Determination 275889
Delay in accepting storm and flood claim and compensation for distress
Summary
Storm and flood claim was denied in June 2011, then accepted in December 2011 and settled in January 2012. AFCA ordered statutory interest from 3 June 2011 to settlement and $500 for distress, rejecting the $3,000 non-financial loss sought and the utmost good faith breach.
Under section 57 of the Insurance Contracts Act, interest is payable from when it was unreasonable to withhold payment, and the FSP is liable for its appointed hydrologist's inaccurate assessment.
Issues
- Delay primary · upheld
“the claim should have been accepted by the FSP by June 2011 and the settlement was not made until the end of January 2012.”
- Claim denial secondary · upheld
“I am satisfied that the FSP should have had adequate information to assess the claim by early June 2011.”
- Poor claim handling secondary · not upheld
“I do not agree that its action constitutes a breach of its obligation to act within the utmost good faith.”
Subjects and remedies
home or building damagenatural disasterpay interestpay non financial loss
Text of the determination
Case No: 275889 Determination Page 1 of 6
Case number: 275889
General Insurance - Domestic Insurance - Home Building - Service - Delay in
Claim Handling - Interest - Compensation for Non-Financial Loss - Utmost
Good Faith - Insurance Contracts Act 1984 Sections 57 and 13
29 August 2012
Background
1. The Applicants held a home building and contents insurance policy with the
Financial Services Provider (FSP) from 15 March 2010 and the policy was
current at the time of the loss.
2. On 25 January 2011, the Applicants lodged a claim with the FSP for damage
sustained to the property as a result of storms and floods experienced in
Queensland on or around 11 January 2011.
3. On 3 June 2011, the FSP denied the Applicants’ claim on the grounds the
damage was caused by flood which is excluded under the policy.
4. However, upon review by the Internal Dispute Resolutions Committee, the
FSP accepted their claim on 28 December 2011 and the settlement was
subsequently made on 30 January 2012.
5. The Applicants believe the FSP should consider payment of interest on the
offer of settlement and to pay compensation for the distress caused by the
FSP’s claims handling process.
6. The FSP rejects the above and says its assessment was purely based on its
expert’s reports and it is not required to make such payments.
Summary of Applicants ’ position
7. The Applicants are represented by solicitor IAL who has made the
submissions on behalf of the Applicants.
8. The Applicants are entitled to interest from the period the FSP had adequate
information to make an appropriate decision on the claim.
9. The FSP has not explained why the claim was subsequently accepted in
December 2011 and what new information it received which led it to change
the outcome of the claim.
Determination
Case No: 275889 Determination Page 2 of 6
10. The time taken to investigate the loss and the FSP’s decision to incorrectly
deny the claim amounts to breach of utmost good faith towards the
Applicants.
11. The Applicants say they were initially informed by one of the FSP’s
representative that the claim will be accepted and its decision to deny the
claim caused them distress.
12. The Applicants were unable to enjoy their hobbies due to the delayed
acceptance of the claim.
13. Additional attention was required to the ponies due to lack of summer rugs,
skinny hoods, turnout rugs, winter rugs etc.
14. The Applicants say the following parts of the claim could have been
accepted after the initial assessment as they were not related to inundation:
Loss caused by power surge; and
Storm water damage to solar panel switches on the roof.
15. The FSP should pay compensation for non-financial loss amounting to
$3,000.
Summary of FSP’s position
16. The FSP says that it organised various investigations and assessments to
assess the cause of the loss to various claimant s’ properties after the
catastrophic event and it was not until 31 May 2011, that its assessment
relating to the Applicants’ location was completed.
17. The denial of the claim was purely based on the assessment and findings of
its hydrologist and the Applicants are not entitled to be paid interest when
there is no evidence that the FSP unreasonable held the claim payout.
18. The FSP ’s assessment was complete and its decision was based on expert
evidence and thereby it has not breached its good faith towards the
Applicants.
19. The Applicants have not demonstrated circumstances (loss of enjoyment of
horse riding, etc) which entitle them to receive compensation.
Issues
20. Whether the FSP is required to pay interest on the ultimate sum paid to them
as settlement.
21. Whether the FSP has failed to act in good faith towards the Applicants.
Case No: 275889 Determination Page 3 of 6
22. Whether the Applicants are entitled to receive compensation for non-
financial loss.
Reasons for decision
23. Due to the nature of this dispute, FOS has considered it appropriate to
expedite the dispute in accordance with the Operational Guidelines to the
FOS Terms of Reference. This dispute has not been the subject of a FOS
Recommendation and has proceeded directly to Determination.
24. I am satisfied that a full exchange of information has taken place between
each party and that each party has had the opportunity to address any
issues raised.
25. I consider the FOS Terms of Reference relevant to this dispute are:
“ 9.3 Other compensation
a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for consequential financial
loss or damage up to a maximum amount of $3,000 per claim made in the
Dispute.
b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for non-financial loss but
only where:
(i) an unusual degree or extent of physical inconvenience, time taken to resolve
the situation or interference with the Applicant’s expectation of enjoyment or
peace of mind has occurred; or
(ii) in the case of a Dispute pertaining to an individual’s privacy rights – injury has
occurred to the Applicant’s feelings or humiliation has been suffered by the
Applicant.
The maximum amount of compensation for non-financial loss will be $3,000 per
claim made in the Dispute.
c) Notwithstanding paragraphs 9.3 a) and b), FOS will not provide compensation
for:
(i) consequential financial loss; or
(ii) non-financial loss,
in a Dispute arising as a result of a claim on a General Insurance Policy that
expressly excludes such liability.
d ) The cap on liability in paragraph 9.3 a) does not in any way restrict FOS’s
ability to make an interest award under paragraph 9.5.
...
9.5 Interest
a) Subject to paragraph 9.5 b) FOS may decide that the Financial Services
Provider pay interest on a payment to be made by the Financial Services
Provider to the Applicant.
b) When deciding an award of interest:
Case No: 275889 Determination Page 4 of 6
(i) if the Insurance Contracts Act 1984 applies - FOS will calculate interest in
accordance with that Act; and
(ii) otherwise:
(A) FOS will calculate interest from the date of the cause of action or matter
giving rise to the claim; and
(B) FOS may have regard to any factors it considers relevant, including the extent
to which either party’s conduct contributed to delay in the resolution of the
matter. ”
Interest
26. Subsequent to the lodgement of the claim, the FSP appointed a loss
assessor and a hydrologist to investigate the cause of the loss, the
circumstances surrounding the claim and to assess the claim.
27. The loss adjustor’s report was brief and does not refer to the storm damage
sustained to solar panel switches or damage sustained as a result of power
surge.
28. I understand the FSP’s decision to deny liability to the Applicants ’ claim was
solely based on the expert evidence presented by the Hydrologist.
29. IAL says the Applicants’ property was located on the borderline or just
outside of Zone 3 (as classified by the hydrologist).
30. I note that had it been assessed correctly, there was no reason why the
claim would have been denied in June 2011 as one of the hydro logist’s
reports concluded that properties located outside of Zone 3 sustained
damage by storm water run-off.
31. However, the hydrologist in his site specific report assessed the Applicants ’
property to be in Zone 3 and based on the various other factors (time of
rainfall, inundation, etc), he arrived at the conclusion the loss was caused by
flood.
32. I am unsure of the reasons why the FSP subsequently accepted the claim in
December 2011. It appears this decision was made based on the revised
report from the hydrologist which indicated that the Applicants had informed
him that inundation related to the ground floor was not part of the claim.
33. I do not understand why the Applicants would make such a statement when
a claim has been lodged for water damage sustained to the property.
34. Nevertheless, the fact remains that the claim should have been accepted by
the FSP by June 2011 and the settlement was not made until the end of
January 2012.
35. As such, the Applicants were deprived of the use of the funds payable under
the claim.
36. Section 57 of the Insurance Contracts Act 1984 reads:
Case No: 275889 Determination Page 5 of 6
“ 57 Interest on claims
(1) Where an insurer is liable to pay to a person an amount under a
contract of insurance or under this Act in relation to a contract of insurance,
the insurer is also liable to pay interest on the amount to that person in
accordance with this section.
(2) The period in respect of which interest is payable is the period
commencing on the day as from which it was unreasonable for the insurer to
have withheld payment of the amount and ending on whichever is the earlier
of the following days:
(a) the day on which the payment is made;
(b) the day on which the payment is sent by post to the person to whom it
is payable.
(3) The rate at which interest is payable in respect of a day included in the
period referred to in subsection (2) is the rate applicable in respect of that day
that is prescribed by, or worked out in a manner prescribed by, the
regulations.
(4) This section applies to the exclusion of any other law that would
otherwise apply.
(5) In subsection (4):
law means:
(a) a statutory law of the Commonwealth, a State or a Territory; or
(b) a rule of common law or equity.”
37. The hydrologist was appointed by the FSP and the FSP is liable for any
inaccurate assessments made by him, even if the findings were based on a
genuine misunderstanding of the Applicants’ claim.
38. Based on the various reports to hand, I am satisfied that the FSP should
have had adequate information to assess the claim by early June 2011 and
that it should pay interest at the statutory rate on the ultimate sum paid to the
Applicants from 3 June 2011 to 30 January 2012.
Utmost Good Faith
39. IAL believes the FSP breached its obligation to act in good faith towards the
Applicants when it relied on the hydrologist ’s reports and denied the claim
without considering the other parts of the claim which were not caused by
inundation.
40. The FSP has not explained on what grounds the claim was subsequently
accepted in December 2011.
41. Section 13 of the Act is below:
“ 13 The duty of the utmost good faith
A contract of insurance is a contract based on the utmost good faith
and there is implied in such a contract a provision requiring each party to it to
Case No: 275889 Determination Page 6 of 6
act towards the other party, in respect of any matter arising under or in
relation to it, with the utmost good faith. ”
42. I agree that the FSP is required to thoroughly investigate a claim prior to
making a final decision whether to accept or deny liability for same.
43. In this case, considering the number of claims lodged at the time after the
catastrophic event, the FSP relies on the general report by the hydrologist
which was specific to the location and then it organised site specific reports.
44. It appears the FSP failed to address the other parts of the Applicants’ claim
which were not related to the inundation.
45. However, I have reviewed the submissions made by both parties and I am
satisfied that the FSP at all times relied on the findings of its expert, the
hydrologist and thereby, I do not agree that its action constitutes a breach of
its obligation to act within the utmost good faith towards the Applicants.
Compensation
46. I note the FSP’s decision to deny the claim would have caused some
distress and interfered with the Applicants ’ expectation and peace of mind
during the period from the denial of the claim until its acceptance on 28
December 2011.
47. The FSP’s decision to deny the claim and another two months to accept the
claim from the day the Applicants requested a review by the internal dispute
resolution committee would have caused further stress.
48. Therefore, pursuant to paragraph 9.3(b) (i) of the Terms of Reference, the
FSP shall pay $500 as compensation to the Applicants.
Determination
49. On the basis of the available information, I determine the FSP should pay
interest at the statutory rate from 3 June 2011 until settlement on 30 January
2012 and the FSP should also pay compensation of $500.
50. Considering the circumstances surrounding the loss, I determine the FSP
has not breached its duty to act with the utmost good faith.