Home / Financial Firm (Unknown - Insurer) / Determination 278468
Determination 278468
Partial denial of Cyclone Yasi damage claim under faulty workmanship exclusion
Summary
The applicant claimed cyclone and roof-leak damage to his home. The FSP accepted some repairs and denied eaves, soffit and wall lining as pre-existing or faulty workmanship. AFCA ordered flooring repairs, roof sheet replacement and reimbursement of the $440 expert report, but upheld the denial of the other damage.
The FSP must show an excluded cause, and it could not do so for the water-damaged flooring, while the eaves and wall cracking were painted over before the claimed event.
Issues
- Claim denial primary · upheld
“I am not satisfied the FSP has established that water damage to flooring resulted from an excluded cause; the FSP is to indemnify the repair of water damaged flooring.”
- Inadequate claim investigation secondary · not upheld
“I am satisfied he is qualified to provide an opinion and that the FSP is entitled to rely on his opinion.”
Subjects and remedies
home or building damagenatural disasterpay claimrepair or rectify
Text of the determination
Case No: 278468 Determination Page 1 of 7
Case number: 278468
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
26 September 2012
Background
1. The Applicant and his wife are insured with the Financial Services Provider
(FSP) under a home building insurance policy that covers the home building
and contents for accidental loss as well as loss or damage caused by
specified events. The policy was arranged through an insurance broker. The
relevant period of insurance is 9 February 2010 to 9 February 2011.
2. On 21 February 2011 the Applicant lodged a claim for damage to the insured
property as result of Cyclone Yasi. Damage was reported to:
fencing around the property;
granny flat kitchen cabinets;
two outdoor ceiling fans;
loss of food.
3. The FSP appointed a loss adjuster to attend the property to inspect the
damage, following which the FSP accepted the claim and arranged
settlement.
4. On 29 June 2011 the Applicant contacted the FSP to notify of water damage
as a result of water exiting an external wall and onto the floor beneath a
kitchen cupboard. The FSP arranged for a plumber to attend the site. The
plumber found a hole in a roof sheet which he sealed with silicone.
5. A building consultant (DM) was appointed to attend the property to report on
the cause of damage. Based on his report the FSP accepted some damage
that was related to the cyclone event. The FSP did not accept all damage
was caused by Cyclone Yasi and referred to the policy exclusion regarding
faulty workmanship.
6. According to the FSP the damage not covered was in relation to:
main residence rear elevation eaves/soffit;
fibro cement weatherboard wall lining;
underside of deck flooring, kitchen and dining room junction.
Determination
Case No: 278468 Determination Page 2 of 7
7. The Applicant disagreed with the FSP’s decision not to accept all the
damage claimed was cyclone related. The Applicant raised issue with faults
contained in DM’s report.
8. The Applicant obtained his own independent report to support his position
with cyclone damage. However, the FSP has maintained its decision that not
all damage claimed is covered.
Summary of Applicant’s position
9. The Applicant says DM was not interested in assessing the claim but in
fabricating faults and misrepresenting the condition of the house.
10. The Applicant says he raised this with the loss adjuster about faults that had
been incorrectly identified by DM but she refused to take this up with the
FSP.
11. The Applicant says he had to appoint his own building inspector to disprove
DM’s findings. The FSP has refused to accept that the faults identified by
DM are flawed.
12. The Applicant says water damage was caused by a puncture in roof
sheeting and has nothing to do with poor quality workmanship and should be
treated as such.
13. The Applicant is seeking the following resolution:
replace roof sheeting and flashings to suit material of similar quality to
existing;
replace and repaint broken eaves sheeting;
repaint internal walls and ceiling where required to match;
replace wall sheeting cracked around doorway;
repair flooring where water has exited;
payment of independent report.
Summary of FSP’s position
14. Solicitors acting on behalf of the FSP have prepared the submission(s) in
response to the Applicant’s dispute.
15. The FSP says it has responded to the claim for damage caused by Cyclone
Yasi.
16. The FSP says the evidence indicates that additional damage claimed is
longstanding and predates the cyclone and was caused by faulty
workmanship.
Case No: 278468 Determination Page 3 of 7
17. The FSP says that even if it was considered the cyclone caused or
contributed to the additional damage, the proximate cause of the loss was
faulty workmanship.
18. The FSP says faulty workmanship is an exclusion under the policy and
accordingly it is not liable for costs in replacing or rectifying damage to eaves
lining, wall lining or underside of the deck.
19. The FSP relies on the following policy provisions:
“ Section 2: Cover for your Home & Contents – Accidental damage
What you are insured against, and what you are NOT
You are insured against malicious damage, accidental loss or damage
(including Specified events listed below) to your home, contents or both at the
site during the period of insurance.
...
Specified events
‘Specified events’ means loss or damage directly caused by the
following Events (a) to (r);
...
(g) storm, tempest, rainwater, wind, hail, tornado, cyclone or hurricane, freeze
or weight if snow
...
Section 7: When you are not covered
General exclusions applying to this Policy
...
Additional exclusions applying to this Policy
These Additional exclusions apply to cover for your home, contents,
Additional benefits, and valuables (if you have chosen that option).
This policy does not cover:
...
(b) loss or damage resulting from or caused by:
...
water seeping through a wall or floor
...
Inherent defects, structural defects, faulty workmanship, faulty design
or any gradual process
w ear, tear, rust corrosion, depreciation or gradual deterioration”
Issue
20. Whether the disputed damage has resulted from an event covered by the
policy.
Case No: 278468 Determination Page 4 of 7
Reasons for decision
21. FOS has considered it is appropriate to expedite the dispute in accordance
with clause 8.6 of the FOS Terms of Reference. This dispute has not been
the subject of a FOS Recommendation and has proceeded directly to
Determination.
22. There has been an exchange of material between the parties. It is not
intended to recite information in this Determination except where considered
relevant.
23. The FSP has raised the issue about the Applicant denying access to the
property. The FSP has not provided any statement from any person who
was purported to have been denied access.
24. According to the Applicant he says he advised the plumber there was no
point in attending the property if he was only going to quote on the
replacement of one roof sheet. I accept the Applicant’s version.
25. The FSP also responded with a reply regarding DM having a vendetta
against the Applicant. In reading the Applicant’s submission he felt the loss
adjuster had a vendetta against him and wanted her replaced as she was
not prepared to consider whether DM’s report has been flawed.
26. Nevertheless, the Applicant did complain about DM ’s report which he says
consisted of fabricated faults and unfounded allegations about the condition
of the house. The Applicant also complained about terminology used by DM
in his report. I note this was in regards to DM’s description of the type of roof
and roof sheeting.
27. DM advised the terminology used by him is commonly used. I have no issue
with the terminology used by DM.
28. According to DM he attended the site to report on the precise extent and
cause of damage and whether the damage claimed directly resulted from
Cyclone Yasi. I am satisfied he is qualified to provide an opinion in such
circumstances and that the FSP is entitled to rely on his opinion.
29. In any case, if the Applicant disagrees with the evidence relied upon by the
FSP it is upon him to provide persuasive evidence to contradict the findings
relied upon by the FSP. The Applicant obtained his own report but the FSP
has not altered its decision.
30. The FSP has accepted the following repairs:
bleedseal and paint kitchen approximately 12 square metres ceiling
and exposed rafters;
bleedseal and repaint one kitchen wall approximately 14 square
metres;
remove and replace matching existing one metal roof sheet.
Case No: 278468 Determination Page 5 of 7
Disputed damage
31. I note the punctured roof sheet was temporarily repaired. The Applicant was
of the view, based on information provided to him that the same profile roof
sheet was no longer available. DM has confirmed the roof sheet can be
replaced. In my determination, the FSP must attend to the replacement of
the roof sheet as soon as possible, and the Applicant must cooperate with
the FSP’s repairer and provide access to the property. I reject the Applicant’s
experts’ (BR and DH) opinion that the entire roof sheeting nee ds to be
replaced.
32. The crux of the dispute entails damage which the FSP says is not covered
by the policy. The disputed damage is:
Eaves/soffit
Fibro cement weatherboard lining
Underside decking floor
33. The FSP relies on the evidence of its appointed consultant that the claimed
cyclone event has not caused this damage but was the result of causes
excluded by the policy.
34. The Applicant disagrees with DM’s findings and obtained his own building
inspector’s (DH) report. DM was provided with a copy of the DH’s report but
DM maintained his position on which the FSP relies on.
35. For the purpose of this determination I will address the disputed damage as
follows.
Eaves/soffit/fibro cement wall lining
36. DM was of the view that the identified cracking was not cyclone damage as
the cracking had been painted over. According to the Applicant this occurred
3-4 years ago.
37. DH has indicated that cyclonic winds can cause abnormal loads on
structures. He says he observed this type of damage after Cyclone Larry. It
was his opinion the paint was applied prior to the crack and it has stretched
(being flexible and elastic) over the crack leaving strands of paint over
cracks.
38. In response to DH’s report, DM also advised he had inspected a large
number of cyclone damage homes from both C yclone Larry and Yasi. DM
maintained his report as being accurate.
39. There is conflicting expert opinion as to whether the cracking is cyclone
damage. Photographs have been provided showing the cracking are not
conclusive to establish the cause but are persuasive in supporting DM’s
opinion that the cracks had been painted over.
Case No: 278468 Determination Page 6 of 7
40. Therefore, in consideration of the evidence, on the balance of probabilities I
am not satisfied the identified cracking has been caused by the claimed
cyclone event.
41. Accordingly, I am satisfied the FSP was entitled to deny indemnity to the the
repair of the eaves/soffit/fibro cement wall lining.
Underside flooring
42. DM reported the water staining the underside of the flooring deck and
kitchen was considered to have resulted from numerous events of various
ages including Cyclone Yasi. DM said water escaped from the roof above
due to inappropriate flashings and poor roofing design.
43. DM also indicated the deck junction and kitchen did not have an appropriate
step down and were found to be near level.
44. DM was of the view this water damage was the result of faulty workmanship.
45. DH reported that the gutters overflowed from the claimed event and that
water staining under the kitchen floor is occurring around the points the
cyclone rods came through the floor. He also indicated he did not have an
issue with the rear deck junction and kitchen floor. He said there was a step
up of approximately 22mm from external to internal.
46. DM maintains his position of defective construction in regards to the step up
and flashing.
47. I note DH has indicated that the timber construction used is something he
has done as a practising builder.
48. However on reading DM’s report it is not succinct as to what the appropriate
construction or flashing should entail. There is no indication that the building
did not comply with any building codes at the time of construction.
49. It is not disputed that water entered through the punctured roof sheet. I am
not satisfied the FSP has established that water damage to flooring resulted
from an excluded cause.
50. The FSP is to indemnify the Applicant for the repair of water damaged
flooring.
Kitchen ceiling
51. I note DH has suggest the entire kitchen ceiling be painted. However due to
the ceiling been separated by rafters the FSP is only obliged to paint the
damaged area of the ceiling which is identified as 12 square metres and
exposed rafters.
Case No: 278468 Determination Page 7 of 7
Determination
52. On the basis of the available information I determine the FSP indemnify the
Applicant, in addition to the already accepted painting repairs, the repair of
the deck and kitchen flooring.
53. The FSP is to arrange the replacement of the damaged iron roof sheet.
54. The Applicant incurred a cost of $440 in obtaining his expert report which
has assisted in determining this matter. Accordingly, the FSP is to reimburse
the Applicant for this cost.