Home / Financial Firm (Unknown - Insurer) / Determination 284019

Determination 284019

Claim denied as flood exclusion for foundation and home interior damage

FirmFinancial Firm (Unknown - Insurer)
Decided2013-02-07
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants' home was flooded in January 2011 and the FSP denied the claim as flood damage. AFCA found the early stormwater runoff caused foundation damage the policy covers, so the FSP must contribute 30% of foundation and interior damage and pay the full stormwater loss for outbuildings and ground-level items, with quantum to be assessed and interest if settled in cash.

Damage from stormwater run-off before floodwater arrival is not excluded as flood, so only damage caused by the later river flood falls within the policy exclusion.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 284019 Determination Page 1 of 11 Case number: 284019 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim 4 January 2013 Background 1. The Applicants‟ home and contents in Charlton Victoria were insured under a personal insurance policy issued by the Financial Services Provider (FSP). 2. On 14 January 2011, following extensive rainfall in the area, water inundated the home causing extensive damage. 3. A claim under the policy was denied by the FSP on the grounds the house was inundated sometime in the afternoon by overflow from the Avoca River and Yeungroon systems and as such was excluded from cover provided by the policy. Summary of Applicants ’ position 4. The Applicants have appointed a legal firm to represent them. References to the Applicants in this determination will include their representative. 5. The Applicants submit that stormwater runoff associated with heavy rain fell between 10 and 14 January 2011and inundated their home causing damage to the lower part of the house as well as to numerous items in the shed. The initial inundation occurred in advance of the arrival of floodwater from the Avoca River. 6. The Applicants rely substantially on hydrological reports commissioned by their representative. 7. The Applicants do not dispute the Avoca River burst its banks. However, they submit that any inundation before 5.30pm on 14 January 2011 was caused by stormwater and local runoff and as concluded in the M reports was responsible for damage to the foundations of the house and items in the shed. 8. The Applicants are claiming for damage below the floor level to the house foundations, internal cracking and other damage consequent upon the foundation damage for which the dispute was brought. Determination Case No: 284019 Determination Page 2 of 11 9. They accept the inundation of the interior of their neighbo ur‟s house occurred at about 7.00pm on 14 January and that the interior of their home was likely inundated by floodwater at the same time. 10. The hydrological site specific report provided by M stipulates that shortly before 5.00pm stormwater had reached the concrete slab foundation of the house being two hours before floodwater inundated the home. 11. The rejection of the claim is therefore unreasonable and it should be paid. Summary of FSP’s position 12. The FSP submits: a. The cause for the inundation was overflow from the Avoca River. b. This comes within the policy definition of „flood‟ and is therefore excluded from cover. c. It has complied with Section 35 of the Insurance Contract Act 1984 (the Act) Cause of inundation 13. The FSP relies substantially on a hydrological report of WT commissioned by it. WT established the home of a neighbour of the Applicants was inundated at about 7.00pm and based on this information concludes the Applicants‟ home was initially inundated in the evening of 14 Ja nuary 2011. 14. The FSP considers it is clear from the conclusion of the WT report, the location of the property to the east of Armstrong Street and the timing of the event, that any water which entered the risk address on the evening of 14 January 2011 must have been overflow from the Avoca River. 15. The FSP relies on the following terms of the policy: “Words with special meaning “Flood” means the inundation of normally dry land by water escaping, or being released from, the normal confines of a reservoir, natural watercourse or lake, (whether or not they have been altered or modified). Flood also includes water discharged from any sewerage or waste water systems due to pressure induced by flood water. ... Accidental Damage Cover We will pay for Accidental Loss or Damage to your Buildings or Contents at the Address other than Occurrences or items referred to in “What you are not insured for.” ... What you are not insured for Case No: 284019 Determination Page 3 of 11 ... 2 Loss or damage to your property caused by: a. Flood. ...” Issues 16. Whether the FSP was entitled to deny liability for damage to the foundations and related damage to the Applicants‟ home and to items in the outbuildings. Reasons for decision 17. Due to the complex nature of this dispute, FOS has considered it appropriate to elevate the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. The dispute has not been the subject of a FOS Recommendation and has proceeded direct to Determination. 18. The decision had been made by a Panel consisting of an Ombudsman, a representative with extensive experience in the insurance industry and a representative with extensive experience in consumer claims. 19. There has been an exchange of material between the parties. Each party therefore is aware of the issues and has had the opportunity to respond. 20. Prior to arriving at a determination, the Panel has read and considered all the material submitted by the parties to FOS. Representatives of FOS have also visited Charlton and spoken to residents. In this matter a site inspection was conducted by the Panel Chair Ombudsman, assisted by another member of the Panel on 11 December 2012. Also present was the female Applicant and a representative of the FSP. Prescribed contract 21. By letter dated 21 June 2011 to the FSP, the Applicants state that the FSP failed to provide them with a policy document for the renewal period in which the loss occurred. They argue that as such, they are entitled to the benefits available according to the „standard cover‟ prescribed by the Insurance Contract Regulations (IC R). 22. The FSP responded to the issue in its letter to the Applicants dated 18 July 2011. The Applicants‟ submission to the Service does not, however, again raise this matter. 23. The issue will therefore not be determined by the Panel. 24. However, for the sake of good order the Panel concurs largely with the arguments put forward by the FSP in its notice of response. In particular that the Applicants were provided with the policy document in 2007 and having provided the PDS, the FSP has complied with the legislation. Case No: 284019 Determination Page 4 of 11 25. The FSP asserts the terms of the policy have not changed in the period since then, to the time of renewal of the policy commencing on 25 August 2010. 26. Section 35 of the Act is relevant. Section 35 of the Act provides that, where a claim is made under a prescribed contract and the event giving rise to the claim is a prescribed event in relation to the contract, an insurer may not refuse to pay an amount equal to the minimum amount of cover set out in the regulations made pursuant to the Act unless it can prove that before the contract was entered into, the insurer clearly informed the insured in writing of the relevant provisions of the contract, or that the insured knew or a reasonable person in the circumstances could be expected to have known of such provision. 27. Section 35 of the Act does not impose on an FSP a duty to provide a policy document to the policyholder on each renewal of the policy. Until such time as the terms of the contract are altered, the FSP is deemed to have clearly informed the policyholder of the policy terms by provision of the policy at inception of the contract. Sections 11(9)(b) and sections 11(10)(a) and (c) of the Act pertain in this regard. 28. Accordingly, the FSP is entitled to rely on the terms of the policy issued to the Applicants in 2007, subject to the policy terms being clear and unambiguous. 29. After examination of the policy the Panel is satisfied that the relevant terms of the policy satisfy that criteria. For these reasons, the Panel accepts the FSP is entitled to rely on the relevant terms of the policy in so far as they apply to this dispute. Water inundation of the Applicants’ property 30. The Panel has been provided with copies of various hydrological reports obtained by the FSP and the Applicants. As these documents have been exchanged it is not intended to recite the details in full in this determination. The Panel will, however, summarise the reports in relation to the information relevant to the issues disputed in this matter. Hydrologist WT report dated 19 April 2011  Historically the town floods on both sides east and west with an area remaining flood free through the centre of town along the St Arnaud- Charlton Road.  Heavy rain fell in the area between 10 and 14 January. The largest fall was recorded at 9am on Friday 14 of January 2011.  The most intense rainfall fell on the morning of 11 th and early morning on the 13 th as shown on the charts (figure 7.4).  The peak flood level of 8.05m was reached early morning on 15 th January being at least 2 days after the most intense rainfall. Case No: 284019 Determination Page 5 of 11  The volume of water suggests either the Yeungroon Creek transferred flows across the flood plain upstream of Charlton or the Avoca River pushed more water into the floodplain upstream of the town.  Given the timing of flooding on the eastern edge of town was similar to the gauged readings, this suggests the Yeungroon Creek and Avoca River flows merged to become one system.  Flow depths in Yeungroon Creek were not expected to impact anywhere west of Kaye Street.  Waters from Yeungroon Creek east of Kaye Street would have been up to 150mm deep on the east side of Kaye Street and between 0.5m and 1m deep further to the east between there and Back St and Arnaud Rd.  After this, flows in Yeungroon Creek began to subside and the Avoca River increased.  From around 5pm on 14 January local reports say the river began to rise rapidly.  From around 6pm houses in the town were inundated with the river peaking in the early hours of 15 January.  The Avoca River peaked at 8.05m resulting in widespread flooding of the town and inundation of multiple properties. A large portion of the town flooded about 12 hours after the last significant rainfall.  Any flooding after lunchtime can be directly attributed to the Avoca River flooding as Yeungroon Creek had peaked earlier in the morning. Hydrological report “M dated 3 November 2011 commissioned by the Applicants Rainfall  The highest rainfall was 15mm per hour from 1700 to 0800 on 13 January 2011. Rainfall rates were persistently high from 2300 hours on 13 January to 0600 on 14 January. No rain fell after 0800 on 14 January 2011.  The radar data for Charlton indicates the rainfall was highly concentrated in short duration bursts. The rainfall which produced the 15mm/hour actually occurred over a period of about 12 minutes.  This situation is similar for the rainfall over night on 13-14 January.  The rainfall intensities in these bursts are much bigger than the recorded hourly rates. Overflow from local drainage systems  Given the intensity of rainfall which was much more than hourly rainfall rates, overflow from local drainage systems and culverts was highly likely. Especially given that the drainage system was already close to capacity from earlier rainfall bursts. Case No: 284019 Determination Page 6 of 11  The timing of overflow would correspond closely to the timing of the rainfall.  The first possible incident of stormwater drainage overflow would have occurred around 0700 on 13 January 2011. Any of the intense rainfall periods recorded between 13 and 14 January could have been responsible for overflow of stormwater drainage systems. The greater probability being from midnight to 4 .00am on 14 January.  Direct overflow is less likely after this time.  Without augmentation from other sources stormwater drainage overflow would be short lived. Runoff from surrounding areas  There were two possible sources of runoff. Runoff was possible from Charlton which does not enter the drainage systems and runoff from surrounding rural areas.  During periods of heavy rainfall bursts, water would have overflowed and contributed to surface runoff. Without augmentation from other sources stormwater drainage overflow would have been short-lived.  It is highly likely that rainfall which fell on 13 and 14 January 2011 was saturation overland flow and would have led to inundation of Charlton on 13 and 14 January before floodwater from the Avoca River entered the town.  Rain water falling south and east of Armstrong and High Streets will tend to move east; with water to the west and north tending to move to the river.  Water runoff as overland flow would concentrate water in the eastern part of Charlton.  The combination of surface runoff from the surrounding area being directed toward east Charlton combined with periodic overflow from drainage systems in other parts of the town would lead to inundation by stormwater and locally derived surface water on the morning of 14 January.  That inundation from locally derived stormwater run-off occurred, rather than Avoca River water, is further supported by the changing sediment loads of water seen in C harlton. Clear water  When the Avoca River overtopped its banks and Charlton was inundated by floodwater the source of that water can be clearly seen because of its high sediment load. Case No: 284019 Determination Page 7 of 11 Flooding from Avoca River  Minor flood level was reached at 0400 on 13 January. Moderate flood levels were reached at 2045 on 13 January 2011. Major flood level was reached at 1715 on 14 January 2011.  Significant inundation of Charlton from the Avoca River did not begin until late afternoon on 14 January and became more severe through the evening and night. Some outlying parts of Charlton would have been inundated mid-afternoon. Summary  Depending on the exact location of properties, they will have begun to be inundated from the Avoca River overflow sometime in the afternoon and early evening of 14 January 2011.  Any property inundation from runoff before this time, particularly corresponding to those times when periods of heavy rainfall occurred on 13 and early morning on 14 January 2011, could not have been caused by inundation from the Avoca River.  It is possible that inundation could have been caused by stormwater/intense rainfall runoff on 13 and early on 14 January 2011.  Inundation from stormwater accumulating in eastern and southern Charlton is probable on the night of 13/14 January 2011 and early morning/early afternoon of 14 January 2011. Hydrological report M dated March 2012 Major flood level  Major flood level in Charlton was reached at 5.15pm on 14 January 2011 and is the point at which water begins to overtop the bank and spill into town. Water has to rise above this level for widespread inundation from the river to occur. There is also a time lag between water overtopping the bank at this location and rising flood water moving across town.  This indicates significant inundation from flood water probably occurred after 5.15pm on 14 January 2011.  Eye witness reports in the east of town describe a rapid rise in water levels and a change from clear to sediment laden water at about 6pm on 14 January.  This is a reasonable estimate of the time delay between the river reaching major flood level and the flood wave moving across town. S ite report at Applicants’ property  The configuration of the road junction (Learmonth Street and High Street) means that if the stormwater drain is blocked or full, water Case No: 284019 Determination Page 8 of 11 ponds above and beyond the drain increasing depths further up Learmonth Street.  Inform ation provided by the Applicants‟ neighbour indicates the open gutter drain in front of the property was overflowing at 4.30pm on 14 January but had not covered the footpath. Shortly before 5pm water levels rose, reaching the concrete slab forming part of the foundations of the Applicants‟ house.  Given the lawn was inundated and water was surrounding the foundations of the house by 5.00pm it is likely that the first phase of inundation was from locally sourced stormwater.  By 7.00pm on 14 January water was shin deep in the neighbour‟s property.  Any damage to the lower part of the house (the slab foundation) can therefore be ascribed to stormwater. Summary 31. The FSP seeks to rely on a clause in the policy to deny the claim and given the policy provides „Accidental Damage‟ coverage, it therefore has the burden of establishing, on the balance of probabilities that the terms of the relevant clause apply to defeat the claim. 32. The timing of the initial inundation to the interior of the Applicants‟ home estimated to be at about 7.00pm on 14 January is not in dispute. According to the M report, water was shin deep in the neighbour‟s home at 7.00pm on 14 January, thus indicating water entered the Applicants‟ home before 7.00pm on that day. 33. The Panel is satisfied that ul timately the Applicants‟ property was flooded by water from the Avoca River. Given the terms of the policy, the Panel accepts that water from the Avoca River is properly categorised as flood water and excluded from cover provided by the policy. 34. The Applicants claim the initial inundation of their site including over the foundations of the home and into the shed was surface runoff rainwater and responsible for the damage claimed. The central issue for determination is, therefore, the time of first inundation of the site to the extent that water saturated the foundations and entered the shed. 35. The evidence in relation to the source of the water which first inundated the Applicants‟ property is divided. The Panel accepts the authors of the reports were highly competent professionals and well qualified to assess and report on the likely source of water which inundated the Applicants‟ property. 36. After careful analysis of the material the Panel considers the reports by M are persuasive and may be relied on for the p urpose of this dispute. The M reports focussed on the influence of surface runoff rainwater on flooding mechanisms in the town. Additionally, the findings in the M report of March 2012 were based on a site inspection of the Applicants‟ property. Case No: 284019 Determination Page 9 of 11 37. The M report confirmed stormwater would have played a major role in the flooding in the town. Stormwater from the east and south east of the town would have inundated many properties before the river overtopped sometime after 5.15pm on 14 January 2011. 38. M report further observed a gradual rise in clear local water occurred up to about 5.30pm on 14 January 2011. Sometime after 6.00pm a rapid rise associated with inundation from the river began. 39. The evidence gathered from this site visit is consistent with evidence considered in respect of many other matters following the January 2011 floods in Charlton. Particularly, some expert evidence has concluded that the inundations occurring from the morning of 14 January 2011 was in fact water overflowing from a watercourse and therefore, flood. Conversely, other expert evidence has concluded that the early inundations, at least up to 5.00pm on that day, are more properly characterised as stormwater. 40. Having reviewed all of the available expert evidence and having carried out many site visits in the town, the Panel has determined in a number of previous disputes before it that water flow from the south and east of Charlton on 14 January 2011 can be properly characterised as stormwater runoff (refer disputes numbers 238492 and 279236) at least until about 5.15pm on 14 January 2011, following which the Avoca River reached its major flood level and floodwater from the river started to inundate properties in the town. 41. The extent to which individual properties would have been inundated i nitially by stormwater and then by floodwater would depend on each property‟s location, the topography of the immediate area and timing. 42. The Panel is satisfied that M‟s conclusions are supported by the information obtained at the site visit on 11 December 2012. 43. The Panel established that the maximum height of water inundation was approximately 800mm, which would equate to approximately 250-300mm inside the house, which is estimated to be approximately 500mm above ground; there are numerous tanks (with motors at ground level), sheds and a garage at the back of the property all of which are approximately at ground level. Along the side of the house are air conditioners/refrigerators and water tanks, similarly at approximate ground level. 44. Discussion with the female Applicant revealed the Applicants accept that damage from water inundation to the interior of the home and the contents therein arose from the policy excluded event of flood; however, it is the Applicants‟ contention that the initial stormwater run -off caused substantial damage to the ground level foundations of the home and by implication everything outside the home as described above, which also reside at the same level as the house foundations. 45. The site inspection further revealed the Federation home, albeit built in about 1910, was very well maintained and in very good condition. According to the Case No: 284019 Determination Page 10 of 11 female Applicant the interior walls of the home used to be straight, level and flat, but since the stormwater allegedly affected the foundations, the interior walls have cracked significantly, with doors unable to close as they are out of square. The site inspection confirmed significant cracking and bulging in some interior walls and the inability to close doors. 46. The Panel notes the property is in close proximity to Armstrong Street. From the many site visits conducted by the Panel to Charlton, it is aware the area was particularly susceptible to stormwater run-off and accordingly it determines the ground level around the house was, on the balance of probabilities, affected by approximately 200mm of stormwater run-off prior to the arrival of flood water from the Avoca River. Furthermore, the female Applicant indicated at the site inspection that her husband left the property at approximately 10.00am on 14 January 2011, at which time water was already pooling in the property‟s grounds. 47. It has been the Panel‟s practice, when contention exists between hydrologists as to levels and timing of inundation, to place probative weight upon credible eyewitness accounts, as being determinative of the issues in play. In this instance, the site inspection established to the Panel‟s satisfaction the female Applicant‟s account of her husband‟s timing of departure and water inundation as credible and accordingly it determines, on the balance of probabilities, that stormwater run-off, sufficient in time and quantity pooled around the house for long enough (probably at least 8 hours) to soak the underlying soils thereby leading to instability in the founding soils and ultimately causing significant damage to the foundations of the house, which in turn caused the damage to the home‟s interior walls and doors. 48. As stated above, the policy provides cover for accidental loss or damage. Damage caused by stormwater is not excluded from the cover. In this case the Panel accepts that the policy will respond to any damage to the home‟s interior that is attributable to the foundations‟ shifting as a result of prolonged exposure to the initial stormwater; albeit, the Panel also acknowledges, as there was a subsequent flood inundation, not all of the damage to the house interior and foundations can be attributed to the initial stormwater. In these circumstances, the Panel, pursuant to its mandate of doing what is „fair in all the circumstances‟, determines the FSP is to contribute 30% of the cost of rectifying the damage to the home‟s foundations and the resultant damage to the interior walls and doors. 49. It follows, therefore that in respect of damage to the numerous tanks (with motors at ground level), sheds and a garage (and contents therein) at the back of the property all of which are approximately at ground level and air conditioners/refrigerators and water tanks at the side of the house, similarly at approximate ground level, the determined level of 200mm of stormwater run-off would have caused very substantial damage and the policy accordingly will respond, albeit the quantum in respect of that damage will be the totality of the assessed loss arising from 200mm inundation and not the restricted 30% as determined for the house foundations and interior. Case No: 284019 Determination Page 11 of 11 50. As no Scope of Works has been carried out for either matters referred to in paragraphs 48 and 49 above, the FSP is directed to task an appropriate expert in relation to an assessment and costing in respect of paragraph 48. In respect of paragraph 49, it should engage with its usual loss assessment process. The parties are asked to work cooperatively to settle this part of the dispute. In the event they are unable to agree within 30 days of acceptance of the Determination, the Panel will determine the amount. Determination 51. On the basis of the available information the Panel determines: a. The FSP is liable for 30% of the damage to the foundations and structural damage within the home‟s interior. The FSP will engage an appropriate expert capable of identifying and costing this damage. b. The FSP is liable for damage pursuant to paragraph 49 abo ve, although not limited to a 30% contribution. c. In the event a dispute arises in relation to quantum, the matter may be referred back to the Panel for determination. d. Should the FSP settle any part of the claim by cash payment, interest is payable in accordance with section 57 of the Act from 1 March 2011 being the date on which the claim was denied until payment is made.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.