Home / Financial Firm (Unknown - Insurer) / Determination 282636
Determination 282636
Rectification of defective kitchen floor tiles and tile installation declined
Summary
The applicant sought $5,500 to replace kitchen floor tiles that were stained and poorly installed, after the FSP declined rectification. AFCA ordered the FSP to have an independent contractor rectify the installation and stained tiles, with cash settlement if that costs more, and $500 if the rectification is carried out.
The lifetime guarantee of workmanship on repairs authorised by the insurer covers defective installation, while the tile choice and wear and tear exclusions do not relate to the workmanship defects.
Issues
- Claim denial primary · upheld
“Panel accepts the installation was faulty due to grouting and lipping, and the lifetime workmanship guarantee requires the FSP to rectify it.”
- Repairs or contractors secondary · upheld
“Panel prefers the expert report finding defective grouting, lipping and sealing by the FSP's authorised tiler, and the tile stains flowing from that installation.”
Subjects and remedies
home or building damagepay compensationrepair or rectify
Text of the determination
Case No: 282636 Determination Page 1 of 9
Case number: 282636
General Insurance - Domestic Insurance - Home Building - Service – faulty
works – declinature of additional works
09 April 2013
Background
1. This is a review of a Recommendation by the Service’s Case Manager dated
17 January 2013. As noted below, an impasse has developed as between
the parties and in the interest of obtaining finality, the matter has been
referred to me for Determination.
2. The relevant background, summaries of the parties’ position and the issue to
be determined are set out in paragraphs 1 to 20 of the Recommendation and
I will restate same.
“1. The Applicant and a co-insured hold a Home Building and Contents Insurance
Policy with the Financial Services Provider (FSP). The policy covers the
building for insured events.
2. On 4 October 2011 the Applicant lodged a claim for damage to the property
arising from a water filter that had failed. The FSP accepted the claim and
arranged for repair works to the property.
3. The Applicant then noted there were marks on the kitchen tiles which could
not be removed, there was grout/silicone left on the tile and there was a
general unevenness in the grouting.
4. The FSP has declined to perform rectification works for the kitchen tiles on the
basis the Applicant chose the tile, the tile is not faulty and the tiling work is not
defective.
5. The Applicant disputes the FSP’s declinature of rectification woks on the basis
the tiling was defective and the tile itself is defective.
Summary of Applicant’s position
6. The Applicant has enclosed a copy of the FSP’s expert report from “S”. The
report provided by S is from a building consultant who is also a licensed
builder. I note the following from this report:
The property is generally considered to be in good condition for its
age.
Determination
Case No: 282636 Determination Page 2 of 9
S observed smudge like staining, similar to an oil stain, throughout the
living and kitchen areas. This type of porcelain tile can have many
microscopic holes in the body. The polishing process removes a fine
layer of the tile’s surface, just as using sandpap er on wood does. This
process can take the tops off some of those holes, thus exposing
them. Liquid borne contaminants added to the tile surface during
cleaning either as part of the installation or subsequent maintenance
can become trapped in these small pores creating a smudged or hazy
appearance.
S notes the Australian Standard 3958.1-2007 Ceramic tiles Part 1:
Guide to Installation of ceramic tiles and quotes the following from
same:
“Penetrating sealers are primarily used to reduce the adhesion of
contaminants and restrict the entry of staining materials on the surface
and grout joints of a tile. Penetrating sealers do not generally alter the
appearance of the tiles or affect their slip resistance. The selection of
the type of penetrating sealer will usually involve its ability to repel oils
or water-based contaminants, or both. Penetrating sealers are
generally used with more porous tiles; however, they are often
beneficial in protecting polished porcelain type tiles from staining”
S was of the opinion that the markings to the surface of the floor tiles
are the result of the polishing process leaving open micro pores which
have collected contaminants as the result of the installation process
which could have been minimised by the application of a penetrating
sealer.
S has provided his observations of lipping and issues with the
grouting. After noting the Australian Standards 3958.1-2007 and
Australian Standard 3958.1-2007, S stated it was his opinion that there
were several instances of defective building work in the installation of
the floor tiles including instances of lipping and incorrect grout
installation.
7. The Applicant is dissatisfied with the FSP’s decision relating to the tiles. The
Applicant states that an FSP employee “AB” stated that the finis h and stains
on the tiles were not acceptable and the FSP would rectify them even if this
included replacing the tiles.
8. The Applicant notes the FSP’s report from “HGBS” and notes it is a trading
name for a sole trader. Further, the tiles are made in China rather than Italy as
claimed. The report from HGBS suggests more effort is required to clean the
tiles. However, the FSP’s builder “R” has already attempted using a stripping
product and the Applicants have also used domestic floor cleaners without
success.
9. The Applicant submits that S has clearly identified workmanship issues with
the tile installation and that the tiles should have been sealed as per
Australian Standards.
10. The Applicant acknowledges that he picked the tiles but confirms this was the
extent of his dealing with the tile supplier. The carriage of the matter in
relation to the warranty claim remains with the FSP and R. The Applicant
contacted Fair Trading who informed him he had no case against the tile
supplier because he did not conduct business dealings with it.
Case No: 282636 Determination Page 3 of 9
11. The Applicant seeks the replacement of the tiles and installation of those tiles
by a tiler of his choosing. The Applicant has obtained a quotation (not
supplied) for $5,500 including GST.
Summary of FSP’s position
12. The FSP relies on the following policy terms and conditions:
“What we don’t cover
Loss, damage, injury or death arising from:
- Rust corrosion, gradual deterioration, depreciation, wear or tear
...
- Mechanical, structural or electrical failure of an item
...
Lifetime guarantee
We provide a ‘lifetime guarantee’ when your home is repaired or rebuilt
by one of our preferred repairers or builders.
This means:
- We guarantee the workmanship of repairs that we authorised for
the lifetime of your home
- We will fix any defect caused by poor workmanship
We will decide on what needs to be done to fix any defect
When you’re not covered by this guarantee
This guarantee does not apply to:
- Repairs you authorised yourself
- Loss, damage or failure of any electrical or mechanical appliances
or machine
- Wear and tear that is consistent with normal gradual deterioration
of your home.”
13. The FSP relies on report dated from HGBS and I note the following from this
report:
The marks on the tile are alum dust. This dust marking would have
occurred as the tiles were being moved along the conveyor belt during
the manufacturing process. The dust is deliberately applied to prevent
tiles sticking and should be removable by cleaning agents.
The tiles laid were made in Italy and are suitable for domestic
application.
The tiles are matt in texture and light in colour so dirt stains are more
visible.
In relation to workmanship of the tile installation complies with
Australian Standards. I note HGBS quotes Section 5 of AS3958.1-
1991 of the Australian Standards.
Case No: 282636 Determination Page 4 of 9
The tiler used adhesives, priming and grout from the one manufacturer
and complied with the manufacturer’s directions and
recommendations.
The tiles show no fault in shade, calibre and its grade.
HGBS recommends a scrubber be used to remove the stubborn
stains.
14. The FSP has enclosed claim records from which I note the following:
The records indicate the Applicant agreed to a replacement of the
existing slate tile with a cheaper ceramic tile.
R arranged the tiler.
An email on 12 April 2012 from the Applicant to the FSP stated the tile
supplier had reviewed the tile installation and stated it was a poor job.
Further, that all the tiles would need to be removed and replaced.
File record of 12 April 2012. The FSP has spoken with the tile supplier
which advised “ ....researching what can be done to clean the glue etc
off the tiles and if this cant (sic) be done the tiles affected can be taken
up and replaced.”
On 23 April 2012 there is a notation that the works outstanding
included booking a tiler to clean up tiles with a special product, do
expansion joints again and replace chipped tiles. Further, the tile
supplier advised he attended the client (Applicant) stated if product
was not available they could cut out and replace the tiles.
An email dated 2 May 2012 from the tile supplier states that:
“After inspecting the tiles I have found that it isn’t a fault with the tiles
but there are silicone residue marks left on the tiles, if the tilers are
unable to clean the residue of (sic) the tiles the tiles will have to be
replaced, there are about 4 boxes of tiles that are left on the site that
can be used.”
A further email from the tile supplier stated the following:
“This is a problem between [R’s name] and the [Applicant’s name], as
we sold the tiles to [R’s name] and we didn’t lay the tiles. We supply
tiles we don’t lay them as we do not and never have employed tilers to
work for us. [R’s name] tilers laid them, We only went out on site to
look at the tiles because they thought it was a fault in the tiles that we
supplied.”
Record dated 11 May 2012 indicates AB of the FSP followed up with
the Applicant regarding cleaning of the tiles. The Applicant informed
that a couple of tiles were cleaned but after drying the staining came
back. AB records the following in this record:
“I apologised for the inconvenience and advised we wanted to
completed (sic) the work satisfactorily and unfortunately it will take
some time. Our insured asked what happens if they don’t clean up
properly. I advised if this is the case we may need to take the effected
tiles out and replace them.”
Record dated 16 May 2012 from another FSP employee “L” regarding
a physical attendance at the property. I note the following from this:
Case No: 282636 Determination Page 5 of 9
“I queried if the tiles should have been sealed – OI and [tiler’s name]
(tiler) advises No the tile company [tile supplier’s name] advised that
the sealant was inbuilt in the tile and did not need sealing once laid.
...
It appears to me that anyone walks on the tile a built (sic) appears to
forming inside the tile which leaves a dirt mark over the tiles if anything
even water is dropped on the tile there is a mark from it that will not
clean successfully...believe this is either a fault in the tile itself or the
type of tile chosen by insured himself and it is not suitable
...
OI wants only the tiles to be cleaned with the tiler will complete today
he is aware that he has to return at some stage to take up
approximately 2 tiles and replace these and to redo the silicone joints”
Record dated 24 May 2012 by L. L appears to have recorded the
telephone notes later as she was in Sydney training. L received a call
from S who informed her that the type of tile chosen by the Applicant
was not sealed on the back and any moisture from the glue is coming
through and showing on the tiles also any moisture dropped on the
tiles near the grout will go through and flow to the back of the tile
causing marks. S intended to speak with the manufacturer.
Record dated 29 May 2012 indicates the FSP had received the report
of S. The record notes that the sealant was supposed to be inbuilt in
the tile and did not need sealing once laid. The Applicant indicated this
was one of the reasons he chose the tile.
Email dated 29 May 2012 from R indicates it was also informed by the
tile supplier that the tiles were sealed in the factory and it would make
no difference applying a sealer.
During a telephone call with S on 31 May 2012, the FSP was informed
that the opening of the micropores occurred during the making process
and that S was aware of this “happening all over the place”. Further,
the tiles were made in China even though they are sold as Italian tiles.
On 1 June 2012 the FSP rang R and asked them to enquire at the tile
supplier in regards to claiming on the warranty for the tiles. R advised
it would do so and get back to the FSP.
On 3 July 2012 the FSP rang the tile supplier and was informed this
matter was with R and that they would need to go through them.
15. The report from S and HGBS together with information from the tile supplier
identified the problem with the tile was staining which was an inherent
manufacturing result. Accordingly, the policy does not respond by way of
replacement or rectification works.
16. The policy excludes loss or damage arising from the structural failure of an
item. The exclusion applies as the tiles are suffering from a fault which allows
contaminants to build up.
17. The Applicant has failed to demonstrate that the loss or damage caused by
the faulty tile was the result of faulty workmanship or such other cause which
enlivens the lifetime guarantee under the policy.
Case No: 282636 Determination Page 6 of 9
18. The FSP has not received any evidence that supports the Applicant’s claim
for loss or damage.
19. The FSP considers it has fulfilled its policy obligations to the Applicant under
the policy and that the Applicant should refer back to the tile supplier.
Issue
20. Whether the FSP was entitled to decline the Applicant’s claim for rectification
of the kitchen floor tiles ” .
Reasons for decision
3. There has been a full exchange of information and each party has had the
opportunity to address the issues that have been raised. I have read all of
the exchanged material and I have considered the parties submissions and I
have considered the exchanges as between the parties and the Service
following the Recommendation.
4. In making her Recommendation, the Service’s Case Manager stated her
reasons and Recommendation in paragraphs 23 to 43 and I will restate
same.
“23. After reviewing the materials provided by each party I consider that there are
two main elements to the Applicant’s claim regarding the kitchen floor tiles.
These are the installation of the tiles and the tiles themselves. I will review
each of these issues separately.
Tile Installation
24. There are two expert reports before me regarding the installation of the tiles
which are quite contrary to one another.
25. S has provided his observations of lipping and issues with the grouting. After
noting the Australian Standards 3958.1-2007 and Australian Standard 3958.1-
2007, S stated it was his opinion that there were several instances of
defective building work in the installation of the floor tiles including instances
of lipping and incorrect grout installation.
26. In contrast HGBS stated the workmanship of the tile installation complies with
Australian Standards. I note HGBS quotes Section 5 of AS3958.1-1991 of the
Australian Standards.
27. I note that S has provided his qualifications within the report but HGBS has
not. Accordingly, it is difficult to determine whether HGBS has the same, more
or less qualifications than S.
28. It is further of concern that whilst S has quoted the Australian Standard with
the year 2007, that HGBS appears to have quoted from the 1991 version of
the standards. It is unclear what changes have been made to the Australian
Standards in relation to the installation of tiles, however any consideration of
Case No: 282636 Determination Page 7 of 9
the tile installation should have been made with the Australian Standards
applicable at the time installation. Due to the date of installation of the tiles it
would appear that a 2007 version of the Standards would be more
contemporaneous than a 1991 version.
29. Given these factors, I prefer expert S’s report over that of expert HGBS. I
therefore accept that the installation of the tiles was indeed faulty due to the
grouting and lipping of the tiles.
30. The policy contains a lifetime guarantee for workmanship. As the
workmanship was defective the FSP would be liable to rectify this faulty
workmanship. It would appear that none of the exclusions relied upon by the
FSP are applicable to the issue of installation as they refer to wear and tear,
deterioration or structural failure. Further, the exclusions provided in the
lifetime guarantee of works do not apply given the repairs were not authorised
by the Applicant and the loss does not arise from electrical/mechanical failure
or wear and tear.
31. It is not clear to me whether the expansion joints were installed as stated
within the claim records of the FSP. If the expansion joints have not yet been
installed within the floor tiles subject of this dispute, then I consider these
works have already been agreed to by the FSP and should be attended to.
The tiles
32. The information provided by expert HGBS is that the tile shows “no fault in
shade, calibre and its grade”. HGBS believed the markings on the tiles were
from alum dust which would have occurred during the manufacturing process.
HGBS believed that the stain could be removed via a scrubber. HGBS stated
that the tiler complied with the manufacturer directions and recommendations.
It is unclear to me whether HGBS knew that cleaning of the tile had already
been attempted and whether this would have altered its opinion regarding
whether the tile was in fact not faulty.
33. S was of the opinion that the markings to the surface of the floor tiles are the
result of the polishing process leaving open micro pores which have collected
contaminants as the result of the installation process which could have been
minimised by the application of a penetrating sealer.
34. The Claim record dated 11 May 2012 indicates AB of the FSP informed the
Applicant “Our insured asked what happens if they don’t clean up properly. I
advised if this is the case we may need to take the effected tiles out and
replace them.”
35. I further note the claim record dated 24 May 2012 by L. S informed L that the
type of tile chosen by the Applicant was not sealed on the back and any
moisture from the glue is coming through and showing on the tiles also any
moisture dropped on the tiles near the grout will go through and flow to the
back of the tile causing marks. S intended to speak with the manufacturer and
it appears that S later became aware of many similar claims.
36. The claim records also show on 16 May 2012 and 29 May 2012 that L had
queried whether the tiles should have been sealed. L was informed that the
tile had been chosen because it was supposed to have inbuilt sealing. The
Case No: 282636 Determination Page 8 of 9
FSP’s builder, R, also informed t he FSP that the tile supplier stated that due
to sealing in the factory that it would make no difference to apply a sealer.
37. On 1 June 2012 the FSP rang R and asked them to enquire at the tile supplier
in regards to claiming on the warranty for the tiles. R advised it would do so
and get back to the FSP. On 3 July 2012 the FSP rang the tile supplier and
was informed this matter was with R and that they would need to go through
them.
38. Both parties have alleged or provided evidence that they have been unable to
claim on the warranty for the tiles. There is insufficient evidence on this point
as it is unclear what the result of R’s investigation with the tile supplier was.
39. It is apparent that the tiles were not properly sealed as alleged by the tile
supplier. I accept the opinion of S that the manufacturing process of polishing
created micropores. Further, that the:
“...micro pores which have collected contaminants as the result of the
installation process which could have been minimised by the application
of a p enetrating sealer.” (my emphasis added)
40. It appears that the tiles themselves were stained during installation and due to
the non-application of a sealer. Whilst I accept that the Applicant and R (as
well as its tiler) have received incorrect advice from the tile supplier, it does
not abrogate the responsibility of the FSP’s authorised repairer/tiler for the
issues caused during installation. S has indicated that a penetrating sealer
could have minimised the issue caused which is part of the installation
pro cess. I do not consider that the Applicant’s choice of tile relevant to the
workmanship. Similarly, the exclusions relating to wear and tear and structural
failure do not relate to the workmanship aspect of the installation.
41. The Applicant has sought $5,500 but has not provided any itemised quotation
regarding these works. There is insufficient evidence that all the tiles need to
be removed and replaced. The cash settlement owed to the Applicant would
be the cost of rectification of the tile installation and replacing the stained tiles
together with the application of a preventative sealant. If these works are
more expensive than the replacement of the entire area, or no party will take
on the rectification work, then the Applicant would be entitled to the full
replacement.
Recommendation
42. On the basis of the available information I recommend that the FSP arrange
either a cash settlement for or undertake repairs to the tiles as follows:
a. Rectify the installation issues to the grouting and lipping of the tiles as
stated by S.’
b. Rectify the stained tiles in accordance with paragraph 41 of this
Recommendation.
43. I further Recommend that the FSP arrange for the works to the tiles, outlined
in paragraph 42, within 30 days of each party accepting this
Recommendation ” .
Case No: 282636 Determination Page 9 of 9
5. In response to the Recommendation, the FSP made a cash offer of $550 in
full and final settlement of the Applicants claim and that offer was firmly
rejected. Having regarded the history of the matter, I am unsurprised that it
did not find favour with the Applicants.
6. Following the further exchanges between the Service and the parties, the
Applicants offered to accept the Recommendation upon conditions. As noted
above, something of an impasse has developed between the parties in
respect of the FSP’s request for a further assessment as to the current
status of the floor.
7. I agree with the Case Manager’s reasoning and with the thrust of her
Recommendation. As noted above, it is in the interest of both parties that the
matter be finalised. This will require a further degree of cooperation as
between the parties, which appears to have been lacking in the past. I
accept the thrust of the report from S that a problem exists in respect of the
sealing of the tiles and in respect of the grouting applied by the contractor. In
particular, I refer to and confirm paragraphs 32 to 35 and paragraphs 39 and
40 of the Recommendation.
Determination
8. Within five working days of receipt of this Determination, the FSP is to
nominate an independent tiling contractor who will be requested by the FSP
to quote for the replacement of damaged or discoloured tiles and to replace
tiles that are subject to lipping (ie not flush) with adjacent tiles.
9. The quotation for that scope of works is to be completed and submitted to
the parties within 14 days.
10. The quotation by the contractor is subject to the contractor agreeing to carry
out the necessary rectification work within 30 days of submitting the
quotation.
11. If the quotation is more expensive than the replacement of the entire area
affected, the FSP will be entitled to cash settle the claim for the cost of
replacement.
12. If the rectification work is carried out the FSP is required to pay the
Applicants the sum of $500 towards accommodation and the cost of removal
and refitting of the fire place.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.