Determination 282636

Rectification of defective kitchen floor tiles and tile installation declined

FirmFinancial Firm (Unknown - Insurer)
Decided2013-04-23
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$500
Non-financial loss—
Amount claimed$5,500
SourceAFCA PDF

Summary

The applicant sought $5,500 to replace kitchen floor tiles that were stained and poorly installed, after the FSP declined rectification. AFCA ordered the FSP to have an independent contractor rectify the installation and stained tiles, with cash settlement if that costs more, and $500 if the rectification is carried out.

The lifetime guarantee of workmanship on repairs authorised by the insurer covers defective installation, while the tile choice and wear and tear exclusions do not relate to the workmanship defects.

Issues

Subjects and remedies

home or building damagepay compensationrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 282636 Determination Page 1 of 9 Case number: 282636 General Insurance - Domestic Insurance - Home Building - Service – faulty works – declinature of additional works 09 April 2013 Background 1. This is a review of a Recommendation by the Service’s Case Manager dated 17 January 2013. As noted below, an impasse has developed as between the parties and in the interest of obtaining finality, the matter has been referred to me for Determination. 2. The relevant background, summaries of the parties’ position and the issue to be determined are set out in paragraphs 1 to 20 of the Recommendation and I will restate same. “1. The Applicant and a co-insured hold a Home Building and Contents Insurance Policy with the Financial Services Provider (FSP). The policy covers the building for insured events. 2. On 4 October 2011 the Applicant lodged a claim for damage to the property arising from a water filter that had failed. The FSP accepted the claim and arranged for repair works to the property. 3. The Applicant then noted there were marks on the kitchen tiles which could not be removed, there was grout/silicone left on the tile and there was a general unevenness in the grouting. 4. The FSP has declined to perform rectification works for the kitchen tiles on the basis the Applicant chose the tile, the tile is not faulty and the tiling work is not defective. 5. The Applicant disputes the FSP’s declinature of rectification woks on the basis the tiling was defective and the tile itself is defective. Summary of Applicant’s position 6. The Applicant has enclosed a copy of the FSP’s expert report from “S”. The report provided by S is from a building consultant who is also a licensed builder. I note the following from this report:  The property is generally considered to be in good condition for its age. Determination Case No: 282636 Determination Page 2 of 9  S observed smudge like staining, similar to an oil stain, throughout the living and kitchen areas. This type of porcelain tile can have many microscopic holes in the body. The polishing process removes a fine layer of the tile’s surface, just as using sandpap er on wood does. This process can take the tops off some of those holes, thus exposing them. Liquid borne contaminants added to the tile surface during cleaning either as part of the installation or subsequent maintenance can become trapped in these small pores creating a smudged or hazy appearance.  S notes the Australian Standard 3958.1-2007 Ceramic tiles Part 1: Guide to Installation of ceramic tiles and quotes the following from same: “Penetrating sealers are primarily used to reduce the adhesion of contaminants and restrict the entry of staining materials on the surface and grout joints of a tile. Penetrating sealers do not generally alter the appearance of the tiles or affect their slip resistance. The selection of the type of penetrating sealer will usually involve its ability to repel oils or water-based contaminants, or both. Penetrating sealers are generally used with more porous tiles; however, they are often beneficial in protecting polished porcelain type tiles from staining”  S was of the opinion that the markings to the surface of the floor tiles are the result of the polishing process leaving open micro pores which have collected contaminants as the result of the installation process which could have been minimised by the application of a penetrating sealer.  S has provided his observations of lipping and issues with the grouting. After noting the Australian Standards 3958.1-2007 and Australian Standard 3958.1-2007, S stated it was his opinion that there were several instances of defective building work in the installation of the floor tiles including instances of lipping and incorrect grout installation. 7. The Applicant is dissatisfied with the FSP’s decision relating to the tiles. The Applicant states that an FSP employee “AB” stated that the finis h and stains on the tiles were not acceptable and the FSP would rectify them even if this included replacing the tiles. 8. The Applicant notes the FSP’s report from “HGBS” and notes it is a trading name for a sole trader. Further, the tiles are made in China rather than Italy as claimed. The report from HGBS suggests more effort is required to clean the tiles. However, the FSP’s builder “R” has already attempted using a stripping product and the Applicants have also used domestic floor cleaners without success. 9. The Applicant submits that S has clearly identified workmanship issues with the tile installation and that the tiles should have been sealed as per Australian Standards. 10. The Applicant acknowledges that he picked the tiles but confirms this was the extent of his dealing with the tile supplier. The carriage of the matter in relation to the warranty claim remains with the FSP and R. The Applicant contacted Fair Trading who informed him he had no case against the tile supplier because he did not conduct business dealings with it. Case No: 282636 Determination Page 3 of 9 11. The Applicant seeks the replacement of the tiles and installation of those tiles by a tiler of his choosing. The Applicant has obtained a quotation (not supplied) for $5,500 including GST. Summary of FSP’s position 12. The FSP relies on the following policy terms and conditions: “What we don’t cover Loss, damage, injury or death arising from: - Rust corrosion, gradual deterioration, depreciation, wear or tear ... - Mechanical, structural or electrical failure of an item ... Lifetime guarantee We provide a ‘lifetime guarantee’ when your home is repaired or rebuilt by one of our preferred repairers or builders. This means: - We guarantee the workmanship of repairs that we authorised for the lifetime of your home - We will fix any defect caused by poor workmanship We will decide on what needs to be done to fix any defect When you’re not covered by this guarantee This guarantee does not apply to: - Repairs you authorised yourself - Loss, damage or failure of any electrical or mechanical appliances or machine - Wear and tear that is consistent with normal gradual deterioration of your home.” 13. The FSP relies on report dated from HGBS and I note the following from this report:  The marks on the tile are alum dust. This dust marking would have occurred as the tiles were being moved along the conveyor belt during the manufacturing process. The dust is deliberately applied to prevent tiles sticking and should be removable by cleaning agents.  The tiles laid were made in Italy and are suitable for domestic application.  The tiles are matt in texture and light in colour so dirt stains are more visible.  In relation to workmanship of the tile installation complies with Australian Standards. I note HGBS quotes Section 5 of AS3958.1- 1991 of the Australian Standards. Case No: 282636 Determination Page 4 of 9  The tiler used adhesives, priming and grout from the one manufacturer and complied with the manufacturer’s directions and recommendations.  The tiles show no fault in shade, calibre and its grade.  HGBS recommends a scrubber be used to remove the stubborn stains. 14. The FSP has enclosed claim records from which I note the following:  The records indicate the Applicant agreed to a replacement of the existing slate tile with a cheaper ceramic tile.  R arranged the tiler.  An email on 12 April 2012 from the Applicant to the FSP stated the tile supplier had reviewed the tile installation and stated it was a poor job. Further, that all the tiles would need to be removed and replaced.  File record of 12 April 2012. The FSP has spoken with the tile supplier which advised “ ....researching what can be done to clean the glue etc off the tiles and if this cant (sic) be done the tiles affected can be taken up and replaced.”  On 23 April 2012 there is a notation that the works outstanding included booking a tiler to clean up tiles with a special product, do expansion joints again and replace chipped tiles. Further, the tile supplier advised he attended the client (Applicant) stated if product was not available they could cut out and replace the tiles.  An email dated 2 May 2012 from the tile supplier states that: “After inspecting the tiles I have found that it isn’t a fault with the tiles but there are silicone residue marks left on the tiles, if the tilers are unable to clean the residue of (sic) the tiles the tiles will have to be replaced, there are about 4 boxes of tiles that are left on the site that can be used.”  A further email from the tile supplier stated the following: “This is a problem between [R’s name] and the [Applicant’s name], as we sold the tiles to [R’s name] and we didn’t lay the tiles. We supply tiles we don’t lay them as we do not and never have employed tilers to work for us. [R’s name] tilers laid them, We only went out on site to look at the tiles because they thought it was a fault in the tiles that we supplied.”  Record dated 11 May 2012 indicates AB of the FSP followed up with the Applicant regarding cleaning of the tiles. The Applicant informed that a couple of tiles were cleaned but after drying the staining came back. AB records the following in this record: “I apologised for the inconvenience and advised we wanted to completed (sic) the work satisfactorily and unfortunately it will take some time. Our insured asked what happens if they don’t clean up properly. I advised if this is the case we may need to take the effected tiles out and replace them.”  Record dated 16 May 2012 from another FSP employee “L” regarding a physical attendance at the property. I note the following from this: Case No: 282636 Determination Page 5 of 9 “I queried if the tiles should have been sealed – OI and [tiler’s name] (tiler) advises No the tile company [tile supplier’s name] advised that the sealant was inbuilt in the tile and did not need sealing once laid. ... It appears to me that anyone walks on the tile a built (sic) appears to forming inside the tile which leaves a dirt mark over the tiles if anything even water is dropped on the tile there is a mark from it that will not clean successfully...believe this is either a fault in the tile itself or the type of tile chosen by insured himself and it is not suitable ... OI wants only the tiles to be cleaned with the tiler will complete today he is aware that he has to return at some stage to take up approximately 2 tiles and replace these and to redo the silicone joints”  Record dated 24 May 2012 by L. L appears to have recorded the telephone notes later as she was in Sydney training. L received a call from S who informed her that the type of tile chosen by the Applicant was not sealed on the back and any moisture from the glue is coming through and showing on the tiles also any moisture dropped on the tiles near the grout will go through and flow to the back of the tile causing marks. S intended to speak with the manufacturer.  Record dated 29 May 2012 indicates the FSP had received the report of S. The record notes that the sealant was supposed to be inbuilt in the tile and did not need sealing once laid. The Applicant indicated this was one of the reasons he chose the tile.  Email dated 29 May 2012 from R indicates it was also informed by the tile supplier that the tiles were sealed in the factory and it would make no difference applying a sealer.  During a telephone call with S on 31 May 2012, the FSP was informed that the opening of the micropores occurred during the making process and that S was aware of this “happening all over the place”. Further, the tiles were made in China even though they are sold as Italian tiles.  On 1 June 2012 the FSP rang R and asked them to enquire at the tile supplier in regards to claiming on the warranty for the tiles. R advised it would do so and get back to the FSP.  On 3 July 2012 the FSP rang the tile supplier and was informed this matter was with R and that they would need to go through them. 15. The report from S and HGBS together with information from the tile supplier identified the problem with the tile was staining which was an inherent manufacturing result. Accordingly, the policy does not respond by way of replacement or rectification works. 16. The policy excludes loss or damage arising from the structural failure of an item. The exclusion applies as the tiles are suffering from a fault which allows contaminants to build up. 17. The Applicant has failed to demonstrate that the loss or damage caused by the faulty tile was the result of faulty workmanship or such other cause which enlivens the lifetime guarantee under the policy. Case No: 282636 Determination Page 6 of 9 18. The FSP has not received any evidence that supports the Applicant’s claim for loss or damage. 19. The FSP considers it has fulfilled its policy obligations to the Applicant under the policy and that the Applicant should refer back to the tile supplier. Issue 20. Whether the FSP was entitled to decline the Applicant’s claim for rectification of the kitchen floor tiles ” . Reasons for decision 3. There has been a full exchange of information and each party has had the opportunity to address the issues that have been raised. I have read all of the exchanged material and I have considered the parties submissions and I have considered the exchanges as between the parties and the Service following the Recommendation. 4. In making her Recommendation, the Service’s Case Manager stated her reasons and Recommendation in paragraphs 23 to 43 and I will restate same. “23. After reviewing the materials provided by each party I consider that there are two main elements to the Applicant’s claim regarding the kitchen floor tiles. These are the installation of the tiles and the tiles themselves. I will review each of these issues separately. Tile Installation 24. There are two expert reports before me regarding the installation of the tiles which are quite contrary to one another. 25. S has provided his observations of lipping and issues with the grouting. After noting the Australian Standards 3958.1-2007 and Australian Standard 3958.1- 2007, S stated it was his opinion that there were several instances of defective building work in the installation of the floor tiles including instances of lipping and incorrect grout installation. 26. In contrast HGBS stated the workmanship of the tile installation complies with Australian Standards. I note HGBS quotes Section 5 of AS3958.1-1991 of the Australian Standards. 27. I note that S has provided his qualifications within the report but HGBS has not. Accordingly, it is difficult to determine whether HGBS has the same, more or less qualifications than S. 28. It is further of concern that whilst S has quoted the Australian Standard with the year 2007, that HGBS appears to have quoted from the 1991 version of the standards. It is unclear what changes have been made to the Australian Standards in relation to the installation of tiles, however any consideration of Case No: 282636 Determination Page 7 of 9 the tile installation should have been made with the Australian Standards applicable at the time installation. Due to the date of installation of the tiles it would appear that a 2007 version of the Standards would be more contemporaneous than a 1991 version. 29. Given these factors, I prefer expert S’s report over that of expert HGBS. I therefore accept that the installation of the tiles was indeed faulty due to the grouting and lipping of the tiles. 30. The policy contains a lifetime guarantee for workmanship. As the workmanship was defective the FSP would be liable to rectify this faulty workmanship. It would appear that none of the exclusions relied upon by the FSP are applicable to the issue of installation as they refer to wear and tear, deterioration or structural failure. Further, the exclusions provided in the lifetime guarantee of works do not apply given the repairs were not authorised by the Applicant and the loss does not arise from electrical/mechanical failure or wear and tear. 31. It is not clear to me whether the expansion joints were installed as stated within the claim records of the FSP. If the expansion joints have not yet been installed within the floor tiles subject of this dispute, then I consider these works have already been agreed to by the FSP and should be attended to. The tiles 32. The information provided by expert HGBS is that the tile shows “no fault in shade, calibre and its grade”. HGBS believed the markings on the tiles were from alum dust which would have occurred during the manufacturing process. HGBS believed that the stain could be removed via a scrubber. HGBS stated that the tiler complied with the manufacturer directions and recommendations. It is unclear to me whether HGBS knew that cleaning of the tile had already been attempted and whether this would have altered its opinion regarding whether the tile was in fact not faulty. 33. S was of the opinion that the markings to the surface of the floor tiles are the result of the polishing process leaving open micro pores which have collected contaminants as the result of the installation process which could have been minimised by the application of a penetrating sealer. 34. The Claim record dated 11 May 2012 indicates AB of the FSP informed the Applicant “Our insured asked what happens if they don’t clean up properly. I advised if this is the case we may need to take the effected tiles out and replace them.” 35. I further note the claim record dated 24 May 2012 by L. S informed L that the type of tile chosen by the Applicant was not sealed on the back and any moisture from the glue is coming through and showing on the tiles also any moisture dropped on the tiles near the grout will go through and flow to the back of the tile causing marks. S intended to speak with the manufacturer and it appears that S later became aware of many similar claims. 36. The claim records also show on 16 May 2012 and 29 May 2012 that L had queried whether the tiles should have been sealed. L was informed that the tile had been chosen because it was supposed to have inbuilt sealing. The Case No: 282636 Determination Page 8 of 9 FSP’s builder, R, also informed t he FSP that the tile supplier stated that due to sealing in the factory that it would make no difference to apply a sealer. 37. On 1 June 2012 the FSP rang R and asked them to enquire at the tile supplier in regards to claiming on the warranty for the tiles. R advised it would do so and get back to the FSP. On 3 July 2012 the FSP rang the tile supplier and was informed this matter was with R and that they would need to go through them. 38. Both parties have alleged or provided evidence that they have been unable to claim on the warranty for the tiles. There is insufficient evidence on this point as it is unclear what the result of R’s investigation with the tile supplier was. 39. It is apparent that the tiles were not properly sealed as alleged by the tile supplier. I accept the opinion of S that the manufacturing process of polishing created micropores. Further, that the: “...micro pores which have collected contaminants as the result of the installation process which could have been minimised by the application of a p enetrating sealer.” (my emphasis added) 40. It appears that the tiles themselves were stained during installation and due to the non-application of a sealer. Whilst I accept that the Applicant and R (as well as its tiler) have received incorrect advice from the tile supplier, it does not abrogate the responsibility of the FSP’s authorised repairer/tiler for the issues caused during installation. S has indicated that a penetrating sealer could have minimised the issue caused which is part of the installation pro cess. I do not consider that the Applicant’s choice of tile relevant to the workmanship. Similarly, the exclusions relating to wear and tear and structural failure do not relate to the workmanship aspect of the installation. 41. The Applicant has sought $5,500 but has not provided any itemised quotation regarding these works. There is insufficient evidence that all the tiles need to be removed and replaced. The cash settlement owed to the Applicant would be the cost of rectification of the tile installation and replacing the stained tiles together with the application of a preventative sealant. If these works are more expensive than the replacement of the entire area, or no party will take on the rectification work, then the Applicant would be entitled to the full replacement. Recommendation 42. On the basis of the available information I recommend that the FSP arrange either a cash settlement for or undertake repairs to the tiles as follows: a. Rectify the installation issues to the grouting and lipping of the tiles as stated by S.’ b. Rectify the stained tiles in accordance with paragraph 41 of this Recommendation. 43. I further Recommend that the FSP arrange for the works to the tiles, outlined in paragraph 42, within 30 days of each party accepting this Recommendation ” . Case No: 282636 Determination Page 9 of 9 5. In response to the Recommendation, the FSP made a cash offer of $550 in full and final settlement of the Applicants claim and that offer was firmly rejected. Having regarded the history of the matter, I am unsurprised that it did not find favour with the Applicants. 6. Following the further exchanges between the Service and the parties, the Applicants offered to accept the Recommendation upon conditions. As noted above, something of an impasse has developed between the parties in respect of the FSP’s request for a further assessment as to the current status of the floor. 7. I agree with the Case Manager’s reasoning and with the thrust of her Recommendation. As noted above, it is in the interest of both parties that the matter be finalised. This will require a further degree of cooperation as between the parties, which appears to have been lacking in the past. I accept the thrust of the report from S that a problem exists in respect of the sealing of the tiles and in respect of the grouting applied by the contractor. In particular, I refer to and confirm paragraphs 32 to 35 and paragraphs 39 and 40 of the Recommendation. Determination 8. Within five working days of receipt of this Determination, the FSP is to nominate an independent tiling contractor who will be requested by the FSP to quote for the replacement of damaged or discoloured tiles and to replace tiles that are subject to lipping (ie not flush) with adjacent tiles. 9. The quotation for that scope of works is to be completed and submitted to the parties within 14 days. 10. The quotation by the contractor is subject to the contractor agreeing to carry out the necessary rectification work within 30 days of submitting the quotation. 11. If the quotation is more expensive than the replacement of the entire area affected, the FSP will be entitled to cash settle the claim for the cost of replacement. 12. If the rectification work is carried out the FSP is required to pay the Applicants the sum of $500 towards accommodation and the cost of removal and refitting of the fire place.