Text of the determination
Case No: 286172 Determination Page 1 of 11
Case Number: 286172
General Insurance – Domestic Insurance – Home Building Insurance – Fire
damage – extent of damage
5 June 2013
Background
1. The Applicants insured their home building under a Home Insurance Building
Policy against loss or damage caused by insured events for $605,000 with a
$300 policy excess.
2. On 23 November 2011, the Applicants‟ locality sustained considerable damage
following the escape of a prescribed burn fire. Properties adjacent to the
Applicants ‟ property were totally destroyed and the Applicants‟ home suffered
damage caused by radiant heat.
3. The Financial Services Provider (FSP) accepted liability for some of the
damage caused by the fire. However, the Applicants contend that the FSP has
denied liability for:
replacement of the entire colourbond roof, gutters, flashing,
polycarbonate sheeting, shade cloth and downpipes;
repair and paint cracks in all external and internal walls;
treat and paint the lintels; and
seal and paint cornice.
Summary of Applicants ’ Position
4. The Applicants are seeking to have their house repaired to what it was prior to
the fire.
5. The fire destroyed two neighbouring properties to the immediate north of their
house. The weatherboard house on the southern side experienced a fire on its
eastern side and an ember caused fire on the northern side.
6. The Applicants were informed by a fire fighter that flames 30 feet high were
fanned by 60km/h winds, as the house next door (six metres away) burnt down.
The fire fighter stated that they could no t fight the fire from their property as the
Determination
Case No: 286172 Determination Page 2 of 11
heat and smoke was overwhelming. The heat was so intense it caused stickers
on their fire appliance to melt.
7. The house to their north literally exploded with the force of the explosion and
the gale force winds, resulting in concrete debris landing on the roof of their
house. Their house was not only showered with concrete debris, it also
received water retardant and ember attacks.
8. Approximately four months after the fire, the FSP appointed a consulting
engineer, „ MCS ‟ , to inspect their property. However, by this time they had
substantially cleaned their property.
9. MCS failed to consider the actual fire damage their property suffered directly
against the garage door, the north-west corner of the house, and windows
broken by the heat. MCS also stated that the downpipes and gutters in this
area are not heat affected. The rear of the downpipe is distorted from heat and
the gutters have several streams flowing from the holes each time it rains.
10. All joins in the guttering are leaking, which the Applicants submit was due to the
extreme heat, embers and concrete debris from the house next door which fell
into the gutters.
11. The solar hot water system on the northern aspect of the roof was destroyed
which is an indication of the heat their property was subjected to. The fact that
metal parts of a two year old solar system had distorted sufficiently from heat to
cause failure means that the temperature the roof was exposed to was
extreme.
12. The Applicants submit that rainwater now leaks into the ceiling cavity, through
the ceiling into the house. The roof leaks are along the ridge capping located
mainly on the north-west corner of the building. This is the area that was most
impacted by the adjoining houses burning down. It is also located in close
proximity to their garage door/retaining wall where the main fire on their
property occurred.
13. They submit that the ridge capping is distorted and slightly raised allowing
water to leak through. They believe that it was either due to the heat of the fire
given its close proximity, or the weight of the water from the aerial dumping that
has caused the damage to the ridge capping.
14. In view of the MCS report and an amended Scope of Works (SOW), the
Applicants engaged a builder, „ BH ‟ , to assess the roof and other parts of their
house. In his report dated 24 April 2012, BH stated:
shade cloth suffered burn marks from embers some of which burnt
through, causing melting and holes in the polycarbonate sheeting below;
the colourbond roof also suffered the same ember attack. The ember
attack is becoming more evident as time goes by as oxidation and
scouring of the coating is starting to show in considerable amounts and
in different places over the roof, some more than others;
Case No: 286172 Determination Page 3 of 11
there are cracks in the walls at window height indicating sufficient heat
to cause movement of the steel lintels which in turn affects the
galvanizing and causes cracking to the structure;
the amount of ash still falling from ceiling cracks at the edge of the
cornice also shows the amount of heat the building had been exposed
to and in turn this causes expansion and contraction.
15. BH considered the following should be addressed:
replace entire roof, gutters, flashings, polycarbonate sheeting, shade
cloth and down pipes;
repair cracks in walls;
repaint cracks in walls; treat/paint lintels;
seal/paint cornice.
16. BH also recommended an engineer be appointed to report on cracking in floor
tiles and comment on the effects from heating of the building.
17. The Applicants also engaged a structural engineer, „ MRSE ‟ , to inspect and
report on the damage to the roof. MRSE inspected the house on 19 April 2012
and stated:
“ Roof inspection requested.
Ember attack has compromised the protective coating of the metal roof
sheeting and is leading to premature rusting. Full roof iron replacement
required.
Heat adjacent to the building has caused metal to expand, cracking render
above windows.
Numerous new cracks within the house were noticed.‟
...
At any place that embers get caught up on a roof, heat in excess of 300◦C
occurs. This destroys the protective barrier of the metal sheeting.
...
The intense heat from the fire shattered windows and have caused steel
lintels to expand and later contract. This has caused cracks inside and outside
along the wall adjacent to the fire zone.
Numerous other cracks were noticed within the house along walls close to fire
zone. The owner states that these are new and progressively appearing.
I have seen this progressive crack appearance in other fire damaged
properties .”
18. The Applicants have provided photographs of their roof taken on 13 July 2012
that show the start of corrosion to the roof where fire related damage occurred
as predicted by MRSE.
Case No: 286172 Determination Page 4 of 11
19. A second photo depicts ash and water stains in the roof cavity which may
provide evidence of the force of the water bombing, or roof damage, that
allowed entry of ash and water.
20. The Applicants submit that in regard to internal wall cracks:
one cornice crack is sufficiently large enough to allow water to leak into
the house;
with the winter rains the foyer has bath mats and a mop to control water
seepage that enters through cracks, even ants are entering which has
never been a problem previously.
21. The FSP‟s original SOW had agreed to repair most of these cracks as the
original assessor and MCS had decided that they were fire related. A second
assessor has also agreed to include the internal wall cracks in the scope of
repair work. Therefore, the Applicants cannot understand why the FSP has now
reversed its decision for these repairs.
22. In addition to previously agreed repair work, the Applicants submit that the FSP
should also indemnify them for:
replacement of the entire colourbond roof, gutters, flashing,
polycarbonate sheeting, shade cloth and downpipes;
repair and paint cracks in all external and internal walls;
treat and paint the lintels; and
seal and paint cornice.
Summary of FSP’s Position
23. On 23 November 2011, the Applicants‟ property was damaged by fire following
the escape of a prescribed fire burn.
24. The FSP arranged for two builders to attend the site and quote on the damage,
and an engineer to attend along with cleaners appointed and arrange
reimbursement of costs that had been incurred by the Applicants.
25. Over the period from the date of the fire on 23 November 2011 to 23 January
2012, cash settlements had been arranged with the Applicants on various items
to assist with their repair process.
26. Following receipt of the two builder quotes, the FSP agreed to instruct builder,
„ RBD ‟, to proceed with repair.
27. A scope of work (SOW) was sent to the Applicants, however, the Applicants
raised issues with various aspects of the SOW and stating that the SOW was
not complete and as such the SOW was not signed off.
Case No: 286172 Determination Page 5 of 11
28. The FSP arranged for its Technical Assessing Manager to attend the site with
the Applicants to review the outstanding items along with determining repairs
that remain in dispute. Agreement could not be reached on items such as the
colourbond roof replacement and cracking to internal walls.
29. The FSP engaged an engineer, MCS, to complete a comprehensive report on
the extent of the damage. The MCS report dated 12 March 2012 made
recommendations of settlement and the FSP has adopted the findings of the
report along with additional repair to the external walls on the left hand side of
the property.
30. The repair to the left hand side of the building is over and above those
recommended by the engineer. Any benefit of doubt to this area of damage had
been passed onto the Applicants.
31. The Applicants did not agree with the findings of MCS and obtained a report
from a local engineering firm and a general builder in the Margaret River region.
32. The FSP‟s offer to settle the claim is based upon the recommendations from
MCS and the FSP has instructed a builder to attend to the repair. The FSP is
willing to offer a cash settlement to the Applicants, however, this has not been
costed as there is no request at this time to proceed with this form of
settlement.
33. However, the FSP has determined that there is insufficient evidence to support
the replacement of the colourbond roof to the home along with repair and
repainting of internal walls and lintels as being damaged by radiant heat as
described by the Applicants.
34. The FSP basis of its offer has been determined in MCS‟s report dated 12
March 2012. These are:
“ 2.c – ...Main dwelling and verandah...there were no visual burn marks from
embers;
2.d.There was no evidence of fire retardant or salt water bombing (FSP is
aware that the Applicants had cleaned the roof previously);
2.e. Reference is made to roof screws being corroded however, this is not due
to fire as a paint seal remains;
2.f. The rear pergola shade cloth and polycarbonate has ember damage
throughout (FSP has accepted liability for this damage);
2.h. The satellite dish remained undamaged;
2.i. PVC downpipe attachments remain unaffected by radiant heat;
3.b.The rainwater tank did not appear to have been damaged;
3.c. The painted weather boards to the loft walls did not bubble or appear to
be affected by radiant heat. ”
35. MCS also reported that there is change to the Applicants‟ roof which is
oxidation to the zinc coating, however, this is due to the proximity to the coast,
age and environmental exposure.
Case No: 286172 Determination Page 6 of 11
36. The FSP submits that there is no evidence that radiant heat has caused
damage to the external brickwo rk based upon engineer MCS‟s findings.
Further, there is no supporting evidence that damage has occurred to internal
parts of the Applicants‟ home.
37. The Applicant engaged a structural engineering company, MRSE, who, in its
report dated 19 April 2012 stated: ‘ ember attack has compromised the
protective coating of the metal roof sheeting and is leading to premature
rusting . Full roof iron replacement required.’
38. The FSP submits that the MCS report does not support this and the only sign of
rusting is to the „tek screws‟ which clearly show corrosion due to age and the
proximity to the ocean.
39. MRSE also reported that numerous cracks were noticed within the house along
walls close to fire zones. The FSP contends that this statement is insufficient to
determine they were damaged in the fire based upon the MCS report.
40. The FSP denies liability for the cost of replacing the roof of the Applicants‟
home and repairs to any damage to external and internal walls , as it maintains
that the damage was not caused by the fire on or about 23 November 2011.
41. However, the FSP maintains its offer to carry out repairs as detailed in its email
to the Applicants dated 30 March 2012. This offer covered:
Rear timber fence;
Rear vegetable garden;
Front rendered wall;
Left-hand side retaining brick wall;
Front garage;
Left-hand side brickwork below verandah;
Wash down external rendered brickwork and glazing on the northern,
southern and western sides of the home;
Water tank pipe work;
Replace garage front door;
Repairs to rear shed;
Rear patio – replace multi-wall roof sheeting;
42. The FSP will also reimburse the Applicants‟ cost they have incurred of $440 for
the report from MRSE.
Case No: 286172 Determination Page 7 of 11
43. The FSP relies on the following policy/contract provisions:
‘Insured events
If you have purchased either Home Building and/or Home Contents insurance as
shown on the Policy Schedule We will cover You and your family for destruction, loss
or damage to the Home building and/or Home contents caused by:
...
(d) FIRE
...
General exclusions
This Policy does not cover:
(a) Destruction, loss or damage caused by:
(i) or attributed to wear, tear, gradual deterioration, lack of maintenance,
defect, error or omission in design, material, product or structural failure,
(ii) mildew, rust, corrosion, rotting or discolouration,‟
Issue
44. Whether the damage to the Applicants‟ home by the insured event fire is
greater than that accepted by the FSP.
Reasons for Decision
45. Due to the nature of the dispute, the FOS has considered it appropriate to
expedite the dispute in accordance with the Operational Guidelines to the FOS
Terms of Reference. Thus, this dispute has not been subject to a FOS
Recommendation and has proceeded directly to Determination. The parties
have been previously advised that a Determination will be issued in this case.
46. The onus of proof is on the Applicants to establish, on the balance of
probabilities, that they have suffered a loss caused by a risk insured against.
47. There has been an exchange of material which the parties rely on. Each party
has had access to the material on which the other party bases its case. As a
consequence it is not necessary to go into all of this material other than when
relevant.
48. In addition to the property damage caused by the fire and accepted by the FSP,
the Applicants submit that the FSP should also:
Replace the entire colourbond roof, guttering and downpipes;
Repair the cracks in the external and internal walls;
Case No: 286172 Determination Page 8 of 11
Replacement of Colourbond roof, guttering and downpipes, rear
polycarbonate sheeting and shade cloth
49. The Applicants‟ maintain that the roof of their home was damaged by ember
attack from the fire and concrete debris from the next door neighbour‟s house
that „exploded‟ while it was burning.
50. During the fire event the Applicants‟ house was water -bombed which the
Applicants submit contributed to the damage to the ridge capping which now
allows water to escape into the roof cavity. Photographs submitted by the
Applicants confirm that water is leaking into the roof cavity.
51. The Applicants engaged structural engineer MRSE and a builder BH to inspect
and report on the damage to their home.
52. In its report dated 19 April 2012, MRSE stated that on inspection it found
considerable evidence of ember attack compromising the roof sheeting. MRSE
also reported that concrete fragments blasted from the adjacent block were
scattered on the roof.
53. MRSE reported that at any place that embers get caught up on a roof, heat in
excess of 300°C occurs, which destroys the protective barrier of the metal
sheeting.
54. In his report dated 24 April 2012, BH stated:
“ Shade cloth on the rear of the pergola shows considerable burn marks from
embers some of which have burnt through and also caused melting of the
polycarbonate sheeting below. Holes in the polycarbonate vary from minute to
100mm in diameter.
It is obvious that the rest of the Surfmist Colorbond roof was exposed to the
same ember attack. This is becoming more evident as time goes by as
oxidation and scouring of the coating is starting to show in considerable
amounts in different places over the roof, some more so than others.”
55. The Applicants also engaged a roofing contractor, „ DCB ‟ , to inspect and report
on the condition of the roof. In his report dated 12 December 2012. DCB stated:
“ SUMMARY
It is evident that this residence was under extreme heat & ember attack from
the northern side of the property. As this inspection was carried out 12 months
after the actual event, the ash deposits and most of the traces of retardant are
very faint. It is still clear that you can see where the embers have landed on
the roof and etched into the colourbond pre-painted protective surface. Rust is
now starting to occur around these areas. The lifespan of this roofing system
has been seriously undermined and in our opinion should definitely be
replaced.... Lastly, with seeing the extent of the corrosion process occurring
after only 12 months, we feel it is important this roof is replaced immediately
to prevent any further dama ged occurring to the residence.”
56. The FSP engaged structural engineer MCS to inspect and report on the
condition of the roof. In its reports dated 12 March 2012 and 15 May 2012,
Case No: 286172 Determination Page 9 of 11
MCS stated that it could not find any evidence of ember or concrete debris
damage to the roof.
57. The Applicants disputed the findings of MCS and in response , the FSP
appointed a consulting forensic and materials scientist firm, „ ZSS ‟ , to report on
the roof. In its report dated 8 March 2013 it stated, in part:
the insured property is approximately 750 metres from the ocean;
the current condition of the roof is consistent with that expected when
exposed to a marine service environment for 12 to 14 years;
the aged original roof sheets are beyond their expected (warranted) life
for the Colorbond finish and accordingly exhibit a very faded look and
the polyester finish is heavily oxidised so it is chalking and it is easily
removed with light abrasion;
there was no evidence of any thermal or impact damage to the roof;
there are a few locations high up near the ridge where there is evidence
of spatter penetration of the colourbond layer to produce brown rust
spots. This is consistent with contact from hot swarf particles as occurs
during roof works or some other localised aggressive agent;
it was not possible to date the localised rust spots and connect them with
the fire;
the effect is far too localised to represent fire ember damage and far too
small in quantity and severity to represent repairable damage that
requires any sheet replacement;
other materials in the roof vicinity such as plastics and paints, which are
highly susceptible to thermal damage from fire debris, did not exhibit any
such damage;
a small section of PVC downpipe at the driveway side nearest the
boundary fence had been distorted by heat;
no other heat damage to roof components were identified.
58. ZSS stated in its report that the Applicants had agreed to withdraw their claim
for the roof. The Applicants deny they agreed to withdraw this aspect of their
claim.
59. MCS agreed that there is evidence of spatter penetration on the roof which has
resulted in rust spots. Although MCS states that it is not possible to date the
localised rust spots , I accept the Applicants‟ expert‟s opinion that embers from
the fire and concrete debris from the exploding house next door caused the
damage to the roof.
Case No: 286172 Determination Page 10 of 11
60. MCS also states that, other than minor heat damage, no othe r heat damage to
roof components was identified. However, a solar hot water system was so
badly affected by the heat that it had to be replaced indicating that the rest of
the roof was subjected to the same extreme temperatures.
61. The Applicants have also submitted photographs of the polycarbonate sheeting
and shade cloth confirming damage caused by falling embers.
62. I am persuaded by the evidence submitted by the Applicants that the roof,
including guttering and downpipes, of their house was damaged by a
combination of ember attack, concrete debris and water bombing.
63. Therefore, the FSP is to indemnify the Applicants for the cost of replacing the
entire roof of the house its guttering and downpipes and polycarbonate
sheeting and shade cloth.
Damage to external and internal walls and cornices and lintels
64. The FSP has accepted liability for the cost of repairs to the external walls on
the western side of the building but it has denied liability for any internal
damage.
65. The Applicants ‟ engineer, MRSE, stated in its report dated 19 April 2012:
“ The intense heat from the fire shattered windows and have caused steel
lintels to expand and later contract. This has caused cracks inside and outside
along the wall adjacent to the fire zone.
Numerous other cracks were noticed within the house along walls close to the
fire zones. The owner states that these are n ew and progressively appearing.”
66. The Applicants‟ builder BH agreed with MRSE that the expanding lintels caused
damage to the structure.
67. The FSP appointed a builder, RBD, to inspect and report on the damage to the
Applicants‟ house. In its report dated 24 January 2012 it included the following
fire damage repairs to be carried out:
Front wholly owned rendered wall;
Left-hand side wholly owned retaining wall;
Front elevation of the garage;
Left-hand side elevation brickwork below verandah;
TV room/kitchen/dining room, stairwell – repair, seal and paint damaged
walls, ceilings and cornices;
Laundry – repair, seal and paint damaged walls, ceiling and cornices;
Bedroom 3 – repair, seal and paint damaged walls, ceiling and cornices.
Case No: 286172 Determination Page 11 of 11
68. The MCS report dated 12 March 2012 reported extensive minor internal
damage although MCS stated that the majority of damage was not caused by
radiant heat from the bushfire.
69. I am of the opinion that the extreme heat from the bushfire did cause some
damage to the exterior and interior of the building. However, in view of the
conflicting reports as to the extent of damage caused by the fire, I consider it is
fair to accept the report submitted by RBD as to external and internal damage
caused by the fire.
Engineer’s costs
70. In response to the FSP‟s appointment of a structural engineer to assess the
damage to the Applicants‟ house, the Applicants, justifiably, also countered by
also engaging a structural engineer. The cost incurred was $440, including
GST, and the FSP should indemnify the Applicants for that cost.
Determination
71. Accordingly I determine that the FSP indemnifies the Applicants for:
a) The cost of replacing the entire colourbond roof of the house, guttering,
downpipes rear polycarbonate sheeting and shade cloth;
b) The cost of repairing any water damage to the interior of the house caused
by rainwater leaking into the ceiling cavity;
c) The cost of completing repairs in accordance with the report prepared by
RBD dated 24 January 2012 and detailed in paragraph 67 above; and
d) Reimbursing the Applicants the amount of $440 for the engineer‟s fee.