Determination 280209

Service quality

FirmFinancial Firm (Unknown - Insurer)
Decided2014-01-17
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$500
Amount claimed—
SourceAFCA PDF

Summary

The applicants' storm-damaged home suffered repeated water entry and the claim was delayed until repairs were agreed in 2013. AFCA found unusual delay and awarded $500 non-financial loss, rejecting financial compensation for consequential loss.

Once the FSP waived the excess the claim should have progressed faster, and consequential loss such as an unsellable home is excluded by the policy.

Issues

Subjects and remedies

home or building damagenatural disasterpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 280209 Determination Page 1 of 4 Case number: 280209 General Insurance - Domestic Insurance - Home Building - Service - Service quality 18 December 2013 Summary Description: This dispute arises under a Home and Contents Policy following storm damage sustained to the property in June 2007 and in early 2011. The dispute arose as to the liability for the cause of inundation. Basis of Determination: This dispute was subject to a Recommendation. Following rejection of the Recommendation by the Applicants and provision of further information, the parties have agreed to resolve the dispute and the FSP ha ve now completed the repairs. The dispute now involves the Applicants‟ claim for an apology and financial compensation on the grounds that the FSP‟s origin al submission lacks credibility and substantiation. The evidence establishes that whilst there were delays in the resolution of the dispute, these delays have been associated with determining the precise cause of the inundation. Determination: The FSP is liable to pay compensation of $500 pursuant to paragraph 9.3(b) of the Terms of Reference. Background 1. The Applicants held a Home and Contents Policy with the FSP. 2. In 2007, the property suffered significant water damage following the Pasha Bulka storm. According to the Applicants, prior to this storm there had been no damp or water intrusion into the property. The FSP accepted liability for the Applicants‟ claim and repairs were completed to the property. 3. According to the Applicants, they had built a dwarf wall and had also installed an additional sump tray around this time. Determination Case No: 280209 Determination Page 2 of 4 4. During heavy rainfall in 2011, the Applicants‟ property was again inundated and further damage sustained. 5. The Applicants maintain the damage sustained in June 2011 was due to issues with the earlier 2007 repairs whilst the FSP believed the water entry was due to issues with the drainage and water proofing of the property. The FSP considered the water leaks will need to form the basis of a new claim. The FSP maintained that whilst it was liable for the consequential damage due to the storm and rain water, it was not liable for the repair of the draining problems as they were due to such things as structural defects, break down or wear and tear. 6. A Recommendation was issued by the Service on 12 June 2013. The Case Manager recommended that the cause of damage to the Applicants‟ home was not due to any failure on behalf of the FSP and that the FSP was entitled to require the water proofing of external and retaining block walls to be completed prior to performing repair work. 7. Whilst the FSP accepted the Recommendation, the Applicants rejected the same. The Applicants have advised on 12 August 2013 that the FSP has now accepted liability for the damage sustained in 2011 and have waived the excess on the lodgement of a second claim. 8. The works have now been completed without any alteration of the existing water proofing membrane and the house restored to the function and design that was present when the FSP agreed to insure the home. The Applicants now seek a Determination that the FSP‟s numerous submissions lacked credibility, an apology for the delay and financial compensation for amongst other things: “Having to live with black mould in the home from 2011 to 2013 The additional time and cost incurred in pursuing their entitlements under the PDS including telephone calls, time loss in attending the various assessors and costs of engaging CH. Compensation for nearly six months from December 2012 to August 2013 when the home was open to the elements causing the need to use excessive heating. Compensation for the fact that the home was unsellable during this period. ” Reasons for decision 9. Lengthy and detailed submissions have been made by the Applicants and the FSP in this matter. There are detailed submissions made prior to the parties agreeing to the completion of the works and after the parties had agreed to the completion of the works. 10. Whilst the Applicants rejected the Recommendation, the Applicants now concede that the Recommendation and the rejection are now “out of currency” as they have been able with the assistance of the FSP‟s Case Manager to organise an agreement between all parties. Case No: 280209 Determination Page 3 of 4 11. I note from this concession that the Applicants refer to the FSP ‟s subsidiary insurer A separately to the FSP. I am satisfied that the concessions made by the Case Manager are concessions made on behalf of the FSP. 12. It appears from the material exchanged that the resolution of this dispute follows the provision of a report from CH and an attendance at the Applicants‟ property by assessor RC. 13. The assessor‟s report identifies that „I‟ had completed the works outlined by CH in relation to the dwarf brick wall and piped drain water from the cavity to the sump. Following completion of this work, internal rectification works were ready to commence. I‟s main concern was that they could not warranty the work if they did not water proof the entire retaining wall. As a result of the agreement reached I‟s concern s were allayed. 14. Although the repairs have been completed and the FSP has accepted liability for resultant damage and completing the repairs to the resultant damage, the Applicants still requested determination that the damage arises from the 2007 event. In my view, the information as exchanged does not allow for that determination to be made. 15. It appears that there is dispute amongst the parties as to whether or not the relevant water proof membrane ever extended to the bottom of the wall. If I accept the comments of CH, it would appear that most likely the membrane had failed due to the corrosive nature of ground salts and the hydrostatic pressure. 16. There is reference in the documentation to drainage being blocked as a result of the silt build up. Again, it is unclear from the information exchanged whether this has occurred or not and if so whether the FSP should have identified this and notified the Applicants of the need for the maintenance to be performed following the 2007 event. 17. In my view, the FSP‟s a greement to waive the excess with respect to the 2011 claim is reasonable and fair in the circumstances given the issues that have been raised by the Applicants and the uncertainty as to whether the repairs from 2007 have caused or contributed to the inundation of the property following the heavy rainfall in 2011. 18. Insofar as the delays and claims handling that occurred after the claim in 2011, I note the FSP in its latest submission again confirmed that as part of its IDR review in November 2011 it informed the Applicants it would accept liability for the resultant damage, but the damage would need to form the basis of a new claim. It was not until the Applicants had lodged their second claim on 11 April 2012 that the FSP agreed to waive the excess. The excess has been waived in acknowledgement of the problems with the original investigation of the cause of water entry. 19. I am satisfied that whilst the FSP could and in fact should have in my view dealt with the damage following from the events of 2011 much earlier, the Case No: 280209 Determination Page 4 of 4 delay in having the matter resolved is complicated by the Applicants refusal to lodge a separate claim. 20. It appears during that period that there may have been a breakdown in communication between the parties or a misunderstanding. In any event, once the second claim had been lodged and the FSP had determined to waive its claim to excess, there seems to be no reason why the claim did not progress more quickly. Certainly some dispute arose as to the membrane wall but in my view this should not have led to a delay until August 2013 to have the repairs commenced. 21. In this respect, I accept the Applicants have suffered an unusual degree of delay and loss of expectation of enjoyment as a result of the FSP‟s conduct . Once the FSP agreed to waive the excess, then in my view greater effort should have been made to reach agreement in this matter. The FSP are entitled to rely on the information provided by their assessors. It was not until the Applicants had engaged CH that the circumstances changed and the parties were able to reach agreement. In these circumstances, I accept that the Applicants have experienced delay in resolving the dispute and in my view the FSP should pay non-financial compensation pursuant to paragraph 9.3(b) of the Terms of Reference in the sum of $500. Insofar as the Applicants seek financial compensation for the fact that the property was unsellable, such loss would be consequential loss and the policy acts to exclude such cover. Determination 24. Accordingly, I determine that the FSP is liable to pay compensation to the Applicants pursuant to paragraph 9.3(b) of the Terms of Reference in the sum of $500.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.