Text of the determination
Case No: 278299 Determination Page 1 of 16
Case number: 278299
General Insurance - Domestic Insurance - Home Building - Instructions –
Delay/Settlement
30 January 2013
Background
1. The Applicant held a landlord’s home building insurance policy with the
Financial Services Provider (FSP) which was current at the time of loss. The
insurance policy provided a building sum insured of $191,800 and a loss of
rent sum insured of $7,500. Applicable excesses relevant to this claim
include a malicious damage excess of $650, basic excess of $250 and a rent
default excess of $650, making a total excess for the claim lodged by the
Applicant of $1,550.
2. The Applicant’s real estate agent, “L”, contacted the FSP on the Applicant’s
behalf on 30 September 2011 reporting damage to the Applicant’s property
which she believed occurred on 22 September 2011. It was indicated
previous tenants had been evicted and subsequent malicious damage had
been infl icted upon the Applicant’s property.
3. The FSP requested further information and appointed an assessor to attend
to inspect the damage. Quotations for repairs were arranged and the
Applicant requested to be cash settled for the claim so he could affect
repairs himself.
4. The Applicant rejected the offer made by the FSP for the repairs, rent default
and loss of rent claim as a result of this incident, saying the amounts offered
could not adequately repair the property, nor was the offer fair and
reasonable. The Applicant has since accepted the amount offered on the
provision that it is not a final settlement and is subject to the outcome of the
dispute with FOS.
Summary of Applicant’s position
5. The Applicant, via his real estate agent , “L” , has provided a quotation for the
repairs required to the property. This quotation takes into account all
damage requiring repairs including those items which were not included in
the FSP’s builder’s scope of works.
Determination
Case No: 278299 Determination Page 2 of 16
6. The upper kitchen cupboards were damaged by steam and should also be
replaced as they may not match the lower cupboards which were damaged
as a result of this incident.
7. The FSP’s builder failed to include items such as the stove/oven, rangehood,
toilet repairs, bedroom robe repairs etc, and these items have been included
in the quote “L” obtained. The FSP’s quotation also needs to include the
costs associated with the removal of rubbish and debris associated with the
repairs.
8. The FSP has caused many lengthy delays in the processing and handling of
his claim and as such, he seeks interest on the amount owed to him.
9. The claim for loss of rent should be until the home was fit to be inhabited
again by tenants. In an email dated 30 November 2012, the property is to be
tenanted from 30 November 2012.
10. The previous tenants had defaulted on rent payments prior to being evicted
and the amount offered for this aspect of the claim does not reflect the true
amount owing to him for rent.
11. He seeks a fair and reasonable settlement for all aspects of his claim.
Summary of FSP’s position
12. The FSP says the offer made to the Applicant is fair and reasonable and
based on quotations it received from builders it appointed who quoted the
repairs in accordance with the scope of works prepared by its assessor.
13. It acknowledges that some minor delays were caused by it and have offered
an additional three weeks loss of rent to the loss of rent settlement. It says
the repair timeframe was estimated at five weeks, and therefore an offer for
eight weeks loss of rent was made to the Applicant.
14. Some delays were experienced by the FSP in awaiting documentation from
“L” in order for it to calculate the rent default settlement and loss of rent
settlement. In addition, it had to await copies of property inspection reports
which were also delayed from “L” .
15. It is not responsible for replacing the upper kitchen cupboards as these items
were not damaged as a result of the events being claimed and the assessor
noted there was no damage to these cupboards or a pantry in the kitchen.
There is no cover for “matching” exis ting undamaged items to those items
being repaired/replaced.
16. Other items detailed by the Applicant and “L” were not noted as being
damaged when the assessor viewed the damage in the company of the
Applicant and “L” , and were not brought to his attention as showing any
signs of damage.
Case No: 278299 Determination Page 3 of 16
17. Some items being claimed are contents items which the Applicant has no
insurance cover for.
18. The FSP relies on the following policy provisions of its Product Disclosure
Statement (PDS):
“ Excesses that may apply when you make a claim
An ‘excess’ is your contribution towards the cost of a claim. We will tell
you if you need to pay an excess when you make a claim.
They type of excess that applies to your policy and the amount of that excess
will be listed on your schedule. You may need to pay more than one type of
excess when you make a claim. You will only need to pay this amount once
when you make a claim.
...
Your excess will be increased by $400 for any loss or damage that occurs as
a result of:
deliberate or intentional acts, or vandalism or malicious acts by your
tenants or their visitors,
your tenant leaving your building,
your tenant ceases to pay rent,
your tenant being evicted from your buildings, or
the theft of any part of your buildings or contents by your tenants or their
visitors.
When a claim is made for what we identify as one or more separate incidents,
you will need to pay any excesses that apply for each separate incident we
have identified.”
(Page 5)
“ Bond money we may deduct when you make a claim
We will reduce the amount we will pay for loss or damage to your
building or contents, rent default or legal expenses by any bond money
that you are entitled to use to pay for or reduce the cost of any loss or
damage. ”
(Page 5)
“ Loss of rent
With this option, if your buildings or sections of your buildings suffer
loss or damage and are uninhabitable as a result, we will cover any loss
of rent equal to the weekly amount as stated on your rental agreement
or periodic tenancy agreement for up to 12 months. The most we will
pay is up to the sum insured, as listed on your schedule.
...
This cover applies when
loss or damage to your buildings or contents occurs as a result of an
incident as listed in this PDS
access to your rental property is prevented due to loss or damage to other
property located near your rental property
Case No: 278299 Determination Page 4 of 16
We will ONLY cover loss of rent while your rental property is uninhabitable.
We will also provide cover for up to two weeks rent, up to $1000 (inclusive of
GST) after
...
This cover will stop immediately if your rental property is re-tenanted.
An excess may apply to this option.
This option is available for buildings or contents policies.”
(Pages 20 and 21)
“ Rent default and theft by a tenant
With this option, we will cover
rent default and theft by a tenant
legal costs you incur as a result of rent default or theft by a tenant.
If you choose this option, it will be listed on your schedule as ‘Rent default and
theft by a tenant’.
We will ONLY cover rent default for the weekly amount your rental property is
leased for, up to $5,000 (inclusive of GST), less any excess or bond money
that applies
...
if your tenant is legally evicted from your rental property
...
We will ONLY pay a rent default claim
if the tenant breaches your rental agreement or periodic tenancy
agreement, and
you have taken all reasonable steps legally available to you under the
Residential Tenancies Act, or other relevant State or Territory Legislation,
to remedy non-payment and evict the tenant.
...
This cover will stop immediately
if your rental property is re-tenanted, or
when the term of your rental agreement ends.
We will ONLY cover theft by a tenant or their visitors of
any part of your buildings, up to the buildings sum insured, as listed on
your schedule, after deducting any excess that applies, if you have
insured your buildings
...”
(Pages 21 to 23)
“ How we settle a buildings claim
We will decide how we will settle your claim
If your buildings suffer loss or damage, we will decide whether to
repair
Case No: 278299 Determination Page 5 of 16
rebuild, or
pay you the cost to repair or rebuild that part of your buildings that
suffered loss or damage.
If we do, we will
pay you up to the buildings sum insured, as listed on your schedule
only repair, rebuild or pay you for the part or parts of the building that
actually sustained loss or damage, including damaged portions of fixed
coverings to walls, floors and ceilings only in the room, hall or passage
where the damage occurred
try to match any material used to repair your buildings with the original
materials or nearest equivalent available to the original materials
...”
(Page 45)
Issues
19. Whether the FSP has offered a fair and reasonable settlement for:
Cost of repairs to the Applicant’s property
Rent default
Loss of rent
20. Whether the Applicant is entitled to any settlement for the cleaning up of the
mess left at the property by the tenant.
21. Whether the Applicant is entitled to any interest on the amounts being
claimed and/or already settled.
Reasons for decision
22. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with the Operational Guidelines to the FOS Terms of
Reference. This dispute has not been the subject of a FOS
Recommendation and has proceeded directly to Determination.
23. I am satisfied there has been a full exchange of material between the parties
and that each party has had the opportunity of clarifying the issues that arise
from the material.
24. Upon receiving advice of a claim for malicious damage to the Applicant’s
rental property, the FSP undertook an assessment to confirm the cause and
extent of the damage. It was advised to the assessor that the Applicant had
cause to evict the previous tenants due to non payment of rent, just prior to
the damage being discovered at the property. The previous tenant had
allegedly threatened the Applicant after being evicted and just prior to the
discovery of the loss.
Case No: 278299 Determination Page 6 of 16
25. The assessor confirmed that after being evicted, the Applicant arranged for
the locks to the property to be changed via “L”. Whilst the property showed
signs of general wear and tear, consistent with a rental property and the age
of the home, the damage being claimed by the Applicant was assessed as
being consistent, for the most part, with malicious damage. The claim was
subsequently accepted by the FSP.
26. The FSP requested further information from the Applicant, via the assessor
to enable it to consider and calculate the rent default and loss of rent aspects
of the claim.
27. Property inspection reports were also requested and I have assumed this
would be to confirm that none of the items claimed as malicious damage,
existed prior to the loss, however this has not been advised in the material
provided.
28. Quotations were sought by the FSP from its appointed builders based on a
scope of works (SOW) prepared by the Assessor.
29. The Applicant requested a cash settlement in order to expedite repairs and
because he believed he could be more sympathetic to the repairs (the
property was previously his family home). The FSP made an offer of
settlement based on the quotations it had received however the offer was
rejected by the Applicant on the basis that the entire kitchen cupboards be
replaced and this had not been quoted and other items were “missing” from
the SOW.
30. The FSP revised its offer to include items which had not been previously
quoted by its builders (but noted on the SOW), in relation to repairs to the
external rumpus room, however this offer was also rejected by the Applicant.
31. “L” on behalf of the Applicant requested addition al items be added to the
assessor’s SOW . However, these items were largely rejected by the FSP on
the basis that they had not been previously raised as being damaged and
the assessor had not seen any damage to the items being claimed. The
issue regarding replacing the entire kitchen cupboards was also raised
again.
32. The Applicant also sought to have his excess waived on the basis of
financial hardship and the FSP advised the Applicant that providing him with
a cash settlement would mean the excess would simply be deducted from
that settlement.
33. There were some delays in some aspects of the settlement due to the
Applicant’s failure to provide his bank account details to the FSP t o allow the
payment to be made and due to “L” not providing the requested
documentation in a timely manner.
34. The FSP has also admitted some delays on its behalf during the claims
process, which it estimates at approximately three weeks, and for which it
offered an additional three week loss of rent settlement to the Applicant.
Case No: 278299 Determination Page 7 of 16
35. More recently the Applicant has agreed to accept the amount which was
offered by the FSP on the basis that it was not a full and final settlement of
his claim, in order for him to effect what repairs he could, in order to be able
to re-let the property. He is awaiting the outcome of the FOS Determination.
36. From reviewing the material provided, I have made the following timeline for
ease of reference:
Date of Loss – 22 September 2011.
Date loss notified to insurer by Applicant’s real estate agent – 30
September 2011.
Ac knowledgement letter sent by FSP to Applicant’s real estate agent
requesting further information and documentation – 30 September
2011.
Assessment conducted by FSP’s assessor in the company of the
Applicant and “L” – 8 November 2011.
Applicant and “L” requested to provide documentation relating to
tenancy, including bond receipts, rent ledgers, previous inspection
reports etc – 8 November 2011 (at assessment).
Scope of works (SOW) provided by assessor to FSP’s builders to
provide quotations for repairs – 11 November 2011.
Quotation for repairs received from FSP’s builder “K” – 16 November
2011.
Quotation for repairs prepared by Applicant’s appointed builder “J” – 17
November 2011.
Quotation for repairs received from FSP’s builder “P” – 5 December
2011.
Information previously requested from Applicant and “L” was again
requested from real estate agent as not received – 5 December 2011.
Email to Applicant from FSP advising it was awaiting the
documentation from him/ ”L” – 22 December 2011.
Email from Applica nt’s real estate agent to FSP with routine inspection
report and invoice for cleaning, requesting payment – 23 December
2011. (This was not the information previously requested by the FSP.)
Offer made for settlement of the rent default aspect of the claim by FSP
based on information provided by “L” – 2 January 2011.
Information previously requested from Applicant and real estate agent
was received from real estate agent – 5 January 2012.
Final property inspection report received from real estate agent – 12
January 2012.
Copy of SOW emailed to Applicant at his request – 25 January 2012.
Case No: 278299 Determination Page 8 of 16
37. After reviewing the material I note the lack of contemporaneous notes
provided by the FSP detailing telephone discussions which it may have had
with the Applicant and “L” . Email communications between the parties have
been provided and these detail some of the issues raised by the Applicant
and “L” .
38. The above timeline represents the important dates for consideration in
relation to this dispute.
Repairs
39. It appears that “L” , on behalf of the Applicant, made several requests to the
FSP to have the SOW altered to include additional items, after it was
received by the Applicant on 25 January 2012.
40. “L” was adamant that the replacement of the upper kitchen cupboards be
replaced in order to place the Applicant in the same position he was in prior
to the event. That is, “L” was of the opinion the FSP should pay to “match”
the upper cupboards to the new cupboards, despite her acknowledgement
that the policy did not provide for this. She also indicated that the cupboards
had been damaged by the tenants.
41. The Applicant and “L” also indicated that the SOW did not include the
oven/cook-top, rangehood, air conditioning unit, heater, ceiling fans, light
fittings, wardrobe internal repairs, vanity repairs, towel rails and toilets. It was
also mentioned by “L” that the SOW did not include the removal of rubbish
and debris by the builder at the completion of repairs. “L” was insistent that
these items be added to the SOW and suggested the quotation provided by
“J” included all necessary repairs.
42. I note the SOW clearly indicates the replacement of the oven/cook-top,
rangehood and light fittings. The assessor’s re port indicates the air
conditioning unit was not damaged, only the aves of the unit required
replacing. He also indicated the damage to the heater was pre-existing as a
knob had been replaced by a socket to enable the unit to be operated. The
socket belonged to the Applicant which indicated the Applicant was also
aware the unit was not working prior to the malicious damage event.
43. The FSP clarified the concerns raised by the Applicant and “L” with the
assessor who advised he noted only one ceiling fan as having been
damaged (bedroom 3), he noted no damage to a vanity, towel rails or toilets.
He concedes that he did omit the internal repairs required to the wardrobe.
44. I have compared the quotation provided by “J” to the SOW and note there
are many differences, which I detail as follows:
A. “J” quotes to replace three internal doors however only two internal
doors are noted on the SOW.
B. “J” quotes to replace the “complete kitchen”.
C. “J” quotes to repair shelving in a sliding robe.
Case No: 278299 Determination Page 9 of 16
D. “J” quotes to repair the vanity unit.
E. “J” quotes to replace a sweep fan to the meals area – the SOW details
the only sweep fan requiring replacement is in Bedroom 3.
F. “J” quotes to replace the bathroom fan/heater/light combination.
G. “J” quotes to replace the air conditioner and aves – the SOW specifies
that only the aves require replacement.
H. “J” quotes to replace two chipped tiles to a bathroom wall – the SOW
specifies that five tiles require replacement.
I. “J” quotes to repair the wall heater.
J. “J” quotes to replace three fly screens and one wire sliding door fly
screen – the SOW specifies only two fly screens require replacement in
addition to the sliding door fly screen.
K. “J” quotes to replace carpet to hall, lounge and three bedrooms.
L. “J” quotes to adjust a roller door operation and report if dam age is found.
M. “J” quotes to clean up during works and on completion.
45. In addition to reviewing the quotations, I have also reviewed the photographs
provided. Whilst the quality of the photographs is not ideal, I am satisfied
they are of a good enough quality to detail the damage at the Applicant’s
property.
46. From the information, I have made the following observations:
Items D, F and L, have not been included on the SOW and from the
photographs I am unable to determine what, if any damage has been
done to the se items. There is no mention by the Applicant or “L” that
these items formed part of the malicious damage claim, other than “L’s”
advice that the damage had been “caused by the tenants”.
Items A, E, H and J show discrepancies relating to agreed items.
Item G relates to the replacement of an air conditioner however, the
assessor notes it is only the aves of the air conditioning unit which
require replacement due to malicious damage.
Item B is disputed by the Applicant and “L”, in that they have insisted
the whole kitchen requires replacement. The FSP says only the lower
cupboards have been damaged as a result of the event and as such,
only the lower cupboards can be considered as part of the claim.
Item I has been itemised in the assessor’s report as being pre-existing
damage, evidence by the use of the Applicant’s own socket set to
operate the unit.
Item K refers to the replacement of carpet, however this is considered a
contents item and as the Applicant has building insurance only with the
FSP, this item is not covered.
Case No: 278299 Determination Page 10 of 16
Item M is, in my opinion, an acceptable item which is absent from the
SOW, however it would be usual practice for most insurance builders to
incorporate such costs into their quotations. Having said that, the FSP
has failed to acknowledge “L’s” query regarding this aspect and I am
not satisfied that the quotation relied upon by the FSP includes this
item.
Item C has not been included in the SOW however the photographs
clearly indicate that shelving within a built-in wardrobe has been
damaged. This item has been acknowledged by the assessor as having
been omitted from the SOW.
47. It should be noted that there are many items included in the SOW which
have not been quoted by “J”. The items missing from “J’s” quote include, but
are not limited to, external downpipe replacement, installation of a new
centenary cable to the rumpus room, security system repairs etc. “J’s”
quotation was for an amount of $26,950 (including GST).
48. The quotation provided by the FSP’s favoured builder, “K”, reads “Our
Tender price for scope provided by [FSP]” and is for an amount of
$17,562.60 (including GST).
49. Neither of the quotations relied upon by either party included repairs to the
rumpus room as this could not be accessed at the time of the assessment
due to it being locked and no key being available. It should be noted that
none of the quotations submitted by any party provide an itemised or
detailed quantum for each item quoted. It is therefore difficult to see where
the differences in the quotations exist , other than in “J’s” quote where items
requiring repairs/replacement have at least been listed.
50. In consideration of the FSP’s advice that it failed to include the
cupboards/shelves within the wardrobe of Bedroom 1 in its SOW and that I
am not satisfied the quotation provided by “K” includes the removal of debris
and rubbish, I am of the opinion that the FSP should arrange a quotation
from “K” for these two items and that the amount quoted should be paid to
the Applicant in addition to the settlement already offered.
51. In further communication received from the FSP, it acknowledges that an
amount for the repairs to the rumpus room, including the sliding door, was
quoted at $968 however only $360 has been paid to the Applicant as part of
the settlement. It therefore acknowledges that an additional payment of $608
needs to be made to the Applicant for the rumpus room repairs.
52. The FSP also advises that the repairs to the bathroom were subject to a
separate and additional excess as the damage was not consistent with
malicious damage, rather it was consistent with “other” damage. It is my
opinion that this is reasonable.
Case No: 278299 Determination Page 11 of 16
53. I am of the opinion that the quotation provided to “L” by “J” is not complete
as it clearly does not include all items detailed on the SOW. In addition,
some items included on the quotation are not covered under the insurance
policy issued by the FSP (ie: contents). The quotation also includes an
amount to replace all kitchen cupboards to which the Applicant is not
entitled, as discussed above.
54. Th e Applicant and “L” have not produced any documentation to show why
these items need to be repaired or replaced, nor has there been any
suggestion that the damage to these items was caused maliciously.
55. I am therefore not satisfied that the additional items claimed by the Applicant
and “L” are part of the malicious damage claims. The assessor saw no
damage referred to by the Applicant and the photographs do not reveal any
such damage. There is no evidence or supporting information from the
Applicant to show this damage was either a) caused by the tenants, or b)
caused as a result of the malicious damage event.
56. If the Applicant and/or “L” believe these additional items have been damaged
by the tenant during the tenancy, ie: the accidental breakage of a toilet, each
item would need to be considered as a separate claim or incident with
separate excesses applying. I am of the opinion the Applicant should submit
to the FSP details of the costs associated with these items so it may
consider separate claims accordingly.
Rent Default
57. The FSP has calculated the settlement of this aspect of the claim based on
rent ledgers and bond receipts etc submitted to it by “L”. From this
information, the FSP found that at the time the tenants were evicted, the
weekly rent payable was $295. It also found that the tenants were in arrears
from around 28 August 2011. As such, the FSP based its settlement from 28
August 2011 until 24 September 2011, being the date the tenant vacated the
property after being evicted. This resulted in a rent default period of 28 days
(four weeks) and was calculated at a loss of $1,180.
58. The FSP considered the documentation provided to it by “L” in relation to the
bond paid by the tenants and what that bond was used for after the tenants
vacated, ie: cleaning costs, water usage etc. This indicated that the
Applicant had to pay more for these items than the retained bond amount,
and as such, no bond was accessible to use for rent default purposes.
59. The applicable excess which applies to the rent default cover is $650.
60. The settlement calculated by the FSP for rent default is:
28 days rent default: $1,180.00
Less Applicable policy excess: 650.00
Total Settlement: $ 530.00
Case No: 278299 Determination Page 12 of 16
61. I am of the opinion that the rent default settlement has been calculated
correctly and is fair and reasonable in the circumstances.
Loss of Rent
62. After its assessment of the Applicant’s property, it was deemed that the
property was uninhabitable due to the damage to the kitchen area. I am of
the opinion that in light of legislation affecting landlords in providing a
property to a potential tenant in a habitable condition, the whole of the
malicious damage repairs would mean the property could not be tenanted
until all damage was repaired.
63. This does not appear to be disputed by the FSP who confirmed with its
preferred builder that the total time to repair the property as per the quotation
and SOW, would be five weeks. I am satisfied this is a fair and reasonable
time period and that loss of rent should be paid for this period.
64. The FSP offered three weeks loss of rent payment to the Applicant in
addition to the repair time of five weeks, to account for delays caused by it
during the assessment process. Using the timeline detailed earlier in this
Determination, I can see that there has be en a “gap” of five weeks and two
days, between the time the claim was reported to and acknowledged by the
FSP and the time of the assessment.
65. The Applicant claims, via “L”, that loss of rent should be paid until the
property is repaired to a state that it can be re-tenanted. I agree on this point,
however, I must also consider any other delays throughout the claims
process which could have been avoided and/or where any delays have been
caused by the FSP.
66. The FSP’s correspondence to the Applicant acknowledgi ng receipt of their
claim on 30 September 2011, whilst requesting further information, also
advised the Applicant that the matter would be sent for assessment. This
assessment did not occur until 8 November 2011. There is no explanation
for the delay in the assessment. I am therefore of the opinion that the time
period between reporting the matter to the FSP and the FSP’s actual
attendance to assess the damage, should be covered in the loss of rent
settlement component.
67. After completing its assessment, the FSP requested quotations for repairs
based on its assessor’s SOW. The first of the requested quotations was
received by the FSP on 17 November 2011 and the second quotation was
received on 5 December 2011. The FSP would not have been in a position
to either offer settlement or authorise repairs until 5 December 2011.
68. I am therefore of the opinion that loss of rent should be paid from the 24
September 2011, being the date the FSP provided settlement for rent default
until, to 5 December 2011 (ie: to 9 January 2012), to allow for the repair
period quoted by the FSP’s builder. This equates to a total of 17 weeks and
two days (17.29 weeks), loss of rent. The FSP has already offered and paid
eight weeks loss of rent.
Case No: 278299 Determination Page 13 of 16
69. The Applicant, in a recent email and after accepting an offer made by the
FSP to progress the claim, but not accepting the offer as a full and final
settlement, advised that the property became tenantable on 30 November
2012.
70. There are several aspects that require consideration in relation to any
additional loss of rent payment. The Applicant says the offer made by the
FSP for the building repairs was not fair and reasonable and he disputed a
number of items which were missing from the quotation. Based on this, he
refused any offer of settlement until August 2012.
71. The Applicant had the option of having the FSP authorise repairs, which the
FSP says was one of three options presented to the Applicant. The Applicant
did not wish the repairs authorised and did not wish to accept any settlement
offer made until he was satisfied that the amount offered would allow him to
repair all damage he believed related to the claim he had made.
72. This rejection of offers caused delays in the processing of the claim because
despite his rejection of the offer, the Applicant relied solely on the quotation
provi ded by “J”, via “L”, which as discussed earlier, was lacking in several
areas and included items which were not covered under the insurance policy
or not deemed as having been damaged when the property was assessed.
The Applicant and “L” failed to provide any new information to support their
opinion on these items.
73. In addition, “L” failed to provide the requested and required documentation
relevant to property condition reports, bond information and other relevant
details as requested at the time of assessment on 8 November 2011 in a
timely manner. The final requested item was not received by the FSP until
12 January 2012. This resulted in the FSP being unable to finalise certain
aspects of the claim until after this date.
74. The delays caused by “L” in failing to provide required information in a timely
manner, and the Applicant in his rejection of offers made to him by the FSP,
cannot be considered as reasonable, nor can I consider that the FSP should
be responsible to pay a loss of rent claim during this period, given that my
opinion is the offers made by the FSP were fair and reasonable.
75. I am therefore satisfied that the FSP is not required to pay any additional
loss of rent, beyond 9 January 2012 as detailed above.
76. The Case Manager has sought clarification from the FSP regarding why loss
of rent was settled at an amount of $260 per week, when the rent default and
copies of relevant lease agreements show that the rent at the time the tenant
vacated the property was in fact $295 per week. The response received from
the FSP in an email dated 19 December 2011, refers to the FSP’s file note of
4 April 2012, which reads:
“... Repairs will take 5 weeks, so allow this (24.9.11 to 29.10.11).
Also allow additional 2 weeks as [FSP employee] has noted delays on our
part (good will gesture).
Case No: 278299 Determination Page 14 of 16
Offer 8 weeks LOR to OI. Note OI has also delayed claim.
$260 per week is $2,080.”
77. The Case Manager sought further clarification as this file note only seemed
to address the time limit provided for loss of rent and not why the weekly rent
amount was settled at $260 instead of $295.
78. In a telephone discussion with the FSP of 2 January 2013, the FSP advised
that:
The team manager who negotiated the settlement for loss of rent was
currently absent
Another team member believed the amount per week had been
negotiated with the Applicant based on the fact that the rent had gone
up in February 2011
There were no file notes made by any of the FSP’s employees
indicating any other information as to why $260 was used to settle the
loss of rent aspect of the claim
79. In addition to this information, the FSP provided a copy of a lease agreement
amendment increasing the rent to $295 (by $10 per week from the previous
weekly rental amount) from February 2011 to February 2012. A copy of the
original lease agreement from February 2009 to February 2010 showed the
original weekly rental amount was $260.
80. I can find no evidence to suggest why the weekly rental amount of $260 was
used and am of the opinion, the correct weekly rental amount for settlement
purposes should be the weekly rental amount being paid by the tenant,
immediately before the tenant vacated the premises. That amount is $295
which is the amount that I have used to calculate the settlement due to the
Applicant.
Clean up costs
81. The Applicant via “L” submitted a quotation/invoice for the costs associated
with cleaning the property after the tenants vacated. These costs relate to
the removal of and cleaning up the tenants contents which were left at the
property.
82. I note that the Applicant has building insurance only for the rental property
and this cover does not cover contents owned by the tenant. As the cleaning
costs being claimed relate to the removal of rubbish and contents, these
costs are not covered under the Applicant’s insurance policy with the FSP,
and therefore, I am unable to consider the costs as part of the Applicant’s
claim and dispute.
Case No: 278299 Determination Page 15 of 16
Interest
83. As some aspects of this claim have not been settled correctly by the FSP, I
am of the opinion that interest should apply to those aspects only. I
acknowledge that the Applicant has delayed accepting any settlement
offered to him which in turn, has delayed the repair process. I am of the
opinion that the FSP is not responsible for this delay and therefore is not
required to pay interest on the entire settlement amount, given it was offered
to the Applicant immediately the FSP was in a position to do so.
84. Interest should therefore be applied on the following items only:
Cost of repairs to internal cupboard/shelves of wardrobe in Bedroom
1(once costs established by the FSP)
Cost of removal of debris and rubbish (once costs established by the
FSP)
Additional settlement for rumpus room repairs, detailed above at $608
Additional loss of rent payment, calculated as what should have been
paid (17.29 weeks at $295 per week, which equates to $5,100.55) less
the amount already paid for loss of rent ($2,080), making a nett
additional loss of rent payment of $3,020.55
Determination
85. On the basis of the available information I determine that:
The cost of repairs to the Applicant’s property, as assessed by the FSP
was fair and reasonable, save for items it acknowledges were omitted
in error.
The offer made for rent default is fair and reasonable.
The offer made for loss of rent was less than what should have been
offered.
In relation to building repairs
a. The FSP is to pay to the Applicant, the amount quoted by its builder for
the repairs to the internal shelves/cupboards of the wardrobe in
Bedroom 1, and a copy of the quotation for these repairs is to be
provided to the Applicant with the FSP’s settlement payment.
b. The FSP is to pay to the Applicant the amount quoted by its builder for
the removal of debris and rubbish as a result of the repairs/damage
clean up, had it completed the repairs and a copy of the quotation for
these costs is to be provided to the Applican t with the FSP’s settlement
payment.
c. The excess applied to the bathroom repairs is correct.
d. The FSP is to pay to the Applicant the amount of $608 previously
overlooked, in relation to the rumpus room repairs.
Case No: 278299 Determination Page 16 of 16
e. The FSP is not required to match the undamaged sections of the
kitchen.
f. The FSP is not required to contribute anything further to building
repairs.
In relation to rent default settlement
a. The FSP has correctly calculated this aspect of the claim and no further
contribution is required by the FSP.
In relation to loss of rent settlement
a. The FSP is to pay to the Applicant an additional amount of $3,020.55
Interest
a. The FSP is to pay to the Applicant, interest on the settlement amounts
detailed above for:
(i) Internal shelves/cupboards (to be determined)
(ii) Removal of debris and rubbish as a result of repairs (to be
determined)
(iii) Additional payment for rumpus room repairs of $608
(iv) Additional loss of rent payment of $3,020.55
b. Interest is to be paid on the above sums from the date of the original
settlement was accepted by the Applicant (23 August 2012) to the date
when this Determination is satisfied. The applicable interest rate should
be calculated pursuant to Section 57 of the Insurance Contracts Act
1984 (Cth) .