Text of the determination
Case No: 279610 Determination Page 1 of 14
Case number: 279610
General Insurance - Domestic Insurance - Home Building & Contents - Storm -
FSP Decision - Denial of claim - Exclusion/condition
27 February 2013
Background
1. This is a Determination following the rejection of a Recommendation by the
Applicant.
2. A dispute has arisen between the Applicant and the Financial Services
Provider (FSP) with whom the Applicant had a Home Building and Contents
insurance policy.
3. The dispute arises from events preceding 29 November 2010 when the
Applicant lodged a claim. Shortly before the lodgement of the claim (and
according to the Applicant) there had been a major storm which caused
damage to the swimming pool on his property. Although the pool was an
“above ground” pool, it had been installed in the ground.
4. After the claim was made, the FSP appointed an assessor to inspect the
site. The assessor determined that an opinion should be obtained from a
building engineer. But, no report was obtained from the building engineer for
approximately nine months. Consequent upon the report from the building
engineer, the FSP advised the Applicant that the claim would be denied and
the matter was then referred to this Service.
5. After the matter was referred to this Service, it was the subject of a
Recommendation. On 16 November 2012, a Case Manager of the Service
recommended that the FSP was entitled to deny the Applicant‟s claim under
the terms and conditions of the policy. However, the Case Manager also
recommended that the Applicant was entitled to compensation for non-
financial loss in the amount of $3,000 pursuant to paragraph 9.3(b)(i) of the
Terms of Reference for this Service.
6. Whilst the FSP accepted the Recommendation, the Applicant has not. He
has made further detailed submissions and has supplied a further report
from his expert. In turn, further written submissions have also been made by
the FSP.
7. The Recommendation was extraordinarily thorough and set out both the fact
situation and the various submissions and other materials from the parties, in
great detail. I think it more convenient if I now set out the Recommendation
Determination
Case No: 279610 Determination Page 2 of 14
in full. I shall then make further comments regarding my observations as to
the matter:
“1. The Applicant held a home building and contents insurance policy with the
Financial Services Provider (FSP) which was in force at the time of the loss.
The policy covered listed insured events only.
2. On 29 November 2010, the Applicant lodged a claim for water damage to his
pool as a result of a storm.
3. The FSP denied the claim on the basis the damage was not caused by an
insured event but by hydrostatic pressure, earth movement and structural
defects or faulty workmanship, all of which are excluded from cover.
4. The Applicant disagrees with this decision and alleges the damage was
caused by the storm. He wants his claim paid in full.
Summary of Applicant’s position
5. Around 28 November 2010, his property was affected by a storm event that
consisted of three days of constant rain. The area received a year‟s rainfall in
three days.
6. During the event, rainwater entered between the walls of his 2.5 year old
swimming pool. The pressure of the constant rainwater after three days of rain
caused the pool wall to collapse on one side and fold inwards. Prior to the
incident, the pool was in as new condition and had no problems.
7. The pool was an above-ground pool which was installed in the ground by a
qualified pool installation company, following the manufacturer‟s instructions.
A complete drainage system was installed around the pool, including a pump
to drain any water that may filter through from the ground level.
8. It took nine months and several telephone discussions for the FSP to send a
building consultant to conduct a full r eport. He disagrees with this report‟s
findings. In the interim, the pool deteriorated to an extent where the entire
pool walls collapsed and a new pool needed to be installed.
9. He organised for independent expert OC to report on the damage. This took
place on 12 December 2011.
10. The policy covers storm, which includes heavy rainfall, hail or snow. He
considers, as does OC, that the collapse of the pool was due to torrential
rainfall which changed the dynamics of the soil profile surrounding the pool.
This resulted in failure of the south-western outer wall of the pool.
11. As to similar damage having occurred to the pool back in 2008, he contends
that this occurred when a gum tree fell during a storm. As a result of this, the
deck area, fence and part of the swimming pool were damaged. His previous
insurer paid him for the damage to the pool and repaired the deck and fence.
12. In summary, the event is covered under storm damage by the policy. He
wants the FSP to pay for the claim in full.
Summary of FSP ’s position
13. Its assessor C and building engineer S inspected the damage to the pool.
Case No: 279610 Determination Page 3 of 14
14. Following S and C‟s findings, the claim was denied on the basis damage was
not caused by a single policy event but by earth movement, structural
defects/faulty workmanship and hydrostatic pressure which are general
exclusions under the policy.
15. The Applicant provided OC‟s report, which confirms that the cause of the
damage is hydrostatic pressure from continuous rainfall and not from a single
event under the policy.
16. It also relies on the Wayne Tank principle. If it is determined that a storm
contributed to the damage, it contends that other concurrent causes, at least
one of which is excluded, contributed to the damage and as such it is entitled
to deny the claim in full.
17. It acknowledges there was a delay with the attendance of the engineer to the
property and apologises. However, the claim was lodged during a time when
several catastrophe events such as the Queensland and Victoria floods
occurred.
18. As to the potential awarding of compensation due to the delay in claims
handling, the FSP contends that:
The FSP was overwhelmed with the number of catastrophe events
between December 2010 and March 2011.
Assessor C was sent within days of claim lodgement and C arrived to a
similar conclusion as S did later on. As such, the Applicant was put on
notice of the likely cause of damage not being covered shortly after claim
lodgement.
Clause 4.3 of the General Insurance Code of Practice provides that due to
the large number of claims, insurers may not be able to meet all standards
of the Code following a catastrophe or disaster.
The Flood Commission and Insurance Council of Australia have supported
insurers for the way they have handled the volume of claims through the
catastrophes and were not surprised delays occurred.
The delay in appointing a building consultant has not affected the
Applicant. Twelve months after he was made aware that the pool would not
be covered, he had not repaired it to mitigate further damage.
Finally, according to clause 9.3 c) of the Financial Ombudsman Service
(FOS) Terms of Reference, FOS will not award compensation for financial
or non-financial loss if the relevant policy expressly excludes consequential
loss. The policy excludes consequential loss; therefore, compensation
cannot be awarded in this instance.
19. The FSP relies on the following policy provisions:
Product Disclosure Statement (PDS)
“ Glossary of words with special meaning
building
...
The domestic residence at the insured address.
It includes structural improvements of a domestic nature, being:
permanently fixed swimming pools, saunas and spas,
including their fixed accessories; and
Case No: 279610 Determination Page 4 of 14
event
...
A single occurrence.
storm A violent wind (including cyclones), sometimes combined
with thunder, heavy falls of rain, hail or snow; or
Thunderstorms or hailstorms, sometimes accompanied by
heavy falls of rain or snow.
It is not persistent bad weather or heavy or persistent rain by
itself.
...
General exclusions – apply to the overall policy
Unless included in additional cover, we will not cover loss, damage or legal
liability caused by:
structural defects and faulty workmanship in the construction of the
building or lack of maintenance to the building and/or contents;
erosion or earth movement including shrinkage;
hydrostatic pressure;
...
Unless it is stated specifically in the policy, this policy does not provide cover
for:
consequential losses or loss of profit;
...
Events you are covered for
Storm
You are covered for loss or damage as a result of storm. ”
Supplementary PDS (SPDS)
“ Storm. You are not covered for storm damage to:
the building or contents where the water, wind or hail has entered the
building through an opening not created by the storm; ...”
Issues
20. Whether the FSP is entitled to deny the Applicant‟s claim under the terms and
conditions of the policy.
21. Whether the Applicant is entitled to compensation for delays in claims
handling.
Reasons for Recommendation
22. I am satisfied a full exchange of information has taken place between the
parties and each party has had the opportunity to address the issues raised.
Case No: 279610 Determination Page 5 of 14
23. I have reviewed the submissions of the parties and observe there is no
dispute that one of the pool walls collapsed, damaging the structure. I shall
now address each of the issues in dispute.
Whether the FSP is entitled to deny the Applicant’s claim under the terms
and conditions of the policy
24. In these circumstances, the insured has the onus to establish on the balance
of probabilities that the claim falls within the definition of an insured event; this
is known as a prima facie claim.
25. Once this is established, the onus shifts to the insurer to establish the
application of any exclusion on which it relies to deny or limit the claim.
26. Since the policy is a listed insured events policy, the Applicant‟s onus is to
establish that the circumstances of the loss fit within an event as defined in
the policy.
27. There is no dispute there was heavy rainfall for a prolonged period around the
date of the loss. The FSP argues the damage did not occur from a single
insured event of storm but rather from heavy rainfalls over a number of days,
which does not qualify as “storm” under the relevant policy definition.
28. There is no available weather data for the area during the relevant period of
time. The Bureau of Meteorology‟s closest weather station (approximately
15km south-east from the risk site) indicates that there had been rain in the
area for a period of approximately three days around the date of the loss.
29. The information available is insufficient to establish whether these heavy rains
were accompanied by thunderstorms, hailstorms or violent winds as required
under the policy definition of “storm”.
30. As such, I am not satisfied there is sufficient information to establish there is a
prima facie claim under the insured event “storm”. However, for the sake of
argument, even if there was a prima facie claim, it is my view that applicable
exclusions would operate to defeat the claim.
31. The FSP contends that although stormwater may have contributed to the
damage, it was also contributed to by earth movement, structural
defects/faulty workmanship and hydrostatic pressure, all of which are
excluded under the policy.
32. To support its position, the FSP has provided the opinion of loss assessor C
and building engineer S. C‟s reports say in summary the following:
Hydrostatic pressure has occurred and the pool liner and framework
were unable to cope and caused the damage.
As per S‟s report, the proximate cause of damage is the void left during
installation of the pressure pump instead of the soil backfill required.
33. S in its report of 9 August 2011 says in summary the following:
The swimming pool is a braceless metal-framed and metal-walled
structure designed to be an above or in-ground pool.
It was purchased in February 2008 and was installed in the ground by
qualified contractors recommended by the seller to install the pool frame
and walls. The Applicant did the backfilling.
Case No: 279610 Determination Page 6 of 14
Concrete paving surrounded the pool‟s perimeter with a gap adjacent to
the immediate perimeter of the pool of approximately 450mm in width by
the depth of the pool.
The Applicant installed an agricultural (ag) drain around the perimeter
base of the pool and then backfilled in behind the pool with 6:1 damp
coarse sand and cement mix to a width of approximately 450mm. S
agrees this complies with the manufacturer‟s recommendations.
The Applicant states he also installed a plastic pit and a submersible
pump adjacent to the base of the pool in the backfill area. The ag drain
pipe drained to the pit which was located in the south-western external
corner of the pool adjacent to the point of collapse.
The pump was installed to remove subsurface groundwater from around
the perimeter of the pool via a plastic ag drain pipe laid across the
surface of the adjacent grassed open space area.
The Applicant noticed, while draining out the water gathering at the
bottom of the pool since the collapse, that the pump would occasionally
stop working. He was unaware if the pump was working correctly whilst
installed in the pit adjacent to the pool.
The soil surrounding the grassed area appears to be black volcanic soil
of a moderate to high reactivity, prone to excessive movement when
subjected to extreme moisture.
The likely cause of the collapse is external pressure exerted on the wall
of pool at the location of the ag drainage pit. The height and width of the
pit and shaft would have taken the place of part of the backfill, thus
creating a void or partial void.
The absence or failure of the backfill in this area has allowed the force
exerted by lateral movement in the adjacent soil to impact locally on the
wall and frame of the pool.
This in turn caused the top of the wall of the pool, where the internal
water pressure is of least resistance, to partially collapse.
The volume of water from torrential rain and overflowing nearby dam
would have contributed to the expansion and lateral movement in the
surrounding soil.
The cause of damage to the swimming pool wall is due to a combination
of lateral movement in the adjacent soil caused by moisture migration
during the storm event and the failure or absence of backfill at the
location of the ag drainage pit and shaft.
34. The Applicant disagreed with C and S‟s findings and provided a report from
civil engineer OC. OC‟s report of 12 December 2011 says in summary:
After approximately three days of excessive rain, the south-western
section of the pool‟s outer wall collapsed.
It would seem that the construction methodology adopted has been in
accordance with the manufacturer‟s specifications.
The surrounding area was well constructed using concrete paving with a
consistent gap against the perimeter of the in-ground pool.
The topography of the surrounding land seems to be levelled. The land
contours at the southern end away from the pool area.
Case No: 279610 Determination Page 7 of 14
It would seem that the primary cause of the failure of the outer wall was
excessive hydrostatic pressure resulting from torrential rainfall, which
changed the dynamics of the surrounding soil profile.
35. Based on the experts‟ reports, I note there is no dispute that rainwater runoff
contributed to the damage. However, S indicates there was a failure of the
wall due to a void in the backfill created when space was allowed for a pit and
shaft for drainage through the ag drain pipe.
36. S notes that the damaged pool wall is close to where this void would have
been. S considers this to be the main cause of damage.
37. I have reviewed the manufacturer‟s instructions on the backfill requirements
for in-ground installations. One of the instructions notes says:
“When the pool is installed partly or fully in the ground in a flat area with no
possibility of gravity drainage of any ground water, the [ag] pipe system
should be brought to an upstand pipe with a surface grating for inspection
of the ground water level prior to emptying the pool. The upstand pipe can
also be used to lower external ground water level locally by means of a
suction pump if desired” [sic].
38. I note the diagrams in the instructions do not indicate how this upstanding
pipe should be installed.
39. Although it seems the Applicant complied with the manufacturer‟s instructions;
I cannot ascertain, due to the lack of detail in the instructions, whether the
way the ag drain, pit, shaft and pump were installed is compliant with the
manufacturer‟s recommendations.
40. OC finds that the primary cause of failure is excessive hydrostatic pressure
due to torrential rainfall; however, he does not report on the adequacy of the
backfill or of the ag drain or the installation of the pump.
41. Accordingly and on the balance of probabilities, I am persuaded by S‟s
findings as they are more detailed with regard to the structure and installation
of the pool and the likelihood of multiple contributing causes.
42. I accept the damage was contributed by rainwater from torrential waters. I
acknowledge it is arguable whether this can be identified as a single storm
event or constant heavy rainfall.
43. However, as previously stated, even if it is accepted it was as a result of a
single storm, I am not satisfied this would have been the sole cause of
damage. Instead, I am satisfied that soil movement but mainly structural
defects/faulty workmanship would have contributed to the damage.
44. Under the Wayne Tank principle, where a loss has two or more proximate
causes, and at least one of them is excluded from cover, the insurer is not
required to indemnify.
45. Accordingly, as structural defect and faulty workmanship are excluded from
cover under the policy, I am satisfied the FSP is entitled to deny liability for the
claim.
Whether the Applicant is entitled to compensation for the delays in claim
handling
46. The Applicant argues the delay of nine months to appoint an engineer to
assess the damage has prejudiced him and in the meantime the pool
sustained further damage and became unrepairable.
Case No: 279610 Determination Page 8 of 14
47. The FSP acknowledges the delay but contends it was justified as it was
experiencing an extraordinary increase in claims due to the Victoria and
Queensland floods.
48. It also contends that as the policy excludes consequential loss, under the
FOS Terms of Reference (TOR), FOS is prevented from awarding any
compensation.
49. I consider the TOR relevant to this dispute are:
“ 9.3 Other compensation
a) Subject to paragraph 9.3c) and paragraph 9.7, FOS may decide
that the Financial Services Provider compensate the Applicant for
consequential financial loss or damage up to a maximum amount of
$3,000 per claim made in the Dispute.
b) Subject to paragraph 9.3c) and paragraph 9.7, FOS may decide
that the Financial Services Provider compensate the Applicant for
non-financial loss but only where:
(i) an unusual degree or extent of physical inconvenience, time
taken to resolve the situation or interference with the
Applicant‟s expectation of enjoyment or peace of mind has
occurred; or
...
The maximum amount of compensation for non-financial loss will be
$3,000 per claim made in the Dispute.
c) Notwithstanding paragraphs 9.3a) and b), FOS will not provide
compensation for:
(i) consequential financial loss; or
(ii) non-financial loss,
in a Dispute arising as a result of a claim on a General Insurance
Policy that expressly excludes such liability ”
50. The Terms of Reference make a distinction as to what is consequential
financial loss and non-financial loss. Given this distinction, I am not satisfied
that by excluding “consequential losses” in the policy, FOS is prevented from
awarding compensation for non-financial loss.
51. In this case, I consider that the time taken to assess the claim warrants the
consideration of award of compensation for non-financial loss.
52. I agree to an extent with the FSP in that the delay is justified considering the
increased number of claims it had to handle during the flood events.
53. However, I am not satisfied this warrants a delay of nine months since claim
lodgement. C first attended the property on 13 December 2010 and S was not
appointed until 3 August 2011.
54. I do not accept that C‟s findings on its first report (that damage might have
been due to hydrostatic pressure) were indicative of the likely result of the
claim. Notably, when S‟s findings indicated that the proximate cause of
damage was another reason altogether.
55. Further , C in its sixth report says “As Insurers will recall the Engineer originally
appointed to this matter had not attended the property so this request was
cancelled and [S] were appointed”.
Case No: 279610 Determination Page 9 of 14
56. The FSP has not provided any specific explanation as to why it took so long to
appoint S after the first engineer did not attend.
57. I may understand a delay due to the floods, however, a delay of eight months
between C‟s first report and the appointment of S, in my view is not justifiable,
in particular when the insured property is not close to flood affected areas or
when the expert required is not a hydrologist.
58. As such, I am satisfied the Applicant is entitled to compensation for non-
financial loss due to the unusual extent of time taken to assess the claim.
59. I refer to the FSP‟s submission of 7 June 2012 in which, under a proposal for
conciliation, the FSP mentions having offered the Applicant $3,000 as a
contribution towards the repairs to the pool.
60. I understand the FSP has assessed this as a reasonable amount to contribute
to the Applicant‟s loss and therefore I am satisfied it is a reasonable amount
for the awarding of compensation for non- financial loss.”
Other Matters
8. It can be seen, therefore, that the thrust of the Recommendation by the Case
Manager was that as to the principal issue, notably the liability of the FSP to
indemnify the Applicant for the damage to the swimming pool, the Case
Manager was of the opinion that the FSP was not liable.
9. The Case Manager was, however, convinced that the matter was
appropriate for an award of compensation for physical inconvenience, time
taken to resolve the situation and interference with the Applicant‟s
expectation of enjoyment or peace of mind and therefore recommended that
the maximum sum, notably $3,000, should be paid under this heading.
10. I have had the benefit of reading all of the material which was supplied to the
FSP by the Applicant, together with the various reports which have been
supplied to the FSP either by “C” (who did inspect the property very shortly
after the incident) or, ultimately, by “S”. The problem confronting the FSP is
that “S” did not report until 9 August 2011. This, not surprisingly, has led to
complaints from the Applicant and also, and perhaps more importantly,
comments from the expert engaged by the Applicant, “OC”, who has queried
whether any value can be attributed to the “S” report having regard to the
time which had elapsed before the representatives of “S” inspected the
property.
11. I regard these criticisms as well founded. I am particularly concerned that by
the time “S” inspected the property, the Applicant had removed the entire fill
which he had installed around the pool. I must say that in the circumstances,
I find it very hard to understand how “S” can be so certain that water had
built-up around the pool in the region of the plastic pit which had been
installed near the south western external corner of the pool. The fact that the
pit containing the pump had been installed at this point, has been sufficient
for “S” to reach the conclusion that external pressure was exerted to the wall
of the swimming pool at the location of the agricultural drainage pit
containing the pump:
Case No: 279610 Determination Page 10 of 14
“as the height and width of the pit and shaft would have taken the place of a
degree of the back fill, thus creating a void or partial void, I am of the opinion
that the absence or failure of back filling this area, which is designed to resist
external lateral ground movement and prevent the swimming pool walls from
collapsing inwards when draining or emptying of the pool is required, has
allowed the force exerted by the lateral movement in the adjacent soil to
impact locally on the wall and frame of the pool. This, in my opinion, has
caused top of the wall of the swimming pool, where the internal water
pressure is of the least resistance, to partially collapse in and under the
existing water level of the swimming pool. This in turn has allowed water to
escape the pool further contributing to the inward collapse of the swimming
pool wall and frame.”
12. The expert from “S” then goes on to say:
“I am also of the opinion that the volume of water deposited on the property
from the torrential rain and the overflowing of the nearby dam during the rain
event experienced in the region at the time has contributed to the expansion
and lateral movement in the surrounding soil.”
I note specifically that even 9 months after the event, the expert from “S” was
of the opinion that water overflowing from the dam may have been a
contributing factor.
13. Leaving aside the delay which elapsed in the obtaining of the “S” report, I
must comment that a number of the responses of the FSP have been
anything but adequate. As an example, after the claim was denied (but
before it was referred to this Service), the Applicant sought an internal
review by the FSP. The response to the request for the internal review was
written by one “LP” of the FSP on 9 January 2012. She reported (correctly)
that the Applicant had reported the claim on 29 November 2010. She then
said that “FSP arranged for “S” Building Consultants to attend your property
to establish the cause of the damage ”, but she failed to mention that this
attendance upon the property was not until a further nine months had
elapsed. No reference was made to the several reports which had been
received from the original assessors, “C” when dealing with the Applicant‟s
case. The IDR report also made reference to an expert report which the
Applicant had supplied from “Claytons Gro up” . This was entirely in error.
14. The IDR report then commented that “the „S‟ report confirms that if the pool
had been built correctly, water from recent rainfall would not have entered
the void area and caused damage. ”
15. I am of the opinion that although th e original assessor, and, later, “S”
considered that the likely cause of the damage to the pool was from a build -
up of water in the region of the pump, no one has actually attributed such an
event to a failure to have the pool built correctly. The Applicant has
established the fact that he purchased the pool from a named supplier, and
that the pool was inserted in the ground by a contractor engaged for that
purpose. As all consultants have commented, the Applicant has satisfied
them that when inserting the fill around the perimeter of the pool, he has
used a strength of 6:1 as opposed to 8:1 as recommended in the
Case No: 279610 Determination Page 11 of 14
specifications. In other words, in the installation of the pool, the Applicant
has gone further than the specifications would have required.
16. As the Applicant‟s own consultant “OC” has commented, it is very hard to
see how this problem has developed as a result of any error in construction
of the pool.
A Storm Event
17. I have read carefully the various submissions from the FSP in which it is
suggested that there is no proof that the initial damage arose as a result of a
storm event. I have also looked at the definition of “storm” within the policy. I
am not persuaded by this submission. In my opinion, there is abundant
evidence that indeed there was a very severe storm. Not only has the
Applicant alerted “C” when “C” has first inspected the property, to the fact
that water has overflowed from a dam on the property, but both “C”, and later
“S”, appear to have accepted that indeed this was the case.
18. At some point in its submissions, the FSP has suggested that a storm is not
evidenced by heavy rain alone. But the fact is that the Applicant has referred
in his initial claim, to the fact that the rain was accompanied by violent and
lashing winds. I am satisfied that there is abundant evidence of a storm
within the definition contained within the policy. I am also satisfied that a
specific cause of the problem which was encountered, was the overflow of
water from the dam. The policy provides for a cover for a flas h flood, and the
definition of flash flooding includes “ the overflow of any lake, river.... or any
other water course ( whether natural, altered or man-made) caused by a
storm where the flooding occurs within 24 consecutive hours of the storm
having commenc ed.”
19. The FSP has further suggested that a consideration of the phone call made
by the Applicant when he first lodged the claim would reveal that the terms of
the definition referred to above are not met.
20. I reject this view. Although the tape recording of the initial call is very hard to
hear, it does make plain that there was a cover above the pool and that it
was only when the Applicant noticed a bulge under the cover that he realised
that something may have occurred to the pool. This does not mean that the
damage to the pool had only occurred shortly before the call was made to
the FSP – indeed the Applicant reports that he had noticed the damage to
the pool the day before he recorded the claim.
The Wayne Tank Principle
21. The FSP has further asserted that if I am satisfied that damage was caused
by a storm, with or without flash flooding from the dam on the Applicant‟s
property, nevertheless, the proximate cause of the collapse of the pool is
hydrostatic pressure.
22. As to this suggestion, the FSP is reinforced both by the reports of “S”, and
also “CO”.
Case No: 279610 Determination Page 12 of 14
23. If I consider that the damage had been caused concurrently by the storm
(with or without the overflow of water from the dam) and hydrostatic pressure
exerted upon the walls of the pool, then I would agree that the decision in
Wayne Tank could properly be applied. In simple terms, under the Wayne
Tank principle, where there are two or more concurrent causes of the loss,
one of which is an insured event and one which is an excluded event, the
insurer is not liable to indemnify under the policy.
24. The difficulty in this case is that because of the absence of any detailed
reports obtained at a reasonable time after the incident, I consider that it
cannot be established that there were two concurrent events. In my opinion,
it is equally arguable that there were consequential events. The first was the
storm, with the accompanying heavy rain, and the overflow of water from the
dam. At some point, the water which has then found its way towards the
swimming pool, has found the weakest point in the surrounds of the pool.
The fact that there was a weakest point does not mean that the pool had
been inadequately constructed, rather, with any construction there will be a
weakest point however robust the construction.
25. I think that the probable explanation is that the water having found its way to
the surrounds of the pool then caused damage to the fill by the speed and
force with which the water built up. Ultimately, the filling combined with the
water, has been sufficient to cause pressure on the sides of the pool
therefore causing a collapse.
26. Perhaps, if reports obtained contemporaneously were available, one could
be more precise about the precise cause of the damage.
The Terms of Reference for this Service
“ 8.2 Dispute resolution criteria
Subject to paragraph 8.1, when deciding a Dispute and whether a remedy
should be provided in accordance with paragraph 9, FOS will do what in its
opinion is fair in all the circumstances, having regard to each of the following:
a) legal principles;
b) applicable industry codes or guidance as to practice;
c) good industry practice; and
d) previous relevant decisions of FOS or a Predecessor Scheme
(although FOS will not be bound by these). ”
27. As can be seen from the paragraph above, I am obliged to do what I
consider is fair in all the circumstances. I do not regard myself as free to
depart from established legal principles and if I were satisfied that the sole
cause of the damage to the pool had been hydrostatic pressure, a finding in
favour of the FSP would be inevitable.
28. But for the reasons that I have set out above and particularly the fact that no
contemporaneous reports are available, I am satisfied that the FSP should
indemnify the Applicant at least in part.
Case No: 279610 Determination Page 13 of 14
29. In reaching this conclusion, I also have regard to the fact that if the Applicant
had been advised as early as he should have been, that the claim was not
one for acceptance, then he could (as he has suggested in his submissions)
have taken remedial action a great deal earlier. I am satisfied that the
ultimate damage could have been considerably reduced if he had been able
to take earlier action, rather than awaiting the engineer‟s report requested by
“C” and which was eventually supplied by “S”. Ultimately, the damage to the
pool amounted to approximately $18,000 and I consider it as appropriate
that the FSP reimburse the Applicant for one half of this sum, notably
$9,000.
Compensation for delays in claim handling
30. As will be seen above, the Case Manager considered that there was no
adequate explanation by the FSP for the failure to obtain an engineer‟s
report earlier and he accepted that the failure of the FSP to act speedily, had
been the cause of a good deal of inconvenience etc. He therefore
considered that the FSP should compe nsate the Applicant in the sum of
$3,000.
31. I note that the Case Manager, very appropriately, alerted the FSP to the
possibility that there would be an award under paragraph 9.3 of the Terms of
Reference. I have noted also the extraordinarily detailed reply written by the
FSP in which it pointed out the large volume of claims arising from the
extraordinary weather events in various parts of Australia.
32. I must say that I do, at least in part, accept that explanation. However, it
seems plain that another enginee r had been engaged by “C” and I fail to
understand why “C” had not followed up the engagement and ensured that
the other engineer should have attended earlier.
33. However, having given the matter a great deal of consideration, I am inclined
to accept the explanation from the FSP as to the reason for the delay.
Further, in the decision which I have reached above, I have given
considerable weight to the absence of contemporaneous reports and the fact
that the absence of such reports casts considerable doubt on the
explanation furnished by “S”, and relied upon by the FSP.
34. In the circumstances, therefore, I do not propose to make a further award
under paragraph 9.3(b) of the Terms of Reference.
Determination
35. I determine that the FSP shall pay to the Applicant the s um of $9,000 being
one half of the costs expended by the Applicant following the collapse of the
swimming pool.
Case No: 279610 Determination Page 14 of 14
36. I further determine that the FSP shall pay interest upon this sum from 9
January 2012 (being the date of the IDR response) at the statutory rate, until
the date of settlement.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.