Text of the determination
Case No: 279496 Determination Page 1 of 9
Case number: 279496
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
12 September 2012
Background
1. A landlord insurance policy was incepted with the Financial Services
Provider (FSP) on 22 April 2009, that was arranged through an Insurance
Broker. The policy was issued in the name of a construction company of
which the Applicant is the director. The policy provided cover for loss or
damage caused by insured events as described in the policy for a home
building up to the sum insured of $160,000. The policy also provided cover
for weekly rent of $200. The building, the subject of the policy was a
residential house which was let to tenants.
2. On 13 April 2010, the Applicant lodged a claim through his Insurance Broker.
The loss occurred on 28 March 2010, as a result of damage to the building
caused by a motor vehicle getting out of control and hitting it.
3. The FSP appointed a loss adjuster to attend the property to inspect the
damage. Subsequently a building consultant was appointed to provide a
scope of works. The FSP obtained two builder’s quotes to repair the building
based on the scope of works.
4. The FSP was prepared to authorise repair of the building based on the
lowest quote of $50,486.15 Inc GST. The Applicant did not agree with this as
he believed the cost to repair the damage was in excess of $100,000. The
Applicant would not allow the FSP’s preferred builder to attend to repairs and
he authorised his own builder to undertake the repair of the building.
5. The Applicant then indicated to the FSP he would pursue recovery of the
buildings repair costs from the motor vehicle insurer of the vehicle which
struck the building. However, on 24 June 2010, the Applicant submitted, to
the FSP, an estimate to repair the building for $89,500.75. The FSP was of
the view the Applicant’s estimate included works not covered by the policy or
was not related to the claimed event and that it was excessive.
6. The FSP wrote to the Applicant on 30 July 2010, advising that as he was not
willing to allow its preferred builder to attend to repairs it would cash settle
Determination
Case No: 279496 Determination Page 2 of 9
him for the quoted amount of $50,486.15 inc. GST less the policy excess of
$200.
7. The FSP requested the Applicant advise within 14 days if he wished to
accept this offer or if he intended to pursue recovery of costs from the motor
vehicle insurer.
8. On 4 August 2010, the Applicant advised he had instructed solicitors to
approach the motor vehicle insurer regarding recovery of his losses. Certain
items of loss, eg carpets, would be potentially recoverable from the motor
vehicle insurer but not this FSP, because there was no contents cover.
9. On 7 March 2012, after a delay of 19 months, the Applicant’s solicitor
contacted the FSP seeking a settlement discussion regarding repairs costs.
It was confirmed that no recovery had been made from the other insurer.
10. The FSP verbally advised that although the Applicant had not substantiated
his incurred repair costs for the building it was prepared to settle the claim
for the amount of $60,000 plus eight weeks loss of rent.
11. The Applicant rejected the FSP’s offer of settlement and has referred this
matter to the Service with the assistance of his solicitor, whose submissions
have been of considerable assistance.
Summary of Applicant’s position
12. The Applicant says he elected to have his own sub-contractors complete the
repair of the building as he wanted it rectified promptly so the tenants could
be returned to the property.
13. The Applicant says the FSP’s offer of $50,486 was unsatisfactory as he
incurred much higher costs in using his sub-contractors to repair the
property.
14. The Applicant says that due to the disparity between the costs, he
commissioned a consulting service to complete a preliminary budget a nd
costs estimate report which calculated the cost of $89,500.75 but this
included an allowance for carpet which he accepts is not covered by the
policy.
15. The Applicant says contact was made with the FSP with the intention to
settle this claim as he had recently obtained a quantity surveyor’s report that
that assessed the rectifications costs at $71,502.
16. The Applicant says he has incurred both legal fees and reports
commissioned in support of his position.
17. The Applicant says that although he has incurred costs of approximately
$110,000 he is prepared to settle the matter for the amount of $70,000.
Case No: 279496 Determination Page 3 of 9
Summary of FSP’s position
18. The FSP says the Applicant refused to allow its preferred builder to carry out
building repairs. Accordingly, it offered cash settlement for quoted amount of
$50,486 based on a building consultant’s prepared scope of works.
19. The FSP says that as the Applicant was not happy with the offered amount
he advised he would pursue his costs from the third party insurer.
20. The FSP says the Applicant’s solicitor contacted it in M arch 2012, seeking
discussion regarding settlement of the claim. The FSP says it verbally
advised it was prepared to offer the total sum of $63,240 including loss of
rent. However this offer was rejected.
21. The FSP says that although the Applicant maintains that the cost of repair of
the building is approximately $110,000 he has not provided any
documentation to establish the incurred costs.
22. The FSP says it is still willing to settle the claim on the amount of $63,240.
23. The FSP relies on the following policy provisions:
“ How we will settle your buildings claim
1. At our option, we will:
a. repair or rebuild the damaged part of your building to the same
condition as when it was new;
b. pay the reasonable cost of repairing or rebuilding any damaged part
of your building to the same condition as when it was new.
...
If we pay the reasonable cost of repairing or rebuilding, this means the cost of
repairing or rebuilding less any discounts available to us were we to repair or
rebuild.
...
other benefits we will provide
...
10 . Rental cost after an insured event
(Applicable only when you have buildings cover or the building is part of a
strata title development and you have contents cover)
If the buildings are damage by an insured event covered by your policy, to
such an extent that your tenant cannot live in them, or we agree access to or
use of the buildings was not possible if any of the insured events covered by
this policy occur during the period of insurance and causes:
damage to other property in the vicinity of the buildings; or
...
this damage prevents access to or use of the building for a minimum
period of 7 days,
we will pay for your loss of rent on the buildings:
Case No: 279496 Determination Page 4 of 9
for the length of time which we agree is necessary to reinstate
your buildings or for which access is denied, or
up to a maximum period of 12 months,
whichever the period of time is the lesser.
The amount we will pay will be based on the weekly rent payable by
your tenant as at the date of damage to the buildings.
We will not pay for loss of rent if:
a. the buildings have not been tenanted for more than 60 consecutive
days immediately before the date of loss or damage; or
b. you did not have a contact in place for your buildings to be
tenanted within the 30 days immediately following the date of loss or
damage.
...
Making a claim
What you must do
...
You must also:
provide us with any original receipts, proof of ownership or
quotes we require to settle your claim;
...
What happens after you make a claim
1. Assist us with your claim
You must assist us with your claim. This means give us all the
information and assistance with your claim which we may
reasonably require. If you do not we may not pay your claim or
provide cover. If we have the right to recover any amount payable
under this policy from any other person, you must co-operate with
us in any action we may take.
...
4. Our rights of recovery
We have the right to recover from any person the amount of any claim
payable to you under this policy and we will have full discretion in the
conduct, settlement or defence of any claim in your name... ”
Issue
24. Whether the FSP ’s offer of settlement for the total sum of $63,240 fulfils its
obligation under the terms and conditions of the policy.
Case No: 279496 Determination Page 5 of 9
Reasons for decision
25. FOS has considered it is appropriate to expedite the dispute in accordance
with clause 8.6 of the FOS Terms of Reference. This is because of the issue
in dispute and quantum. This dispute has not been the subject of a FOS
Recommendation and has proceeded directly to Determination.
26. There has been an exchange of material between the parties. It is not
intended to recite information in this Determination except where considered
relevant.
27. It is not disputed the Applicant is covered by the policy for his loss. What has
been disputed is the FSP’s offer of settlement for damage caused to the
property. According to the FSP it verbally advised the Applicant it was
prepared to settle the claim for the total sum of $63,240 following contact
made in March 2012.
28. When the Applicant lodged his dispute with the Service it was indicated he
was prepared to accept $70,000 to resolve this matter. However in a letter
from his solicitor dated 17 May 2012, the amount sought for settlement was
now $85,568.This was itemed as:
cost of repairs based on quanti ty surveyor’s report dated 5 March 2012
- $71,502.
12 weeks rent at $200 - $2,400
cost of consultant’s report - $935
cost of quanti ty surveyor’s report - $2,288
legal fees for A pplicant’s solicitor - $1,700
other legal fees - $6,743
I consider that the “other legal fees” of $6,743 relate, in all probability to the
proposed claim against the third party or insurer.
29. It was also requested that the FSP pay interest in accordance with section
57 of the Insurance Contacts Act 1984 (the Act) on the amount of $85,568.
30. The Applicant is subject to the terms and conditions of the policy that he has
with the FSP. According to the policy the method by which a claim is settled
is at the FSP’s option. It can either:
(a) repair or rebuild the damaged part of your building to the same
condition as when it was new;
(b) pay the reasonable cost of repairing or rebuilding any damaged
part of your building to the same condition as when it was new.
(c) pay you up to the amount of the sum insured shown in the
current schedule for your relevant building.
31. According to the FSP it was willing to authorise repairs as it had a builder
prepared undertake the work. However, this option was not available when
Case No: 279496 Determination Page 6 of 9
the Applicant refused to allow the builder to do the work and authorised his
own builder.
32. T he Applicant’s solicitor says the Applicant maintains that before electing to
have his own company repair the property he was happy to have the
property repaired by the FSP’s appointed repairer.
33. However, he was concerned about the nature and scope of works which
underpinned the two quotes submitted by the builders to the FSP. The
Applicant says he was never provided with an itemised quote from the
builders.
34. I note the Applicant was ultimately provided with the scope of works on
which the quotes were based. Therefore the Applicant was aware of the
works required. The Applicant was advised by the loss adjuster that once
repairs commenced, if other unseen damage that was claim related became
apparent, this was still covered by the policy. The FSP would be liable for
any such additional work.
35. According to the Applicant’s solicitor, it was in June 2010, that the Applicant
elected to have his own company undertake the repair in an attempt to
mitigate his losses as the property had been untenanted for eight weeks.
36. However, I note an invoice dated July 2010 from the Applicant’s construction
company would indicate otherwise as it supervised the job from 28 March
2010.
37. The Applicant appointed his own building consultant to provide an estimate
of repairs. This report dated 11 June 2010, was submitted to the FSP for
consideration. Nonetheless, the FSP maintained its position as set out in its
letter dated 30 July 2010, it would cash settle on the amount of $50,486 in
accordance with the terms and conditions of the policy.
38. The Applicant again rejected this and advised in August 2010, he would
pursue recovery from the third party insurer.
39. It was not until March 2012, that contact was made with the FSP by the
Applicant’s solicitor seeking a settlement discussion. At this t ime the FSP
verbally advised its offer of settlement of $63,240.
40. F ollowing the exchange of information between the parties the Applicant’s
solicitor noted that the builder who quoted $50,486 withdrew his offer to
repair the property for that sum in June 2010, and that the FSP’s latest offer
was based on the other obtained builder’s quote.
41. The Applicant’s solicitor has raised an issue as to why this offer was not
made in 2010, when the preferred builder withdrew his offer.
42. I concur with the Applicant’s solicitor on this and I am not satisfied the FSP
acted in good faith in maintaining its offer to cash settle for $50,486 when it
was aware this quote had been withdrawn. I note the builder who provided
Case No: 279496 Determination Page 7 of 9
the second quote of $63,240 was not asked if he would have been prepared
to undertake the repairs.
43. Nevertheless, I cannot be satisfied, and indeed I doubt, the Applicant would
have accepted the offer of $63,240 had it been made at a more appropriate
time. Particularly as the Applicant had also rejected this amount based on
the loss adjuster’s 5 th report dated 22 June 2010.
44. Aside from this, I would have expected the FSP to have confirmed its offer of
settlement of $63,240.00 in writing to the Applicant.
Cost of repairs
45. I have considered the materials submitted by the parties including the
various castings, reports and other documentation. There is no suggestion
that the repairs undertaken by the Applicant were not covered by the scope
of works obtained by the FSP.
46. The Applicant obtained a quantity surveyor ’ s report dated 5 March 2012,
which is the surveyor’s opinion of the cost of rectification and repairs works.
47. However, I don’t consider the quantity surveyor’s report assist s the Applicant
at this time as the building was repaired in 2010 and according to the
Applicant it cost him approximately $100,000. Therefore I would expect him
to provide evidence of such or that the repairs could not have been
un dertaken by the FSP’s builder for the quoted amount.
48. The Applicant has submitted various documents in support of his
expenditure. I have reviewed these documents and I am somewhat
perplexed by them as evidence of expenditure.
49. The documents consist of invoices, quotations and photocopies of cheques
stubs. I would have expected all supporting documents would have been
invoices in support of expenditure.
50. Some are invoices which predate when the Applicant say he elected to have
sub-contractors undertake the repairs.
51. Some of the documents are duplicated and do not reflect they relate to the
insured property. Also some fall well short of appropriate evidence e.g.
invoice of $11,000 written on hotel notepaper.
52. I have considered the documents and am prepared to allow the documents
numbered 2, 4, 6, 7, 8, 9, 14, 17, 18, 19, 21, 22, and 23 as substantiation.
However these only account up to approximately half of the FS P’s
settlement offer of $63,240 which includes loss of rent. In summary the
Applicant has not substantiated his claimed expenditure of $100,000.
Case No: 279496 Determination Page 8 of 9
A later estimate provided to the FSP
53. I am also concerned that indeed the FSP had received an additional
estimate of costs from what I regard as a reliable source. The firm which
prepared the Scope of Works (AA) had produced its own estimate to the
FSP on 26 July 2012, in the sum of $68,695. However, the FSP chose to
rely upon two lower quotes received, one of which had been withdrawn. I
consider that the AA estimate forms the best evidence of the cost of repairs.
Reimbursement for reports
54. The Applicant has also requested payment for his reports. In view of my
comments in the preceding paragraph, I think that the Applicant was justified
in seeking a further report.
55. I consider an allowance of $1,500 should be made for the reports obtained
by the Applicant.
Legal fees
56. The Applicant has also asked for legal fees to be covered. I no te this relates
to two legal firms but only one has had dealings with the FSP and this did
not occur until March 2012. No documentation has been submitted in
support of legal costs, although I note that the current solicitors engaged by
the Applicant have done a great deal of work which has assisted in
determining this matter.
57. I consider that the FSP should pay $1500 towards the Applicant’s legal fees.
58. The question of interest is more difficult than usual, as considerable delay
has been caused by the Applicant’s decision to pursue his rights against the
other insurer. On the other hand the FSP has had the benefit of the
settlement money throughout.
59. I think the fairest course to adopt is to require the FSP to pay interest on the
sum of $68,695 from 20 June 2010, until 30 March 2012, at half the statutory
rate, and from 31 March 2012, until the date of settlement at the statutory
rate.
Determination
60. I determine the FSP has not fulfilled its obligations under the terms and
condition of the policy with its offer of settlement of $63,240.I am not
satisfied that this covered the repair of the building and loss of rent.
61. I determine that the FSP should pay to the Applicant the sum of $68,695
being the assessment by AA.
Case No: 279496 Determination Page 9 of 9
62. I further determine that the FSP reimburse the Applicant in the sum of
$2,000 for ten weeks rent.
63. I further determine that the FSP shall pay interest in accordance with
paragraph 60 and 61 above.
64. I also determine that the FSP shall pay to the Applicant the sum of $1,500
for the Reports and $1,500 for legal fees incurred to his current legal
advisors.