Text of the determination
Case No: 278477 Determination Page 1 of 10
Case number: 278477
General Insurance - Domestic Insurance - Home Building - FSP Decision –
Service Quality – Compensation
21 February 2013
Background
1. This is a Determination following a rejection of a Recommendation.
2. On 26 March 2012, the Applicant referred to this Service a dispute with their
insurer (the Financial Services Provider (FSP)) with whom they held a home
building and contents insurance policy.
3. They had previously lodged a claim under the policy for damage to the
building arising from a water leak in the ensuite shower plumbing.
4. After the FSP accepted the claim, issues arose following inadequate
workmanship by a person or persons first entrusted to carry out the work.
Subsequently issues arose between the Applicants and the FSP as to the
FSP’s refusal to cover costs associated with additional works to maintain
uniform appearance, or to carry out additional work in an area that was not
actually damaged by an insured event.
5. On 6 September 2012, the matter was the subject of a Recommendation.
The Case Manager made the following Recommendation:
“On the basis of the available information I recommend that that the FSP is
not obliged to authorise under the claim:
The replacement and/or installation of the tiled shower hub in the main
bathroom to match that installed in the en-suite.
Replacement of the installed shower screens or vanity units in an
effort to ensure uniformity of appearance.
Installation of the floor to ceiling tiles on the walls of the bathrooms to
ensure a better finish.
Refund the excess and/or waive the applicable policy premium.
The FSP is to at a time convenient to the Applicants make arrangement to
have the main bedroom carpet and walk in wardrobe professionally cleaned.
The FSP is to ensure the Applica nts’ concerns in respect to the fitted vanity
unit are rectified as part of the authorised scope of works.
Determination
Case No: 278477 Determination Page 2 of 10
The FSP within 14 days of acceptance of this Recommendation by the parties
is to make arrangement to issue payment in the amount of $500 to the
Appli cants by way of compensation in line with paragraphs 48 to 51.”
6. The Applicants did not accept the Recommendation. They initially rejected it
on a number of grounds. However, by further email of 18 November 2012,
the Applicants narrowed the grounds for the dispute. In that email, they
confirmed that as a result of the Recommendation, certain works were taking
place and that issues relating to what I may describe as “the original dispute”
were being resolved.
7. However the Applicants continued to reject that aspect of the
Recommendation which dealt with the compensation payable under
paragraph 9.3(b)(i) of the Terms of Reference for this Service (see
paragraphs 47 – 51 of the Recommendation).
8. Thus, in summary, they reject the Case Manager’s Recommendation that
they should be paid the sum of $500 pursuant to paragraph 9.3(b)(i).
9. Before determining this matter I have read all of the material on the file,
including the material relating to what may be described as “the original
dispute”. I have then read the Recomme ndation and I have since read the
material filed by either party since the Recommendation including the
Applicants’ email of 18 November 2012.
10. For the sake of convenience it is preferable if I now set out the
Recommendation in full. I shall then make additional comments.
“ Background
1. The Applicants held a Home Building & Contents Insurance Policy (the
policy) with the Financial Services Provider (FSP).
2. A claim was lodged under the policy for building damage at the insured
property arising from a water leak in the ensuite shower plumbing.
3. The FSP accepted the claim however has refused to cover costs associated
with additional works to maintain uniform appearance and/or works in an
area that was not actually damaged by an insured event.
4. The Applicants remain dissatisfied with the outcome of their claim and are
seeking a review of their concerns by the Service.
Summary of Applicants’ position
5. The Applicants remain dissatisfied with the FSP’s management of their
claim, the time it has taken since lodgement and the service and/or quality of
works completed by its appointed builders.
6. The additional damage done to the insured property, the poor quality of
repairs undertaken and the unavailability of a replacement shower base are
all matters that are outside of the Applicants’ control.
Case No: 278477 Determination Page 3 of 10
7. The Applicants refute the FSP’s allegation that they refused the builders
access to the property. Rather, it was a case of mutual understanding that
the works be placed on hold until resolution of this dispute as they
(Applicants and builder) were not aware of what direction the FSP will take
in respect to authorising scope of works under the claim.
8. The Applicants (prior to the claim) had two bathrooms with matching
features including the shower bases, vanity units and shower screens. Now
due to the fault of the FSP’s representatives they are left in a position
completely unacceptable to them.
9. The Applicants are seeking for:
The shower hub in the main bathroom to be installed the same as the
tiled one installed in the ensuite by the FSP.
Both bathrooms (main and ensuite) to be installed with matching shower
screens and vanity units.
Walls in both bathrooms to be tiled from floor to ceiling (all walls).
Carpet in main bedroom and the walk in robe to be cleaned
professionally.
If the above cannot be authorised then in addition to undertaking the
approved scope of works the FSP refund the $500 excess and monthly
premium from the start of the claim to completion of the job.
Compensation in recognition of the time it has taken to undertake
repairs, stress caused, loss of enjoyment of their home etc.
Summary of FSP’ s position
10. The policy does not cover costs associated or required to repair and/or
rebuild property which has not been physically damaged due to an insured
event.
11. The FSP acknowledges the repairs undertaken under the claim were not
completed to an acceptable standard however since being made aware of
this it has taken all necessary steps to address this issue.
12. The Applicants’ demand for authorisation to install floor to ceiling tiles i s only
to achieve a better finish (look) however there is no damage and therefore
this is not covered under the policy.
13. Further, the policy does not allow for additional costs to be incurred under a
claim with the sole purpose of achieving cosmetic uniformity.
14. The FSP is prepared to fulfil its obligations as set out under the policy
however it is not prepared to include in its settlement benefits not covered
under the policy.
15. The FSP relies on the following policy provisions:
“ How we will settle your buildings claim
2. When it is not possible to use original materials during the repair or
rebuilding process, the nearest available equivalent to the original
materials will be used. We will not pay to repair or rebuild property
which has not been physically damaged.
…
Case No: 278477 Determination Page 4 of 10
When we will not pay a claim under your policy
…
2. Unless we state differently in your policy, we will not pay for:
b. any loss or damage which is not caused directly by one of the
insured events; ”
Issue
16. Whether the FSP is required to authorise additional repairs under the claim
in line with the Applicants stated expectations.
17. Whether the Applicants are entitled to compensation from the FSP in line
with the relevant paragraphs of Service’s Terms of Reference.
Reasons for Recommendation
18. I am satisfied that a full exchange of information has taken place between
each party and that each party has had the opportunity to address any
issues raised.
19. I have reviewed the submissions of the parties in relation to the terms and
conditions of the policy and will only refer to the relevant submissions and
materials raised.
20. I note the parties do not dispute the following:
The Applicants held an active home building and contents insurance
policy with the FSP at the time of loss.
The FSP provided and the Applicants received the relevant policy
documentation including the Product Disclosure Statement (PDS).
The insured property suffered significant damage arising from water
leaking in the vicinity of the two bathrooms and lounge room. The cost
of repairs although initially assessed to be at under $5,000 now stands
at an estimated value of over $17,000.
The FSP accepted the claim and authorised the scope of works quoted
by its appointed representative “P”. However the works, undertaken by
the original sub-contractor (O) appointed by P, were not completed to
an acceptable standard.
The FSP on being made aware of the Applicants’ concerns proceeded
to appoint a different builder “SC” with whom the Applicants’ seem to be
satisfied however works have been placed on hold pending an outcome
of this dispute.
The parties agree on the degree of damage arising from the insured
event as well as the additional damage done by O in the process of
undertaking the original repairs under the management of the FSP.
21. I have carefully considered the parties submissions and am satisfied that the
reason for this dispute being referred to the Service does not stem from the
extent, degree and cause of the damage authorised under the claim, as both
parties seem to be accept this aspect of the claim.
Case No: 278477 Determination Page 5 of 10
22. The issues in contention and which require consideration under this
Recommendation are in respect to the Applicants’ dissatisfaction with the
FSP’s management of the claim and what in their opinion constitutes
appropriate compensation under the claim. I have considered the various
alternate outcomes sought by the Applicants and the FSP’s response to
these demands under the below headings.
Shower hub in main bathroom
23. I note it is not in dispute that the FSP has accepted and authorised remedial
repair works in the home due to the additional damage caused by O during
the course of the original repairs. Further, arising from the fact that a similar
shower tray to the installed one was not available, the builders proceeded to
install a tiled shower tray/hub.
24. The Applicants maintain that this has resulted in there being a difference
between the two shower recesses in the ensuite and main bathroom areas.
This is unacceptable to them and accordingly they are seeking for the FSP
to bear the cost to install a similar shower tile hub in the main bathroom as
well.
25. I accept that the cause for the need to install the tile shower hub in the
ensuite arose as a result of O causing additional damage whilst undertaking
repairs in the area and the subsequent unavailability of a matching shower
tray. However in saying that, I acknowledge that the FSP’s authorised
representatives have accepted to undertake the remedial repairs at a cost to
them.
26. I have considered the policy and note that the relevant provision allows the
FSP, in the instance it is not possible to use and/or source the original
materials, to use the nearest available equivalent materials. Further, that the
policy does not allow for the repair/rebuild of property which has not been
physically damaged.
27. Accordingly, although I acknowledge the Applicants concerns in respect to
returning the property to the condition it was in prior to the claim, I am
satisfied that the FSP has reasonably attended to the remedial repairs and is
not obliged to install the tile shower hub in the main bathroom to achieve
uniformity.
Shower screens and Vanity units
28. Similar to the issue discussed above the Applicants have expressed their
dissatisfaction with respect to the fact that the FSP did not install matching
shower screens and vanity unit’s in each of the two bathrooms under the
claim.
29. Following on from the matters discussed in the above paragraphs 28 and
29, I am satisfied that in replacing the shower screens and vanity units with
new units of reasonably equivalent quality the FSP would fulfill its obligations
under the policy.
30. However I note the Applicants have raised concerns in respect to the
specifications of the vanity unit which is clearly larger than the original which
limits the available space for use of the toilet. I am not satisfied that this is
equivalent to placing the Applicants in the same position they were in prior to
the damage and accordingly the FSP is obliged to rectify this issue under
the claim.
Case No: 278477 Determination Page 6 of 10
Installation of floor to ceiling tiles
31. The Applicants, arisi ng from their dissatisfaction of the FSP’s management
of the claim and its authorised representatives’ poor quality workmanship,
are seeking for the FSP to authorise the installation of floor to ceiling tiles on
the walls in the bathrooms.
32. I note the Applicants had raised this matter with the FSP previously and
requested that it consider authorising the said works on an ex-gratia basis to
make up for the apparent short comings in the management of the claim.
33. The FSP notes the Applicants request in this respect arises from the
comments of the commissioned builders that the installation of the floor to
ceiling tiles to the walls of the bathrooms would help achieve a better finish
(look). However, the FSP maintains that there is no damage to the relevant
areas and accordingly these works are not covered under the policy.
34. I acknowledge the opinions of the parties in this respect and have
considered the relevant policy provisions. As noted above, the policy does
not provide indemnity for costs associated with the repair/rebuilding of
property which has not been physically damaged.
35. Accordingly, I accept the FSP is not required under the contract to authorise
the installation of the floor to ceiling tiles in the bathrooms. In respect to such
works being authorised on an ex-gratia basis or in pursuit of customer
service, this decision lies with the FSP only.
Carpet and walk in wardrobe
36. The Applicants have raised concerns in respect to a lack of consideration by
the FSP’s representatives when using the space in the ma in bedroom and
walk in wardrobe resulting in the carpet and wardrobe area requiring a
professional clean.
37. I note the FSP has not sought to counter this claim by the Applicants in any
detail. However, in light of the conduct of the FSP’s appointed
represent atives i.e. O, I am satisfied that the Applicants’ allegation in this
respect would, on the balance of probabilities, be accurate.
38. Accordingly, I am satisfied that in order to satisfy its obligations under the
claim, the FSP is to make arrangements for the main bedroom carpet and
walk in wardrobe to be professionally cleaned under the claim.
Refund of excess and policy premium payments
39. The Applicants have sought, as an alternative to the above discussed
issues, for the FSP to reimburse the $500 excess paid in addition to a
waiver of the policy premium for the period equal to the time elapsed since
lodgement of the claim and up until its final settlement.
40. I am satisfied that the payment of an excess is an obligation under the
policy. Accordingly the FSP is entitled to request for its payment whilst the
Applicants are obliged to make this contribution to the cost of the claim.
41. In respect to the policy premium, this is not a matter for which I am able to
provide a recommendation and such a decision lies with the FSP. In saying
that, I note that the premium applies to the policy as whole and is paid in
respect to obtaining indemnity for a set period and is not limited only to claim
in question. Indemnity under the policy and the FSP’s obligation to the
Case No: 278477 Determination Page 7 of 10
Applicants continued over the relevant time and was subject to the payment
of the premium.
Time taken and management of the claim
42. The Applicants maintain that the FSP earlier in the claim had assured them
that the approved scope of works would be completed by January 2012.
However, at the time of lodging this dispute with the Service it had already
been just under nine months since lodgement of the claim.
43. Further, that the delay in finalising the repairs was due to poor management
of the claim by the FSP, the poor quality of repairs originally undertaken and
the issue in respect to the appointed builders not showing up to the property
or only attending for short periods.
44. The FSP has not refuted the Applicants’ position in this respect in much
detail, however maintain s that on being made aware of the Applicants’
concerns it took all necessary steps to address them.
45. I have carefully considered the available information in relation to the FSP’s
management of the claim, the communication between all parties concerned
and the affect of the relevant issues on the Applicants. I do note that the
scope of works did require updating on a number of occasions due to
additional damage being identified whilst repairs were being completed.
46. In saying that, I also note that a major reason for additional repairs and
therefore time, relates to the poor quality repairs originally completed by O
(requiring rectification) and the additional damage it also caused during
these repairs.
47. Further, I am also satisfied that the Applicants have established, on the
balance of probabilities, that they throughout the life of the claim had to
continually contact the FSP and/or its representative to obtain updates on
the status of the claim.
48. Accordingly, I am satisfied that the FSP’s (and its represen tatives) conduct
caused an unusual delay in the finalisation of the repairs, unusual degree of
physical inconvenience and interference with their expectation of enjoyment
or peace of mind of the Applicants over this extended period.
49. I consider the following FOS Terms of Reference relevant to this dispute:
“ 9.3 Other compensation
a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that
the Financial Services Provider compensate the Applicant for
consequential financial loss or damage up to a maximum amount of
$3,000 per claim made in the Dispute
...
b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that
the Financial Services Provider Compensate the Applicant for non-
financial loss but only where:
(i) an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the Applicant’s expectation of
enjoyment or peace of mind has occurred; or
(ii) in the case of a Dispute pertaining to an individual’s privacy rights –
injury has occurred to the Applicant ’s feelings or humiliation has been
suffered by the Applicant.”
Case No: 278477 Determination Page 8 of 10
50. Under 9.3(b) of the Terms of Reference (TOR) there must be an unusual
degree or extent of physical inconvenience, time taken to resolve the
situation or interference with the Applicant’s expec tation of enjoyment or
peace of mind has occurred before compensation for non-financial loss may
be determined. As noted above, I am satisfied that the evidence before me
establishes such an usual degree of time taken, inconvenience and
interference during the life of the claim did occur.
51. Therefore, I am satisfied that in line with clause 9.3(b) of the Terms of
Reference the Applicants are entitled to compensation for non financial loss.
Recommendation
52. On the basis of the available information I recommend that that the FSP is
not obliged to authorise under the claim:
The replacement and/or installation of the tiled shower hub in the main
bathroom to match that installed in the en-suite.
Replacement of the installed shower screens or vanity units in an effort
to ensure uniformity of appearance.
Installation of the floor to ceiling tiles on the walls of the bathrooms to
ensure a better finish.
Refund the excess and/or waive the applicable policy premium.
53. The FSP is to at a time convenient to the Applicants make arrangement to
have the main bedroom carpet and walk in wardrobe professionally cleaned.
54. The FSP is to ensure the Applicants’ concerns in respect to the fitted vanity
unit are rectified as part of the authorised scope of works.
55. The FSP within 14 days of acceptance of this Recommendation by the
parties is to make arrangement to issue payment in the amount of $500 to
the Applicants by way of compensation in line with paragraphs 48 to 51. ”
Other Comments
11. As set out above, the only issue now remaining for consideration is the
question as to whether the Applicants are entitled to an award of
compensation for non-financial loss, pursuant to paragraph 9.3(b)(i) of the
Terms of Reference.
12. It must be understood that the making of awards of compensation under this
heading is not common. The power to make such awards was introduced in
2010 and the decisions taken at this Service have continually stressed that
in order to be eligible for compensation pursuant to these paragraphs, the
Applicants must establish an unusual degree or extent of inconvenience, or
time taken to resolve the situation, or interference with the Applicants ’
expectation of enjoyment or peace of mind.
13. To an extent it must be recognised that many claims against an FSP will be
stressful. An FSP has the reasonable expectation that it will not be liable for
claims except as specified in the contract of insurance between the parties.
Case No: 278477 Determination Page 9 of 10
14. My assessment of this matter is that at the early stages of the claim, the
matter proceeded normally and satisfactorily. Assessors were engaged at an
early stage but problems appear to have arisen as a result of the work which
was carried out by the first contractors who were engaged.
15. When the matters between the parties took on the form of a dispute, it was in
relation to a number of matters which I would describe as quite serious.
Ultimately some $17,000 has been expended. The relief which the
Applicants were seeking against the FSP involved the serious matters
referred to in paragraphs 23-38 of the Recommendation.
16. However, the most serious items were the claim of installation of floor to
ceiling tiles and the claim in respect to the shower hub in the main bathroom.
17. In respect to both of these items, I consider that the Case Manager’s
Recommendation was correct. In other words, whilst I can understand why
the Applicants considered that these were matters for which they were
entitled to relief, I consider that the Case Manager was correct in his
decision that they were not.
18. Having said this, I recognise that the Case Manager did make
recommendations in favour of the Applicants as to other aspects of the
matter, and having read all of the material I entirely agree with the Case
Manager’s comments that the Applicants have established , on the balance
of probabilities, that they had to frequently contact the FSP and/or its
representatives to obtain updates as to the status of the claim and that a
large proportion of the “quite extraordinary” delay, has been due to the
inadequate workmanship of the first contractor “O” who was engaged on
behalf of the FSP.
19. Therefore, having considered the matter anew, I have considered whether
the FSP has had the reasonable opportunity to consider this issue.
20. It is noted that in their original letter of 25 March 2012 to this Service, the
Applicants made plain the fact that they were complaining about the quality
of the Service offered by the FSP.
21. In the FSP’s response of 20 April 2012, the FSP chose to deal with the
Applicants’ complaints about the quality of service in the following man ner:
“we apologise to the Applicants for any inconvenience caused to them during
the management of this claim by all parties involved and especially for the
poor workmanship performed by the initial builder.”
22. I therefore do conclude that the FSP has been alerted to the fact that the
Applicants are seeking compensation of the kind which is described in
paragraph 9.3(b)(i).
23. Since the Recommendation, the FSP has acted, in my view, very
appropriately. It is plain that arrangements have been made for a meeting
between the Applicants, and various contractors on behalf of the FSP. The
matters which were previously at issue have been substantially resolved. (I
Case No: 278477 Determination Page 10 of 10
note that, incorrectly, the FSP has paid the sum of $500 recommended by
the Case Manager pursuant to paragraph 9.3(b)(i). This sum should not
have been paid until the Applicants had accepted the Recommendation.
24. In my view at least part of the delay which has followed once the parties
became involved in a dispute, has been because of the Applicants’ requests
for items for which they were not entitled to cover pursuant to the policy.
These matters have been dealt with appropriately in the Recommendation.
On the other hand, there is no doubt that a large part of the reasons for the
dispute initially, was because of the poor work carried out by “O” and the
issues which arose as to the rectification of his work.
25. For these reasons, and after giving the matter a great deal of consideration, I
am satisfied that the Applicants are entitled to an award of compensation
pursuant to the Terms of Reference.
26. I am of the view, however, that the sum which should be awarded is a
relatively modest figure. Again, after considering the matter in some detail, I
consider that the appropriate figure is $1,000. In awarding this sum, I have
been conscious of the fact that the FSP has decided to forego the excess.
This is not a course which is usually followed. It is a matter appropriate for
consideration.
Determination
27. Within 14 days of acceptance of this Determination, the FSP pay to the
Applicants the sum of $500, being the sum of $1,000 which I determine to be
appropriate pursuant to paragraph 9.3(b)(i) of the FOS Terms of Reference,
less the sum of $500 already paid by the FSP to the Applicants pursuant to
the Terms of Reference.