Home / Financial Firm (Unknown - Insurer) / Determination 276678

Determination 276678

Denial of Claim

FirmFinancial Firm (Unknown - Insurer)
Decided2013-05-20
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed$24,486
SourceAFCA PDF

Summary

The Applicant's strata unit water damage claim was denied by the FSP as long-term defect damage, after it had paid $506 for storm roof repairs. AFCA required the FSP to accept resultant damage from most listed items but not from the retro-fitted kitchen window.

Section 46 of the Insurance Contracts Act prevents reliance on pre-contract construction defect exclusions, except for the window installed around 1998, which was an alteration outside the original construction.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 276678 Determination Page 1 of 12 Case number: 276678 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of Claim 24 April 2013 Background 1. The Applicant is the owner of a unit which has insurance protection under a strata residential unit insurance policy with the Financial Services Provider (FSP). The policy provides cover to a number of units for a total building sum insured of $3,245,000 which includes common contents. The policy has a $250 excess which applies to all claims. 2. On 14 June 2011 the FSP received a claim from the Applicant for storm damage to the roof of his unit which occurred on 21 March 2011. The invoice submitted with the claim for roof repairs was $506 and the FSP paid this amount. Shortly after settlement had been made, the FSP received a further quotation from the Applicant for additional work which had occurred as a result of the same event. 3. The FSP denied the Applicant‟s additional claim after seeking advice from building experts on the cause and extent of damage being claimed. The claim was denied on the grounds that the damage had not been caused by a storm event, rather it was as a result of long term deterioration, multiple events of water ingress, faulty workmanship, gradual deterioration and faulty design. 4. The Ap plicant disputes the FSP‟s decision and seeks to have his claim accepted and repairs completed to his unit. Summary of Applicant’s position 5. The Applicant says he noticed a wall was damp in a downstairs room of his unit in May 2011. After investigating further he found that water had entered the top of the unit at the front and had gone down through the internal walls of the unit. 6. He purchased the unit only 12 months prior to discovering the damage and had no prior knowledge of there being any issues with the property until he discovered the damage. Determination Case No: 276678 Determination Page 2 of 12 7. He says another owner of another unit at the same property experienced similar damage around the same time to a lesser extent and had a similar incident approximately five years prior which had been covered by insurance. 8. The FSP‟s expert appeared to concentrate on the condition of the building and concluded that he had prior knowledge of the issues with the building, which he denies. 9. The Applicant says the FSP‟s expert has not been truthful in his reports to the FSP however, the FSP was not willing to listen to his evidence to support this. 10. His unit has suffered significant residual damage due to water ingress from repetitive storm activity which is accidental in nature and something he was not aware of until May 2011. 11. He seeks to have his claim accepted and repairs for the water damage to be paid for by the FSP. Summary of FSP’s position 12. The FSP says the Applicant asserted that the damage to the roof of his unit occurred during a storm. 13. The initial claim received from the Applicant was for a minimal amount and it did not investigate further, rather it promptly settled the claim for $506. It was not until it received a further claim from the Applicant for additional damage as a result of the same event, that it investigated the claim further. 14. The investigation undertaken by its experts revealed that the Applicant‟s unit had suffered damage resulting from many building faults and poor workmanship. 15. The FSP says the damage is not covered by the insurance policy pro vided. 16. The FSP relies on the following policy provisions of its Product Disclosure Statement (PDS): “ Exclusions We will not cover Your Insured Property for Damage arising from or caused by: ... 6. Damage that occurred outside the Period of Insurance stated on the Schedule. ... 8. Fading, scratching or marring, developing flaws, normal up-keeping or making good. ... Case No: 276678 Determination Page 3 of 12 13. Mould and/or fungi, mildew, atmospheric or climatic conditions. ... 17. Rust, corrosion, oxidization, gradual deterioration, concrete or brick cancer, wear or tear, wet or dry rot. 18. The failure of or a defect in any item, faulty workmanship, structural defect or faulty design. ... 20. Water entering Your Building(s) because of a structural defect, faulty design or faulty workmanship when Your Building(s) were constructed. 21. Water entering Your Building(s) through an opening made for any building, renovation or repair work.” (Page 17) Issue 17. Whether the FSP is entitled to deny the Applicant‟s claim in accordance with the terms and conditions of the policy. Reasons for decision 18. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 19. I am satisfied there has been a full exchange of material between the parties and that each party has had the opportunity of clarifying the issues that arise from the material. Claim 20. Upon being notified by the Applicant of roof damage to his Unit at the insured address, the FSP accepted and paid the cost of repairs to fix a roof which had been damaged by storm. The amount settled was $506 and the claim was finalised. 21. Shortly after this time a further approach was made by the Applicant for additional damage to the property as a result of the same storm event. The Applicant forwarded a further quotation for additional repairs totalling $24,486.26. On receipt of this additional quotation, the FSP chose to appoint an assessor, “ CR ” , to investigate further. 22. It is noted that the claim received by the FSP relates to two Units, only one of which is owned by the Applicant and it is this Unit that is the subject of dispute. Case No: 276678 Determination Page 4 of 12 23. CR reported that he met with the Applicant on site who advised him that the damage had occurred over a four to six week period, between May and June 2011. CR confirmed that the area had been subjected to notable storm activity which brought torrential rainfall over a prolonged period as well as gale force winds. However, CR noted that the damage now being claimed did not appear to be as a result of recent storm activity. 24. CR says: “Whilst it is no doubted that the inclement conditions associated with these storms may have (an in all likelihood did have) resulted in water ingress, the evidence presents to indicate that such water ingress was borne out of circumstances including initial design, construction and / or maintenance flaws. Further, these damaged are undoubtedly long term with evidence indicating attempted rectifications through sealants etc. being applied to various window and door trims over a long period of time. The reason we suspect long term issues of water ingress is by virtue of the condition of the internal resultant damages to wall and floor linings to both units and in particular, advanced rotting of timber wall studs, plates, substrate chipboard flooring and possibly event timber floor joists. Not to mention plasterboard wall linings and in the case of [the Applicant‟s Unit], the chipboard kickboards of the kitchen cupboard assembly. ... The deterioration and rotting to much of the affected areas ([both Units]) is so severe that in places, timber framework has virtually disintegrated. As such, we are adamant this is the result of long term and ongoing water ingress as opposed to storm damages in the recent weeks resulting from a defined event and / or storm created opening. On that note, please be advised that although roof repairs were carried out, there is no clear and obvious indications of storm created opening/s and where again, given the severe and widespread nature of the damages to both [both Units], we doubt that these damages could have been the result of water entry from the roof alone. So severe and deteriorated are the claimed damages, especially to the timber wall frames downstairs to both units that we fell the unit occupants would have or ought to have reasonably suspected or identified their presents. Interestingly, in the course of discussions with [the Applicant], he advised that the premises were purchased just over 12 months ago and in this short period of ownership, he has noticed accumulating water in the downstairs wall / floor junctures. [The Applicant] initially attributed this to suspecting a previous owner may have left a window open during a storm event leading to water ingress through an open window but on the other hand, in contradiction to this he did concede having attended to sealing the window / door trims at his own cost, apparently as a „precaution‟. Strangely, no pre-purchase inspection of the property was commissioned by [the Applicant] who advised that he purchased the premises at Auction; it was under Strata and on that basis he presumed all would be in order. Overall, whilst we are satisfied that exposure of the true extent of the damages was realised following the recent storm activity, and where water ingress occurred during such inclement conditions, the proximate cause was Case No: 276678 Determination Page 5 of 12 not storm activity at any stage in 2011. In fact, we consider the problem has existed for at least several years and realisation of this has only come about once the structural integrity of the wall and floor linings has deteriorated to a point of failure.” (sic) 25. It was CR‟s suggestion that a specialised building consultant be appointed and on the FSP‟s authority, “ CS ” was appointed to inspect and report on the condition of the Applicant‟s Unit. He also noted the following in relation to the quotations provided by the Applicant for repairs: “Noting the contents of the sco pe of work contained within repair quotations of [Q] ([the Applicant‟s Unit] and [IC] (both Units), we are satisfied that the documents provide a scope that is reflective of damages occasioned. However, notwithstanding this, for the reasons detailed in the foregoing at this stage we are not satisfied that all such works can be claimable under the [insurance policy].” (sic) 26. CS attended the Applicant‟s Unit on 5 August 2011 and provided a report to the FSP on his findings. CS provided the following informatio n:  The complex of Units is approximately 20 years old and most of the units are used by the owners as weekenders, as advised to CS by the Applicant.  Extreme deterioration of timber framing and timber flooring on the ground floor was noted to a degree that the vast majority of the framing and flooring had virtually disintegrated.  A section of particleboard flooring appeared in a newer condition to the remaining flooring – the Applicant advised he was not aware of any repairs being undertaken to the property prior to his purchase of it.  The timber framing and flooring was still retaining large amounts of moisture ranging from 70% to 98% as tested by CS‟s moisture meter which were considered to be extreme. This was despite the fact there had not been substantial rains for some weeks prior to the inspection.  The masonry brickwork had daylight visible through the perpendicular mortar joints between the bricks – this was noted as being an obvious entry point for water, either from wind driven rain or water running down the external wall.  The twisted veneer ties (galvanised) had completely corroded through and were no longer providing lateral support between the veneer skin and the timber frame. Today‟s building standards would see stainless steel ties being used in this area.  A scratch test was done to the mortar joints between the bricks and this revealed that the mortar was starting to break down. It also revealed that the mortar was „lean‟, indicating a minimal amount of cement had been used at the time of construction).  A TV coaxial cable to the TV antenna on the roof extends down the brick cavity and penetrates through the cross cavity flashing to the first floor which renders the cross cavity flashing useless as a drainage diversion as water was easily escaping around the coaxial cable Case No: 276678 Determination Page 6 of 12 penetration. This penetration is directly above the most severe area of damage.  An inspection of the extern elevations and brickwork of the ground floor area also revealed a very lean mortar mixture between the brick joints.  Several different types of flexible sealants had been applied to the window reveals, indicating an ongoing attempt to prevent water ingress.  Flashing/door sill is allowing water ingress to the first floor area causing damage to carpet. The moisture meter recorded a leve l of 50% to 60% moisture in this area which is considered extremely high and suggested a failed flashing and/or failed door sill.  Damage to kitchen cupboards and vinyl flooring in the kitchen was attributable to a retro fitted window which in CS‟s opinion had not been installed to an acceptable building practice. It was noted that the type of installation used resulted in a failure to install a head sill above the window to divert any moisture which enters the cavity and prevent water penetrating around the window frame.  A large majority of weep holes over the kitchen window and sliding door to the dining area were filled with flexible filler which was aged and deteriorated suggesting it had been in place for some time.  All window and door reveals displayed several different types of flexible sealant suggesting there were ongoing moisture issues with the Unit and attempts made to rectify the problems.  The aluminium sliding door had been installed with a standard type sill and due to it being located in an area with no eave overhang, CS suggested that a sub-sill with an internal drainage system would have been the preferred method of construction.  The sliding door frame was retaining moisture due to the design flaws and this was allowing water penetration evident through the staining under the carpet.  Several broken roof tiles around the area of water ingress were inspected – these had been rectified prior to CS‟s inspection. The tiles were aged and had been in place in this condition for an extended period of time.  Minor cracking to the point of the barge tile at the gable end of the roof was noticed and this would allow wind driven rain into the cavity and ultimately into the residence.  The Applicant advised CS that he accessed the roof cavity during a rain event and noted water running down the inside skin of the veneer masonry walls. 27. CS opined that the damage to the Applicant‟s Unit had been experienced over an extended period of time and estimated this to be at least a three year period. He found no storm created openings to the building which would allow water ingress. Case No: 276678 Determination Page 7 of 12 28. CS advised that water had entered the premises through defective installation of a retro-fitted window; design issues surrounding the aluminium sliding door, sealed weep holes in the brickwork , deterioration of „lean‟ mortar and the penetration of the cross cavity flashing for the purposes of installing a TV coaxial cable. 29. CS reviewed the quotation for repairs from IC and advised the following items relevant to repairs at the Applicant‟s Unit a s being upgrades due to design flaws or maintenance related issues:  Raking out loose mortar, replacing mortar joints and cleaning;  Removal of aluminium sliding door, cut down and fit a sub -sill and new angles;  The application of a silicone paste chemical to prevent further water ingress into the building to the 1,200mm turn down side walls;  Sealing around the penetrations where the coaxial cable has penetrated through the cavity flashing; and  Removal and replacement of any loose pointing to roof tiles with flexi- point as required. 30. The FSP relies on the information provided by CS and on receiving this report, denied the Applicant‟s claim (and the claim of the owner of the second unit). 31. The Applicant disputed the denial of the claim and raised concerns with the validity of CS‟s report. These concerns were raised with CS and the following is noted:  Concern raised – only 1m 2 of flooring was damaged, not the “vast majority”. CS corrected his previous statement and said “1m 2 of extremely damaged and deteriorated flooring due to ongoing water ingress. Vast majority of floor (overall) deteriorated.”  Concern raised – property was inspected on 5 August 2011 and during 20 July 2011 and 4 August 2011 it rained 11 days and a total of 222mm of rain was recorded in the area – the Applicant disputed CS‟s advice that no substantial rain had fallen for some week‟s prior to his inspection. CS responded that if this was the case, that the damage contained within the building was not as a result of the rains which occurred during this 15 day period.  Concern raised – the Applicant disputes that high level of rains can enter through the small hairline cracks in the mortar referred to by CS. CS responded that water can quite easily enter through these cracks in the brick opening and that he has not advised that all water has entered in this fashion.  Concern raised – the Applicant did not see CS conduct any „scratch test‟ and believes CS‟s comments are pure speculation. CS responded that he arrived at the property before the Applicant and conducted the test during this time. He did not have the sample taken tested however , Case No: 276678 Determination Page 8 of 12 could arrange for this and as he is a fully qualified bricklayer, he was able to determine the „lean‟ content of the mortar.  Concern raised – the Applicant advised he had arranged for silicon to be applied to the window reveals as a pre-construction/finishing task for a pergola he had received approval to build in the relevant area. He had no prior knowledge and there was no significant indication that water was coming through the windows via the reveals. CS responded that the damage to the kitchen was adjacent to the retro fitted window where silicon had been applied indicating there was a leak at this location.  Concern raised – CS‟s report made mention of a significant amount of carpet being removed and that a window installation specialist had previously inspected the door and flashing and found it to be correct and doing its job. The sliding door rollers had deteriorated and the door did not close properly however, when a garden hose was put on the area only an insignificant amount of water was entering the property. He added that the water ingress was via the roof due to repetitive storm damage. CS responded that carpet had been removed along the full length of the sliding door and high levels of moisture were found to the centre of the door opening with no signs of ingress above to the ceiling or the door head, indicating water was entering under the door. There was no evidence of roof damage caused by storm at the time of his inspection.  Concern raised – the building was constructed in accordance with building codes at the time and approved as such. Suggesting that additional construction could be carried out to further prevent water ingress, is speculative and an „after the fact‟ comment. The roof in the area of the first floor verandah had already been repaired due to storm damage. CS responded that he is satisfied the property would have been approved for occupation at the time of its completion however, he believed that the design issues could be a contributing factor of the water ingress. Evidence of this is in the form of someone having sealed the weep holes with flexible sealant to prevent water penetrating through the external elevation.  Concern raised – the retro fitted window had been approved by the Strata Company and installed by a professional builder. A window installation expert had inspected the window who found the window to be correctly fitted with flashing and header plate in place. Water tests on the window using a garden hose saw only a small amount of water enter via the weather strips only. CS responded by providing a copy of the relevant Building Code, Australian Standard (AS) 3700 Masonry Structures. He reiterated that at the time of his inspection he failed to find any signs that the flashings complied with the relevant standard. There were also indications that the wall ties did not meet the same standard with respect to spacing and type.  Concern raised – a lot of the water ingress is coming in through several broken roof tiles, pointing and barge ends which were damaged during storm events. CS responded that the tiles were aged and were not Case No: 276678 Determination Page 9 of 12 allowing water entry as there was no staining evident to suggest this is how water was entering the Unit.  Concern raised – CS found no storm created opening. This is contrary to storm damage to the roof which had already been repaired and the Applicant‟s visual sighting of water entering a light fixture of a ceiling. The main point of entry had been fixed by the Strata Company as maintenance. CS did not inspect the roof cavity as the batteries to his torch were flat and therefore, he could not accurately assess the roof or roof cavity. CS responded that a full inspection of the roof cover was conducted and no damaged sighted to suggest the roof had been damaged by any recent storm event. The roof cavity was not inspected as it was not required to locate a storm created opening.  Concern raised – the damaged to the floor was not noticed through normal foot traffic as the damaged area had been under a wardrobe which the Applicant had not moved. There was no mould evident at this location on the wall and only a small amount of mould was found under the carpet when it was pulled up. CS requested the Applicant provide a pre-purchase inspection report to substantiate this claim. 32. The Applicant and the FSP have raised several issues throughout the course of the claim and subsequent dispute. The Applicant has not provided any independent building reports. The FSP has relied solely on the one inspection and one report undertaken by CS. 33. The FSP says that there are additional “gaps” at the property, including a gap between the house proper and the deck which could have also contributed to the water ingress. 34. The Applicant has also provided evidence to show that around 1998 approval was sought from the Strata Company to install a window near the kitchen area, which has been referred to by CS as being incorrectly installed. 35. I note that CS has relied on a number of building codes and Australian Standards. What is concerning to me is that there is no mention as to when these codes and standards applied, if they applied at the time of construction or sometime after construction. Whilst I am persuaded by CS‟s evidence of the condition of the building, in particular the mortar, sliding door installation, window installation etc, I am not persuaded that the installation of these items was in any way in breach of any code or standard at the time they were installed or constructed. 36. Of quite some concern to the Applicant was CS‟s failure to inspect the roof cavity. To this end, the Applicant provided photographic evidence of staining to the ceiling of his Unit, damaged sarking evident in the roof cavity, damage to the ceiling and water pooling in a light fitting. The FSP‟s response to this was that CS did not need to access the roof cavity to be able to see that there was no storm created opening caused to the roof to allow water to enter. Case No: 276678 Determination Page 10 of 12 37. However, the FSP had previously paid $506 for roof repairs as a result of the storm and the Applicant says the damaged tiles noted by CS on his inspection were also damaged in the storm. CS says the damaged tiles were aged. I am unsure what this means or how it is attributable to them being damage d. I am therefore not satisfied, in light of the FSP‟s acknowledgement that some storm damage had been suffered to the property, that the damaged roof tiles were not as a result of a storm event, or several storm events. Consideration of the Evidence 38. The onus of proof rests on the Applicant to establish that, on the balance of probabilities, he has suffered a loss caused by an insured event. Once the Applicant has established that the loss was caused by an event insured under his policy, the onus then shifts to the FSP to show that, on the balance of probabilities, the loss falls within an exclusion clause in the policy. 39. The FSP has suggested that the Applicant failed to obtain a pre -purchase inspection report prior to buying the property and as such, he elected not to find out about the condition of the property prior to purchasing it. The FSP says that this is tantamount to saying that the Applicant did not want to know about the condition of the property. The Applicant says he purchased the property at auction and did not have an opportunity to obtain such a report. 40. I am of the opinion that it is not expected that a reasonable person would obtain a pre-purchase condition report for a property going to auction. The costs involved in obtaining such reports o n a chance that a person may be the successful bidder, is not a reasonable expectation. In this instance, I also note that there is no such provision of the FSP‟s PDS to suggest that the Applicant should have done this prior to purchasing the property. 41. I am also of the opinion that even if a pre -purchase condition report was obtained, it is unlikely that the degree of damage discovered by the Applicant would have or could have been identified, without substantial dismantling of the property. For example, the damage noticed by the Applicant, and agreed to by CS, involves damage to the internal cavities of walls, floors which had carpet laid on top of them etc. 42. In this case, the Applicant had purchased the Unit approximately 12 months prior to noticing the damage, was not living at the property on a permanent basis (he was using the property as a „weekender‟/holiday home) and only discovered the extent of the damage when he began removing floor coverings to lay tiles etc. It appears this occurred shortly prior to the claim in about May/June 2011. I therefore do not agree with the FSP‟s contention that the Applicant ought to have been aware of the existing damage at the time of purchase, in this situation. 43. The FSP‟s policy is an accidental damage policy, providi ng accidental damage cover for the buildings owned by the Strata Company. There is no dispute that storm related damage is considered accidental and there is no denial by the FSP that storm damage is covered by the policy. Case No: 276678 Determination Page 11 of 12 44. I also note that the PDS has no clause pertaining to whether the damage must be from a single event. There is no dispute between the parties that there has been water ingress to the property through rainwater/storm and that the ingress has occurred over a number of years, from multiple storm events. 45. I am therefore satisfied in this instance, that the Applicant has met his obligation of demonstrating he has suffered a loss as a result of an insured event. The onus now rests with the FSP to demonstrate an exclusion applies. 46. The FSP has relied on several exclusions of its PDS as detailed above , including exclusion 20 that refers to water entering from structural defects, faulty design or faulty workmanship when the building was constructed. From the information provided by the FSP, water ingress has occurred due to faulty workmanship or design at the time of construction. Other exclusions seem to flow from this one proximate cause. 47. I also note that the roof has been accepted and paid for by the FSP as having been storm damaged without investigation. As such, it stands to reason that it accepts there must be some cause for water ingress from the roof. I am satisfied that the photographs provided by the Applicant support his claim in this regard and the acknowledgement by CS that he did not enter the roof cavity to inspect this area, is to the FSP‟s detriment. Law Involved 48. Section 46 of the Insurance Contracts Act 1984 (Cth) (the Act) provides that if a claim is made in respect of a loss that occurred in whole or in part as a result of a defect or imperfection in a thing and the insured was not aware of the defect or a reasonable person in the circumstances could not be expected to have been aware of the defect or imperfection the insurer may not rely on an exclusion clause that refers to the condition of the thing before the contract was entered into. 49. I note that for section 46 of the Act to be applied, the FSP is required to rely on a provision in the contract that has the effect of limiting or excluding the FSP‟s liability under the contract by re ference to the condition, at a time before the contract was entered into, of the thing. 50. In this case, I note the significant exclusion relied upon by the FSP is, exclusion 20, which reads: “20. Water entering Your Building(s) because of a structural defect , faulty design or faulty workmanship when Your Building(s) were constructed. ” 51. This exclusion clearly refers to the condition of a thing prior to the policy being entered into as it refers to the condition of the building at the time of construction. Accordingly, I consider that in this instance, section 46 applies. 52. However, it should be noted that section 46 only applies to those areas of damage associated with the structural defects, faulty design or faulty Case No: 276678 Determination Page 12 of 12 workmanship of those items at the time the building was constructed. In this case, I consider the retro-fitted window to be outside the scope of section 46 as this was an alteration to the construction of the building and was done circa 1998. 53. There is no information from either party to indicate when the TV coaxial cable was added to the building or the decking, and I must therefore consider it reasonable that these items were part of the original building construction. Accordingly, section 46 would apply to these items. Determination 54. On the basis of the available information I determine that the FSP must accept the resultant damage from all items it has identified as being as a result of the structural defect, faulty design or faulty workmanship associated with the building‟s construction, namely:  sliding door;  mortar joints;  roof;  deck; and  TV coaxial cable. 55. The FSP is not required to contribute to any damage caused by water ingress from the retro fitted window installed adjacent to the kitchen. Resultant damage to this area must be borne by the Applicant. 56. The Applicant or the Strata Company must attend to all maintenance related issues identified by the FSP prior to any resultant damage being repaired at the FSP‟s authority.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.