured back on the 9 December 2010
concerning the preparation of a repair quotation. The Insured explained the
difficulties they had faced in doing this but were hoping to have the boat
moved the a repair facility within a few weeks.” (sic)
60. It appears the Applicant again agreed to transport the vessel to the nearest
repairer (presumably in Cardwell) with Q awaiting confirmation as to when
this occurred. The FSP forwarded this email to the Applicant on 4 January
2011.
61. Despite the fact some progress appeared to have been made, the Applicant
again omitted to make any further contact with either the FSP or Q until 1
June 2010, being 5 months later. Further, this contact was in response to
Q‟s email to the FSP dated 31 May 2010 where Q noted that no further
contact was received from the Applicant and it sought confirmation as to
whether the Applicant intended to proceed with this claim. Q also warned
Case No: 286857 Determination Page 11 of 17
that if no response was forthcoming in the next 14 days, the claim would be
presumed withdrawn.
62. The FSP forwarded this email to the Applicant on 1 June 2011 who
responded on the same date advising the claim was not withdrawn. In this
email, he highlighted the costs in obtaining a quotation by stating the
following:
“Just spoke to [PN] Marine Cardwell …
Lift out lift in $9.25 ft
per day slipped $1.95 ft
after all the work from Yasi damage to boats in the [FSP‟s] „safe‟ marina [PN]
can now fit in our job / work
[PN] can possibly come to Mission Beach in about 2 weeks for a quote (for a
fee) …
we would require calm conditions & correct tides to get the boat to Cardwell
safely”
63. Again, no reasonable explanation was offered as to why the vessel had not
been transported despite his previous assurances. Furthermore, the
Applicant had again undertaken to transport the vessel to Cardwell and also
provided an assurance that a quotation would be obtained.
64. The FSP informed Q of the Applicant‟s communic ation on the same date and
both parties awaited the quotation promised by the Applicant. This is
reasonable given the Applicant‟s clear and unambiguous communication.
65. Yet again, no contact was forthcoming from the Applicant and the FSP
followed him up twice (6 July and 10 August 2011). It was only in response
to the second follow up that the Applicant decided to respond in an email
dated 16 August 2011 by stating the following:
“The fellow never arrived for the quote as promised.
I am in New Zealand until mid September.
I propose to take the vessel directly to Cardwell for Yasi repairs plus the
insurance quote & repairs within a few weeks of returning from NZ.”
66. This was two and a half months since his last contact and was again in
response to a threat that the claim would be closed. Further, the Applicant
again stated he would transport the vessel to Cardwell with no indication that
he sought any assistance in this regard.
67. The FSP forwarded this email to Q on the same date. Q responded in an
email dated 24 August 2011 asking to be notified as to when the Applicant
decided to undertake the voyage. The FSP forwarded this email to the
Applicant with the following request:
“Please provide that „advance notice‟ to us at [FSP] in due course (not directly
to [Q] - a s we will wish to coordinate all aspects).”
Case No: 286857 Determination Page 12 of 17
68. Yet again, no contact was forthcoming from the Applicant. As a result, Q
followed up the FSP two and a half months later on 13 October 2011. The
FSP forwarded this follow up to the Applicant and then stated the following:
“I am forwarding this email from [Q] & I must say this insurer is demonstrating
remarkable patience.
From [FSP‟s] point of view, our endeavours in gaining a settlement for you are
now exhausted.
We have not been your Insurance Broker for boat insurance since 27/7/2010 -
when [Q] declined to continue coverage …
In view of this & the lack of resolution of this matter, we not provide
formal notice of [FSP’s] immediate withdrawal from any further
involvement …”
69. The FSP informed Q of this email. No contact from the Applicant was
forthcoming.
70. The Panel is aware that Q wrote to the Applicant directly on 30 November
2011, being one and a half months later, advising that the file would be
closed within 21 days if nothing was forthcoming.
71. The Applicant did not respond to either party. According to the information
available to the Panel, the Applicant‟s next contact was approximately on 30
March 2012 with the FSP ‟s underwriting agent . Prior to this, Event Four had
occurred whereby the vessel had sunk and was a constructive total loss.
72. It was only after the vessel had sunk that the Applicant began to pursue his
insurance rights with much more vigour. This appears due to the fact that he
was now experiencing severe financial distress and was seeking
compensation as a matter of urgency to deal with his financial
circumstances.
Remarks and conclusions about the claim
73. When considering these events carefully, the Panel cannot accept the
Applicant‟s substantive allegations against the FSP have any foundation.
The chronology of events showed a systematic and continued failure by the
Applicant to pursue his dispute with any vigour.
74. In particular, upon reviewing the series of events in detail and analysing the
FSP‟s conduct in cont ext of its communications with the Applicant, the Panel
does not accept any of its communications was inappropriate or
unreasonable. In addition, the FSP promptly responded to all of the
Applicant‟s enquiries and consistently provided him with direction re garding
how to progress the claim.
75. The Applicant does argue that the FSP ought to have provided more
constructive assistance, particularly given the fact the vessel was
unseaworthy and the perilous journey he had to undertake to Cardwell.
However, the Panel does not accept this argument for the following reasons:
Case No: 286857 Determination Page 13 of 17
At all times, the Applicant continually agreed to arrange the transport.
It was only in the email dated 13 July 2010 that the Applicant firstly
indicated the vessel may not be 100% seaworthy. Howe ver, he still
stated he would arrange the vessel to be transported to Cardwell a
number of times after this.
In none of his communications does he ever indicate that he could not
afford to arrange the transport or wished for Q to arrange this on his
behalf. Although he has stated numerous times in his submission to the
Service of his reluctance to do so because of the dangers involved, this
was not evident in any of his written communications to either the FSP
or Q.
76. In addition, according to the Applicant‟ s initial submission to the Service, he
indicated a repairer would be prepared to provide a quote if their travelling
costs were to be paid. This was set out by his following words:
“[FSP] and [Insurer] had been advised many times of the problems and futility
to obtain multiple fixed price quotes for the repairs at some time in the future,
from multiple busy repairers, who each required payment upfront of > $200 (3
hours @ $65- $80hr).”
77. This indicates the cost of obtaining a quote is $250. If the Applicant had
pursued this option, this would have progressed the claim and possibly
avoided the journey to Cardwell if Q accepted the claim and paid the cost of
repairing the vessel at its location.
78. In addition, it would have resulted in the claim being assessed and reviewed
promptly.
79. Accordingly, the Panel cannot accept the FSP breached its duty in its
conduct surrounding the claim.
Failing to inform Applicant of benefits of policy
80. The Applicant has raised a number of arguments regarding this, particularly
about the fact that he did not receive the policy and the FSP, in all of its
communications, never informed him of the following policy benefit:
“If your boat gets into difficulties or is damaged accidentally, we will pay the
reasonable cost of taking acti on to … remove the boat to safety (including
emergency towing) …”
81. The FSP has responded stating that a policy was sent and provided a copy
of a Policy Checklist corroborating this. The Applicant has disputed this
noting this evidence is insufficient in proving the policy was actually sent.
82. The Panel is inclined to accept the Applicant‟s argument to this extent. That
is, the FSP‟s evidence does not of itself provide persuasive support that the
policy was sent. However, the Panel does accept there was refere nce to the
policy‟s existence in the FSP‟s communication to the Applicant. For instance,
in the invoice sent by the FSP to the Applicant on 12 November 2008, there
were numerous references to the policy.
Case No: 286857 Determination Page 14 of 17
83. In addition, the Applicant claims that if he had received the policy, he would
have read it thoroughly, discovered this benefit and sought access to same.
However, the Panel does not accept this based on the following:
The Applicant would have, or should have, been aware the terms and
conditions of insurance cover is normally set out in a policy contract.
Further, there were numerous references to the policy in the FSP‟s
communications to him. However, he made no effort to obtain a copy
despite now stating that he was highly interested in its contents and
would have read it thoroughly.
The policy benefit states that Q will “pay the reasonable cost …” It does
not state that the FSP will actually arrange for the vessel to be towed.
Instead, it implies the cost would still need to be initially borne by the
Applicant.
84. Further, the Panel does not accept the FSP breached its duty in omitting to
inform the Applicant of this benefit. As evident, the FSP believed a copy of
the policy was sent to the Applicant given:
It referred to same in its communication to the Applicant.
The checklist corroborated the policy was sent.
In none of his communications between the policy being incepted and
Event Four did the Applicant ever state, or even hint, that he did not
have a copy of the policy.
85. Accordingly, it was reasonable for the FSP to presume that the Applicant
had the policy or if he did not, that he would have either sought a copy or
enquired with it about the policy coverage.
86. In any event, the policy subject of this dispute is a „pleasure craft policy‟
which is not a prescribed contract for the purposes of 35 of the Insurance
Contracts Act (1984) or the Insurance Contracts Regulations 1985.
87. To the extent that the FSP was required to inform the Applicant of any
„unusual terms‟, in the Panel‟s view even had the FSP failed to provide a
PDS, it was not to the disadvantage of the Applicant in this instance.
88. In addition, there was no reference in any of the Applicant‟s communications
that he was experiencing financial difficulty to enable the FSP to foresee that
this policy provision should be drawn to his attention.
89. The Panel also accepts the FSP‟s submission about the possibility that the
benefit may not even have been applicable. This is due to the fact that for
almost three years after Event One, the Applicant did not seek to transport
the vessel despite appearing to have the financial means and opportunity to
do so. Accordingly, there is an argument that the vessel was not unsafe at its
location given the significant period of time that passed between Events One
& Two and Events Three & Four.
90. The Panel therefore does not accept the Applicant has established the FSP
breached its duty to the Applicant in this regard.
Case No: 286857 Determination Page 15 of 17
Policy Renewal
91. The FSP was first contacted concerning non-renewal of the policy by Q in an
email dated Friday 25 June 2010. The reason given was as follows:
“Type of mooring - swing mooring at Mission Beach, Queensland.”
92. Upon receipt of this, the FSP undertook the following actions:
a. The FSP emailed another pleasure craft insurer (CM) on 1 July 2010
enclosing the survey report dated 21 July 2008 and seeking a
quotation. CM responded later that date enclosing a quotation but
stating cover would only be provided if a full out of water survey was
provided.
b. The FSP attempted to phone the Applicant on 5 July 2010 to seek
instructions. According to the file note recorded:
“Spoke to son - [Applicant & wife] on boat. Send email not able to phone. May
take a couple of days for them to reply.”
c. The FSP sent an email to the Applicant later that day seeking
confirmation that the vessel was still located on a swing mooring at
Mission Beach, enclosing CM‟s quotation and noting a current out of
water survey report was required.
d. The Applicant responded to this in his email dated 13 July 2010. The
email confirmed the vessel was still located on a swing mooring in
Mission Beach. In regards to the out of water survey, he stated it could
not be completed until he returned from Europe on 10 August 2010. He
also queried CM‟s quote and asked the FSP to ascertain if Q would be
willing to insure the vessel until he arranged alternative cover.
e. On that date, the FSP emailed Q‟s underwriting agent seeking an
extension. Q telephoned the FSP later that day stating it would not do
so.
f. The FSP then emailed both CM and another pleasure craft insurer
(AM) on 14 July 2010 seeking a quotation. In this communication, the
FSP informed them that the vessel had sustained some electrical
damage from Event One (this had not been previously notified to CM).
g. AM responded that same day setting out a quotation. Howe ver, it
required a new “out of water” survey and photographs, together with a
rigging report, before agreeing to provide cover.
h. The FSP had a telephone discussion with CM the following day who
confirmed that a survey report is still required. Further, the y would
require confirmation from an electrician that the outstanding repairs
have been addressed before providing cover. This was later
corroborated in an email.
93. Following this, the FSP emailed the Applicant on 15 July 2010 which set out,
in clear and unambiguous terms, the issues in obtaining alternative cover.
This email stated the following of relevance:
Case No: 286857 Determination Page 16 of 17
“… I have to tell you straight up that you have some real problems in gaining
insurance on your vessel past 27/7/2010 - unless some urgent attention is
given to points that are detailed below.
It is appreciated that you are currently overseas but we trust there is someone
in Australia acting in your interests that may be able to address the issues
…
On taking the position up with two alternate insurers that will consider swing
mooring situations, [AM & CM], each have baulked at the pre-existing
damage. Neither will offer terms without an out of water Survey + full details of
the extent of the unrepaired damage.
Both Insurers would be seeking higher premium & excess than has been the
case with [Q] policy but this cannot be quantified until the other aspects are
clarified.
So, where from here?
We have exhausted our options in gaining any form of cover for you after
27/7/10 - if all remains “as is”.
If there is some way you can organise the boat to be taken to Cardwell, prior
27/7/10, for (a) an out of water Survey + (b) as assessment of claim by an
Assessor, we might then be able to negotiate coverage with other Insurers &
progress the claim.
In saying this, [Q] is still to receive a completed Claim Form from you (via
{FSP]) & it is necessary for this to be attended immediately. I understand you
have this required documentation.
We are sorry that we cannot offer more favourable advice but it is hoped the
abo ve information suitably outlines the position.”
94. The Applicant responded the next day stating:
“Thanks for your detailed reply.
The boat simply cannot be taken to Cardwell till I get back.
I will send a more detailed reply later”
95. As evident in the Panel‟s p revious analysis, it is clear the Applicant never
followed through with his email despite being clearly notified that the vessel
was uninsured from 27 July 2010 onwards.
96. The Panel cannot accept the FSP‟s conduct during this process could
constitute a breach of any duty owed given the following:
The FSP only became aware of Q‟s decision not to invite renewal on 25
June 2010.
Although the Applicant indicated this should have been identified
earlier, there is no foundation to this. Section 58 of the Insurance
Contracts Act 1984 (the Act) says an insurer is only required to inform
an insured of this fact 14 days or more before the policy expires. In this
case, Q sent notice more than a month prior.
The FSP approached two reputable pleasure craft insurers shortly after
receiving this communication. Both of these insurers provided
consistent information regarding pre -conditions to cover.
Case No: 286857 Determination Page 17 of 17
The FSP clearly and promptly communicated this to the Applicant when
it ascertained same. In addition, this was communicated 12 days prior
to the policy expiring.
The fact the Applicant was overseas was not something the FSP could
have foreseen given the Applicant never notified it prior to his email
dated 13 July 2010.
Despite returning from Europe, the Applicant did not end eavour to
follow through with the FSP‟s suggested course of action. In particular,
one and a half years passed since the vessel became uninsured and
Event Four occurred.
97. The Panel does acknowledge the Applicant‟s argument that the FSP‟s initial
communication on 13 July 2010 did not indicate that CM actually required
confirmation that the repairs from Events One & Two had to be addressed
before cover would be provided. However, the FSP clarified this in its email
sent two days later and almost two weeks prior to the policy's expiry. Further,
the Applicant sustained no prejudice from this discrepancy.
98. Accordingly, the Panel does not accept the Applicant‟s allegations that the
FSP failed to properly advise and assist him with respect to Q‟s decision to
not offer renewal.
99. In the Panel‟s view no negligence has been demonstrated on the part of the
FSP and it is not required to compensate the Applicant for any part of his
loss.
Determination
100. On the basis of the available information and after carefully reviewing all of
the material, the Panel does not accept that the Applicant has established
the FSP breached any of its duties towards him.
101. As the Applicant has not established any breach, he is therefore not entitled
to any of the remedies he is seeking.