Home / Financial Firm (Unknown - Insurer) / Determination 279241

Determination 279241

Denial of stormwater damage claim under flood exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2012-09-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant's property was damaged by water in January 2011 and the FSP denied the claim as flood. AFCA found the initial stormwater damage covered and the later floodwater damage excluded, ordered indemnity for the stormwater part with the amount to be settled, and ordered interest.

The policy covers stormwater runoff, and the Panel found the cellar, foundation and shed damage occurred from stormwater before floodwaters arrived.

Issues

Subjects and remedies

natural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 279241 Determination Page 1 of 9 Case number: 279241 General Insurance - Domestic Insurance - Home Building & Contents - FSP Decision – Flood – Policy exclusion - Denial of claim 24 August 2012 Background 1. The Applicant held a Home Building & Contents Insurance Policy (the policy) with the Financial Services Provider (FSP). 2. The insured property sustained extensive damage on 14 January 2011 when inundated by water following the significant weather events experienced in Charlton in January 2011. 3. The Applicant lodged a claim for stormwater damage that was rejected by the FSP on the grounds that the damage arose from flood which is excluded under the policy. 4. The Applicant remains dissatisfied with the FSP‟s decision to decline his claim on the basis the loss is due to the excluded event of “Flood”. Summary of Applicant’s position 5. The Applicant in disputing the FSP‟s decision to decline the claim has sought the assistance of legal representatives “M”. In the interest of brevity both M and the Applicant will be referred to as the “the Applicant” for the purpose of this determination. 6. The Applicant maintains:  The damage to the property is due to stormwater runoff inundation arising from the significant rainfall in the area over the period 10 January – 14 January 2011.  The Applicant was present at the insured property when clear water from east/southeast surrounded the home at around 4.30pm on 14 January 2011.  The Applicant observed water rise up through the floor and lift the carpet at approximately 10.30pm on 14 January 2001.  The Applicant does not dispute Avoca River subsequently broke its banks and inundated the property to the maximum levels noted. Determination Case No: 279241 Determination Page 2 of 9 However, this was after the initial inundation by stormwater runoff which came down Donald Street.  The reports including lo ss adjusters “C” and hydrologists‟ “F” commissioned by the FSP are not sufficiently specific to the Applicant‟s circumstances. Further, the loss adjuster “B” is not adequately qualified to provide an opinion on the cause for the water damage.  The Service s hould give preference to the hydrology report by “PM” obtained and relied upon by the Applicant.  The property is in close proximity to stormwater drainage system so is more susceptible to stormwater runoff inundating the home. Summary of FSP’s position 7. The FSP maintains:  The policy is a “Defined Events” contract of insurance which includes „Storm and rainwater‟ as one of the listed defined events. However, the policy excludes from cover under all sections, loss arising from the event flood.  The Applicant has not made available the specific/written eyewitness accounts relied upon and accordingly is these alleged statements and/or accounts are considered hearsay evidence.  The FSP maintains the information noted in C‟s report is in line with what the Applicants advised the attending loss adjuster at the time of the inspection. Further, this information supports floodwater inundation of the home occurred late in the evening on14 January 2011.  PM‟s report does not refer to or provide a time for the alleged clear water inundation of the property.  PM‟s report provides the Avoca River reache d major flood levels at 5.15pm on 14 January 2011, which further confirms inundation would be due to floodwater.  F maintains that all rainfall in the area ceased by 8.00am on 14 January 2011, therefore inundation of the property later in the day was not the result of direct rainfall.  F‟s hydrology report specifically addresses the cause of water inundation at the insured property.  F concluded that the Avoca River initially broke its banks approximately 20km upstream of Charlton.  The FSP maintains that B does hold adequate qualifications to provide his opinion in respect to the cause of the water damage. 8. The FSP relies on the following policy provisions: “ Home Building Insurance Policy Case No: 279241 Determination Page 3 of 9 What we cover – insured events You are covered for damage or loss to your home building occurring during the period of cover and caused by the following events: Yes Storm and rainwater including stormwater runoff from areas surrounding the site, or water escaping from any water main, drain, pipe, street gutter, guttering or surface. No Damage or loss caused by flood . Flood means the inundation or covering of normally dry land by water which: escapes or overflows from, or cannot enter, because it is full or has overflowed, or is prevented from entering, because other water has already escaped or been released from it, the normal confines of any watercourse or lake, including any that may have been modified by human intervention, or reservoir, canal, dam or stormwater channel. … What we do not cover – general exclusions You are not covered under any section of the policy for damage, loss, cost or liability caused by or arising from or involving: flood, … Home Contents Insurance Policy What we cover – insured events You are covered for damage or loss to your contents while they are in your home or at the site, occurring during the period of cover, caused by the following events: Yes Storm and rainwater including stormwater runoff from areas surrounding the site, or water escaping from any water main, drain, pipe, street gutter, guttering or surface. No Damage or loss caused by flood . Flood means the inundation or covering of normally dry land by water which: escapes or overflows from, or cannot enter, because it is full or has overflowed, or is prevented from entering, because other water has already escaped or been released from it, the normal confines of any watercourse or lake, including any that may have been modified by human intervention, or reservoir, canal, dam or stormwater channel. Case No: 279241 Determination Page 4 of 9 … What we do not cover – general exclusions You are not covered under any section of the policy for damage, loss, cost or liability caused by or arising from or involving: flood ” Issues 9. Whether damage to the Applicant‟s property was inundated by floodwater and/or stormwater as defined by the policy. 10. Whether the FSP is entitled to decline indemnity to the Applicant under the policy. Reasons for decision 11. The Panel is satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issues raised. 12. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the FOS Terms of Reference. This is due to the circumstances of the dispute. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 13. This decision has been made by a Panel consisting of an Omb udsman, a representative with extensive experience in the insurance industry and a representative with extensive experience in consumer claims. 14. The Panel notes that the parties do not dispute the following:  The Applicant held an active home building and co ntents insurance policy with the FSP at the time of loss.  The FSP provided and the Applicant received the relevant policy documentation including the Product Disclosure Statement (PDS).  The insured property suffered significant damage arising from the inundation of the property by water on 14 January 2011.  The insured building is quite old and prior to the loss was subject to a certain degree of wear and tear. 15. The Panel having reviewed the available evidence is satisfied that the main issue in contention between the parties is whether the insured property was initially inundated by stormwater which would give rise to a degree o f indemnity under the policy. Case No: 279241 Determination Page 5 of 9 Cause of the Loss 16. The parties to the dispute have each obtained and rely upon information made available by their appointed consultants. The Panel notes that this information has been exchanged between the parties, each having had the opportunity to comment. Accordingly, in the interest of brevity, the Panel will only reiterate information from these reports it finds necessary in providing this Determination. Consultants’ Reports PM’s Charlton Floods - January 2011 dated 3 November 2011  The town of Charlton experienced heavy rainfall between 10 January- 14 January with extensive flooding in the area from Avoca River from 14 January onwards.  Total rainfall over this period was recorded at 168.6mm with 66.2mm falling between 9.00am on 13 January and 9.00am on 14 January.  The highest intensity rainfall recorded was 15mm/hr between 7.00am - 8.00am on 13 January. There was no rainfall recorded after 8.00am on 14 January.  Although the records calculate the rainfall intensity on an hourly basis, PM maintains that the rainfall periods at Charlton were highly concentrated in short duration burst e.g. 10 to 12 minute intervals. Accordingly, if calculated on this basis it would represent 20-50 year ARI rainfall events as opposed to 1-2 year ARI events (based on hourly intervals).  Accordingly, overflow from local drainage systems and culverts was highly likely as these systems are only designed to cope with 2-5 year ARI rainfall events.  There are two possible sources of rainwater run-off in Charlton, run-off which does not enter the stormwater drainage system and second run- off from surrounding rural areas.  All rainfall that fell on 13 January and 14 January would have become saturated overland flow and followed natural drainage lines into Charlton. This would have led to the inundation of Charlton on these dates prior to the arrival of floodwaters from Avoca River.  Floodwaters from Avoca River would be of high sediment loads (muddy/mucky) and would not be clear. Clear water inundation would support that prior to the arrival of floodwaters from Avoca River there was water sourced from local stormwater.  Depending on the exact locations of the properties, they will have begun to have been inundated from floodwater sometime on the afternoon or early evening 14 January. Any inundation before this time would be from runoff particularly corresponding to times when heavy rainfall were occurring (13 January and early morning 14 January). Case No: 279241 Determination Page 6 of 9 C’s Report  Date of inspection 29 January 2011.  The dwelling was in a generally poor condition with the habitable floor level 30cm above ground level.  Inundation of dwelling occurred between 10.00pm -11.00pm on 14 January 2011 with water from the west and dirty in nature.  Depth of inundation around 15cm inside the dwelling and 45cm in the shed.  Seems clear that it is floodwater inundation. F’s Flood and Stormwater Investigation Report March 2011  Charlton has a history of flooding.  Catchment area to Avoca River is 274,945 hectares to Charlton Township. Since the river is narrow and shallow, a significant catchment to the river is likely to cause frequent flooding within the area.  Hourly rainfall data indicates the maximum rainfall recorded was 15mm/hr which corresponds to a 1 in 2 year ARI rainfall event.  The town is reasonably flat with a fall of 0.1% across town north to south.  Site inspections were undertaken on 16 and 17 February in the presence of homeowners. There were minor inconsistencies observed regarding the time and date of inundations. Almost all advised water started inundating dwellings between 3.00pm-6.00pm on 14 January.  The level of water continued rising until the occupants were evacuated around 8.00pm on 14 January.  The last rainfall recorded in the area ceased at 8.00am on 14 January and therefore the rising water level was not due to direct rainfall.  The Applicant advised between 4.00pm-5.00pm water was level with the street. At 11.30pm water rose above floor level.  The property has a cellar approximately 2m deep with the side walls having a clay soil face, which collapsed due to the water.  The home was inundated to a depth of 500mm above ground level inside the home and 400mm above slab i n the garage.  The water causing the inundation from rear to front on Donald Street and from Wright Street. The property‟s surface is 100mm higher than the front boundary.  F formed the opinion that the inundation of the property was due to floodwaters from Avoca River on 14 January. 17. In view of the issues arising in this dispute, the Panel Chair Ombudsman and a member of the Panel conducted a site inspection of the property in the Case No: 279241 Determination Page 7 of 9 presence of the Applicant and a representative of the FSP on 27 June 2012. The Panel notes the following information from the site inspection:  The property is quite a large block located on the eastern side of Armstrong Street on the southern side of the township.  The Applicant advised that he first witnessed water crossing the road running down from Donald Street from the south/southeast and by 4.30pm (14 January) it spread right across his block.  There was a constant rush of water resulting in a considerable build up after approximately 4.00pm. The rushing water has inundated the ce llar under the rear of the property which has then collapsed. The collapse of the cellar impacted the stumps in this area of the home, which also collapsed.  The Panel members note that the dwelling was old and run down. Further, that the materials used in original construction were very susceptible to water damage i.e. would readily absorb moisture resulting in a significant degree of damage even with the slight introduction of moisture.  According to local residents Armstrong Street is the high point within the town. On discussing the unfolding of the events with witnesses present and having discussed this with other Applicants in the area, there was a consistent view that prior to the arrival of floodwater from the Avoca River, there was a strong flow of wa ter that came down Armstrong Street from the south and towards the centre of the town. Local residents claim this results from the Charlton-St Arnaud road having been raised and acting as a levy for the natural floodplain restricting the flow towards the Avoca river and diverting the water towards town.  According to the local residents in an attempt to ensure the road to the airport (Charlton St Arnaud Road which turns into Armstrong Street) remained free of flooding, the Council had built up the road with a number of culverts constructed under the road designed to channel the water towards the river to the west.  The Ombudsman, Panel member and FSP representatives met with a number of local residents at this point in the road. Witness accounts confirmed that the culverts were inadequate to channel the approaching stormwater runoff from the south/southeast. This stormwater approached the town as overland flow along a flood plain with no clear boundaries and/or bank etc. Unable to flow through the culverts this water has changed direction and flowed along the built up road through the paddocks towards Wright Street.  With the increase in stormwater runoff the flow has then overtopped the Charlton-St Arnaud Road and flowed north/northwest towards the township along the road which close to the township converts into Armstrong Street. Case No: 279241 Determination Page 8 of 9 18. The site visits undertaken by the Panel members have assisted in the Panel in gaining a greater understanding of the topography and impact of the stormwater runoff in the area prior to the arrival of floodwater from the Avoca River. The Panel notes the local residents ‟ information does not seem to have been considered in the hydrologists‟ reports provided by the parties. 19. The policy clearly provides cover for stormwater runoff from areas surrounding the site, or water escaping from any water main, drain, pipe, street gutter, guttering or surface. 20. Based on the Applicant‟s description of the initial inundation, the height of the habitable area of the Applican t‟s premises above ground level, relevant street levels and the hydrologist evidence provided by the parties, the Panel is satisfied that the collapse of the underground cellar, damage to the foundations and damage to the sheds and contents contained therein located on the property were initially inundated by stormwater that rushed through the property prior to the arrival of floodwaters. 21. It is unlikely stormwater inundated the residence above floor level. However, the floor boards within the residence and the wall coverings were such tha t sub floor water would be easily absorbed through them. In the absence of information to precisely indentify the extent of the damage that occurred due to stormwater the Panel determines it is fair in the circumstances that the FSP also meet the damage sustained to the wall coverings and floor coverings. 22. It is likely based on the Applicant‟s observations of the water lifting the floor, the hydrology and other information available that by around 10.30pm, there was the combined impact of stormwater runoff, overland flow and floodwaters from the Avoca River. The Applicant confirmed he observed the water entering the above floor area of the house around that time. Damage after this time would be excluded under the policy as flood damage. 23. The Panel has not been provided with sufficient information which would allow it to come to an informed decision as to the extent/degree (monetary) of the FSP‟s liability under the claim arising from the initial stormwater inundation of the sheds and dwelling (including the collapse of the cellar and impact of the building stumps in this area). The Panel accepts however given the nature of the building that the damage would be significant with the majority of building damage impacted by the initial inundation. 24. Save for the damage to the contents of the shed and damage to the floor coverings, the Panel is satisfied the remaining contents damage was most likely due to the combined effect of stormwater and flood and therefore are excluded under the policy. 25. Accordingly, the Panel urges the parties to act in a cooperative manner to reasonably establish the extent of damage to the insured property arising from the initial inundation including contents stored in the sheds. Case No: 279241 Determination Page 9 of 9 Determination 26. On the basis of the available information the Panel determines that the FSP is liable under the policy to provide indemnity to the Applicant in line with the matters discussed above. 27. Insofar as the FSP determines to cash settle the dispute. The FSP is to pay to the Applicant interest at the statutory rate, in line with Section 57 of the Insurance Contracts Act 1984, upon the final settlement figured agreed between the parties from 28 September 2011 (date of final decision) to final settlement of the claim.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.